This document summarizes a student construction management project to build a substation in Raniyah, Kurdistan. The project involves constructing a two-floor building measuring 711.36 square meters to convert electrical power from 132kV to 33kV and 11kV. The students calculated quantities, costs, durations and schedules for 41 construction items like excavation, reinforcement, formwork using Microsoft Project and Primavera. They developed a work breakdown structure, calculated a total project cost of $543,145.76, and planned the schedule to be completed in segments of 100%, 75%, 50% and 25%.
Double Revolving field theory-how the rotor develops torque
Construction m.emu master student project1
1. EASTERN MEDITERRANEAN UNIVERSITY
CIVIL ENGINEERING DEPARTMENT
CONSTRUCTION MANAGEMENT - I
PROJECT NUMBER 01
Prof. Dr. TAHİR ÇELİK
Student Names Student Numbers
BILAL MOHAMMED PIROT 145292
TWANA OTHMAN M.AMIN 145291
SEVAR DILKHAZ SALAHADDIN 145233
REBIN SARDAR HUSAIN 145281
1
RANIYAH 132/33/11 kv SUBSTATION
2. Raniyah 132/33/11 Kv Substation
In our project we have a two-flatted building
which is specialized for a specific work that is
(changing the electrical power from 132 kv to -
33 and 11-kv).
2
3. DESCRIPTION OF THE PROJECT
• The area of the building is 711.36 m2 (with dimensions of 68.4m*10.4m), so
the building is divided into two joints in the longitudinal direction.
• The project located in Raniyah where is a city in Kurdistan therefore in the
calculation of the project cost we used the prices in the markets of
Kurdistan with US Dollars.
• We calculated Durations for all items with regarding to output per crew
(and sometimes we used more than one crew per day for a specific item to
speed up the progress of the item).
3
4. STEPS OF CALCULATION
QUANTITY CALCULATION
After obtaining all DWG files for the project we began to calculate the Quantities for
items.
4
5. Details for Excavation ( As an example )
5
In our project we had
41 items, but here we
will take Excavation
as an example to
show how all
calculations have
done.
7. OBTAINING COSTS
7
In our country ( Kurdistan ) the cost of excavation is 4.00 US Dollars per one cubic
meter of Excavation for substations.
Then we calculated all the ( quantities and costs ) for the other items, and the total
cost of the project reached 543,145.76 US Dollars.
8. DURATION CALCULATIONS
8
And also based on the ( Quantities and standards of productivity per crew ) we
calculated the Durations for each item, as some examples shown below:
12. We calculated the reinforcement for the concrete items from the foundation to the
roof slab. We will take the foundation reinforcement as an example.
12
REINFORCEMENT CALCULATION
16. Just like the reinforcement we calculated the formwork for the concrete items from
the foundation to the roof slab.
And also we will take the foundation formwork as an example.
16
FORMWORK CALCULATION
23. 23
THE PROJECT WITH
MICROSOFT PROJECT & PREMAVERA
• Based on the durations we calculated the previously for each item we planned for
the project by using MS Project & Primavera.
• And also we made the proceedings of activities based on our engineering
experience.
For 100% Complete
I. MS PROJECT