SlideShare a Scribd company logo
1 of 1
Download to read offline
www.yachtinvestor.com 49°Family Office & Yacht Management Management Legal Analysis Profile
FamilyOffice&YachtManagement
Liquid
DamagesIn the recent case of Cavendish v Makdessi, the Supreme Court clarified the law relating
towhenaliquidateddamagesclauseshouldbestruckdownasanunenforceablepenaltyclause.
In this update, Adam Ramlugon, Managing Partner at superyacht law firm Bargate Murray,
breaks down how the Court’s findings might have an impact on the superyacht industry.
case law update
THE CONCEPT OF LIQUIDATED DAMAGES
in not a foreign one to those involved with
superyachts.
In brief, the idea is that the parties to, for
example, a yacht construction contract agree on
what sum, or sums, a yacht builder should pay to
the buyer if the finished yacht does not conform to
certain aspects of the yacht’s specification. These
are usually key performance areas such as speed
or vibration, but can also cover other matters such
as unjustified delay in delivery or, when applying to
the buyer, delay in making payment to the yard.
The benefit to the parties in negotiating such a
clause is that they can avoid the expense and delay
that might be incurred if the court is required to
assess the level of damages payable in the event
of the breach. They have already agreed a level of
compensation which, on the face of the contract, is
to be paid to the wronged party upon breach.
For public policy reasons however, it has long
been established that where a liquidated damages
clause strays into the territory of what is termed a
“penalty clause”the courts will hold that it is legally
unenforceable. Parties to commercial contracts
should therefore take care to ensure that any
liquidated damages clause they seek to rely on
does not cross that line. In answering that question,
the courts have often focussed on whether the
particular provision represents a“genuine pre-
estimate of loss”. In short, if it does, then the clause
is not a penalty clause and is therefore enforceable.
The recent Supreme Court judgment in
the case of Cavendish v Makdessi considered
whether posing that test was an end to the matter.
Whilst the Court held that it remains a relevant
consideration (in some cases a conclusive one), it
formulated a new test which asks:
“…whether the impugned provision… imposes
a detriment on the contract breaker out of all
proportion to any legitimate interest in the
enforcement of the… obligation”
(Emphasis added).
The question is what impact, (if any), this
reformulated test will mean for the superyacht
industry - principally yacht owners, buyers,
charterers and shipyards. This article cannot hope
to capture every relevant aspect of the case, but a
summary of the key points might look as follows:
Key points for the superyacht industry
1 	 The Cavendish case has not“re-invented
the wheel”but it does remind us that there
are other points to consider, other than the
pre-estimate of loss test, when determining
whether or not a liquidated damages clause
should be struck down as an unenforceable
penalty.
2 	 The pre-estimate of loss test remains good law
but should generally be regarded as part of a
wider set of matters to be considered when
analysing a liquidated damages clause, such as
the tests of“proportionality”and“legitimacy”
referred to above.
3	 As is the case with any case of analysing
what a contract means, the context in which
a liquidated damages clause is agreed (by
reference to both the other clauses of
the agreement and the relevant factual
background) is crucial. Careful drafting
consideration should therefore be given to
this point. Ideally, to protect against the risk
of a clause being struck down, the agreement
should include some wording which explains
the basis upon which the parties have agreed
that the clause does no more than protect the
wronged party’s interest on terms consistent
with the reasoning in Cavendish.
4 	 In a yacht construction context, it is
noteworthy that the court made express
reference to the“uniqueness”of the subject
matter of the transaction as a factor which
would tend to support the conclusion that
the party had a legitimate interest in the
enforceability of a liquidated damages clause.
Accordingly, under an agreement to build a
“one of a kind”superyacht, a buyer’s legitimate
interests in the deal might stretch beyond the
usual commercial considerations.
5	 It is questionable, in our view, whether this
point would translate into the context of a
yacht charter where, in a case of delay or
cancellation, a charterer may quite easily be
able to source and charter another yacht of at
least similar quality. Moreover in such a case,
any actual loss would be relatively easy to
calculate. In this regard, liquidated damages
clauses which call for as much as 50% of the
charter fee to be repaid to the charter upon
cancellation remain, in our view, at risk of
being struck down as unenforceable penalty
clauses.
Adam Ramlugon, Managing Partner	
Superyacht and Aviation Group, Bargate Murray.
Disclaimer and Copyright© Bargate Murray Limited, 2015. All rights reserved. This article is for information purposes only. The information and
opinion expressed in this document does not constitute legal advice and should not be regarded as a substitute for legal advice.
©ISTOCKPHOTO The benefit to the parties in
negotiating such a clause is that
they can avoid the expense and
delay that might be incurred if
the court is required to assess
the level of damages payable in
the event of the breach

More Related Content

What's hot

Security for Performance
Security for PerformanceSecurity for Performance
Security for PerformanceLaina Chan
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction ProjectsLaina Chan
 
Power Point for Contract Damages
Power Point for Contract DamagesPower Point for Contract Damages
Power Point for Contract DamagesLaina Chan
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond Laina Chan
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Laina Chan
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Risk allocation in offshore E&P projects
Risk allocation in offshore E&P projectsRisk allocation in offshore E&P projects
Risk allocation in offshore E&P projectsClydeCoOffshore
 
Ethics Presentation
Ethics PresentationEthics Presentation
Ethics PresentationLaina Chan
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Karthik Madhavan
 
CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?Kheng Hoe Advocates
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspensionbreyerhanna
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)Wei Lie Lim
 
Z Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your ContractZ Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your Contractjpeabody
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
 

What's hot (20)

Security for Performance
Security for PerformanceSecurity for Performance
Security for Performance
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction Projects
 
Power Point for Contract Damages
Power Point for Contract DamagesPower Point for Contract Damages
Power Point for Contract Damages
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond
 
Defect exclusions
Defect exclusionsDefect exclusions
Defect exclusions
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
 
Payment terms in construction industry
Payment terms in construction industryPayment terms in construction industry
Payment terms in construction industry
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Risk allocation in offshore E&P projects
Risk allocation in offshore E&P projectsRisk allocation in offshore E&P projects
Risk allocation in offshore E&P projects
 
Ethics Presentation
Ethics PresentationEthics Presentation
Ethics Presentation
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Chapter 14 sections 1-2
Chapter 14 sections 1-2Chapter 14 sections 1-2
Chapter 14 sections 1-2
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872
 
CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?CIPAA Update June 2019 - a case of creeping complexities?
CIPAA Update June 2019 - a case of creeping complexities?
 
Breach of contract
Breach of contractBreach of contract
Breach of contract
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)
 
Z Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your ContractZ Subcontracting and Flow Down Clauses What's In Your Contract
Z Subcontracting and Flow Down Clauses What's In Your Contract
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
 

Similar to Liquidated Damages post Cavendish v Makdessi

Layout of MLC financial security article in Yacht Investor - AR (FINAL)
Layout of MLC financial security article in Yacht Investor - AR (FINAL)Layout of MLC financial security article in Yacht Investor - AR (FINAL)
Layout of MLC financial security article in Yacht Investor - AR (FINAL)Adam Ramlugon
 
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...Abraham Vergis
 
Indemnity Provisions In Energy Agreements
Indemnity Provisions In Energy AgreementsIndemnity Provisions In Energy Agreements
Indemnity Provisions In Energy Agreementskenwbullock2
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.GE 94
 
Bulletin aerospace legal developments june 2013
Bulletin aerospace legal developments june 2013Bulletin aerospace legal developments june 2013
Bulletin aerospace legal developments june 2013Eliot Norman
 
bungesavniderabvarticle
bungesavniderabvarticlebungesavniderabvarticle
bungesavniderabvarticleMichael Davar
 
Tricks & Traps: Practical Tips for Your Appellate Practice
Tricks & Traps: Practical Tips for Your Appellate PracticeTricks & Traps: Practical Tips for Your Appellate Practice
Tricks & Traps: Practical Tips for Your Appellate PracticeKelly Hart & Hallman LLP
 
8º Encontro de Resseguro do Rio de Janeiro
 8º Encontro de Resseguro do Rio de Janeiro 8º Encontro de Resseguro do Rio de Janeiro
8º Encontro de Resseguro do Rio de JaneiroCNseg
 
8º Encontro de Resseguro do Rio de Janeiro
 8º Encontro de Resseguro do Rio de Janeiro 8º Encontro de Resseguro do Rio de Janeiro
8º Encontro de Resseguro do Rio de JaneiroCNseg
 
Common Oil and Gas Lease Conundrums eBook
Common Oil and Gas Lease Conundrums eBookCommon Oil and Gas Lease Conundrums eBook
Common Oil and Gas Lease Conundrums eBookMarcellus Drilling News
 
Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Pamela McGovern
 
Energy Bulletin - Uncertainty Rises for Energy Sector Bankruptcies
Energy Bulletin - Uncertainty Rises for Energy Sector BankruptciesEnergy Bulletin - Uncertainty Rises for Energy Sector Bankruptcies
Energy Bulletin - Uncertainty Rises for Energy Sector BankruptciesCohenGrigsby
 
Article on implied term in building contract
Article on implied term in building contractArticle on implied term in building contract
Article on implied term in building contractHafizul Mukhlis
 
Master supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaMaster supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaEliot Norman
 
COVID-19 and force majeure
COVID-19 and force majeureCOVID-19 and force majeure
COVID-19 and force majeureGabrielė Songin
 
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docx
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docxShow Me My Money (Reisenfeld & Company v. The Network Group Inc..docx
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docxedmondpburgess27164
 

Similar to Liquidated Damages post Cavendish v Makdessi (20)

Layout of MLC financial security article in Yacht Investor - AR (FINAL)
Layout of MLC financial security article in Yacht Investor - AR (FINAL)Layout of MLC financial security article in Yacht Investor - AR (FINAL)
Layout of MLC financial security article in Yacht Investor - AR (FINAL)
 
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...
2017.12 CIFG Special Assets Capital I Ltd (formerly known as Diamond Kendall ...
 
Indemnity Provisions In Energy Agreements
Indemnity Provisions In Energy AgreementsIndemnity Provisions In Energy Agreements
Indemnity Provisions In Energy Agreements
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
 
Bulletin aerospace legal developments june 2013
Bulletin aerospace legal developments june 2013Bulletin aerospace legal developments june 2013
Bulletin aerospace legal developments june 2013
 
Cargo clauses09
Cargo clauses09Cargo clauses09
Cargo clauses09
 
George horsington
George horsingtonGeorge horsington
George horsington
 
bungesavniderabvarticle
bungesavniderabvarticlebungesavniderabvarticle
bungesavniderabvarticle
 
Tricks & Traps: Practical Tips for Your Appellate Practice
Tricks & Traps: Practical Tips for Your Appellate PracticeTricks & Traps: Practical Tips for Your Appellate Practice
Tricks & Traps: Practical Tips for Your Appellate Practice
 
8º Encontro de Resseguro do Rio de Janeiro
 8º Encontro de Resseguro do Rio de Janeiro 8º Encontro de Resseguro do Rio de Janeiro
8º Encontro de Resseguro do Rio de Janeiro
 
8º Encontro de Resseguro do Rio de Janeiro
 8º Encontro de Resseguro do Rio de Janeiro 8º Encontro de Resseguro do Rio de Janeiro
8º Encontro de Resseguro do Rio de Janeiro
 
Common Oil and Gas Lease Conundrums eBook
Common Oil and Gas Lease Conundrums eBookCommon Oil and Gas Lease Conundrums eBook
Common Oil and Gas Lease Conundrums eBook
 
Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)
 
Energy Bulletin - Uncertainty Rises for Energy Sector Bankruptcies
Energy Bulletin - Uncertainty Rises for Energy Sector BankruptciesEnergy Bulletin - Uncertainty Rises for Energy Sector Bankruptcies
Energy Bulletin - Uncertainty Rises for Energy Sector Bankruptcies
 
Reducing The Risks in Joint Ventures
Reducing The Risks in Joint VenturesReducing The Risks in Joint Ventures
Reducing The Risks in Joint Ventures
 
Article on implied term in building contract
Article on implied term in building contractArticle on implied term in building contract
Article on implied term in building contract
 
Master supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaMaster supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usa
 
COVID-19 and force majeure
COVID-19 and force majeureCOVID-19 and force majeure
COVID-19 and force majeure
 
39 40
39 4039 40
39 40
 
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docx
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docxShow Me My Money (Reisenfeld & Company v. The Network Group Inc..docx
Show Me My Money (Reisenfeld & Company v. The Network Group Inc..docx
 

Liquidated Damages post Cavendish v Makdessi

  • 1. www.yachtinvestor.com 49°Family Office & Yacht Management Management Legal Analysis Profile FamilyOffice&YachtManagement Liquid DamagesIn the recent case of Cavendish v Makdessi, the Supreme Court clarified the law relating towhenaliquidateddamagesclauseshouldbestruckdownasanunenforceablepenaltyclause. In this update, Adam Ramlugon, Managing Partner at superyacht law firm Bargate Murray, breaks down how the Court’s findings might have an impact on the superyacht industry. case law update THE CONCEPT OF LIQUIDATED DAMAGES in not a foreign one to those involved with superyachts. In brief, the idea is that the parties to, for example, a yacht construction contract agree on what sum, or sums, a yacht builder should pay to the buyer if the finished yacht does not conform to certain aspects of the yacht’s specification. These are usually key performance areas such as speed or vibration, but can also cover other matters such as unjustified delay in delivery or, when applying to the buyer, delay in making payment to the yard. The benefit to the parties in negotiating such a clause is that they can avoid the expense and delay that might be incurred if the court is required to assess the level of damages payable in the event of the breach. They have already agreed a level of compensation which, on the face of the contract, is to be paid to the wronged party upon breach. For public policy reasons however, it has long been established that where a liquidated damages clause strays into the territory of what is termed a “penalty clause”the courts will hold that it is legally unenforceable. Parties to commercial contracts should therefore take care to ensure that any liquidated damages clause they seek to rely on does not cross that line. In answering that question, the courts have often focussed on whether the particular provision represents a“genuine pre- estimate of loss”. In short, if it does, then the clause is not a penalty clause and is therefore enforceable. The recent Supreme Court judgment in the case of Cavendish v Makdessi considered whether posing that test was an end to the matter. Whilst the Court held that it remains a relevant consideration (in some cases a conclusive one), it formulated a new test which asks: “…whether the impugned provision… imposes a detriment on the contract breaker out of all proportion to any legitimate interest in the enforcement of the… obligation” (Emphasis added). The question is what impact, (if any), this reformulated test will mean for the superyacht industry - principally yacht owners, buyers, charterers and shipyards. This article cannot hope to capture every relevant aspect of the case, but a summary of the key points might look as follows: Key points for the superyacht industry 1 The Cavendish case has not“re-invented the wheel”but it does remind us that there are other points to consider, other than the pre-estimate of loss test, when determining whether or not a liquidated damages clause should be struck down as an unenforceable penalty. 2 The pre-estimate of loss test remains good law but should generally be regarded as part of a wider set of matters to be considered when analysing a liquidated damages clause, such as the tests of“proportionality”and“legitimacy” referred to above. 3 As is the case with any case of analysing what a contract means, the context in which a liquidated damages clause is agreed (by reference to both the other clauses of the agreement and the relevant factual background) is crucial. Careful drafting consideration should therefore be given to this point. Ideally, to protect against the risk of a clause being struck down, the agreement should include some wording which explains the basis upon which the parties have agreed that the clause does no more than protect the wronged party’s interest on terms consistent with the reasoning in Cavendish. 4 In a yacht construction context, it is noteworthy that the court made express reference to the“uniqueness”of the subject matter of the transaction as a factor which would tend to support the conclusion that the party had a legitimate interest in the enforceability of a liquidated damages clause. Accordingly, under an agreement to build a “one of a kind”superyacht, a buyer’s legitimate interests in the deal might stretch beyond the usual commercial considerations. 5 It is questionable, in our view, whether this point would translate into the context of a yacht charter where, in a case of delay or cancellation, a charterer may quite easily be able to source and charter another yacht of at least similar quality. Moreover in such a case, any actual loss would be relatively easy to calculate. In this regard, liquidated damages clauses which call for as much as 50% of the charter fee to be repaid to the charter upon cancellation remain, in our view, at risk of being struck down as unenforceable penalty clauses. Adam Ramlugon, Managing Partner Superyacht and Aviation Group, Bargate Murray. Disclaimer and Copyright© Bargate Murray Limited, 2015. All rights reserved. This article is for information purposes only. The information and opinion expressed in this document does not constitute legal advice and should not be regarded as a substitute for legal advice. ©ISTOCKPHOTO The benefit to the parties in negotiating such a clause is that they can avoid the expense and delay that might be incurred if the court is required to assess the level of damages payable in the event of the breach