3. Planning of Distribution System
A distribution system deals with the distribution of
electrical energy. A good system planning should provide
for an orderly development of the system to meet the power
requirements for a period of about five years and to obtain
optimum benefit from the available resources. The main
purpose of planning is:
To make the system economical while conforming
to the Indian electricity rules.
To minimize losses and maintain regulation within
permissible limits. For proper Planning of a distribution
system. Load survey and load forecasting of the area is
necessary.
4. * Load Survey *
The load survey of a particular area is carried out to find present load
requirement as well as the expected load growth over a period of 5 to 7 years.
The following basic data should be collected for starting this work:
A detailed map of the area showing important features.
The number of houses, population and the new construction
anticipated the area.
The expected number of shops post-office, rural health center
Panchayat office etc.
Details of hospital s, railway stations, public health sewage systems and
water supply schemes.
The cultivated area, number of wells, available irrigation facilities and
irrigated area.
The type of industries and number of industries possible in these areas.
Development programs implemented and envisaged in the area.
5. * Load Calculation of Hostel *
1st Year Block 10.48 kW
2nd Year Block 12.21 kW
3rd Year Block 12.21 kW
Common Room 0.883 kW
Dining Room 0.883 kW
6. * Load Calculation of Nodal Office *
Regional Office 9.004 kW
VET Office 2.667 kW
7. * Load Calculation of College Building *
Workshops & Laboratories 153.67 kW
Classrooms 20.68 kW
Teachers’ Rooms 4.95 kW
Other Official Rooms 8.41 kW
Stadium 79.42 kW
8. * Demand Factors *
Single Storied → 0.8 Public Building → 0.8
Double Storied → 0.7 Commercial Building → 0.9
Triple Storied → 0.6 Cinema Hall → 0.9
Multi Storied → 0.8 Industry → 0.8
Street Light → 1.0
Public Fan → 0.9
Domestic Fan → 0.3 to 0.6
Domestic Light → 0.3 to 0.6
Public Light → 0.8 to 0.9
Commercial Light → 0.5 to 0.75
Industrial Motor → 0.95
Pump Motor → 0.95
9. * Total Load Calculation *
1st Year Block 10.48 kW
2nd + 3rd Year Block 26.136 kW
Nodal Office 9.004 kW
Workshops 37.662 kW
College 118.273 kW
Automobile 1st Yr+Mechanical 1st Yr 1.996 kW
Stadium 79.420 kW
Total Load 282.971 kW
10. * Some Important Definitions
*
Connected Load: It is the sum the continuous rating in KW of all electrical devices at the consumers premises
and connected to the supply system.
Demand factor: Demand factor is defined as the ratio of maximum demand made by the load to the rating of
the connecting load.
Demand Factor= (Maximum demand made by the Load)/ (Rating of Connected Load)
The value of Demand Factor determines the rating and hence the cost of power equipments to
supply given connected load.
Load Factor : Load Factor is the ratio of average Demand to the Maximum Demand during a certain period of
time such a month or a day or a year and is applicable to both generating equipment or receiving equipment.
Load Factor = (Average Demand)/ (Maximum demand)
Connected Load Factor: It is the ratio of average power input to the connected load and related only to the
receiving equipment.
Connected Load Factor = (Average Power Input)/ (Connected Load)
12. By back calculation the current turns negative at between e and
f. hence, f point in the minimum potential point where current turns
negative.
Now, as per I.E rule voltage drop up to MP is 11.5 V (5% of 230v).
45𝝆 x224.09 + 125 𝝆 x 176.75 + 100 𝝆 x32.88 + 95 𝝆 x 13.9 = 11.5 V
Hence 𝝆 =0.00031 ohm/ m
=0.31 ohm/ km.
15. * Calculation for Water Works *
Assume, total Population= 450.
Water used by each= 25 Gallons/Head/Day.
So, Water necessary= 11,250 Gallons/ Day.
Now, H.P.= = 17.08 HP
Here, W= Specific Gravity= 62.4 Lb/ft.
Q= Discharge in cubic ft./sec.
H= Total head (In ft.)
Taking Efficiency of the Pump= 70% & Demand Factor= 1,
we can calculate that Maximum Demand for Water Works=
18 kW
16. * Prediction of Future Loads
*
Forecasting the future load requirement is essential part of power
project design. This forecast of lone is done by two namely statically
method and field survey method.
Fundamental law of statistical is that every phenomenon in future
obeys some mathematical law which can be represented by a smooth curve
load development in any area except due to unforeseen developments such
as the establishment to this low. According to this method of annual
maximum demand pertaining to the area is collected for past several years.
In the field survey method, existing requirement area is found out
under different classes of load i.e. residential, commercial, industrial,
municipal and agricultural. Future load requirement are then forecast taking
into account various factors such as population growth , natural resources of
the region standard of living of the people, topography and climate of the
region.
17. TRANSMISSION AND DISTRIBUTION
SYSTEMS *
(In Accordance With Indian Electricity Rules
1956 and IS: 585-1962)
1. VOLTAGE:
1.1 Declared voltage The declared voltage is the voltage at the consumers’ terminals declared by the supplier of
electrical energy. It is to maintenance within the limits prescribed the Indian electricity rules.
1.2 System Voltage (Nominal Voltage) This is the line-to-line voltage for which the system is designed and
installed. This is the voltage by which the system is generally designed. It is not necessarily the rated voltage of
every piece of apparatus connected to the system.
1.3 Rated voltage This is the voltage at which the apparatus connected to the system is designed to operate under
normal conditions. This is normally the same as the system voltage.
1.4 Low voltage A voltage not exceeding 250 V under normal conditions is considered low.
1.5 Medium Voltage A voltage exceeding 250 V but not 650 V under normal conditions are considered high.
1.6 High Voltage Voltages exceeding 650 V but not 33 KV under normal conditions are considered high.
1.7 Extra-High Voltage It is a voltage exceeding 33 KV under normal conditions.
18. 2. STANDARD VOLTAGE FOR SINGLE - PHASE SYSTEM:
The standard voltage system for a two-wire single-phase system is 240V.
3. STANDARD VOLTAGE FOR THREE-PHASE SYSTEM:
The standard preferred voltage for three-phase systems is as follows.
415 V (Voltage to neutral=240V)
3.3 kV 66 kV
6.6 kV 132 kV
11 kV 220 kV
33 kV 400 kV
Note: The above voltage refers to line-to-line voltages.
19. 4. VOLTAGE LIMITS:
The voltage at the point of commencement of supply under conditions should not vary from
the declared voltage by more than:
(i) 6% in case low or medium voltages.
(ii) 6% on the higher side or by more than 9% on the lower side, in case of high voltages.
(iii)12.5% In case of extra-high voltages.
5. STANDARD SYSTEM FREQUENCY:
The standard system frequency is 50 Hz. The frequency of an alternating current supply
should not very from the declared frequency by more than 3%.
20. * INDIAN ELECTRICITY RULES,
REGARDING THE CLEARANCE
OF OVERHEAD LINES *
IV.1 Rule- 77 CLEARENCE ABOVE GROUND OF THE LOWEST CONDUCTOR:
1. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low and medium voltage lines 5,971 m (19 ft).
(ii) For high voltage lines 6,096 m (20 ft).
2. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low and medium voltage lines 5,486 m (18 ft).
(ii) For high voltage lines 5,791 m (19 ft).
3. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low, medium and high voltage lines up to and including 11,000 V if bare 4,572m (15 ft).
(ii) For low, medium and high voltage lines up to and including 11,000 V if insulated 3,962 m (13 ft).
(iii) For high voltage lines above 11,000 V 5,182 m (17 ft).
(iv) For extra –high voltage lines, the clearance above ground shall not be less than 5,182 m (17 ft) plus
0.305 m (1 ft) for every 33,000 V or part thereof by which the voltage of the line exceeds 33,000 V provided
that the minimum clearance along or across any street is not less than 6.096 m (20 ft).
21. IV.3 Rule- 79 CLEARANCE FROM OF BUILDING OF LOW AND
MEDIUM VOLTAGE LINES AND SERVICE LINES:
1. Where a low or medium voltage overhead line passes above or adjacent to or terminates on any
building, the following minimum clearance from any accessible point, on the basis of maximum sag
shall be observed:
(i) For any flat, roof, open balcony, verandah, roof and lean to roof: (a) when the line passes above
the building a vertical clearance of 2.439 m(8 ft) from the highest point, (b) when the line passes
adjacent to the building, a horizontal clearance 1.219m (4 ft).
(ii) For pitched roof: (a) When the line passes above the building a vertical clearance of 2.498m (8
ft), immediately under the lines and (b) When the line passes adjacent to the building, a horizontal
clearance of 1.219m (4 ft).
2. Any conductor so situated as to have a clearance less than that specified in sub rule 1 shall be
adequately insulated and shall be attached at suitable interval to a bare earthed bearer when having a
breaking strength of not less than 377.51 kg (700ib).
3. The horizontal clearance shall be measure when the is at a maximum deflection from the vertical due
to wind pressure.