RENOVATION & MODERNIZATION IN THERMAL POWER STATIONS

Another 30 Years !!

SANTOSH PARDHI
Deputy Manager
Adani Infra (India)Ltd.

1











The requirement of power is felt as an important input for economic growth,
more so in a power deficit scenario like India.
Old operating units lose efficiency and capacity due to aging.
New boilers are more expensive and take longer to install.
Disposal of old operating boiler plant is a problem.
Renovation and modernization of older units is one of the least cost effective
means of generating additional power.
Fuel availability changes over years of operation .
Pressure Parts need replacement to ensure safe operation after certain length of
operation
Re-powering can increase the cycle efficiency and hence reduce emission of
greenhouse gases and pollutants
Operating pressure and temperature of these old plants are lower and there is
no reheating in some of the units

2












R&M will involve up gradation of milling system, APH, ESP, firing system etc
and refurbishment of turbine, condenser, pressure parts, fans etc.
R&M may involve following changes in plant design :
• Adoption of higher steam parameters .
• Introduction of topping cycle, old turbine may be retained in bottoming
cycle.
• Bottoming turbine cycle efficiency improvement by adoption of high
efficiency blade design
New Plants –costly.
Longer gestation period of new plant.
Limited availability of new site.
Old plants can be renovated and Modernised at lower costs and life extension
achieved.
Availability and efficiency can be improved.
Pressure Part replacements that make use of improved materials and redesign
of heat transfer surface for extended boiler life.

3













R&M solutions cost just a third of a new boiler in terms of cost & time

Improve performance by introduction of new technology.
To upgrade the units to comply with fast changing Environmental / statutory
standards / guidelines.
Clean Coal Technology to reduce .
SOX ,NOX & CO2 Emissions
Sub Critical Steam Parameters To Supercritical Parameters
Increase in Pressure and temperature to like 250bar and 565 deg C.
Re-powering Technology
For better efficiency, pollution control and less cost besides life extension
Minimum environmental impact and R&R problems for additional capacity.
Renovation & Modernization of old existing units is an important tool for
capacity enhancement, life extension and improvement in availability,
reliability & efficiency

4










Operational History & Problems being faced to run the plant.
Major modifications carried out from the original design condition.
Age of the plant, its existing condition and generic problems in its inherited
design
Collect all engineering as build drawing and sketches.
Model the existing boiler plant based on original design data .
Input current operating condition to verify the model.
Input revised (new) operating conditions .

5


BOILER & AUXILIARIES
◦ Replacement/Augmentation Of Pressure Parts.
◦ Retrofitting/ Modifications Air Pre Heater.
◦ Augmentation Of Milling System.
◦ Provision Of Flame Scanners, ignitors.
◦ Renovation of Draft System.
◦ Retrofitting Of ESPs.
 TG & AUXILIARIES
◦ Replacement of turbine blades with latest design.
◦ Modernization of condensers by change in type and material of
tubes, augmenting with tube cleaning mechanism.
◦ Modernisation of power cycle equipment's with more efficient pumps
and improved Regenerative Heaters.
◦ Modification of air evacuation system with Vacuum pumps.

6
7
8
Another 30
Years

R&M

THERMAL

POWER

9
10

More Related Content

What's hot

Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPSManohar Tatwawadi
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and FillShad Edwards
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat BalanceManohar Tatwawadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...Saikat Halder
 
SOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxSOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxanujgupta862927
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiencyManohar Tatwawadi
 
Energy performance assessment of boilers
Energy performance assessment of boilersEnergy performance assessment of boilers
Energy performance assessment of boilersUtsav Jain
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 

What's hot (20)

Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and Fill
 
Drum level
Drum levelDrum level
Drum level
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Heat balance diagram
Heat balance diagramHeat balance diagram
Heat balance diagram
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
 
SOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptxSOOT BLOWERS - Copy.pptx
SOOT BLOWERS - Copy.pptx
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
Energy performance assessment of boilers
Energy performance assessment of boilersEnergy performance assessment of boilers
Energy performance assessment of boilers
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient Steam Systems -
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 

Similar to R&M Extends Thermal Power Plant Life

Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Shaun West
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)HARSHIT GUPTA
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperiencePooja Agarwal
 
Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationCANDHARE
 
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET Journal
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar
 
Revamps for Ageing Methanol Plants
Revamps for Ageing Methanol PlantsRevamps for Ageing Methanol Plants
Revamps for Ageing Methanol PlantsGerard B. Hawkins
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsGerard B. Hawkins
 
Key lessons to optimise ammonia plant
Key lessons to optimise ammonia plantKey lessons to optimise ammonia plant
Key lessons to optimise ammonia plantPRAVEEN SINGH
 
Strategic meet_Engineering.pptx
Strategic meet_Engineering.pptxStrategic meet_Engineering.pptx
Strategic meet_Engineering.pptxmukeshsingh71872
 
Super inverter epcen08 114-catalogues_english (2)
Super inverter epcen08 114-catalogues_english (2)Super inverter epcen08 114-catalogues_english (2)
Super inverter epcen08 114-catalogues_english (2)Henry Hollands
 
Thermo Tech Engineering (Tte)1
Thermo Tech Engineering (Tte)1Thermo Tech Engineering (Tte)1
Thermo Tech Engineering (Tte)1rajputdanish
 
Revamps for Ageing Ammonia Plants
Revamps for Ageing Ammonia PlantsRevamps for Ageing Ammonia Plants
Revamps for Ageing Ammonia PlantsGerard B. Hawkins
 
Improved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaImproved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaRazin Sazzad Molla
 
Ammonia plant efficiency
Ammonia plant efficiencyAmmonia plant efficiency
Ammonia plant efficiencyHimanshu Sharma
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)Ashok Yadav
 
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...IRJET Journal
 
Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towersAbdelrahim Ramadan
 

Similar to R&M Extends Thermal Power Plant Life (20)

Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 
Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmization
 
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass ValveIRJET- Fatigue Life Estimation of Turbine Bypass Valve
IRJET- Fatigue Life Estimation of Turbine Bypass Valve
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'
 
Revamps for Ageing Methanol Plants
Revamps for Ageing Methanol PlantsRevamps for Ageing Methanol Plants
Revamps for Ageing Methanol Plants
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen Plants
 
Key lessons to optimise ammonia plant
Key lessons to optimise ammonia plantKey lessons to optimise ammonia plant
Key lessons to optimise ammonia plant
 
Strategic meet_Engineering.pptx
Strategic meet_Engineering.pptxStrategic meet_Engineering.pptx
Strategic meet_Engineering.pptx
 
Super inverter epcen08 114-catalogues_english (2)
Super inverter epcen08 114-catalogues_english (2)Super inverter epcen08 114-catalogues_english (2)
Super inverter epcen08 114-catalogues_english (2)
 
Thermo Tech Engineering (Tte)1
Thermo Tech Engineering (Tte)1Thermo Tech Engineering (Tte)1
Thermo Tech Engineering (Tte)1
 
Revamps for Ageing Ammonia Plants
Revamps for Ageing Ammonia PlantsRevamps for Ageing Ammonia Plants
Revamps for Ageing Ammonia Plants
 
Improved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad MollaImproved efficiency of gas turbine by Razin Sazzad Molla
Improved efficiency of gas turbine by Razin Sazzad Molla
 
Ammonia plant efficiency
Ammonia plant efficiencyAmmonia plant efficiency
Ammonia plant efficiency
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
 
Heat rate- pulse rate of power plant
Heat rate-  pulse rate of power plantHeat rate-  pulse rate of power plant
Heat rate- pulse rate of power plant
 
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...
Study & Review of Heat Recovery Systems for SO2 Gas Generation Process in Sug...
 
Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towers
 

Recently uploaded

3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Narsimha murthy
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一lvtagr7
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证nhjeo1gg
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...Amil baba
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...narwatsonia7
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)jennyeacort
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,bhuyansuprit
 

Recently uploaded (20)

3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
定制(RMIT毕业证书)澳洲墨尔本皇家理工大学毕业证成绩单原版一比一
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
 
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
NO1 Famous Amil Baba In Karachi Kala Jadu In Karachi Amil baba In Karachi Add...
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full NightCall Girls Aslali 7397865700 Ridhima Hire Me Full Night
Call Girls Aslali 7397865700 Ridhima Hire Me Full Night
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
 
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
Bus tracking.pptx ,,,,,,,,,,,,,,,,,,,,,,,,,,
 

R&M Extends Thermal Power Plant Life

  • 1. RENOVATION & MODERNIZATION IN THERMAL POWER STATIONS Another 30 Years !! SANTOSH PARDHI Deputy Manager Adani Infra (India)Ltd. 1
  • 2.          The requirement of power is felt as an important input for economic growth, more so in a power deficit scenario like India. Old operating units lose efficiency and capacity due to aging. New boilers are more expensive and take longer to install. Disposal of old operating boiler plant is a problem. Renovation and modernization of older units is one of the least cost effective means of generating additional power. Fuel availability changes over years of operation . Pressure Parts need replacement to ensure safe operation after certain length of operation Re-powering can increase the cycle efficiency and hence reduce emission of greenhouse gases and pollutants Operating pressure and temperature of these old plants are lower and there is no reheating in some of the units 2
  • 3.         R&M will involve up gradation of milling system, APH, ESP, firing system etc and refurbishment of turbine, condenser, pressure parts, fans etc. R&M may involve following changes in plant design : • Adoption of higher steam parameters . • Introduction of topping cycle, old turbine may be retained in bottoming cycle. • Bottoming turbine cycle efficiency improvement by adoption of high efficiency blade design New Plants –costly. Longer gestation period of new plant. Limited availability of new site. Old plants can be renovated and Modernised at lower costs and life extension achieved. Availability and efficiency can be improved. Pressure Part replacements that make use of improved materials and redesign of heat transfer surface for extended boiler life. 3
  • 4.        R&M solutions cost just a third of a new boiler in terms of cost & time Improve performance by introduction of new technology. To upgrade the units to comply with fast changing Environmental / statutory standards / guidelines. Clean Coal Technology to reduce . SOX ,NOX & CO2 Emissions Sub Critical Steam Parameters To Supercritical Parameters Increase in Pressure and temperature to like 250bar and 565 deg C. Re-powering Technology For better efficiency, pollution control and less cost besides life extension Minimum environmental impact and R&R problems for additional capacity. Renovation & Modernization of old existing units is an important tool for capacity enhancement, life extension and improvement in availability, reliability & efficiency 4
  • 5.        Operational History & Problems being faced to run the plant. Major modifications carried out from the original design condition. Age of the plant, its existing condition and generic problems in its inherited design Collect all engineering as build drawing and sketches. Model the existing boiler plant based on original design data . Input current operating condition to verify the model. Input revised (new) operating conditions . 5
  • 6.  BOILER & AUXILIARIES ◦ Replacement/Augmentation Of Pressure Parts. ◦ Retrofitting/ Modifications Air Pre Heater. ◦ Augmentation Of Milling System. ◦ Provision Of Flame Scanners, ignitors. ◦ Renovation of Draft System. ◦ Retrofitting Of ESPs.  TG & AUXILIARIES ◦ Replacement of turbine blades with latest design. ◦ Modernization of condensers by change in type and material of tubes, augmenting with tube cleaning mechanism. ◦ Modernisation of power cycle equipment's with more efficient pumps and improved Regenerative Heaters. ◦ Modification of air evacuation system with Vacuum pumps. 6
  • 7. 7
  • 8. 8
  • 10. 10