SEPTIC TANK
 Process:
 Horizontal continuous flow sedimentation tank
(with longer detention time)
 12-36 hours detention
 Closed tank – Anaerobic decomposition of settled
sludge
 Thus Two processes-Sedimentation and
Anaerobic Sludge digestion
 It is suitable for population up to 300.
Purposes :
 Sedimentation
 Digestion tank
 Storage of digested sludge
WORKING
 The septic tank is a buried, water-tight container
usually made of concrete, brick masonry,
fiberglass or polyethylene.
 Its job is to hold the wastewater long enough to
allow solids to settle down to the bottom (forming
sludge), while the oil and grease floats to the top
(as scum).
 Compartments and a T-shaped outlet prevent the
sludge and scum from leaving the tank
 The liquid wastewater (effluent) then exits the
tank into the drainfield.
 From there it percolates into the soil, naturally
removing harmful bacteria, viruses, and nutrients.
 Following reaction occurs:
 Organic materials +Nutrients = CH4 + CO2
+NH3 + H2S + Biomass
 Sulfates, under the anaerobic conditions of septic
tanks, are reduced to hydrogen sulfide (H2S), a
pungent and toxic gas.
 Nitrates and organic nitrogen compounds are
reduced to ammonia (NH3).
 Because of the anaerobic conditions,
fermentation processes take place, which
ultimately generate carbon dioxide and methane.
Construction details:
 Long, continuous flow tank of RCC and sides
water proof.
 Facility for gas vent through vent pipe.
 Bottom (slope) to facilitate pumping of sludge.
 Manhole for removal of sludge
 Inlet and outlet, Tee’s will be provided
 Sometimes baffles to reduce disturbances
Construction details
DESIGN OF SEPTIC TANK
Design criteria:
 Capacity of septic tank: capacity for sewage+
capacity for sludge
 Quantity of sewage :40-70litres/capita/day (if
only water closets are connected to septic
tank),90-150litres/capita/day if sullage is also
discharged into septic tank.
 Quantity of sludge accumulated -30 l/capita/
years
 Depth - 1.2 – 1.8 m
 Length to Breadth ratio: 2-3
 Min width – 90 cm
 Outlet ~ in let level difference = 5-7.5 or up
to 15 cm
 Detention time = 24 hours
 Free board: 0.3-0.5m
DESIGN STEPS
1. Detention period (t) is assumed in between 12 to 36 hrs
(common value = 24 hrs)
2. Assuming rate of sewage flow (lpcd) [90 to 150 lpcd]
and knowing population to be served; total discharge
(Q) is determined.
3. Volume for sewage storage ,V1 is calculated by
V=Q. t
4. Assuming rate of accumulation of sludge 30 l/capita/
years and period of cleaning as 1 year, total sludge
deposited,V2 is determined
volume of sludge deposited in liters =30 l/capita/
years *population*1
5. Total Capacity of septic tank: V1+V2
6. Depth is assumed 1 to 2 m
7. Surface area is calculated by
As = V / depth
8. Assuming L/B ratio in between 2 to 4, length and
breadth can be fixed.
Advantages
1.Ease in construction.
2.No maintenance problem(except periodical
cleaning).
3.Cost of construction is less.
4.Effluent can be discharged without any trouble.
5.It is suitable for isolated community.
6.Very little attention is needed.
Disadvantages
1.If ST is not properly functioning, effluent will be
very foul & dark.
2.Leakage of gases from top cover of ST may
cause bed smells & environmental pollution.
3.Periodical cleaning, removal and disposal of
sludge remains a tedious problem.
4.Size required is large for larger communities.
5.Effluent contains high BOD.
6.Problem of ground water contamination
Disposal Of Effluent
Effluent from septic tank can be disposed by soil
absorption systems and anaerobic filters.
The soil absorption system may be of the
following types:
1. Soak pit/ Cess pool
2.Under drain /absorption /dispersion trenches
SOAK PIT/SEEPAGE PIT
SOAK PIT/SEEPAGE PIT
 A closed circular or rectangular pit through which
effluent will be soaked or absorbed into the
surrounding soil.
 Soak pit may be either be filled with stone
aggregates or may be kept empty.
 Soak pits are used for soils where percolation
rate is below 30 min/cm.
 They are not appropriate for areas that are prone
to flooding or have high groundwater tables
SOAK PIT
SOAK PIT
DISPERSION TRENCHES
DISPERSION TRENCHES
 Effluent is allowed to enter into a masonry
chamber(distribution box) from where it is
uniformly distributed through an underground
perforated pipes into absorption trenches which
are filled with gravel and well graded aggregate.
 Trenches are 0.5 to 1 m deep and 1 m wide.
 Maximum length of trench is 30 m.
 Spacing between trenches is 2m.
 One distribution box is provided for every 3 to 4
trenches
 Suspended organic matter will be absorbed in the
trenches where as clear water will seep down to
the water table.
DISPERSION TRENCHES
 They are not recommended in areas where
fibrous roots of trees or vegetation are likely to
penetrate the system and case blockages.
 Dispersion trenches are used for soils where
percolation rate is below 60 min/cm.
problem
Septic tank

More Related Content

What's hot (20)

P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
 
Water Supply
Water SupplyWater Supply
Water Supply
 
Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
 
L 11 screen chamber
L 11 screen chamberL 11 screen chamber
L 11 screen chamber
 
Disinfection Process
Disinfection ProcessDisinfection Process
Disinfection Process
 
Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Sewerage
SewerageSewerage
Sewerage
 
01 Sewage Generation, Collection and Conveyance
01 Sewage Generation, Collection and Conveyance01 Sewage Generation, Collection and Conveyance
01 Sewage Generation, Collection and Conveyance
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
 
GREY WATER RECYCLING SYSTEM
GREY WATER RECYCLING SYSTEMGREY WATER RECYCLING SYSTEM
GREY WATER RECYCLING SYSTEM
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
Septic tank
Septic tank Septic tank
Septic tank
 
Sludge treatment and disposal 1
Sludge treatment and disposal 1Sludge treatment and disposal 1
Sludge treatment and disposal 1
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
Che 4 house drainage system
Che 4 house drainage systemChe 4 house drainage system
Che 4 house drainage system
 
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPSDRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
 
Drainage System
Drainage SystemDrainage System
Drainage System
 
Sewage Disposal
Sewage DisposalSewage Disposal
Sewage Disposal
 
SEWERAGE SYSTEMS ppt by mayank oza
SEWERAGE SYSTEMS ppt by mayank ozaSEWERAGE SYSTEMS ppt by mayank oza
SEWERAGE SYSTEMS ppt by mayank oza
 
Trickling filters ppt.
Trickling filters ppt.Trickling filters ppt.
Trickling filters ppt.
 

Similar to Septic tank

Sewage Treatment and a case study of treatment plant
Sewage Treatment and a case study of treatment plantSewage Treatment and a case study of treatment plant
Sewage Treatment and a case study of treatment plantGeetika Singla
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tankkalyanmaji
 
Human waste (excreta disposal) mechanisms
Human waste (excreta disposal) mechanismsHuman waste (excreta disposal) mechanisms
Human waste (excreta disposal) mechanismsMtMt37
 
Sanitation
SanitationSanitation
SanitationAurleneJ
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxPRACHI DESSAI
 
Treatment of water
Treatment of waterTreatment of water
Treatment of waterdhavalsshah
 
septic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfseptic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfMood Naik
 
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tankvvsasane
 
BECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste managementBECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste managementBECM, RUET, Bangladesh
 
On site Liquid waste disposal.pptx
On site Liquid waste disposal.pptxOn site Liquid waste disposal.pptx
On site Liquid waste disposal.pptxVinayKumar2893
 
Bhutan septic-system-manual
Bhutan septic-system-manualBhutan septic-system-manual
Bhutan septic-system-manualBhim Upadhyaya
 
Sanitary drainage fittings
Sanitary drainage fittingsSanitary drainage fittings
Sanitary drainage fittingsSupta Sarkar
 
filtration of water edited october 2022.pdf
filtration of water  edited october 2022.pdffiltration of water  edited october 2022.pdf
filtration of water edited october 2022.pdf20UCE023SolomonLava
 
Septictank 150312104320-conversion-gate01
Septictank 150312104320-conversion-gate01Septictank 150312104320-conversion-gate01
Septictank 150312104320-conversion-gate01Newaz Kabir
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenancesKaranVaru1
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethimulugetakassa1988
 

Similar to Septic tank (20)

Septictankprocessdesign
SeptictankprocessdesignSeptictankprocessdesign
Septictankprocessdesign
 
Low Cost Sanitation Systems
Low Cost Sanitation SystemsLow Cost Sanitation Systems
Low Cost Sanitation Systems
 
Sewage Treatment and a case study of treatment plant
Sewage Treatment and a case study of treatment plantSewage Treatment and a case study of treatment plant
Sewage Treatment and a case study of treatment plant
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tank
 
Human waste (excreta disposal) mechanisms
Human waste (excreta disposal) mechanismsHuman waste (excreta disposal) mechanisms
Human waste (excreta disposal) mechanisms
 
Sanitation
SanitationSanitation
Sanitation
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptx
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
 
septic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfseptic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdf
 
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
1. Onsite sanitation system and disposal of sludge slide series (1) septic tank
 
BECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste managementBECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste management
 
On site Liquid waste disposal.pptx
On site Liquid waste disposal.pptxOn site Liquid waste disposal.pptx
On site Liquid waste disposal.pptx
 
Bhutan septic-system-manual
Bhutan septic-system-manualBhutan septic-system-manual
Bhutan septic-system-manual
 
Sanitary drainage fittings
Sanitary drainage fittingsSanitary drainage fittings
Sanitary drainage fittings
 
filtration of water edited october 2022.pdf
filtration of water  edited october 2022.pdffiltration of water  edited october 2022.pdf
filtration of water edited october 2022.pdf
 
Septictank 150312104320-conversion-gate01
Septictank 150312104320-conversion-gate01Septictank 150312104320-conversion-gate01
Septictank 150312104320-conversion-gate01
 
Physical Unit Operations
Physical Unit OperationsPhysical Unit Operations
Physical Unit Operations
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenances
 
Excreta Disposal.pptx
Excreta Disposal.pptxExcreta Disposal.pptx
Excreta Disposal.pptx
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethi
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Septic tank

  • 1. SHEMEERA K.H ASSISTANT PROFESSOR DEPARTMENT OF CIVIL ENGINEERING IIIT NUZVID Low cost sanitation: Septic tanks Low cost sanitation: Septic tanks by Shemeera is licensed under a Creative Commons Attribution- ShareAlike 4.0 International License.
  • 3.
  • 4.  Process:  Horizontal continuous flow sedimentation tank (with longer detention time)  12-36 hours detention  Closed tank – Anaerobic decomposition of settled sludge  Thus Two processes-Sedimentation and Anaerobic Sludge digestion  It is suitable for population up to 300.
  • 5. Purposes :  Sedimentation  Digestion tank  Storage of digested sludge
  • 6.
  • 7. WORKING  The septic tank is a buried, water-tight container usually made of concrete, brick masonry, fiberglass or polyethylene.  Its job is to hold the wastewater long enough to allow solids to settle down to the bottom (forming sludge), while the oil and grease floats to the top (as scum).  Compartments and a T-shaped outlet prevent the sludge and scum from leaving the tank  The liquid wastewater (effluent) then exits the tank into the drainfield.  From there it percolates into the soil, naturally removing harmful bacteria, viruses, and nutrients.
  • 8.
  • 9.  Following reaction occurs:  Organic materials +Nutrients = CH4 + CO2 +NH3 + H2S + Biomass  Sulfates, under the anaerobic conditions of septic tanks, are reduced to hydrogen sulfide (H2S), a pungent and toxic gas.  Nitrates and organic nitrogen compounds are reduced to ammonia (NH3).  Because of the anaerobic conditions, fermentation processes take place, which ultimately generate carbon dioxide and methane.
  • 10. Construction details:  Long, continuous flow tank of RCC and sides water proof.  Facility for gas vent through vent pipe.  Bottom (slope) to facilitate pumping of sludge.  Manhole for removal of sludge  Inlet and outlet, Tee’s will be provided  Sometimes baffles to reduce disturbances
  • 12. DESIGN OF SEPTIC TANK Design criteria:  Capacity of septic tank: capacity for sewage+ capacity for sludge  Quantity of sewage :40-70litres/capita/day (if only water closets are connected to septic tank),90-150litres/capita/day if sullage is also discharged into septic tank.  Quantity of sludge accumulated -30 l/capita/ years  Depth - 1.2 – 1.8 m  Length to Breadth ratio: 2-3
  • 13.  Min width – 90 cm  Outlet ~ in let level difference = 5-7.5 or up to 15 cm  Detention time = 24 hours  Free board: 0.3-0.5m
  • 14. DESIGN STEPS 1. Detention period (t) is assumed in between 12 to 36 hrs (common value = 24 hrs) 2. Assuming rate of sewage flow (lpcd) [90 to 150 lpcd] and knowing population to be served; total discharge (Q) is determined. 3. Volume for sewage storage ,V1 is calculated by V=Q. t 4. Assuming rate of accumulation of sludge 30 l/capita/ years and period of cleaning as 1 year, total sludge deposited,V2 is determined volume of sludge deposited in liters =30 l/capita/ years *population*1 5. Total Capacity of septic tank: V1+V2 6. Depth is assumed 1 to 2 m
  • 15. 7. Surface area is calculated by As = V / depth 8. Assuming L/B ratio in between 2 to 4, length and breadth can be fixed.
  • 16. Advantages 1.Ease in construction. 2.No maintenance problem(except periodical cleaning). 3.Cost of construction is less. 4.Effluent can be discharged without any trouble. 5.It is suitable for isolated community. 6.Very little attention is needed.
  • 17. Disadvantages 1.If ST is not properly functioning, effluent will be very foul & dark. 2.Leakage of gases from top cover of ST may cause bed smells & environmental pollution. 3.Periodical cleaning, removal and disposal of sludge remains a tedious problem. 4.Size required is large for larger communities. 5.Effluent contains high BOD. 6.Problem of ground water contamination
  • 18. Disposal Of Effluent Effluent from septic tank can be disposed by soil absorption systems and anaerobic filters. The soil absorption system may be of the following types: 1. Soak pit/ Cess pool 2.Under drain /absorption /dispersion trenches
  • 19.
  • 21. SOAK PIT/SEEPAGE PIT  A closed circular or rectangular pit through which effluent will be soaked or absorbed into the surrounding soil.  Soak pit may be either be filled with stone aggregates or may be kept empty.  Soak pits are used for soils where percolation rate is below 30 min/cm.  They are not appropriate for areas that are prone to flooding or have high groundwater tables
  • 25. DISPERSION TRENCHES  Effluent is allowed to enter into a masonry chamber(distribution box) from where it is uniformly distributed through an underground perforated pipes into absorption trenches which are filled with gravel and well graded aggregate.  Trenches are 0.5 to 1 m deep and 1 m wide.  Maximum length of trench is 30 m.  Spacing between trenches is 2m.  One distribution box is provided for every 3 to 4 trenches  Suspended organic matter will be absorbed in the trenches where as clear water will seep down to the water table.
  • 27.  They are not recommended in areas where fibrous roots of trees or vegetation are likely to penetrate the system and case blockages.  Dispersion trenches are used for soils where percolation rate is below 60 min/cm.