2. A project team is identifying risks for a building construction project. The project will contract with
several different vendors to produce the highly specialized deliverables of the project. Acquiring
services from outside the organization may increase or decrease overall project risk and may
introduce additional individual project risks. What should the project team review in order to
develop a comprehensive list of individual project risks related to goods and services provided from
outside the organization?
A. Project charter
B. Procurement documentation
C. Vendor risk register
D. Probability and impact matrix
HINT: What documentation would serve as an input to the Identify Risks process and provide
relevant procurement information?
QUESTION:
3. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
4. The correct answer is B
Based on the scenario described, the project team is carrying out the Identify Risks process.
One input to the Identify Risks process is procurement documentation. The initial procurement
documentation should be reviewed as procuring good and services from outside the
organization may increase or decrease overall project risk and may introduce additional
individual project risks. Procurement documentation may include the statement of work,
payment information, contractor work performance information, plans, drawings, and other
correspondence.