SlideShare a Scribd company logo
1 of 18
Wastewater Engineering
ONSITE SANITATION-SEPTIC TANKS, SOAK PIT &
IMHOFF TANKS
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
1
What is Septic tank?
Primary sedimentation tank
large detention time (12 to 36hrs against a period
of 2hrs in an ordinary sedimentation tank).
Suitable for disposal of night soil.
But sufficient water should be available as water
is required for flow of the night soil from latrine
to the septic tank
Size - Sewage is retained in the tank for 24hrs
Biological decomposition by the action of
anaerobic bacteria takes place which liquefies
and breaks the night soil leaving small quantity
of soil which is known as sludge and settles at
the bottom of the tank
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
2
What is Septic tank?
Clear water known as effluent flows out of the
tank.
The effluent from the septic tank is usually
disposed by absorption in the soil through soak
pit
If municipal drainage line exists in the area, the
effluent is discharged to the drain.
It is to be noted that disinfection agent such as
bleaching powder, phenyl etc. should not be used
in cleaning latrines as disinfectant entering the
septic tank kills the bacteria growth as a result of
which rate of biological decomposition is
retarded.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
3
Design of Septic Tank
The capacity of septic tank depends on number of users and interval of sludge removal.
Normally sludge should be removed every 2 years.
The liquid capacity of tank is taken as 130 liters to 70 liters per head.
A septic tank is usually provided with brick wall in which cement mortar [not less than 20cm (9
inch)] thick and the foundation floor is of cement concrete 1:2:4.
Both inside and outside faces of the wall and top of the floor are plastered with minimum thickness
of 12mm (one-half inch) thick cement mortar 1:3 mix.
All inside corners of septic tank are rounded.
Water proofing agent such as Impermo, Cem-seal or Accoproof etc. is added to the mortar at the rate
of 2% of the cement weight.
For proper convenience in collection and removal of the sludge, the floor of septic tank is given a
slope of 1:10 to 1:20 towards the inlet side.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
4
Dimensions of Septic Tank Components
i) Length, Width and Depth of Septic Tank
Width = 900 MM
Length = 2 to 4 times width
Depth = 1000 to 1300mm. (min below water level) + 300 to 450mm free board
Maximum depth = 1800mm + 450 mm free board
ii) Detention period
Detention period of 24hrs (mostly) considered in septic tank design. The rate of flow of effluent must
be equal to the rate of flow of influent.
iii) Inlet and outlet pipes
An elbow or T pipe of 100mm diameter is submerged to a depth of 220-600mm below the liquid
level. For outlet pipe an elbow or T type of 100mm diameter pipe is submerged to a depth of 200-
500mm below the liquid level. Pipes may be of stone ware or asbestos.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
5
Dimensions of Septic Tank Components
iv) Baffle Walls of Septic Tank
For small tanks, RCC hanging type scum baffle walls are provided in septic tanks. Baffle walls are
provided near the inlet. It is optional near the outlet.
The baffle wall is generally extended 150mm above to scum level and 400-700mm below it.
Scum being light, generally floats at the water level in the tank. Thickness of the wall varies from
50mm to 100mm. for large tanks lower portion are having holes for flow of sludge.
v) Roofing Slab of Septic Tank
The top of the septic tank is covered with a RCC slab of thickness of 75-100mm depending upon the
size of the tank. Circular manholes of 500mm clear diameter are provided for inspection and
desludging. In case of rectangular opening clear size is kept as 600X450mm.
vi) Ventilation Pipe
For outlet of foul gases and ventilation purpose cast iron or asbestos pipe of 50-100mm diameter is
provided which should extend 2m (min) above ground level. Top of the ventilation pipe is provided
with a mosquito proof wire mess or cowl.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
6
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
Fig: Sectional plan ZZ shoes the
typical layout of the septic tank.
Section XX shows the Cross-
Sectional detail of septic tank.
7
Why do we Need Soak Pit Tank ?
The water in the septic tank is not
pure, it is called grey water
because it still contains organic
materials that need to be filtered
out.
A Soak Pit is a covered, porous-
walled chamber that allows water
to slowly soak into the ground.
Pre-settled effluent from septic
tank is discharged to the
underground chamber from where
it infiltrates into the surrounding
soil.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
8
Design
The following considerations for the design of a soak-pit such as:
It should be between 1.5 m and 4 m deep but as a general rule, never less than 2 m above the
groundwater table.
From a drinking water source, it should be located at a safe distance ideally more than 30 m and it
should also be kept away from high-traffic areas.
To provide support and prevent collapse, it can be left empty and lined with a porous material.
From collapsing, the rocks and gravel will prevent the walls but for wastewater, we will still provide
adequate space.
A layer of sand and fine gravel should be spread over the bottom to help disperse the flow in both
cases.
A removable lid should be used to seal the pit until it needs to be maintained to allow for future
access.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
9
Working & Maintenance
Working
As waste-water percolates through the soil from the soak pit , small particles are filtered out by the
soil matrix and organics are digested by micro-organism.
Soak pit are best suited to soils with good absorptive properties;
Maintenance
• The effluent should be clarified or filtered well to prevent excessive build up of solids.
• The Soak Pit should be kept away from high-traffic areas.
• Particles and biomass will clog the pit so need to be cleaned or moved.
• For future access a removable lid should be used to seal the pit.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
10
Aadvantages & Disadvantages
Advantages
• Can be built and repaired with locally available materials.
• Small land area required.
• Power conservative.
• Simple technique for all users.
Disadvantages
• Pre-treatment is required to prevent clogging, although eventual clogging is inevitable.
• Negatively affects soil and groundwater properties.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
11
Imhoff Tank
Improvement over Septic Tank
Sewage is not allowed to mix with Sludge and
outgoing effluent is not allowed to carry with it
large organic load
Mr. Karl Imhoff - Designer
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
12
Constructional Details:
Double Chamber Rectangular Tank
Upper Chamber - Sedimentation Chamber or Flow through Chamber
Lower Chamber - Digestion Chamber (Anaerobic Decomposition -
Sludge)
Sloping Bottom at the sides of Sedimentation Chamber
Slope 1.25 vertical to 1
Entrance Slot - 15 cm (Overlapped) prevent direct contact of Gases
Gas Vent/Scum Chamber -gases to escape
To prevent entry of Sludge into sedimentation Chamber 45 cm
clearance has to be kept (Neutral Zone)
Digestion Chamber - 3 to 4 interconnected Compartments
Hopper Bottom (Sloping 1:1)
Cleaned after 1 to 1.5 months
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
13
Advantages and Disadvantages of Imhoff
Tanks:
Advantages
• Small Sized treatment plants
• Economical
• Do no require Skilled Supervision
• 60 - 65 % removal of Solids
• 30 - 40 % removal of BOD
Disadvantages
• More depth - Construction Costlier
• Offensive odours
• Unsuitable for Acidic Waste
• Foam or Boil
• No Control over operation
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
14
Treated Effluent Disposal
Natural Evaporation
• large impoundments with no discharge.
• Depends on the climatic conditions
• Net evaporation, storage requirements, and possible percolation and groundwater pollution.
• Beneficial where recovery of residues is desirable such as for disposal of brines.
Groundwater Recharge
• Rapid infiltration by effluent
• Impoundment, intermittent percolation, and direct injection.
• Risks for groundwater pollution exists.
• High costs of treating effluent and injection facilities.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
15
Treated Effluent Disposal
Irrigation
• Substitute for scarce natural waters or sparse rainfall in arid areas.
• In most cases food chain crops (i.e. crops consumed by humans and those animals whose
products are consumed by humans) may not be irrigated by effluent.
• However, field crops such as cotton, sugar beets, and crops for seed production are grown
with wastewater effluent.
• Wastewater effluent has been used for watering parks, golf courses and highway medians.
Recreational Lakes
• Stored in a lagoon for approximately 30 days.
• Chlorinated and then percolated through an area of sand and gravel, through which it
travels for approximately 0.5 km and is collected in an interceptor trench.
• Discharged into a series of lakes used for swimming, boating and fishing.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
16
Treated Effluent Disposal
Aquaculture
• Production of aquatic organisms
• Production of food, fiber and fertilizer.
• Lagoons are used for aquaculture, although artificial and natural wetlands are also being
considered.
• Uncontrolled spread of water hyacinths is itself a great concern because the flora can clog
waterways and ruin water bodies.
Municipal Uses
• Meet drinking water quality standards.
• Emergency basis.
• Many natural bodies of water that are used for municipal water supply are also used for
effluent disposal which is done to supplement the natural water resources by reusing the effluent
many times before it finally flows to the sea.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
17
Treated Effluent Disposal
Industrial Uses
• Used as a cooling water or boiler feed water.
• Deciding factors for effluent reuse by the industry include
○ availability of natural water
○ quality and quantity of effluent, and cost of processing
○ pumping and transport cost of effluent
○ industrial process water that does not involve public health considerations.
Discharge into Natural Waters
Discharge into natural waters is the most common disposal practice. The self-purification or
assimilative capacity of natural waters is thus utilized to provide the remaining treatment.
REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N
MODI
18

More Related Content

What's hot

L11-Disinfection.pptx
L11-Disinfection.pptxL11-Disinfection.pptx
L11-Disinfection.pptxPRACHI DESSAI
 
L9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptL9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptPRACHI DESSAI
 
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptxL10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptxPRACHI DESSAI
 
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxL11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxPRACHI DESSAI
 
L7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxL7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxPRACHI DESSAI
 
L8 - Construction Safety.pptx
L8 - Construction Safety.pptxL8 - Construction Safety.pptx
L8 - Construction Safety.pptxPRACHI DESSAI
 
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxL12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxPRACHI DESSAI
 
L12- Softening of Water.pptx
L12- Softening of Water.pptxL12- Softening of Water.pptx
L12- Softening of Water.pptxPRACHI DESSAI
 
L6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxL6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxPRACHI DESSAI
 
L3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxL3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxPRACHI DESSAI
 
L7- Sedimentation.pptx
L7- Sedimentation.pptxL7- Sedimentation.pptx
L7- Sedimentation.pptxPRACHI DESSAI
 
L2 - Sources of water.ppt
L2 - Sources of water.pptL2 - Sources of water.ppt
L2 - Sources of water.pptPRACHI DESSAI
 
L5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxL5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxPRACHI DESSAI
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.pptPRACHI DESSAI
 
L5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxL5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxPRACHI DESSAI
 
L1 - Introduction.ppt
L1 - Introduction.pptL1 - Introduction.ppt
L1 - Introduction.pptPRACHI DESSAI
 
L9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxL9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxPRACHI DESSAI
 
L10 - Employee Training.ppt
L10 - Employee Training.pptL10 - Employee Training.ppt
L10 - Employee Training.pptPRACHI DESSAI
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxPRACHI DESSAI
 
L4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxL4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxPRACHI DESSAI
 

What's hot (20)

L11-Disinfection.pptx
L11-Disinfection.pptxL11-Disinfection.pptx
L11-Disinfection.pptx
 
L9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.pptL9 - Personal Protective Equipments.ppt
L9 - Personal Protective Equipments.ppt
 
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptxL10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx
L10 -PRELIMIARY AND PRIMARY TREATMENT OF SEWAGE.pptx
 
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptxL11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
L11 -SECONDARY TREATMENT OF SEWAGE - TRICKLING FILTERS.pptx
 
L7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptxL7- CHARACTERISTICS OF SEWAGE.pptx
L7- CHARACTERISTICS OF SEWAGE.pptx
 
L8 - Construction Safety.pptx
L8 - Construction Safety.pptxL8 - Construction Safety.pptx
L8 - Construction Safety.pptx
 
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptxL12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
L12 -SECONDARY TREATMENT OF SEWAGE ACTIVATED SLUDGE PLANT.pptx
 
L12- Softening of Water.pptx
L12- Softening of Water.pptxL12- Softening of Water.pptx
L12- Softening of Water.pptx
 
L6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptxL6- Screening & Aeration Systems.pptx
L6- Screening & Aeration Systems.pptx
 
L3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptxL3- SYSTEMS OF SANITATION.pptx
L3- SYSTEMS OF SANITATION.pptx
 
L7- Sedimentation.pptx
L7- Sedimentation.pptxL7- Sedimentation.pptx
L7- Sedimentation.pptx
 
L2 - Sources of water.ppt
L2 - Sources of water.pptL2 - Sources of water.ppt
L2 - Sources of water.ppt
 
L5 - OSH and Laws.pptx
L5 - OSH and Laws.pptxL5 - OSH and Laws.pptx
L5 - OSH and Laws.pptx
 
L3 -Intake Structures.ppt
L3 -Intake Structures.pptL3 -Intake Structures.ppt
L3 -Intake Structures.ppt
 
L5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptxL5 -Water Quality Criteria and Paremeters.pptx
L5 -Water Quality Criteria and Paremeters.pptx
 
L1 - Introduction.ppt
L1 - Introduction.pptL1 - Introduction.ppt
L1 - Introduction.ppt
 
L9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptxL9- SELF PURITIFCATION OF STREAMS.pptx
L9- SELF PURITIFCATION OF STREAMS.pptx
 
L10 - Employee Training.ppt
L10 - Employee Training.pptL10 - Employee Training.ppt
L10 - Employee Training.ppt
 
L5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptxL5 - ESTIMATION OF SEWAGE.pptx
L5 - ESTIMATION OF SEWAGE.pptx
 
L4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptxL4- Water Supply Scheme & Importance.pptx
L4- Water Supply Scheme & Importance.pptx
 

Similar to L14 - ONSITE SANITATION.pptx

septic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfseptic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfMood Naik
 
Storm water rain water harvesting
Storm water   rain water harvestingStorm water   rain water harvesting
Storm water rain water harvestingDipesh Jain
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tankkalyanmaji
 
Techniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areasTechniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areasIEI GSC
 
Rooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRevadhBalraj
 
CSA Symposium 2016 -Shawn Miller Day 1 Session 3
CSA Symposium 2016 -Shawn Miller  Day 1 Session 3CSA Symposium 2016 -Shawn Miller  Day 1 Session 3
CSA Symposium 2016 -Shawn Miller Day 1 Session 3ACDI/VOCA
 
401506777-Rain-water-harvesting-seminar-ppt.pptx
401506777-Rain-water-harvesting-seminar-ppt.pptx401506777-Rain-water-harvesting-seminar-ppt.pptx
401506777-Rain-water-harvesting-seminar-ppt.pptxshrishridharshri3693
 
Rain water harvesting by Dr. Arun Kumar
Rain water harvesting by Dr. Arun KumarRain water harvesting by Dr. Arun Kumar
Rain water harvesting by Dr. Arun KumarArun Kumar
 
Prayas Session: Rain Water Harvesting by Soumalya Nandi
Prayas Session: Rain Water Harvesting by Soumalya NandiPrayas Session: Rain Water Harvesting by Soumalya Nandi
Prayas Session: Rain Water Harvesting by Soumalya NandiTenet Systems Pvt Ltd
 
rainwaterharvestingpresentation.pdf
rainwaterharvestingpresentation.pdfrainwaterharvestingpresentation.pdf
rainwaterharvestingpresentation.pdfTaranJot7
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvestingArchy Bhatt
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2ctlachu
 
Rooftop rainwater harvesting system.
Rooftop rainwater harvesting system.Rooftop rainwater harvesting system.
Rooftop rainwater harvesting system.AbhishekPal808015
 
Rainwaterharvesting by...prabhunath sharma
Rainwaterharvesting by...prabhunath sharmaRainwaterharvesting by...prabhunath sharma
Rainwaterharvesting by...prabhunath sharmaPrabhunath Sharma
 
Rain water harvesting presentation
Rain water harvesting presentationRain water harvesting presentation
Rain water harvesting presentationsuraj vishwakarma
 
Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02muhammed ajeeb
 
Rainwater harvesting an alternative source of water
Rainwater harvesting  an alternative source of waterRainwater harvesting  an alternative source of water
Rainwater harvesting an alternative source of waterShabarinath R
 
rain-water-harvesting-Seminar-Report-pdf.pdf
rain-water-harvesting-Seminar-Report-pdf.pdfrain-water-harvesting-Seminar-Report-pdf.pdf
rain-water-harvesting-Seminar-Report-pdf.pdfshrishridharshri3693
 

Similar to L14 - ONSITE SANITATION.pptx (20)

Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
septic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdfseptic_tank_concept_and_design.pdf
septic_tank_concept_and_design.pdf
 
Storm water rain water harvesting
Storm water   rain water harvestingStorm water   rain water harvesting
Storm water rain water harvesting
 
Presentation for safegard septic tank
Presentation for safegard septic tankPresentation for safegard septic tank
Presentation for safegard septic tank
 
Techniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areasTechniques of rain water harvesting in urban and rural areas
Techniques of rain water harvesting in urban and rural areas
 
Rooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource management
 
CSA Symposium 2016 -Shawn Miller Day 1 Session 3
CSA Symposium 2016 -Shawn Miller  Day 1 Session 3CSA Symposium 2016 -Shawn Miller  Day 1 Session 3
CSA Symposium 2016 -Shawn Miller Day 1 Session 3
 
401506777-Rain-water-harvesting-seminar-ppt.pptx
401506777-Rain-water-harvesting-seminar-ppt.pptx401506777-Rain-water-harvesting-seminar-ppt.pptx
401506777-Rain-water-harvesting-seminar-ppt.pptx
 
Rain water harvesting by Dr. Arun Kumar
Rain water harvesting by Dr. Arun KumarRain water harvesting by Dr. Arun Kumar
Rain water harvesting by Dr. Arun Kumar
 
Prayas Session: Rain Water Harvesting by Soumalya Nandi
Prayas Session: Rain Water Harvesting by Soumalya NandiPrayas Session: Rain Water Harvesting by Soumalya Nandi
Prayas Session: Rain Water Harvesting by Soumalya Nandi
 
rainwaterharvestingpresentation.pdf
rainwaterharvestingpresentation.pdfrainwaterharvestingpresentation.pdf
rainwaterharvestingpresentation.pdf
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2
 
Rooftop rainwater harvesting system.
Rooftop rainwater harvesting system.Rooftop rainwater harvesting system.
Rooftop rainwater harvesting system.
 
Rainwaterharvesting by...prabhunath sharma
Rainwaterharvesting by...prabhunath sharmaRainwaterharvesting by...prabhunath sharma
Rainwaterharvesting by...prabhunath sharma
 
Rain water harvesting presentation
Rain water harvesting presentationRain water harvesting presentation
Rain water harvesting presentation
 
Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02Rainwaterharvestingby prabhunath-120911061513-phpapp02
Rainwaterharvestingby prabhunath-120911061513-phpapp02
 
Rainwater harvesting an alternative source of water
Rainwater harvesting  an alternative source of waterRainwater harvesting  an alternative source of water
Rainwater harvesting an alternative source of water
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
rain-water-harvesting-Seminar-Report-pdf.pdf
rain-water-harvesting-Seminar-Report-pdf.pdfrain-water-harvesting-Seminar-Report-pdf.pdf
rain-water-harvesting-Seminar-Report-pdf.pdf
 

More from PRACHI DESSAI

L3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxL3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxPRACHI DESSAI
 
L2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxL2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxPRACHI DESSAI
 
L1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxL1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxPRACHI DESSAI
 
L3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxL3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxPRACHI DESSAI
 
2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptxPRACHI DESSAI
 
1. Introduction to EIA.pptx
1. Introduction to EIA.pptx1. Introduction to EIA.pptx
1. Introduction to EIA.pptxPRACHI DESSAI
 
L10-Chlorination.pptx
L10-Chlorination.pptxL10-Chlorination.pptx
L10-Chlorination.pptxPRACHI DESSAI
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxPRACHI DESSAI
 
L7 - Emergency Response.ppt
L7 - Emergency Response.pptL7 - Emergency Response.ppt
L7 - Emergency Response.pptPRACHI DESSAI
 
L2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxL2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxPRACHI DESSAI
 
L4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptL4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptPRACHI DESSAI
 
L3- Accident investigation.ppt
L3- Accident investigation.pptL3- Accident investigation.ppt
L3- Accident investigation.pptPRACHI DESSAI
 

More from PRACHI DESSAI (12)

L3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptxL3- PERMISSIBLE THRESHOLD LIMITS.pptx
L3- PERMISSIBLE THRESHOLD LIMITS.pptx
 
L2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptxL2- OCCUPATIONAL HAZARDS.pptx
L2- OCCUPATIONAL HAZARDS.pptx
 
L1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptxL1- INTRODUCTION TO OSHA.pptx
L1- INTRODUCTION TO OSHA.pptx
 
L3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptxL3- FIRE HAZARDS.pptx
L3- FIRE HAZARDS.pptx
 
2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx2. Environmental Mangement Plan.pptx
2. Environmental Mangement Plan.pptx
 
1. Introduction to EIA.pptx
1. Introduction to EIA.pptx1. Introduction to EIA.pptx
1. Introduction to EIA.pptx
 
L10-Chlorination.pptx
L10-Chlorination.pptxL10-Chlorination.pptx
L10-Chlorination.pptx
 
L8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptxL8- Sedimentation aided with coagulation.pptx
L8- Sedimentation aided with coagulation.pptx
 
L7 - Emergency Response.ppt
L7 - Emergency Response.pptL7 - Emergency Response.ppt
L7 - Emergency Response.ppt
 
L2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptxL2 - Occupational Health Hazards.pptx
L2 - Occupational Health Hazards.pptx
 
L4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.pptL4 - Accident and Report Writing.ppt
L4 - Accident and Report Writing.ppt
 
L3- Accident investigation.ppt
L3- Accident investigation.pptL3- Accident investigation.ppt
L3- Accident investigation.ppt
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

L14 - ONSITE SANITATION.pptx

  • 1. Wastewater Engineering ONSITE SANITATION-SEPTIC TANKS, SOAK PIT & IMHOFF TANKS REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 1
  • 2. What is Septic tank? Primary sedimentation tank large detention time (12 to 36hrs against a period of 2hrs in an ordinary sedimentation tank). Suitable for disposal of night soil. But sufficient water should be available as water is required for flow of the night soil from latrine to the septic tank Size - Sewage is retained in the tank for 24hrs Biological decomposition by the action of anaerobic bacteria takes place which liquefies and breaks the night soil leaving small quantity of soil which is known as sludge and settles at the bottom of the tank REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 2
  • 3. What is Septic tank? Clear water known as effluent flows out of the tank. The effluent from the septic tank is usually disposed by absorption in the soil through soak pit If municipal drainage line exists in the area, the effluent is discharged to the drain. It is to be noted that disinfection agent such as bleaching powder, phenyl etc. should not be used in cleaning latrines as disinfectant entering the septic tank kills the bacteria growth as a result of which rate of biological decomposition is retarded. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 3
  • 4. Design of Septic Tank The capacity of septic tank depends on number of users and interval of sludge removal. Normally sludge should be removed every 2 years. The liquid capacity of tank is taken as 130 liters to 70 liters per head. A septic tank is usually provided with brick wall in which cement mortar [not less than 20cm (9 inch)] thick and the foundation floor is of cement concrete 1:2:4. Both inside and outside faces of the wall and top of the floor are plastered with minimum thickness of 12mm (one-half inch) thick cement mortar 1:3 mix. All inside corners of septic tank are rounded. Water proofing agent such as Impermo, Cem-seal or Accoproof etc. is added to the mortar at the rate of 2% of the cement weight. For proper convenience in collection and removal of the sludge, the floor of septic tank is given a slope of 1:10 to 1:20 towards the inlet side. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 4
  • 5. Dimensions of Septic Tank Components i) Length, Width and Depth of Septic Tank Width = 900 MM Length = 2 to 4 times width Depth = 1000 to 1300mm. (min below water level) + 300 to 450mm free board Maximum depth = 1800mm + 450 mm free board ii) Detention period Detention period of 24hrs (mostly) considered in septic tank design. The rate of flow of effluent must be equal to the rate of flow of influent. iii) Inlet and outlet pipes An elbow or T pipe of 100mm diameter is submerged to a depth of 220-600mm below the liquid level. For outlet pipe an elbow or T type of 100mm diameter pipe is submerged to a depth of 200- 500mm below the liquid level. Pipes may be of stone ware or asbestos. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 5
  • 6. Dimensions of Septic Tank Components iv) Baffle Walls of Septic Tank For small tanks, RCC hanging type scum baffle walls are provided in septic tanks. Baffle walls are provided near the inlet. It is optional near the outlet. The baffle wall is generally extended 150mm above to scum level and 400-700mm below it. Scum being light, generally floats at the water level in the tank. Thickness of the wall varies from 50mm to 100mm. for large tanks lower portion are having holes for flow of sludge. v) Roofing Slab of Septic Tank The top of the septic tank is covered with a RCC slab of thickness of 75-100mm depending upon the size of the tank. Circular manholes of 500mm clear diameter are provided for inspection and desludging. In case of rectangular opening clear size is kept as 600X450mm. vi) Ventilation Pipe For outlet of foul gases and ventilation purpose cast iron or asbestos pipe of 50-100mm diameter is provided which should extend 2m (min) above ground level. Top of the ventilation pipe is provided with a mosquito proof wire mess or cowl. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 6
  • 7. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI Fig: Sectional plan ZZ shoes the typical layout of the septic tank. Section XX shows the Cross- Sectional detail of septic tank. 7
  • 8. Why do we Need Soak Pit Tank ? The water in the septic tank is not pure, it is called grey water because it still contains organic materials that need to be filtered out. A Soak Pit is a covered, porous- walled chamber that allows water to slowly soak into the ground. Pre-settled effluent from septic tank is discharged to the underground chamber from where it infiltrates into the surrounding soil. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 8
  • 9. Design The following considerations for the design of a soak-pit such as: It should be between 1.5 m and 4 m deep but as a general rule, never less than 2 m above the groundwater table. From a drinking water source, it should be located at a safe distance ideally more than 30 m and it should also be kept away from high-traffic areas. To provide support and prevent collapse, it can be left empty and lined with a porous material. From collapsing, the rocks and gravel will prevent the walls but for wastewater, we will still provide adequate space. A layer of sand and fine gravel should be spread over the bottom to help disperse the flow in both cases. A removable lid should be used to seal the pit until it needs to be maintained to allow for future access. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 9
  • 10. Working & Maintenance Working As waste-water percolates through the soil from the soak pit , small particles are filtered out by the soil matrix and organics are digested by micro-organism. Soak pit are best suited to soils with good absorptive properties; Maintenance • The effluent should be clarified or filtered well to prevent excessive build up of solids. • The Soak Pit should be kept away from high-traffic areas. • Particles and biomass will clog the pit so need to be cleaned or moved. • For future access a removable lid should be used to seal the pit. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 10
  • 11. Aadvantages & Disadvantages Advantages • Can be built and repaired with locally available materials. • Small land area required. • Power conservative. • Simple technique for all users. Disadvantages • Pre-treatment is required to prevent clogging, although eventual clogging is inevitable. • Negatively affects soil and groundwater properties. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 11
  • 12. Imhoff Tank Improvement over Septic Tank Sewage is not allowed to mix with Sludge and outgoing effluent is not allowed to carry with it large organic load Mr. Karl Imhoff - Designer REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 12
  • 13. Constructional Details: Double Chamber Rectangular Tank Upper Chamber - Sedimentation Chamber or Flow through Chamber Lower Chamber - Digestion Chamber (Anaerobic Decomposition - Sludge) Sloping Bottom at the sides of Sedimentation Chamber Slope 1.25 vertical to 1 Entrance Slot - 15 cm (Overlapped) prevent direct contact of Gases Gas Vent/Scum Chamber -gases to escape To prevent entry of Sludge into sedimentation Chamber 45 cm clearance has to be kept (Neutral Zone) Digestion Chamber - 3 to 4 interconnected Compartments Hopper Bottom (Sloping 1:1) Cleaned after 1 to 1.5 months REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 13
  • 14. Advantages and Disadvantages of Imhoff Tanks: Advantages • Small Sized treatment plants • Economical • Do no require Skilled Supervision • 60 - 65 % removal of Solids • 30 - 40 % removal of BOD Disadvantages • More depth - Construction Costlier • Offensive odours • Unsuitable for Acidic Waste • Foam or Boil • No Control over operation REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 14
  • 15. Treated Effluent Disposal Natural Evaporation • large impoundments with no discharge. • Depends on the climatic conditions • Net evaporation, storage requirements, and possible percolation and groundwater pollution. • Beneficial where recovery of residues is desirable such as for disposal of brines. Groundwater Recharge • Rapid infiltration by effluent • Impoundment, intermittent percolation, and direct injection. • Risks for groundwater pollution exists. • High costs of treating effluent and injection facilities. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 15
  • 16. Treated Effluent Disposal Irrigation • Substitute for scarce natural waters or sparse rainfall in arid areas. • In most cases food chain crops (i.e. crops consumed by humans and those animals whose products are consumed by humans) may not be irrigated by effluent. • However, field crops such as cotton, sugar beets, and crops for seed production are grown with wastewater effluent. • Wastewater effluent has been used for watering parks, golf courses and highway medians. Recreational Lakes • Stored in a lagoon for approximately 30 days. • Chlorinated and then percolated through an area of sand and gravel, through which it travels for approximately 0.5 km and is collected in an interceptor trench. • Discharged into a series of lakes used for swimming, boating and fishing. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 16
  • 17. Treated Effluent Disposal Aquaculture • Production of aquatic organisms • Production of food, fiber and fertilizer. • Lagoons are used for aquaculture, although artificial and natural wetlands are also being considered. • Uncontrolled spread of water hyacinths is itself a great concern because the flora can clog waterways and ruin water bodies. Municipal Uses • Meet drinking water quality standards. • Emergency basis. • Many natural bodies of water that are used for municipal water supply are also used for effluent disposal which is done to supplement the natural water resources by reusing the effluent many times before it finally flows to the sea. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 17
  • 18. Treated Effluent Disposal Industrial Uses • Used as a cooling water or boiler feed water. • Deciding factors for effluent reuse by the industry include ○ availability of natural water ○ quality and quantity of effluent, and cost of processing ○ pumping and transport cost of effluent ○ industrial process water that does not involve public health considerations. Discharge into Natural Waters Discharge into natural waters is the most common disposal practice. The self-purification or assimilative capacity of natural waters is thus utilized to provide the remaining treatment. REFERENCE – SEWAGE TREATMENT DISPOSAL & WASTE WATER ENGINEERING – P.N MODI 18