2. Which of the following activities is not included in the Conduct Procurements process?
A. Obtaining seller responses
B. Selecting potential sellers
C. Selecting a seller
D. Awarding a contract
HINT: Potential sellers are identified during planning for the procurement management.
QUESTION:
3. The correct answer is B.
The Conduct Procurements process is a process of obtaining and evaluating the bidder
responses, selecting the best bidder for making a contract. In contrast, the list of potential
bidders could be developed in the Plan Procurement Management process by conducting
market research to identify the capability of the market and certain vendors.
ANSWER: