SPECIFICATIONS OF
BUILDINGS
Table of Contents
 Definition
 Purpose
 Factors
 Classification
 General Specifications for buildings
 General Specifications for roads
 Detailed Specifications for buildings
Definition
• Describes the nature and class of work,
materials to be used in work etc.
• Describe quantity of materials,
proportion of mortar, workmanship etc.
which are not mentioned in drawings.
• Drawings and Specifications
collectively define the full structure.
Purpose of giving Specifications
•The cost of an unit quantity of work is governed by its specifications.
•Specification of a work is required to describe the quality and quantity of different
materials required for a construction work and is one of the essential contract
documents
•This also specifies the workmanship and the method of doing the work. Thus
specification of a work serves as a guide to a supervising staff of a contractor as well
as to the owner to execute the work to their satisfaction.
•A work is carried out according to its specification and the contractor is paid for the
same. Any change in specification changes the tendered rate.
•As the rate of work is based on the specification, a contractor can calculate the rates
of various items of works in tender with his procurement rates of materials and labour.
Thus tender rate without specification of works is baseless, incomplete and invalid.
•Specification is necessary to specify the equipment tools and plants to be engaged for
a work and thus enables to procure them beforehand.
•The necessity of specification is to verify and check the strength of materials for a
work involved in a project.
Factors
The factors on which specifications
depend upon are mentioned below :
• Nature of the work
• Strength of materials
• Availability of materials
• Quality of Materials
Classification
Specifications are of two types :
• General or Brief Specification : It is different for
different classes of buildings i.e.
◦ First Class
◦ Second Class
◦ Third Class
◦ Fourth Class
• Detailed Specifications
General Specification
(for First Class Buildings)
Foundation and Plinth :
DPC : 1:1.5:3 cement concrete of 1” thickness
with standard water proofing material
mixed with cement and two coatings of
bitumen
General Specifications
(Foundation and Plinth)
First Class
Buildings
Ist class
brickwork
in 1:6
cement
mortar
Over
1:4:8
cement
concrete
Second Class
Buildings
Ist class
brickwork
with lime
mortar over
Lime
concrete
Third Class
Buildings
IInd class
brickwork in
lime mortar
over lime
concrete
Fourth Class
Buildings
Sun-dried or
kutcha
bricks in
mud mortar
General Specifications
(Damp Proof Course)
First Class
Building
1:1.5:3
cement
concrete of
with
standard
water
proofing
material
mixed with
cement and
bituminous
material
Second
Class
Building
1:2 cement
mortar of
1” thickness
2cm
thickness
water
proofing
material
Third
Class
Building
1:2 cement
with standard mortarof
2cm
thickness with
standard
water
Fourth
Class
Building
---
General Specifications
(Superstructure )
First
Class
Building
First class
brickwork
with 1:6
cement
mortar.
Lintels over
doors and
windows
shall be of
RCC.
Second
Class
Building
Second class
brickwork in
lime mortar.
Lintels over
doors and
windows shall
be of RB.
Third
Class
Building
Second class
brickwork in
mud mortar.
Doors and
window
openings
provided with
arches of
second class
brickwork in
lime mortar or
wooden planks
Fourth
Class
Building
Sun-dried or
kutcha bricks in
mud mortar.
Doors and
window
openings
provided with
arches of
second class
brickwork in
lime mortar or
wooden planks
General Specifications
(Roofing)
First
Class
Building
Height of
rooms shall
not be less
than 12’.
Over RCC
slab
insulation
layer should
be provided.
Second
Class
Building
R.B. slab with
7.5cm lime
concrete
terracing above
Third
Class
Building
Mud over
bricks or
planks over
OR G.I. sheet
wooden beams
Fourth
Class
Building
Tile roof over
wooden beams
bambooand
wooden
supports
General Specifications
(Flooring)
First
Class
Building
2.5cm
cement
concrete
over 7.5cm
lime
concrete
Class
Building
2.5cm cement
concrete over
7.5cm lime
concrete.
Verandah floor
shall be of
brick tile over
lime concrete
Second
Class
Building
Brick on edge
floor over well
rammed earth
Fourth
Class
Building
Kutcha floor or
earthen floor
finished with
cow-dung
lapping.
Third
General Specifications
(Roads)
Subgrade : Well consolidated and
compacted with camber 1 in 60
Soiling : Minimum 1’ wider than metaled
width of road with –
◦ Over burnt bricks filled up with sand and 1”
thick earth lightly compacted
◦ Stone boulders 6” thick well packed and
compacted earth over it
Inter Coat and Top Coat : Stone ballast
or over burnt brick ballast of 4.5” and
consolidated as well as compacted to 3”
General Specifications
(Roads)
Bitumen first coat : Stone grit of 20mm
gauge at 220 kg asphalt or Tar no.3 and 1.35
cum stone grit per 100 sqm.
Bitumen second coat : Stone grit of 12mm
gauge at 120 kg asphalt and 0.75 cum stone
grit per 100 sqm.
Brick Edging : Over burnt bricks on both
sides
Misc. :
◦ For heavy traffic wearing surface may be
provided with cement concrete
◦ If subgrade is soft or weak well compacted
thick sub base of inferior materials to be used
Detailed Specifications
The detailed specifications form a part of a contract document. They
specify the qualities, quantities and proportions of materials and the
method of preparation and execution for a particular item of works in a
project. The detailed specifications of the different items of the work are
prepared separately and they describe what the work should be and how
they shall be executed. While writing the detailed specifications, the same
order sequence as the work is to be carried out is to be maintained.
RCC (reinforced Cement Concrete) Specifications
Specifications for Brick masonry in Cement Mortar
Specifications for Plain Cement Concrete (PCC)
RCC Specifications
•Shuttering shall be done using seasoned wooden boards of thickness not less than
30mm.
•Surface contact with concrete shall be free from adhering grout, nails, splits and other
defects.
•All the joints are perfectly closed and lined up.
•The shuttering and framing is sufficiently braced.
•Nowadays timber shuttering is replaced by steel plates.
•All the props of approved sizes are supported on double wedges and when taken out,
these wedges are eased and not knocked out.
•All the framework is removed after 21 days of curing without any shocks or
vibrations.
•All reinforcement bars conform IS specifications and are free from rust, grease oil etc.
•The steel grills are perfectly as per detailed specifications.
•The covers to concrete are perfectly maintained as per code.
•The materials proportion should be as per the specifications of the concrete.
Number of Cement bags required for a specific cement concrete ratios
•For cement concrete of ratio 1:1:2(1 cement:1sand/coarse sand:2graded
stone aggregate) require 11no bags of 50kg.
•For cement concrete of ratio 1:1.5:3 require 7.8no bags of 50kg.
•For cement concrete of ratio 1:2:4 require 6 no bags of 50kg.
•For cement concrete of ratio 1:3:6 require 4.25no bags of 50kg.
•For cement concrete of ratio 1:4:8 require 3.2 no bags of 50kg.
•For cement concrete of ratio 1:5:10 require 2.50 no bags of 50kg.
•For cement concrete of ratio 1:6:12 require 2.25 no bags of 50kg.
Specifications for Brick masonry in Cement Mortar
•The bricks shall be of first class, regular in shape, size and colour.
•The bricks should be free from flaws, cracks and lumps of any kind.
•Shall have minimum crushing strength 10.5N/mm2.
•The bricks shall not absorb the water more than one sixth of the weight of the
brick.
•The sand used shall be medium coarse, clean, sharp, free from clay, mica and other
organic matter.
•The cement used shall satisfy the requirement of Bureau of Indian Standard.
•The mortar is designated in specified proportion of cement and sand. The
materials are weighed or measured and mixed on watertight platform after allowing
bulkage of sand.
•Bricks before laying shall be thoroughly soaked in water.
•The bricks laid truly horizontal in course with frogs upwards.
•The brickwork shall be raised 1m in height at a strength all round the building.
•Only fresh mortar within ½ hour for cement mortar, the time of adding water shall
be used.
•During rains, no brickwork is carried out when special arrangements are made.
•The brickwork shall be kept wet for atleast 10 days.
THANK YOU

More Related Content

Similar to specifications of buildings.pptx

Similar to specifications of buildings.pptx (20)

CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN) CONSTRUCTION PROCESSES  in CIVIL ENGINEERING (HISTORICAL AND MODERN)
CONSTRUCTION PROCESSES in CIVIL ENGINEERING (HISTORICAL AND MODERN)
 
General Specifications (Architecture)
General Specifications (Architecture)General Specifications (Architecture)
General Specifications (Architecture)
 
Specifications
SpecificationsSpecifications
Specifications
 
Specification and estimation
Specification and estimationSpecification and estimation
Specification and estimation
 
Proportions of concrete
Proportions of concreteProportions of concrete
Proportions of concrete
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
SPECIFICATION
SPECIFICATIONSPECIFICATION
SPECIFICATION
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Concrete
ConcreteConcrete
Concrete
 
Adv.Construction - assignement.pdf
Adv.Construction - assignement.pdfAdv.Construction - assignement.pdf
Adv.Construction - assignement.pdf
 
Creation of low cost Housing
Creation of low cost HousingCreation of low cost Housing
Creation of low cost Housing
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
concrete technology lecture notes for BTech students
concrete technology lecture notes for BTech studentsconcrete technology lecture notes for BTech students
concrete technology lecture notes for BTech students
 
Ppt on cement grade project
Ppt on cement grade projectPpt on cement grade project
Ppt on cement grade project
 
Conventional Construction : Concrete Construction
Conventional Construction : Concrete Construction Conventional Construction : Concrete Construction
Conventional Construction : Concrete Construction
 
Building construction/Unit 2 /Basic civil engineering
Building construction/Unit 2 /Basic civil engineeringBuilding construction/Unit 2 /Basic civil engineering
Building construction/Unit 2 /Basic civil engineering
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test
 
Concrete technology and masonry structures
Concrete technology and masonry structuresConcrete technology and masonry structures
Concrete technology and masonry structures
 

More from rakesh11032000 (7)

Building cracks for structural and non structural
Building cracks for structural and non structuralBuilding cracks for structural and non structural
Building cracks for structural and non structural
 
Disaster Preparedness and planning
Disaster Preparedness and planningDisaster Preparedness and planning
Disaster Preparedness and planning
 
The-Importance-of-Maintenance-in-Repair-and-Rehabilitation presentation.pptx
The-Importance-of-Maintenance-in-Repair-and-Rehabilitation presentation.pptxThe-Importance-of-Maintenance-in-Repair-and-Rehabilitation presentation.pptx
The-Importance-of-Maintenance-in-Repair-and-Rehabilitation presentation.pptx
 
Reinforcing steel cleaning presentation.pdf
Reinforcing steel cleaning presentation.pdfReinforcing steel cleaning presentation.pdf
Reinforcing steel cleaning presentation.pdf
 
Precast structure
Precast structure Precast structure
Precast structure
 
MOS Column.pptx
MOS Column.pptxMOS Column.pptx
MOS Column.pptx
 
Berlin.pptx
Berlin.pptxBerlin.pptx
Berlin.pptx
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 

Recently uploaded (20)

Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 

specifications of buildings.pptx

  • 2. Table of Contents  Definition  Purpose  Factors  Classification  General Specifications for buildings  General Specifications for roads  Detailed Specifications for buildings
  • 3. Definition • Describes the nature and class of work, materials to be used in work etc. • Describe quantity of materials, proportion of mortar, workmanship etc. which are not mentioned in drawings. • Drawings and Specifications collectively define the full structure.
  • 4. Purpose of giving Specifications •The cost of an unit quantity of work is governed by its specifications. •Specification of a work is required to describe the quality and quantity of different materials required for a construction work and is one of the essential contract documents •This also specifies the workmanship and the method of doing the work. Thus specification of a work serves as a guide to a supervising staff of a contractor as well as to the owner to execute the work to their satisfaction. •A work is carried out according to its specification and the contractor is paid for the same. Any change in specification changes the tendered rate. •As the rate of work is based on the specification, a contractor can calculate the rates of various items of works in tender with his procurement rates of materials and labour. Thus tender rate without specification of works is baseless, incomplete and invalid. •Specification is necessary to specify the equipment tools and plants to be engaged for a work and thus enables to procure them beforehand. •The necessity of specification is to verify and check the strength of materials for a work involved in a project.
  • 5. Factors The factors on which specifications depend upon are mentioned below : • Nature of the work • Strength of materials • Availability of materials • Quality of Materials
  • 6. Classification Specifications are of two types : • General or Brief Specification : It is different for different classes of buildings i.e. ◦ First Class ◦ Second Class ◦ Third Class ◦ Fourth Class • Detailed Specifications
  • 7. General Specification (for First Class Buildings) Foundation and Plinth : DPC : 1:1.5:3 cement concrete of 1” thickness with standard water proofing material mixed with cement and two coatings of bitumen
  • 8. General Specifications (Foundation and Plinth) First Class Buildings Ist class brickwork in 1:6 cement mortar Over 1:4:8 cement concrete Second Class Buildings Ist class brickwork with lime mortar over Lime concrete Third Class Buildings IInd class brickwork in lime mortar over lime concrete Fourth Class Buildings Sun-dried or kutcha bricks in mud mortar
  • 9. General Specifications (Damp Proof Course) First Class Building 1:1.5:3 cement concrete of with standard water proofing material mixed with cement and bituminous material Second Class Building 1:2 cement mortar of 1” thickness 2cm thickness water proofing material Third Class Building 1:2 cement with standard mortarof 2cm thickness with standard water Fourth Class Building ---
  • 10. General Specifications (Superstructure ) First Class Building First class brickwork with 1:6 cement mortar. Lintels over doors and windows shall be of RCC. Second Class Building Second class brickwork in lime mortar. Lintels over doors and windows shall be of RB. Third Class Building Second class brickwork in mud mortar. Doors and window openings provided with arches of second class brickwork in lime mortar or wooden planks Fourth Class Building Sun-dried or kutcha bricks in mud mortar. Doors and window openings provided with arches of second class brickwork in lime mortar or wooden planks
  • 11. General Specifications (Roofing) First Class Building Height of rooms shall not be less than 12’. Over RCC slab insulation layer should be provided. Second Class Building R.B. slab with 7.5cm lime concrete terracing above Third Class Building Mud over bricks or planks over OR G.I. sheet wooden beams Fourth Class Building Tile roof over wooden beams bambooand wooden supports
  • 12. General Specifications (Flooring) First Class Building 2.5cm cement concrete over 7.5cm lime concrete Class Building 2.5cm cement concrete over 7.5cm lime concrete. Verandah floor shall be of brick tile over lime concrete Second Class Building Brick on edge floor over well rammed earth Fourth Class Building Kutcha floor or earthen floor finished with cow-dung lapping. Third
  • 13. General Specifications (Roads) Subgrade : Well consolidated and compacted with camber 1 in 60 Soiling : Minimum 1’ wider than metaled width of road with – ◦ Over burnt bricks filled up with sand and 1” thick earth lightly compacted ◦ Stone boulders 6” thick well packed and compacted earth over it Inter Coat and Top Coat : Stone ballast or over burnt brick ballast of 4.5” and consolidated as well as compacted to 3”
  • 14. General Specifications (Roads) Bitumen first coat : Stone grit of 20mm gauge at 220 kg asphalt or Tar no.3 and 1.35 cum stone grit per 100 sqm. Bitumen second coat : Stone grit of 12mm gauge at 120 kg asphalt and 0.75 cum stone grit per 100 sqm. Brick Edging : Over burnt bricks on both sides Misc. : ◦ For heavy traffic wearing surface may be provided with cement concrete ◦ If subgrade is soft or weak well compacted thick sub base of inferior materials to be used
  • 15. Detailed Specifications The detailed specifications form a part of a contract document. They specify the qualities, quantities and proportions of materials and the method of preparation and execution for a particular item of works in a project. The detailed specifications of the different items of the work are prepared separately and they describe what the work should be and how they shall be executed. While writing the detailed specifications, the same order sequence as the work is to be carried out is to be maintained. RCC (reinforced Cement Concrete) Specifications Specifications for Brick masonry in Cement Mortar Specifications for Plain Cement Concrete (PCC)
  • 16. RCC Specifications •Shuttering shall be done using seasoned wooden boards of thickness not less than 30mm. •Surface contact with concrete shall be free from adhering grout, nails, splits and other defects. •All the joints are perfectly closed and lined up. •The shuttering and framing is sufficiently braced. •Nowadays timber shuttering is replaced by steel plates. •All the props of approved sizes are supported on double wedges and when taken out, these wedges are eased and not knocked out. •All the framework is removed after 21 days of curing without any shocks or vibrations. •All reinforcement bars conform IS specifications and are free from rust, grease oil etc. •The steel grills are perfectly as per detailed specifications. •The covers to concrete are perfectly maintained as per code. •The materials proportion should be as per the specifications of the concrete.
  • 17. Number of Cement bags required for a specific cement concrete ratios •For cement concrete of ratio 1:1:2(1 cement:1sand/coarse sand:2graded stone aggregate) require 11no bags of 50kg. •For cement concrete of ratio 1:1.5:3 require 7.8no bags of 50kg. •For cement concrete of ratio 1:2:4 require 6 no bags of 50kg. •For cement concrete of ratio 1:3:6 require 4.25no bags of 50kg. •For cement concrete of ratio 1:4:8 require 3.2 no bags of 50kg. •For cement concrete of ratio 1:5:10 require 2.50 no bags of 50kg. •For cement concrete of ratio 1:6:12 require 2.25 no bags of 50kg.
  • 18. Specifications for Brick masonry in Cement Mortar •The bricks shall be of first class, regular in shape, size and colour. •The bricks should be free from flaws, cracks and lumps of any kind. •Shall have minimum crushing strength 10.5N/mm2. •The bricks shall not absorb the water more than one sixth of the weight of the brick. •The sand used shall be medium coarse, clean, sharp, free from clay, mica and other organic matter. •The cement used shall satisfy the requirement of Bureau of Indian Standard. •The mortar is designated in specified proportion of cement and sand. The materials are weighed or measured and mixed on watertight platform after allowing bulkage of sand. •Bricks before laying shall be thoroughly soaked in water. •The bricks laid truly horizontal in course with frogs upwards. •The brickwork shall be raised 1m in height at a strength all round the building. •Only fresh mortar within ½ hour for cement mortar, the time of adding water shall be used. •During rains, no brickwork is carried out when special arrangements are made. •The brickwork shall be kept wet for atleast 10 days.