2. QUALITY ASSURANCE PLAN Doc. NO. CONTRACTOR /
PANORAMA/QAP/MAT
Project : GOLDEN PANORAMA Luxury Apartments at BANGALORE.
CLIENT : M/s. Golden Gate Properties Pvt. Ltd. Rev. – 0
PMC: FBA Consulting PMC
QUALITY ASSURANCE PLAN – MATERIAL
S.
No.
Material Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency of
test
Code of
Confirmation
1
Borrowed
Soil, Natural
Soil
- MDD
I S – 2720
-Per Source - Review of test reports
I S – 2720
Compacted
Earth
- OMC
- FDD
- Per 250 M2 forroad work
- Per 100M3 Back filling
- Review of test reports
- Random Witness
2 Cement
(Physical Test )
- Initial Setting time
- Final Setting Time
- Compressive Strength
- Consistency of standard
cement Paste
- Fineness
- Soundness
IS – 4031
- To be procured from
approved Make.
- Submission of MTC
- Per source of Brand /
- Per Week No./
- Per 1000 bag receiving
- Review of MTC & Test
reports IS – 8112-1989
3. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency
of test
Code of
Confirmation
Cement
- (Chemical Test )
- Lime Saturation Factor
- Ratio of Alumina to
Iron Oxide
- % Insoluble Residue
- % magnesia
- %Sulphuric
Anhydride
- % Loss of Ignition
- Chloride
- Tri calcium Aluminate
IS – 4031
- To be procured from
approved Brand
- Submission of MTC
- Per Source of Brand
- Review of MTC & Test
Reports
IS – 8112-1989
3
Stone
Aggregate
20 mm &
10 mm
- Deleterious Material
IS : 2386-
1963
Once Per Source
- Review of test reports
- Random Witness
IS : 393-1970
- Sieve Analysis
- Specific Gravity
- Surface Moisture
- Organic Impurities
50 M3 Receiving
- Crushing Value
- Abrasion Value
- Aggregate Impact
Value
- Flakiness Index
- Elongation Index
Weekly
4. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency
of test
Code of
Confirmation
4 Sand
- Specific Gravity
IS : 2386-1963
- Once Per Source
- Review of test reports
- Random Witness
IS: 383-1970
- Sieve Analysis
- Organic Impurities
- Bulking of sand
- 50 M3 Receiving
- Silt Content CPWD
Specification
- Per Lot CPWD
Specifications
5
Cement
Concrete
- Slum
- Compressive Strength
- Per 20 Cum
- As Per IS 456 : 2000
- Witness
- Review Test Report
6 Steel
- (Physical Test)
- Dimension & Unit weight
- Ultimate tensile Strength
- 0.2% Proof Stress
- Elongation %
- Bend & rebend test
- (Chemical Test)
- Carbon,
- Sulpher
- Phosphorus
- Sulpher+Phosphorous
IS: 1608-1972
IS : 1599-1974
- Submission of MTC
- Once per Brand /
- Once per Batch/
- Once Per 50 Mt
Review of MTC & test
reports
IS : 1786-2008
7 Bricks
- Dimensional Tolerance
- Water Absorption
- Compressive Strength
- Efflorescence
IS: 3495-1976 - Per Source/
- Per Brand /
- Per 10,000 Bricks
- Review of Test reports
- Random Witness IS : 1077-1976
8
Water
(construction
Purpose )
All Tests as per IS : 456 IS – 3025 - Per Source
- Every 3 Month
- Review of test reports IS : 456
5. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency of
test
Code of
Confirmation
9 Anti Termite
All tests as per IS : 8944 IS – 6313 - Submission of
MTC
- Per Brand
Review of MTC & test
reports
IS – 8944
10
EPDM Water
Proofing &
HDPE Board
- Thickness,
- Unit Weight
- Tensile Strength
- Ultimate Elongation %
- Water Absorption
- Tearing resistance
- Liner Dimension
Change
- Hardness
- Puncture resistance
ASTM
D412
D471
D624’
D 1204
D 2240
E 154
- To be procured from
approved Make.
- Submission of MTC
- Per Brand/
- Per 1000 M²
Review of MTC & Test
reports
ASTM
D412
D471
D624’
D 1204
D 2240
E 154
12 Admixture
- Workability
- Setting Time
- Bleeding
- Air Permeability
- Compressive Strength
- Flexural strength
- Chemical composition
IS- 9103 - To be procured from
approved Make.
- Submission of MTC
- Per 1 Tonne
Review of test reports &
MTC
IS- 9103
13 RCC Pipe
- Permeability
- Dimensional Test
- Hydrostatic Pressure
- Water Absorption
IS – 458
- Submission of MTC
-Factory Testing
Per Dia /
Per 100 Rm
Review of MTC & test
reports
Randomly Witness
IS – 458
6. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency
of test
Code of
Confirmation
14
Bitumen
Impregnated
fiber board
- Compression
- Extrusion
- Water Absorption
- Density
- Bitumen Content
IS : 10566-
1983
- Per Batch
- Per 100 Sqm
Review of test reports IS : 1838
15
Glazed Tiles/
Vitrified tiles
/Alkali
Resistance
Tile
- Dimensions and surface
Quality
- Physical Properties
- Chemical Properties
IS : 777 / IS :
13630
To be procured from
approved Make.
Per Batch /
Per 3 000 Nos
Review of test reports IS :4457
IS :15622
IS:13712
16
Marble/
Granite /Kota
Stone
- Thickness
- Moisture Absorption
- Hardness
- Specific Gratuity
IS : 1122-1974
IS : 1124-1974
Per Type
Per 100 sqm/
Per lot receiving.
Review of test reports IS : 1130-1969
IS : 3316
7. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role
/ Frequency of test
PMC Role /
Frequency of test
Code of
Confirmation
17
Footpath
Tiles/ Paver
Blocks
- Water absorption
- Crushing strength
- Hardness
Relevant IS
Code
- Per Branch/
- Per 10,000 Nos
Review of test report IS : 15638
18
Wood / Door
Frame
- Moisture Content As per CPWD
specification
IS : 3364
- Per Source /
- Per 1 Cum
Review of Test reports IS : 190-1974
19 Flush Door
- End Immersion test
- Knife Test
- Glue adhesion test
IS 2202
Appendix F
- Per Brand/
- Per 50 Nos
Review of Test reports IS 2202:1999
20 Mortice Lock
- Testing of Spring IS 2209
Appendix ‘G’
- Per Brand
- Per 100 Nos
Review Test Reports IS 2202
21 Glass
- Distribution of
Allowable Defects
(Gaseous Inclusions,
Open Gaseous
Inclusions, Knots,
Dirts and Stones,
Scratches, Rubs and
Crush, Reams, Strings
and Lines, Waviness,
Sulphur Stains,
Corner Breakage and
Chip)
- Cluster of defects
- Thickness
- Warp
- Fragmentation Test
- Resistance to Shock
Test
-
IS: 2835-1987
IS: 2835-1987
IS: 2553-1990
IS: 2553-1990
IS: 2553-1990
IS: 2553-1990
To be procured from
approved Make.
Submission of MTC
Per 500 Sqm
Review of MTC & test
reports
Relevant IS Code
8. 22
Laminated
Sunmica
- Resistance to
immersion boiling
water
- Resistance to dry heat
- Dimensional Stability
- Resistance to impact
- Resistance to
Scratching
- Resistance to stem
IS 2046 To be procured from
approved Make
Submission of MTC
Per 1000 Sqm
Review of MTC & test
reports
IS 2046:1995
23
Aluminum
sections
- Thickness of anodic /
powder coating
- 0.2% proof stress,
- Tensile strength
- Elongation
Relevant IS
Code
- To be procured from
approved Make.
- Per Brand /
- Per 5 MT
Review of Test
Reports
IS:733-1975
IS : 1285-1975
24 Stainless steel
- Tensile Strength
- Yield Stress
- Elongation
- Mass per meter
IS: 1608-2005 To be procured from
approved Make.
Submission of MTC
Per 5 MT
Review of MTC & test
reports
IS: 1608-2005
25 ACP
- Aluminum Thickness
- Compressive
Strength
- Tensile Strength
- Water resistance
- Fire Resistance
Relevant IS
Code
To be procured from
approved Make.
Submission of MTC
Per 500 Sqm
Review of MTC & test
reports
ASTM D-638
9. 26
Gypsum
Board for
false ceiling
- Dimension
- Transverse strength
- Mechanical &
Chemical Properties
of Supporting
material
IS : 2542-1981 To be procured from
approved Make.
Once for 1000 Sqm
Review of test reports IS : 2095-1982
27
Pre-coated
metal False
ceiling &
Panel
- Chemical Tests
- Mass of Zinc Coating
- Bend Test
- Pencil Hardness Test
- Impact Resistance
Test
- Cross Hatch Test
- Mechanical &
Chemical Properties
of Supporting
material
IS: 513:2008
IS277
To be procured from
approved Make.
Submission of MTC
Per 1000 Sqm
Review of MTC & test
reports
IS:14246-1995
10. S.
No.
Item Test to be carried out
Code of
Testing
CONTRACTOR Role /
Frequency of test
PMC Role / Frequency of
test
Code of
Confirmation
28
Coarse
Aggregate for
(WBM,
Premix Carpet
Asphalt
Concrete)
- Gradation
- Los Angles Abrasion
Value
- Specific Gravity
- Water absorption
IS : 2386
BIS : 812
IS : 6241
Per Source
Per 50 Cum
Review of Test reports
Randomly witness
IRC/ Morth
29
Binder
(Bitumen )
- Specific Gravity
- Flash Point
- Softening Point
- Penetration
- Ductility
- Loss on heating
IS: 1202-1978
IS: 1209-1978
IS: 1205-1978
IS: 1205-1978
IS: 1208-1978
IS: 1212-1978
Submission of MTC
Per source
Review of MTC & test
reports
IS : 73-1961
30
Open graded
carpet / BM/
BC
- Job Mix
- Sieve Analysis
- Temperature
- Marshal stability
- Flow Value test
- Percent Air voids
- Density of compacted
layer
MORTH Submission of job mix
design
Core test per 250 Sqm
Review of Test reports
Randomly witness
IS : 73/
MORTH
31
Kerb stone
- Transverse Strength
- Water Absorption
Appendix-A
Appendix-B
To be procured from
approved Make.
Submission of MTC
Per 1000 Nos
Review of MTC & test
reports
IS: 5758-1984
11. 32 GI pipe
- Dimensions
- Mass per meter
- Visual Test
- Uniformity of Zinc
Coating
- Adhesion Test
- Tensile Strength
- Elongation on guage
length
- Bend Test
- Mass of Zinc Coating
- Chemical Analysis
IS: 1239(Pt-I)-
2004
IS:2629-1985
IS:2633-1986
IS:2629-1985
IS:1608-2005
IS:1608-2005
IS:2329-1985
IS:6745-1972
IS: 228
To be procured from
approved Make
Submission of MTC
Per Dia.
Per 1000 Rmt
Review of MTC & test
reports
IS: 1239-2004
IS: 4736-1986
33 CI Pipe
- Hammer Test
- Brinell Hardness Test
- Hydrographic Test
- Dimension Test
- Coating Test
IS 1500 To be procured from
approved Make
Submission of MTC
Per Dia.
Per 1000 Rmt
Review of MTC & test
reports
IS: 3989-1984
34 SW pipe
- Hydrographic Test
- Water Absorption
- Resistance to acids
- Resistance to alkalies
- Crushing Strength
- Dimensions
IS: 651-1992 To be procured from
approved Make
Submission of MTC
Per Dia.
Per 1000 Rmt
Review of MTC & test
reports
IS: 651-1992
35 PVC pipe
- Dimensions
- Visual Appearance
- Opacity
- Effect on Water
- Reversion Test
- Density
- Sulphated Ash
IS: 4985-2000 To be procured from
approved Make
Submission of MTC
Per Dia.
Per 1000 Rmt
Review of MTC & test
reports
IS: 12235
IS: 133660
12. - Hydrostatic Pressure
36 CPVC pipe
- Dimensions
- Visual Appearance
- Flattening Test
- Hydrostatic Pressure
Test
- Reversion Test
ASTM D2846
ASTM D2846
ASTM D2846
ASTM D2846
IS: 12235
To be procured from
approved Make
Submission of MTC
Per Dia
Per 1000 Rmt
Review of MTC & test
reports
ASTM D
2846
IS: 4985-2000
37 HDPE pipe
- Dimension Test
- Construction
- Compression Test
- Impact Test
- Bend Test
Relevant IS
Code
To be procured from
approved Make
Submission of MTC
Per Dia.
Per 1000 Rmt
Review of MTC & test
reports
IS: 14930
14. INDEX
SL.
NO.
Name Of Activity Document No.
1 Inspection and test plan for Surveying. PANORAMA/ITP-CIVIL/01
2 Inspection and test plan for Earthwork. PANORAMA/ITP-CIVIL/02
3
Inspection and test plan for Filling of earth/ Borrowed
earth.
PANORAMA/ITP-CIVIL/03
4 Inspection and test plan for PCC PANORAMA/ITP-CIVIL/04
5 Inspection and test plan for RCC (Sub- Structure) PANORAMA/ITP-CIVIL/05
6 Inspection and test plan for RCC (Super- Structure) PANORAMA/ITP-CIVIL/06
7 Inspection and test plan for Brick Work PANORAMA/ITP-CIVIL/07
8 Inspection and test plan for Plastering Work PANORAMA/ITP-CIVIL/08
9 Inspection and test plan for Flooring Work PANORAMA/ITP-CIVIL/ 09
10. Inspection and test plan for Doors/Windows PANORAMA/ITP-CIVIL/10
11 Inspection and test plan for Painting Work PANORAMA/ITP-CIVIL/11
12 Inspection and test plan for False Flooring PANORAMA/ITP-CIVIL/12
15. INSPECTION AND TEST PLAN Doc No. PANORAMA/ITP-
CIVIL/01
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. – 00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR SURVEYING
S.
No.
Activity/ Description
CONT
RACT
OR
PMC
Documents to be
submitted
1 Calibration certificates of Survey Equipments WC RW Calibration Certificate
2
Establishment of control pillars & Bench
Marks.
WC S
3 Co-ordinates of Control Points. WC W
4 Checking Layout & Level. WC S Level Book
5
Preparation of Drawing of Spot levels and
layout WC S
Drawing
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
16. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/02
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No.-00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR EARTH WORK
S.
No.
Activity/ Description CONTRACTOR PMC Documents to
be submitted
1 Marking for Excavation WC S
2 Taking Initial Ground Levels WC W Level Book
3
Barricading of area and other safety
measures
WC S
4
Check existing service/ obstacle
encountered (cables pipes, conduits Etc.)
WC W
5
Slope of Excavation, benching &
Overburden
WC S
6
Check for Subsoil water & dewatering if
required
WC S
7 Excavation WC S
8
Dressing of bottom level of excavation &
Compaction
WC W
9
Checking the excavated levels as per
drawing
WC W Level Book
10 Dressing & leveling of disposed soil WC S
11 Disposal of debris, if found WC W Joint record
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
17. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/03
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
Rev. No. – 00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR FILLING OF EARTH/
BORROWED EARTH
S.
No.
Activity/ Description CONTRACTOR PMC
Documents to be
submitted
1
Approval of material/ selected earth
for filling
WC S MDD Test Report
2 Check for treatment of soil, if any WC W
3
Check initial ground levels before
start of filling
WC S Level Book
4
Filling the soil in specified layers,
watering & compaction of soil
WC RW
5
Review of Calibration Certificate of
testing instruments
WC RW
Calibration
Certificate
6
Compaction test (FDD) for each
layer for specified area as per QAP.
WC S
N005-06/ F-13,F-
20
7
Filling to required level, check the
top level as per approved
construction Joint.
WC S Level Book
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
18. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/04
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR PLAIN CEMENT
CONCRETE
S.
No.
Activity/ Description CONTRACTOR PMC Documents to be
submitted
1
Checking layout and compaction of sub
grade.
WC S
MTC/ Lab and
Field test Report -
N005-06/F-13,
N005-06/F-23.
2 Checking of material including water WC S
3
Calibration of weigh batcher/ batching
plant
WC W Calibration Report
4
Mix Proportion & use of water proofing
material if any
WC S
5 Check for shuttering , dewatering if any WC W N005-06/F-19
6
Checking of level pads and reduced
levels as per drawing
WC W
7 Concreting works as per specification. WC S
8
Finishing & checking of top level and
thickness of PCC
WC W N005-06/F-19
9 Curing WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
19. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/05
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR RCC (Sub-Structure)
S.
No.
Activity/ Description CONTRACTOR PMC
Documents to be
submitted
1 Approval of materials WC W
MTC/ Test
Reports
2
Calibration certificate of instruments,
testing equipments
WC RW
3
Checking of layout & condition of
underneath PCC/ Leveling course
WC W
5
Confirmation of Mix proportion after
Design of mix & trial Mix at site.
WC RW/HP Mix design
6
Check for Sub-soil water & dewatering
arrangement, if any
WC S
7
Check for line & level of shuttering
with shutters condition including
number of repetition, Cleaning &
Oiling properly to each shutter/board
and its rigidity.
WC S
8 Verification of dimensions WC W
9
Reinforcement & covers to
reinforcement
WC W
10
Inserts Anchor bolts & Pipe sleeves,
pockets, dowels etc.
WC S
11
Check for obstacle encountered
(Electrical conduits, pipeline etc.)
WC S
12 Submission of pour card WC HP N005-06/F-19
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
20. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/05
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
S.
No.
Activity/ Description CONTRACTOR PMC
Documents to be
submitted
13 Check for pouring arrangement WC S
14
Check for safety and lighting
arrangements
WC S
15
Concreting, testing, compaction &
finishing
WC S
16 Checking of Slump WC W
17 Casting of Cubes WC W
18 Curing for a period of 14 days WC S
19 Testing of cubes WC W N005-06/F-08
20 Removal of shuttering WC S
21
Check for water tightness, rendering if
any
WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
21. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/06
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTIONAND TEST PLAN FOR RCC (SUPER STRUCTURE)
S.
No
.
Activity/ Description
CONT
RACT
OR
PMC
Documents to be
submitted
1.
Approval of materials
WC RW MTC & Test Reports
2.
Concept & design of Shuttering
WC RW Shuttering Design
3.
Checking of layout.
WC S
4.
Proper chipping of construction joint removing
all loose aggregate. Applying jointing material
over construction joint if any.
WC S
5.
Mix design/Ready mix concrete
WC RW/ HP
Lab report of Mix
Design
6.
Check the alignment including size &
diagonals of shutting and level of shuttering.
Check condition of ply & plates. Cleaning and
oiling to shuttering. Filling gaps if any. Ensure
sufficient wooden/MS battens to the ply.
Confirm proper supporting arrangement.
WC S
7.
Check scaffolding includes size/ thickness of
members & spacing between members as per
given design. Verticality of vertical members
(Props), firm Horizontal/cross bracing, Jacks
are properly tighten, base plates supports on
firm surface. Hoisting arrangements.
WC S
8.
Check for Rubber liner shuttering if any
WC S
9.
Verification of dimensions
WC S
10.
Reinforcement & cover to reinforcement
WC W
11.
Inserts, bolts, pipe sleeves, MS rungs,
concealed electrical conduits, fan hooks,
dowels, etc. including welding if any
WC S
22. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/06
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
S.
No.
Activity/ Description CONT
RACT
OR
PMC Documents to be
submitted
12. Pockets/ openings WC W
13. Expansion joints, if any WC S
14. Check for water stops, slopes, stoppers, if any WC S
15.
Ensure proper functionality all electrical &
mechanical equipments viz. concrete pump,
transit mixers, Vibrators & Nozzles etc.
WC S
16.
Check for safety and lighting arrangements
WC S
17. Filling of Pour Card WC HP N005-06/F-19
18. Check for pouring arrangement in case of RMC WC S
19. Concreting, testing, compaction & finishing WC S
20. Checking of Slump WC W
21. Casting of cubes WC W
22. Curing for a period of 14 days WC S
23. Testing of cubes WC W
24. Removal of formwork/ staging WC S N005-06/F-08,
25. Hacking the exposed surface if necessary WC S
26. Check for water tightness, rendering, if any WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
23. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/07
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INPECTION TEST PLAN FOR BRICK WORK
S.
No.
Activity/ Description CONTRACTOR PMC
Documents to
be submitted
1. Approval of material WC W N005-06/ F-09.
2. Cleaning of surface WC S
3. Soaking of bricks WC S
4.
Cement mortar proportion/ Water cement
Ratio
WC S
6.
Check for thickness of Brick Work/
Locations of Doors & Window WC S
7. Staging & scaffolding WC S
8.
Hacking of concrete surface/Cement
Punning to the concrete surface.
WC S
9.
Check for bond/closers, thickness of joints,
and height of masonry work in a day.
WC S
10. Line, level & plumb. WC S
11. Reinforcement in Brick work as per SOR WC S
12. Raking out joints, keys in brick work, if
any.
WC S
13.
Check for RCC
bonds/Reinforcement/PCC flooring, in
case of partition brick work
WC S
14 Embedment of fixtures WC S
15 Curing for a period of 7 days WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
24. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/08
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR PLASTERING WORK
S.
No.
Activity/ Description CONTRACTOR PMC
Documents to be
submitted
1
Curing of area for plaster before 12 hours
of start of plaster work.
WC S
2
Approval of material
WC W
N005-06/ F-16, F-
22
3
Check for completeness of all hidden jobs
like piping, conducting.
WC S
4
Sample preparation for finish and its
approval.
WC W
5
Fixing of Chicken Mesh as applicable
WC W
6
Hacking and cleaning the surface,
removing loose particles, wetting the
surface.
WC S
7
Preparation of mortar as per SOR
including addition of water proofing
compound if necessary.
WC S
8
Checking level pads.
WC S
9
Checking thickness of plastering work,
plumb and even surface.
WC W
10
Check for grooves, openings, plumb and
even surface.
WC S
11
Curing for a period of 7 days
WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
25. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/09
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR FLOORING WORK
S.
No.
Activity/ Description CONTRACTOR PMC
Documents
to be
submitted
1 Cleaning the surface for flooring WC S
2
Approval of flooring material by shade,
colour & design pattern and field test
results also material for mortar.
WC RW/HP
Lab Reports,
N005-06/ F-
24, F-25
3
Checking thickness of Tiles / Marble /
Granite at site.
WC W
Register
4
Checking of underneath floor level &
Finished floor level as per drawing.
WC S
5
Check design pattern as per the drawing
of decorative/marble flooring before
actual lying.
WC S
6 Checking mortar proportion & thickness WC S
7
Checking the Joint & filling of required
colour pigments in joint
WC S
8
Checking the thickness of the flooring
Checking the Level/slope.
WC S
9 Laying of tiles/marble. WC S
10
Checking the polishing at required degree
/smoothness.
WC S
11 Curing for a period of 7 days WC S
12 Cleaning floored surface. WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
26. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/10
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR DOORS / WINDOWS
Sl.
No.
Activity/ Description CONTRACTOR PMC
Documents
to be
submitted
1 Checking the material and its test report WC RW
LAB
REPORT
2 Check for sections & dimensions WC W
3 Section joinery details WC S
4
Checking dimensions of the
window/Doors
WC W
5 Grouting with lugo/dash fasteners WC S
6 Checking of Hold Fasteners. WC S
7
Checking of anchorage and fixing of hold
fasteners & rubber gas kit
WC S
8 Check for thickness & type of glazing WC W
9 Checking of Pataam. WC W
10 Checking of Facia WC S
11 Checking of plumb/levels WC S
12
Shade of pints, no. of coats including
surface preparation.
WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
27. INSPECTION AND TEST PLAN Doc. No. PANORAMA
/ITP-CIVIL/11
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTION AND TEST PLAN FOR PAINTING
Sl
no.
Activity/Description CONTRACTOR PMC
Documents to be
submitted
1. Surface preparation WC S
2.
Firm scaffolding and covering of Floor
to avoid marks of paint on tiles.
WC S
3. Checking colour scheme WC RW/HP
4. Approval of material WC RW
Procurement from
approved make –
Purchase proof
5.
Checking type/Quality of
putty/primer/paint/putty.
WC S
6.
Checking and matching of colour
coats/pattern/texture. Uniformity in
appearance and desired finish.
WC S
7. Checking number of coats/thickness. WC S
8. Curing if required. WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
28. INSPECTION AND TEST PLAN Doc. No. PANARAMA
/ITP-CIVIL/12
PROJECT: GOLDEN PANORAMA Luxury Apartments
at BANGALORE.
CLINT : M/s. Golden Gate Properties Pvt. Ltd. Rev. No. -00
PMC : FBA Consulting PMC
INSPECTIONAND TEST PLAN FOR FALSE CEILING WORK
Sl
no.
Activity/Description
CONTRACTOR
PMC
Documents to be
submitted
1 Checking/testing of material WC W/RW
MTC/ Lab test
report
2 Checking of rendering of slab WC S
3. Clearance of services above false ceiling WC S
4. Checking of BoFC level as per drawing WC S
5.
Checking hanging arrangement & grid
arrangement
WC S
6 Fixing of false ceiling tiles WC S
7
Marking, cutting & fixing of electrical & AC
points as per drawing.
WC W
8 Checking of final leveling & alignment. WC W
9 Removal plastic coating in case of metal tiles WC S
10
Filling of joints & painting in case of gypsum
board
WC S
LEGEND
HP - HOLD POINT
WC - 100% EXAMINATION BY CONTRACTOR
W - WITNESS POINT
RM - RANDOM CHECKING
RW - REVIEW OF CONTRACTOR’S DOCMENTATION
S - SURVEILLANCE INSPECTION BY OWNER/PMC
29.
30. INDEX – TEST PROCEDURE
SR.
NO.
PROCEDURE NAME PROCEDURE NUMBER
1
DETERMINATION OF DRY DENSITY OF SOIL
BY CORE CUTTER METHOD
PANORAMA/TP - 01
2
PROCEDURE FOR COMPRESSIVE STRENGTH
TESTING OF CONCRETE
PANORAMA/TP - 02
3
PROCEDURE FOR DETERMINATION OF AGG.
CRUSHING VALUE
PANORAMA/TP - 03
4
PROCEDURE FOR DETERMINATION OF AGG.
ELONGATION INDEX
PANORAMA/TP - 04
5
PROCEDURE FOR DETERMINATION OF AGG.
FLAKINESS INDEX
PANORAMA/TP - 05
6
PROCEDURE FOR DETERMINATION OF AGG.
SPECIFIC GRAVITY & WATER ABSORPTION
PANORAMA/TP - 06
7
PROCEDURE FOR FIELD TEST TO
DETERMINE SILT CONTENT IN SAND
PANORAMA/TP - 07
8
PROCEDURE TO FILL CUBES OF FRESH
CONCRETE
PANORAMA/TP - 08
9
PROCEDURE FOR SAMPLING INSPECTION
TESTING OF RMC
PANORAMA/TP - 09
10
PROCEDURE FOR SEIVE ANALYSIS OF
COARSE AGGREGATE
PANORAMA/TP - 10
11
PROCEDURE FOR SEIVE ANALYSIS OF FINE
AGGREGATE
PANORAMA/TP - 11
12 PROCEDURE FOR SLUMP TEST PANORAMA/TP - 12
13
PROCEDURE FOR COMMON BURNT CLAY
BRICKS
PANORAMA/TP - 13
14
PROCEDURE FOR SAMPLING OF
AGGREGATE
PANORAMA/TP - 14
15 PROCEDURE FOR SAMPLING OF BRICKS PANORAMA/TP - 15
16
PROCEDURE FOR SAMPLING OF EARTH
SOW
PANORAMA/TP - 16
17
PROCEDURE FOR SAMPLING OF FRESH
CONCRETE
PANORAMA/TP - 17
18
PROCEDURE FOR DETERMINATION OF
WATER CONTENT OF SOIL SAMPLE
PANORAMA/TP - 18
31. DRY DENSITY OF SOIL IN PLACE BY
CORE CUTTER METHOD
Doc. No. /PANORAMA/TP-01
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
DETERMINATION OF DRY DENSITY OF SOIL IN PLACE
BY CORE-CUTTER METHOD
(I.S: 2720-XXIX)
Aim: To determine the field dry density of fine grained soil by using core cutter. It
is less accurate than Sand Replacement Method and recommended for well
Compacted soils.
Apparatus:
Core cutter / Dolly / Rammer.
Weigh balance of 1 g accuracy.
Pallet knife, Straight edge, Steel rule, Pick axe etc.
Soil sample is termed as fine-grained if 90% by weight passes through IS sieve
4.75 mm.
Procedure:
Internal Volume ( Vc, cm3 ) of core cutter shall be calculated by taking
Dimensions to nearest the 0.25 mm (By vernier).
Cutter shall be weighed to nearest g. ( Wc, g )
A small area, approximately 30 cms square of the soil layer to be tested shall
be exposed and leveled.
Cutter shall be placed vertically on soil with dolly on top.
Cutter shall be rammed down vertically into the soil layer until only about 15
mm of dolly protrudes above surface.
Care should be taken that cutter shall not rock sideways while hammering.
The cutter shall be dug out of surrounding soil by pick axe. Please take care so
as to have some protruding soil mass from the lower edge.
Soil from both the ends shall be trimmed flat to the ends of cutter.
The cutter containing soil mass shall be weighed to nearest g ( Ws, g )
The soil mass shall be removed from cutter and representative sample shall be
tested for water contents.
At least 3 tests are required to make an average result.
32. Remarks – Often, problem is encountered when soil mass is dry and cutter is not
properly filled up or loses soil while handling. In such case test is to be done
by sprinkling water and testing after suitable lapse of time. Core cutter shall be
removed, trimmed and kept in polythelene bag to take it to laboratory. It shall
be weighed with cutter and any loose soil mass collected in bag.
Calculations :
Bulk Density Yb of Wet Soil is as below:
Yb = ( Ws – Wc ) / Vc , gms /cm3
Dry Density Yd is as below:
Yd = 100 Yb / ( 100 + w ) , gms /cm3 Where w = Water content %
Format to be used:
N005-06/F-13
33. COMPRESSIVE STRENGTH TESTING
FOR CONCRETE
Doc. No. PANORAMA/TP-02
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE. Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR COMPRESSIVE STRENGTH TESTING FOR CONCRETE
Aim : To establish Compressive strength of concrete sample for acceptance.
Apparatus :
1. Compressive Testing Machine having adequate capacity.
2. Weighing Balance.
3. Measuring Scale.
Procedure :
Remove the cubes required for testing from curing tank. Wipe off water and
air dry them to surface dryness.
Stack cubes in sequence as per mix, dates, locations etc.
Record the actual surface area ( Sq cm)of the cube which will be in contact
with the platen of CTM ( A in Sqcm or Sqmm ).
Weigh the cubes and record the weights in the register in kg.
Place the cube on platen centrally keeping trowelled side in front.
Position the top platen on cube surface. See that there is no gap left between
cube top and platen.
Load the CTM at desired speed without any shocks. ( Pointer and needle shall
move together)
When crushing takes place in the specimen, needle will start falling back but
pointer will remain at maximum reading.
Record the reading shown by pointer viewing perpendicular to the face of
dial. ( Load applied in kN or tonne- W)
Relieve the load from CTM. Remove the cube. Clean the platens.
Check the features of cube failure. Good failure is when the cube mass
retained has concavity on sides. If failures are occurring consistently by crack
developing only on one side it means cubes are eccentrically loaded. If cracks
are always developed centrally means point load is getting applied due to
Convexity of platens. Remedial measures are required to be taken for this.
34. Calculations:
1. Compressive Stress ( c ) in N / mm2 or Kg / cm2 as below :
c = Wx1000 /A in N/mm2 or Kg /cm2
Average of the set of Three or more cubes to be recorded (c’ ).
2. When three or more cubes from single batch/lot is tested, max variation is
allowed +/- 15%. If any cube is showing more variation, result of that cube is
discarded and average of two or more is to be taken.
Recording :
Record is generated as per the sample format given in chronological order.
Format to be used:
Cube Register
Compression testing of cube testing - N005-06/F-08
35. AGGREGATE CRUSHING VALUE Doc. No. PANORAMA/TP-03
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR DETERMINATION OF AGGREGATE CRUSHING VALUE
( I.S : 2386-IV )
Aim:
To calculate aggregate Crushing value by testing aggregate passing 12.5 mm sieve
and retained on a 10 mm sieve. (This is an alternate method for Aggregate Impact
Value.)
Apparatus:
15 cm dia steel cylinder with plunger and base plate, tamping rod 16 mm dia and
600 mm long with one end rounded, Weighing balance of accuracy 1 g, Sieves 12.5
mm , 10 mm & 2.36 mm, Drying Oven, CTM
Procedure :
Take sample of aggregates by sieving through 12.5mm and retained on
10mm.
The aggregate shall be tested in surface dry condition. If dried by heating, the
period of drying shall not exceed 4 hours and temp shall be 100-110 deg C.
Sample shall be cooled down to room temperature before testing. Take
approximately 6 kgs of sample.
The quantity of the sample shall be such that the depth of material in the
cylinder after tamping shall be 10cms.
Cylinder shall be filled up in 3 layers and each layer shall be tamped 25 times
with tamping rod and finally leveled off.
The weight of material comprising the test sample shall be determined. ( A ),
g
The plunger shall be placed in position and the apparatus shall be then placed
between the platens of CTM.
36. Load shall be applied at uniform rate so that load of 40T is reached in 10
minutes.
The load shall be removed from the cylinder and sieved through 2.36 mm
Sieve. The fraction passing sieve 2.36 mm shall be weighed to nearest 1g.
Such two tests shall be taken.
Reporting:
Aggregate Crushing Value, % = (B / A) x100
The mean of the two results shall be reported to the nearest whole number.
Format to be used:
N005-06/F-03
37. ELONGATION INDEX OF AGGREGATE Doc. No. PANORAMA/TP-04
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR DETERMINATION OF ELONGATION INDEX OF
AGGREGATE
(IS: 2386 – I)
Aim:
To determine the Elongated shape of particles of Coarse Aggregate greater than 6.3
mm size.
Apparatus:
Balance with accuracy of 0.1% of weight of the sample, Elongation Index Gauge
All other as per Sieve analysis.
Sample:
It shall be taken from retained material from Sieve analysis preferably and should
Have at least 200 pieces of any fraction.
Procedure:
Each sample of 20mm and 10mm metal shall be taken from retained fraction.
Each fraction shall be gauged in turn for thickness on metal gauge.
The total amount passing the gauge shall be weighed.
Report:
The Elongation Index is the total weight of the material passing the various
Thickness gauges; expressed as a % of the weight of total sample gauged.
Format to be used:
N005-06/F-01
38. FLAKINESS INDEX OF AGGREGATE Doc. No. PANORAMA/TP-05
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR DETERMINATION OF FLAKINESS INDEX OF
AGGREGATE
(IS: 2386 – I)
Aim:
To determine the Flakiness of particles of Coarse aggregate greater than 6.3 mm
size.
Apparatus :
Balance with accuracy of 0.1% of weight of sample, Flakiness Index Gauge
All other as per Sieve analysis.
Sample :
It shall be taken from retained material from Sieve analysis preferably and should
have at least 200 pieces of any fraction.
Procedure :
Each sample of 20 mm and 10mm shall be taken from retained fraction.
Each fraction shall be gauged in turn for thickness on metal gauge.
The total amount retained on the gauge shall be weighed.
Report :
The flakiness Index is the total weight of the material passing the various
thickness gauges; expressed as a % of the weight of total sample gauged.
Format to be used:
N005-06/F-02
39. SILT CONTENT IN SAND Doc. No PANORAMA /TP-07
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR FIELD TEST FOR SILT CONTENT IN SAND
Aim : To determine Silt content in Sand by volumetric method field test.
Apparatus :
Measuring cylinder 250 ml, Common Salt.
Procedure :
Prepare 1% solution by mixing 10 gms of common salt in 1 litre of water.
Put this solution in measuring cylinder up to the mark of 50 ml.
Add Sand as received in the cylinder till its level reaches 100 ml.
Add Solution again so that the mixture reaches the level of 150 ml.
Cylinder top is now covered with the palm of hand and shaken vigorously by
turning upside down.
Then allow it to stand undisturbed for 3 hours.
Take reading for top layer of Silt ( A ) and layer of Sand ( B ).
Calculations :
Silt content % Volumetric = (A / B) x100
Reporting :
% Silt contain (Volumetric ) shall be reported in whole number.
Note : This method is approximate and conversion to weight basis ( which is
Acceptance criteria ) is dependent on fineness of material. However 8% volumetric
content is treated as reliable. It was suggested that weight ratio is obtained by
multiplying volumetric ratio by ¼ for natural sand and ½ for Crushed sand.
Accurate test when 8% limit of silt contain is exceeded can be done as per IS method
of Sedimentation if required.
Format to be used:
N005-06/F-21
40. FILLING CUBES FROM FRESHLY MIXED
CONCRETE
Doc. No. PANORAMA/TP-08
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR FILLING CUBES FROM FRESHLY MIXED CONCRETE
Aim : To prepare specimens for the test of Compressive Strength of concrete.
Apparatus :
Cube moulds fitted tightly on base plate (size in mm 150x150x150) in required set
(One set comprises of 6 moulds.)
Smooth Tamping rod of size 16 mm dia and length of 600 mm with one rounded
edge.
Trowels small and large.Collection pan, scoop, measuring scale etc.Flat working
platform of adequate size.
Procedure of Cube Casting:
Cube moulds shall be verified for dimensions and tight fitting assembly. They
shall be lightly oiled and have clean surfaces.
Cube moulds shall be arranged in sets on working platform.
Sample is collected as per the procedure given earlier.
Concrete is filled in cubes one by one in three layers. Each layer is tamped 35
times with tamping rod evenly. Tamping shall penetrate the layer below. Care
to be taken particularly at corners. Small trowel can be used at the sides to
ensure proper surface of sides and allow entrapped air to escape.
Cubes shall be filled slightly above top surface of mould.
The top extra layer shall be struck off by large trowel, flush to the top.
Cubes shall not be disturbed till at least 6 hours after the casting.
Cube concrete surface shall be marked with Cube I.D. , Mix, location of use,
date, source of concrete ( additional) when adequately set.
Cubes thus cast, shall be covered with wet gunny bags till they are replaced in
curing tank.
41. After about 10-12 hours cubes can be opened and place them in curing tank.
Cubes shall be checked for surface correctness, sharp edges and incorrect
filling. Such defective cubes may be rejected there it self. In such case
Corrective /Preventive actions shall be taken.
Procedure for Tank Curing :
Cubes shall be arranged in the curing tank sequentially as per ID mark,
datewise.
Cubes shall be sorted out for 7 days , 28 days tests. Cubes shall be placed in
the tank in layer of three cubes with marked top upside.
Cubes once placed in tank shall not be handled, disturbed frequently so that
edges are not broken.
Water in tank shall cover cubes by at least 50-75 mm all the time.
Water temperature must be maintained in winter.
Procedure for In-Situ Curing :
This method is deployed to decide stripping time of shuttering when shuttering
stripping is planned earlier than given as per IS: 456. This method shall not be
deployed for the cubes to be tested for compressive strength of concrete at 28 days.
Record :
Details of Cubes thus sampled shall be entered serially in Cube Register maintained
for testing compressive strength. The number of cube samples cast shall also be
entered in pour card with proper traceability to cube register.
Format to be used:
It shall be recorded in Cube register & pour card
42. SAMPLING / INSPECTION / TESTING
RMC CONCRETE
Doc. No. PANORAMA/TP-09
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR SAMPLING / INSPECTION / TESTING RMC CONCRETE
Aim:
To Check, Inspect Conformity of RMC Concrete which is manufactured outside and
supplied at site.
Pre-requisites:
RMC supplier shall be given prior information by the site regarding following:
1. Grade of Concrete.
2. Minimum Cement or cementations material contents. (EIL Appro. required)
3. Slump required and tolerances in slump. (EIL Approval required)
4. W/C ratio.
5. Method of Concreting (Manual, Bucket or Pumping)
6. Control of temperature if required shall be specified in case of Mass concreting.
7. Quantity of Concrete required – Total, Phase wise, day wise.
8. Supplier shall know site condition, distance and shortest route to the site from his
plant.
RMC Supplier shall give following Information to Site:
1. Mix design details including admixtures/ additives and cement used.
2. Material testing results for Cement, Admixtures / Additives, water, Coarse and
Fine aggregate.
3. Transit mixer Capacity & time to travel from RMC plant to site.
4. Minimum and maximum quantity that can be supplied in a single pour.
43. 5. Supplier’s In-house testing facilities.
6. Method of concreting which Supplier can undertake for the pours.
7. Communication system which Supplier adopts.
8. Name of Important Plant Personnel.
44. SIEVE ANALYSIS OF COARSE
AGGREGATES
Doc. No. PANORAMA/TP-10
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR SIEVE ANALYSIS OF COARSE AGGREGATES
( I.S. : 2386-I )
Aim : To determine the properties of Coarse aggregate for size and grading
distribution ( Nominal 20mm/12.5or10 mm metal).
Apparatus :
Drying Oven, IS Sieves 40 mm, 20 mm,16 mm, 12.5 mm, 10mm, pan. – for Analysis of
20 mm metal.
IS Sieves 20 mm, 16 mm,12.5 mm, 10 mm, 4.75 mm ,2.36mm pan - for Analysis of
10/12.5 metal.
Weigh scale to the accuracy of 1gm, Brush, Metal trays etc.
Procedure:
Sample of aggregate shall be collected as given earlier.
Sieves shall be cleaned and arrange in sequence in descending order. Pan
shall at the lower most end and Lid on top.
Take around 5 kg of sample and dry it in oven at temp of 100-110 deg C.
Dried sample shall be then weighed ( 5 kg preferably) and sieved successively
on sieves starting with 40mm and then through 4.75mm( For 20 mm down aggregate
size ) and through 2.36 mm (For 12.5/10 mm down aggregate size) .
Each sieve shall be shaken at least for two minutes on clean tray until no more
trace passes.
Motion shall be varied like back and forth, left to right, circular clockwise and
anti-clockwise and with frequent jarring.
Material shall not be forced through the mesh. But for coarser than 20mm
particles, placing is permitted (passing particles through sieve opening
manually).
45. Sieves shall be brushed from underneath of mesh and pass on to the next.
On completion of sieving, material retained on each sieve is to be weigh
Separately.
Reporting:
The cumulative % by weight of the total sample passing each sieves, to the
Nearest whole number.
Or
The % by weight of the total sample passing one sieve and retained on the next
smaller sieve to the nearest 1 decimal.
Check for permissible limits for passing.
Format to be used:
N005-06/F-14
46. SIEVE ANALYSIS OF FINE AGGREGATES Doc. No. PANORAMA /TP-11
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR SIEVE ANALYSIS OF FINE AGGREGATES
( I.S. : 2386-I )
Aim : To determine the properties of Fine aggregate for size and distribution by
calculating Fineness modulus and deciding Grading Zone.
Apparatus :
Drying Oven, IS Sieves 10 mm, 4.75mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron,
150 mm, Pan, Weigh scale to the accuracy of 1g, Brush , Metal trays etc.
Procedure:
Sample of sand shall be collected as given earlier.
Sieves shall be cleaned and arrange in sequence in descending order. Pan
shall at the lower most end and Lid on top.
Take around 1 kg of sample and dry it in oven at temp of 100-110 deg C.
Dried sample shall be then weighed ( 1 kg preferably) and sieved successively
on sieves starting with 10mm and then through 150 micron.
Each sieve shall be shaken at least for two minutes on clean tray until no more
trace passes.
Motion shall be varied like back and forth, left to right, circular clockwise and
anti-clockwise and with frequent jarring.
Material shall not be forced through the mesh. Lumps in fines shall be broken
against the wall of sieve.
Sieves shall be brushed from underneath of mesh and pass on to the next.
On completion of sieving, material retained on each sieve is to be weigh
separately.
47. Calculations:
Fineness Modulus: Add values of Cumulative % Retained on each sieves and
Divide by 100. (Normally accepted limit of FM is value between 2.2 to 3.2.
Higher value of FM indicates Coarser sand whereas lesser value indicates Finer one.
)
Grading Zone of Fine Aggregate – Value is shown between I to IV.
Where zone- I is associates with Coarser Fine aggregate and Zone IV is Finer.
Zones are decided from values of 600 micron passing % in sieve analysis.
( Refer Table-4 of IS : 383 )
Zone –I – 15-34%, Zone-II – 35-59 %, Zone-III- 60-79%, Zone-IV- 80-100%
Reporting:
The cumulative % by weight of the total sample passing each sieves, to the
nearest whole number.
Or
The % by weight of the total sample passing one sieve and retained on the next
smaller sieve to the nearest 1 decimal.
Calculate F.M. of the material and decide Grading Zone of material.
Format to be used:
N005-06/F-14
SIEVE ANALYSIS OF FINE
AGGREGATES
Doc. No. PANORAMA/TP-11
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
48. SLUMP TEST Doc. No. PANORAMA/TP-12
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR SLUMP TEST FOR FRESH CONCRETE (IS: 1199)
Aim : To check Workability of Freshly mixed Concrete by Standard Slump Cone
Method. This method is suitable for max size of aggregate upto 38 mm only.
Apparatus :
Slump cone with base plate and cone having bottom dia 20 cms , top dia 10
cms and height 30 cms.
Smooth Tamping rod 16 mm dia and 600 mm long with one rounded edge.
Scoop , Trowel, Collection pan, measuring scale ( Tamping rod also have
marking ).
Smooth / Leveled platform for working.
Procedure :
Sample is collected as per the sampling procedure given earlier.
Internal surface of the cone shall be cleaned and freed from extra moisture
and any layer of set cement slurry.
Conical mould shall be fixed tight on the base with screw arrangement
ensuring that no cement slurry will leak from the joint.
Assembly shall be placed on smooth and truly horizontal surface rigidly.
Mould shall be filled up in 4 layers. Each layer shall be tamped with tamping
rod for 25 times evenly. Tamping shall penetrate in layer below.
The top level shall be struck off by trowel or rod flush to the top of cone.
The Cone shall loosened at the base and shall be lifted carefully vertically
without disturbing concrete mass.
The subsidence shall be measured immediately.
Above operations shall be carried out at place free from vibrations and shock.
49. The whole exercise is to be done within two minutes from sampling.
In any test in which specimen collapses or shears the test will be repeated.
Record :
Slump shall be recorded in mm.
If in repeat test the slump shears, it is to be recorded.
Format to be used:
N005-06/F-17
50. PROCEDURE FOR TEST ON COMMON
BURNT CLAY BRICKS
Doc. No. PANORAMA/TP-13
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR TESTS ON COMMON BURNT CLAY BRICKS
(I.S: 3495-I&II )
A. DETERMINATION OF COMPRESSIVE STRENGTH OF BRICKS:
Aim: To determine Compressive Strength of Common Burnt Clay bricks
Apparatus :
M.S. Packing Plates 10 / 12 mm thk of adequate size ( 250mm x 150 mm)- 2 nos,
minimum Plywood sheets 3mm thk /3 ply – 2 nos, CTM, Measuring Scale
Clean sand screened through 3 mm sieve ( Remark-Sieving through 4.75 mm
normally will do), O.P. Cement, jute cloth
Pre- Conditioning:
Record the measurements of the samples to nearest 1mm.
Remove the unevenness observed in the bed faces to provide two smooth and
parallel faces by grinding ( rubbing )
Immerse the specimens in the water at room temperature for 24 hours.
Remove specimen and drain out surplus moisture. Fill the frog and voids in
the bed faces with CM 1:3 flushed to the surface.
Store under damp jute cloth for 24 hrs and then immerse in water for 3 days.
Remove specimen from water and wipe traces of moisture.
Procedure :
Place the specimen with flat faces horizontal and mortar filled face upward
between two ply sheets and required packing plates. Center it carefully.
Apply load at rate of 140 kg /cm2 per minute ( 30 tonne per minute ) , till
failure occurs.
Note the maximum load at the failure.
51. Calculations :
Compressive Strength, kg /cm2 = Max Load in Kg / Avg area of the bed faces of the
specimen, cm2
Report: Average of the results shall be reported.
B. DETERMINATION OF WATER ABSORPTION:
Aim :
To determine water absorption of specimen by 24 hours immersion in cold water.
Apparatus :
Balance with accuracy of 1g, Oven, Measuring scale.
Pre- conditioning :
Dimensions shall be measured to accuracy of 1 mm of test specimen
Dry specimen in oven at temperature 105-115 deg C till it attains substantially
constant mass.
Cool the specimen to room temperature and obtain weight – M1, g ( Specimen
warm to touch shall not be weighed. )
Procedure:
Immerse completely dried specimen in clean water at temperature 27+/- 2 deg
C.
Remove specimen after 24 hours and wipe out any traces of water with damp
cloth.
Weigh the specimen within 3 minutes after removing from water. ( M2, g )
Calculations :
% Water Absorption = ( M2-M1 /M1) x100
Report :
Average of the results to be reported.
Format to be used: Field Dry Density Test - N005-06/F-09
52. SAMPLING OF AGGREGATES Doc. No. PANORAMA/TP-14
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROCEDURE FOR SAMPLING
FOR AGGREGATES (IS: 2430):
Sample from Stock Pile of the Coarse / Fine aggregate:
Samples from stock piles should be made up of at least 10 increments; taken
Equally from top third, mid point and bottom third.
Outer layer of sampling point shall be removed and the sample is taken from
the material beneath.
Gross Sample – the sample thus collected will be the gross sample. Qty of
gross sample is depends on the aggregate size :
SL. No. Aggregate Size Gross Sample
1 2.36mm/4.75mm 10 KG
2 12.5 mm 15 KG
3 20 mm 25 KG
4 40 mm 80 KG
Reduction of Gross Sample : Will be done as per method of Quartering to
required sample size for testing.
Quartering Method :
Take the gross sample on plain platform. For Fine aggregate use Tray so that
residual fines can be collected by brushing.
The aggregate shall be mixed and then scooped into a cone shape pile.
After the cone is formed, it shall be flattened by pressing the top.
Then it is divided in four quadrants diagonally.
The bulk of the sample is reduced by rejecting any two diagonally opposite
Quarters
53. This method is repeated till sample size is approximately achieved for given
lot.
SAMPLING OF BRICKS
Doc. No PANORAMA /TP-15
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
BRICKS (As per IS: 5454)
Sampling a lot which shall contain maximum 50000 bricks. In case a
consignment has bricks more than 50000 bricks of same classification, size and
manufactured under relatively similar conditions, it shall be divided into lots
of 50000 bricks or part thereof.
Sampling from the stack – When it is necessary to take sample from the stack,
the stack shall be divided into number of real or imaginary sections and
required number of bricks shall be drawn from each section. For the purpose
bricks in the upper layers of the stack shall be removed to enable units to be
sampled from places within the stack.
Sample size – For Visual / Dimensional Characteristics –
Lot Size of bricks Sample size for Individual brick Sample size For group of Check 20
bricks Check
Sl. No. Range Min. Sample Collection
1 2001-10000 20-40
2 10001-35000 32-60
3 35001-50000 50-80
Sample size For Physical Characteristics –
Lot size of bricks Sample size for Comp. Strength, water absorption, Efflorescence
etc.
Sl. No. Range Min. Sample Collection
1 2001-10000 5-10
2 10001-35000 10-20
3 35001-50000 15-30
54. FOR EARTH / SOIL
Doc. No. PANORAMA/TP-16
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
FOR EARTH / SOIL (IS: 2720 -I)
If the earth received for testing is wet for handling then same is air dried on
platform in outdoor.
The Gross sample shall be as below:
Max size of particles Min. Gross Sample in Substantial qty in kg
Sl. No. Max Size of particles Min. Gross Sample
1 75 mm 100 KG
2 40 mm 80 KG
3 19mm 35 KG
4 10mm 25 KG
5 4.75 mm 20 KG
Sample size for required test shall be made as per quartering method
described above.
Care to be taken that no fines are lost in the operation as soil properties
mostly depend on them for testing.
55. FRESH CONCRETE IN THE FIELD Doc. No. PANORAMA/TP-17
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
FOR FRESH CONCRETE IN THE FIELD
( IS : 1199 )
Sample from Mixer:
At least three approximate equal samples totaling 0.02 m3 (equivalent to fill 6
Cube moulds) shall be taken from a batch.
For collection a scoop shall be used. No tool with flat edges ( like phawra)
shall be used.
3 samples are taken at about the time interval when ¼, ½ and ¾ of concrete is
discharged.
Sample from Place and Time of Deposition:
Sample shall be taken immediately after or during discharge at site.
Samples shall be collected from not less than 5 well distributed points
avoiding
the edges of the mass where segregation may have occurred.
Mixing of Sample :
Sample thus received shall be immediately remixed on non-absorbent
platform
and made ready for testing.
Frequency of Sampling :
The minimum frequency of sampling of concrete of each grade shall be as
below:
Qty of Concrete in the No of Samples *
SL. No. Qty of Concrete –M3 No. of Sample- Set
1 1-5 1
2 6-15 2
3 16-30 3
4 31-50 4
56. 5 51 & above 4+1 additional sample for each additional 50
m3 or part thereof.
Note:
At least one sample taken from each shift.
Where concrete is produced at continuous production unit such as RMC plant,
frequency of sampling may be agreed upon mutually.
Three specimens shall be made for each sample for testing at 28 days.
Additional samples may be required for determining strength at 7 days or at the
time of striking formwork.
Remarks :
Sample* means qty of concrete required to fill one set of cubes ( 3nos / 6 nos ) for
testing.
Hence number of sample is equivalent to number of cube sets (3 / 6 nos.). 3 cubes
are drawn when only cube testing is done at 28 days. 6 cubes are drawn for tests at 7
/ 28 days required.
CONCRETING IN HIGH TEMPERATURE REGIONS (IS: 7861-1)
Ice is added
Water Cement Ratio should not change with addition of Ice
Adjust Quantity of water accordingly to the volume of melting ice
CONCRETING IN LOW TEMPERATURE REGIONS (IS: 7861-2)
Precautions must be taken to keep the temperature in control during mixing
and placing Concrete.
The commonly adopted method is by using hot water upto 60 C .
In extreme frost conditions the concrete surface is covered with dry blankets
of straw, cement bags, tarpaulins etc.
57. WATER CONTENT IN SOIL SAMPLE Doc. No PANORAMA /TP-18
PROJECT: GOLDEN PANORAMA Luxury
Apartments at BANGALORE.
Rev.-00
CLINT : M/s. Golden Gate Properties Pvt. Ltd.
PMC : FBA Consulting PMC
PROECEDURE FOR DETERMINATION OF WATER CONTENT IN SOIL
SAMPLE
(IS: 2720-II)
A. By Oven Drying Method:
Aim :
To determine Water Content in Soil Sample at Laboratory by Oven Method
Apparatus :
Container – Any suitable non-corrodable air tight container. ( Remarks- These can be
300ml aluminum or stainless steel boxes with lid )
Balance – Having accuracy of 0.04% of the weight of soil taken for test.
Remarks-
Balance of capacity 500 g and accuracy of 0.1g can be used when accurate
working is required. If normal weighing balance with 1g accuracy is used then
accuracy of water content will be around 0.2 to 0.5% only; depending on sample
size 500 to 200 g respectively.
Drying Oven – Thermostatically controlled.
Soil Specimen:
It shall be true representative of soil mass. The size of specimen is recommended for
general laboratory use as below. However, the dryer the soil,
Greater shall be size. Remarks: Preferably take 500g sample when weighing
Accuracy is 1g.
Size of particles - 37.5mm, 19mm, 9.5mm, 4.75mm, 2mm
More than 90% passing
Min qty of soil specimen 1000gm, 500gm, 300gm, 200gm, 50gm
58. Procedure:
Clean the container with lid, dry and weigh (W1, g)
Take the required quantity of the soil specimen in container, crumble clods
and place loosely and weigh with the lid ( W2, g )
Keep filled container in an oven with the lid removed and maintain the
temperature at 110+/- 5 deg C. for maximum 24 hours.
Cool the container and record Final mass of container with lid and dried
sample ( W3, g ).
Calculations :
% of Water Content = 100 x ( W2-W3 ) / ( W3- W1)
Report :
The water content % shall be expressed to two significant figures ( e.g.- 23, 2.3,
0.23 )
Note : Oven drying at 110 +/- 5 deg C does not result in reliable values for soil
containing Gypsum and any other mineral having water of hydration or significant
amount of organic matter. Reliable values can be obtained in an oven by drying at
temperature around 60-80 deg C.
Remarks: Traces of Gypsum / lime / Alum can be seen as white particles. That of
organic matter will show black colour fibrous traces. Particles of Green / Bluish
Green can be minerals having water of hydration.
B. By Sand Bath Method ( Suitable as Field Test )
This method is not suitable for soil containing a large portion of Gypsum ,
Calcareous Matter or Organic matter.
Aim :
To determine water content in soil specimen in the field.
Apparatus:
Container – Any suitable Air tight container as given in Oven drying method.
Sand Bath : Suitable size and containing clean sand to a depth of 3 cms.
Stove, Spatula
Soil Specimen :
As given in Oven drying method.
59. Procedure :
Clean the container with lid, dry and weigh ( W1 , g )
Take the required quantity of the soil specimen in container, crumble the
clods and place loosely and weigh ( W2, g )
Add few pieces ( 3-4 small) of white paper if necessary. This the indicator for
over-heating. While heating the soil paper pieces shall not turn brown.
Place the container with lid removed on sand bath and heat sand bath on the
stove.
During heating sample shall be turned frequently and thoroughly to assist
evaporation. It shall be done carefully so as no soil mass is spilled over.
When drying is complete, remove the container and cool it down. Remove
pieces of papers.
Weigh the container with lid on. ( W3, g )
Calculations :
w % = 100x ( W2 - W3 ) / ( W3 –W1 )
Report :
Same as Oven drying method to two significant figures (e.g. – 23, 2.3, 0.23)