You are establishing the relative priorities of individual risks identified in the project.
Which of the following tasks is the least likely to impact this prioritization?
A. Reviewing the assumption log
B. Examining the risk register
C. Researching the stakeholder register
D. Creating the risk report
HINT: Which document is not an input to the Perform Qualitative Risk Analysis process?
Question
The risk report is a project document that provides information on sources of overall project risk as well as the
summary information on individual project risks and is created as an output from the Identify Risks process,
rather than being used as an input to the Perform Qualitative Risk Analysis process, making the risk report the
best answer to the question asked.
The correct answer is D.
Establishing the relative priorities of individual project risks, an activity described in the scenario, is done as part
of the Perform Qualitative Risk Analysis process. This process prioritizes the risks for further analysis or action by
assessing their probability of occurrence and impact as well as other characteristics.
The assumption log, risk register, and stakeholder register are all project documents which may serve as inputs
into the Perform Qualitative Risk Analysis process. Note, the question is asking for the 'least' likely activity to be
performed as part of this process.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

Similar to Free PMP Exam Sample Question

Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
Daniel Ackermann
 

Similar to Free PMP Exam Sample Question (20)

Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
 
Free CAPM Exam Sample Question
Free CAPM Exam Sample QuestionFree CAPM Exam Sample Question
Free CAPM Exam Sample Question
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
Free CAPM Exam Sample Q & A
Free CAPM Exam Sample Q & AFree CAPM Exam Sample Q & A
Free CAPM Exam Sample Q & A
 
Kansas Elsas Top-Cycle
Kansas Elsas Top-CycleKansas Elsas Top-Cycle
Kansas Elsas Top-Cycle
 
project management
project managementproject management
project management
 
Guide to Software Estimation
Guide to Software EstimationGuide to Software Estimation
Guide to Software Estimation
 
An Evaluation Study of General Software Project Risk Basedon Software Practit...
An Evaluation Study of General Software Project Risk Basedon Software Practit...An Evaluation Study of General Software Project Risk Basedon Software Practit...
An Evaluation Study of General Software Project Risk Basedon Software Practit...
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
An Evaluation Study of General Software Project Risk Basedon Software Practit...
An Evaluation Study of General Software Project Risk Basedon Software Practit...An Evaluation Study of General Software Project Risk Basedon Software Practit...
An Evaluation Study of General Software Project Risk Basedon Software Practit...
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
 
Project risk management
Project risk managementProject risk management
Project risk management
 
project-closure-software-engineering.ppt
project-closure-software-engineering.pptproject-closure-software-engineering.ppt
project-closure-software-engineering.ppt
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...
AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...
AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6
 

More from OSP International LLC

More from OSP International LLC (20)

Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 

Recently uploaded

Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 

Recently uploaded (20)

Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use Cases
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Simple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfSimple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdf
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 

Free PMP Exam Sample Question

  • 2. You are establishing the relative priorities of individual risks identified in the project. Which of the following tasks is the least likely to impact this prioritization? A. Reviewing the assumption log B. Examining the risk register C. Researching the stakeholder register D. Creating the risk report HINT: Which document is not an input to the Perform Qualitative Risk Analysis process? Question
  • 3. The risk report is a project document that provides information on sources of overall project risk as well as the summary information on individual project risks and is created as an output from the Identify Risks process, rather than being used as an input to the Perform Qualitative Risk Analysis process, making the risk report the best answer to the question asked. The correct answer is D. Establishing the relative priorities of individual project risks, an activity described in the scenario, is done as part of the Perform Qualitative Risk Analysis process. This process prioritizes the risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics. The assumption log, risk register, and stakeholder register are all project documents which may serve as inputs into the Perform Qualitative Risk Analysis process. Note, the question is asking for the 'least' likely activity to be performed as part of this process. Answer
  • 4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.