SlideShare a Scribd company logo
1 of 22
A Presentation on:
Electrification on “Malda
Polytechnic”:
Planning & Designing of
Distribution System
Project
Members:
Sourav Das
Milan kr Das
Santu Majee
Ujjwal Maiti
Santu Maiti
Pratim
Chakrabortty
Debabrata
Karmakar
Subho Mondal
Animesh Kanrar
Jahir Mallick
Manas Adak
Planning of Distribution System
A distribution system deals with the distribution of
electrical energy. A good system planning should provide
for an orderly development of the system to meet the power
requirements for a period of about five years and to obtain
optimum benefit from the available resources. The main
purpose of planning is:
 To make the system economical while conforming
to the Indian electricity rules.
 To minimize losses and maintain regulation within
permissible limits. For proper Planning of a distribution
system. Load survey and load forecasting of the area is
necessary.
* Load Survey *
The load survey of a particular area is carried out to find present load
requirement as well as the expected load growth over a period of 5 to 7 years.
The following basic data should be collected for starting this work:
 A detailed map of the area showing important features.
 The number of houses, population and the new construction
anticipated the area.
 The expected number of shops post-office, rural health center
Panchayat office etc.
 Details of hospital s, railway stations, public health sewage systems and
water supply schemes.
 The cultivated area, number of wells, available irrigation facilities and
irrigated area.
 The type of industries and number of industries possible in these areas.
 Development programs implemented and envisaged in the area.
* Load Calculation of Hostel *
 1st Year Block 10.48 kW
 2nd Year Block 12.21 kW
 3rd Year Block 12.21 kW
 Common Room 0.883 kW
 Dining Room 0.883 kW
* Load Calculation of Nodal Office *
Regional Office 9.004 kW
 VET Office 2.667 kW
* Load Calculation of College Building *
 Workshops & Laboratories 153.67 kW
 Classrooms 20.68 kW
 Teachers’ Rooms 4.95 kW
 Other Official Rooms 8.41 kW
 Stadium 79.42 kW
* Demand Factors *
 Single Storied → 0.8 Public Building → 0.8
 Double Storied → 0.7 Commercial Building → 0.9
 Triple Storied → 0.6 Cinema Hall → 0.9
 Multi Storied → 0.8 Industry → 0.8
Street Light → 1.0
 Public Fan → 0.9
 Domestic Fan → 0.3 to 0.6
 Domestic Light → 0.3 to 0.6
 Public Light → 0.8 to 0.9
 Commercial Light → 0.5 to 0.75
 Industrial Motor → 0.95
 Pump Motor → 0.95
* Total Load Calculation *
 1st Year Block 10.48 kW
 2nd + 3rd Year Block 26.136 kW
 Nodal Office 9.004 kW
 Workshops 37.662 kW
 College 118.273 kW
 Automobile 1st Yr+Mechanical 1st Yr 1.996 kW
 Stadium 79.420 kW
 Total Load 282.971 kW
* Some Important Definitions
*
 Connected Load: It is the sum the continuous rating in KW of all electrical devices at the consumers premises
and connected to the supply system.
 Demand factor: Demand factor is defined as the ratio of maximum demand made by the load to the rating of
the connecting load.
Demand Factor= (Maximum demand made by the Load)/ (Rating of Connected Load)
The value of Demand Factor determines the rating and hence the cost of power equipments to
supply given connected load.
 Load Factor : Load Factor is the ratio of average Demand to the Maximum Demand during a certain period of
time such a month or a day or a year and is applicable to both generating equipment or receiving equipment.
Load Factor = (Average Demand)/ (Maximum demand)
 Connected Load Factor: It is the ratio of average power input to the connected load and related only to the
receiving equipment.
Connected Load Factor = (Average Power Input)/ (Connected Load)
* Distributor Design *
By back calculation the current turns negative at between e and
f. hence, f point in the minimum potential point where current turns
negative.
Now, as per I.E rule voltage drop up to MP is 11.5 V (5% of 230v).
45𝝆 x224.09 + 125 𝝆 x 176.75 + 100 𝝆 x32.88 + 95 𝝆 x 13.9 = 11.5 V
Hence 𝝆 =0.00031 ohm/ m
=0.31 ohm/ km.
* Determination of Load Centre
*
* Graphical Representation of ‘Load Centre’ *
* Calculation for Water Works *
Assume, total Population= 450.
Water used by each= 25 Gallons/Head/Day.
So, Water necessary= 11,250 Gallons/ Day.
Now, H.P.= = 17.08 HP
Here, W= Specific Gravity= 62.4 Lb/ft.
Q= Discharge in cubic ft./sec.
H= Total head (In ft.)
Taking Efficiency of the Pump= 70% & Demand Factor= 1,
we can calculate that Maximum Demand for Water Works=
18 kW
* Prediction of Future Loads
*
Forecasting the future load requirement is essential part of power
project design. This forecast of lone is done by two namely statically
method and field survey method.
Fundamental law of statistical is that every phenomenon in future
obeys some mathematical law which can be represented by a smooth curve
load development in any area except due to unforeseen developments such
as the establishment to this low. According to this method of annual
maximum demand pertaining to the area is collected for past several years.
In the field survey method, existing requirement area is found out
under different classes of load i.e. residential, commercial, industrial,
municipal and agricultural. Future load requirement are then forecast taking
into account various factors such as population growth , natural resources of
the region standard of living of the people, topography and climate of the
region.
TRANSMISSION AND DISTRIBUTION
SYSTEMS *
(In Accordance With Indian Electricity Rules
1956 and IS: 585-1962)
1. VOLTAGE:
1.1 Declared voltage The declared voltage is the voltage at the consumers’ terminals declared by the supplier of
electrical energy. It is to maintenance within the limits prescribed the Indian electricity rules.
1.2 System Voltage (Nominal Voltage) This is the line-to-line voltage for which the system is designed and
installed. This is the voltage by which the system is generally designed. It is not necessarily the rated voltage of
every piece of apparatus connected to the system.
1.3 Rated voltage This is the voltage at which the apparatus connected to the system is designed to operate under
normal conditions. This is normally the same as the system voltage.
1.4 Low voltage A voltage not exceeding 250 V under normal conditions is considered low.
1.5 Medium Voltage A voltage exceeding 250 V but not 650 V under normal conditions are considered high.
1.6 High Voltage Voltages exceeding 650 V but not 33 KV under normal conditions are considered high.
1.7 Extra-High Voltage It is a voltage exceeding 33 KV under normal conditions.
2. STANDARD VOLTAGE FOR SINGLE - PHASE SYSTEM:
The standard voltage system for a two-wire single-phase system is 240V.
3. STANDARD VOLTAGE FOR THREE-PHASE SYSTEM:
The standard preferred voltage for three-phase systems is as follows.
415 V (Voltage to neutral=240V)
3.3 kV 66 kV
6.6 kV 132 kV
11 kV 220 kV
33 kV 400 kV
Note: The above voltage refers to line-to-line voltages.
4. VOLTAGE LIMITS:
The voltage at the point of commencement of supply under conditions should not vary from
the declared voltage by more than:
(i) 6% in case low or medium voltages.
(ii) 6% on the higher side or by more than 9% on the lower side, in case of high voltages.
(iii)12.5% In case of extra-high voltages.
5. STANDARD SYSTEM FREQUENCY:
The standard system frequency is 50 Hz. The frequency of an alternating current supply
should not very from the declared frequency by more than 3%.
* INDIAN ELECTRICITY RULES,
REGARDING THE CLEARANCE
OF OVERHEAD LINES *
IV.1 Rule- 77 CLEARENCE ABOVE GROUND OF THE LOWEST CONDUCTOR:
1. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low and medium voltage lines 5,971 m (19 ft).
(ii) For high voltage lines 6,096 m (20 ft).
2. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low and medium voltage lines 5,486 m (18 ft).
(ii) For high voltage lines 5,791 m (19 ft).
3. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a
height less than:
(i) For low, medium and high voltage lines up to and including 11,000 V if bare 4,572m (15 ft).
(ii) For low, medium and high voltage lines up to and including 11,000 V if insulated 3,962 m (13 ft).
(iii) For high voltage lines above 11,000 V 5,182 m (17 ft).
(iv) For extra –high voltage lines, the clearance above ground shall not be less than 5,182 m (17 ft) plus
0.305 m (1 ft) for every 33,000 V or part thereof by which the voltage of the line exceeds 33,000 V provided
that the minimum clearance along or across any street is not less than 6.096 m (20 ft).
IV.3 Rule- 79 CLEARANCE FROM OF BUILDING OF LOW AND
MEDIUM VOLTAGE LINES AND SERVICE LINES:
1. Where a low or medium voltage overhead line passes above or adjacent to or terminates on any
building, the following minimum clearance from any accessible point, on the basis of maximum sag
shall be observed:
(i) For any flat, roof, open balcony, verandah, roof and lean to roof: (a) when the line passes above
the building a vertical clearance of 2.439 m(8 ft) from the highest point, (b) when the line passes
adjacent to the building, a horizontal clearance 1.219m (4 ft).
(ii) For pitched roof: (a) When the line passes above the building a vertical clearance of 2.498m (8
ft), immediately under the lines and (b) When the line passes adjacent to the building, a horizontal
clearance of 1.219m (4 ft).
2. Any conductor so situated as to have a clearance less than that specified in sub rule 1 shall be
adequately insulated and shall be attached at suitable interval to a bare earthed bearer when having a
breaking strength of not less than 377.51 kg (700ib).
3. The horizontal clearance shall be measure when the is at a maximum deflection from the vertical due
to wind pressure.
Planning & Designing of Distribution System

More Related Content

What's hot

Role of Flexible AC Transmission in Power System Contingency
Role of Flexible AC Transmission in Power System ContingencyRole of Flexible AC Transmission in Power System Contingency
Role of Flexible AC Transmission in Power System ContingencySayantan Datta
 
Pd 1995 10-2-the upfc a new approach to power transmission control
Pd 1995 10-2-the upfc a new approach to power transmission controlPd 1995 10-2-the upfc a new approach to power transmission control
Pd 1995 10-2-the upfc a new approach to power transmission controlSudeepthg Sudeepth
 
Power System Control And Line Compensation
Power System Control And Line CompensationPower System Control And Line Compensation
Power System Control And Line CompensationAnakin Akshat Assal
 
BASICS of MODERN FACTS DEVICES
BASICS of MODERN FACTS DEVICES BASICS of MODERN FACTS DEVICES
BASICS of MODERN FACTS DEVICES saravanapsp
 
UPFC in order to Enhance the Power System Reliability
UPFC in order to Enhance the Power System ReliabilityUPFC in order to Enhance the Power System Reliability
UPFC in order to Enhance the Power System ReliabilityIJMER
 
Flexible Ac Transmission Systems 2Mark Materials and Question Bank
Flexible Ac Transmission Systems 2Mark Materials and Question BankFlexible Ac Transmission Systems 2Mark Materials and Question Bank
Flexible Ac Transmission Systems 2Mark Materials and Question BankSanthosh Kumar
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission systemUday Wankar
 
Vishws jain seminar
Vishws jain seminarVishws jain seminar
Vishws jain seminarVishwas Jain
 
power quality improvement of power system network using UPFC
power quality improvement of power system network using UPFCpower quality improvement of power system network using UPFC
power quality improvement of power system network using UPFCBikash Gyawali
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesRajaram Meena
 
Power factor improvement using upfc
Power factor improvement using upfcPower factor improvement using upfc
Power factor improvement using upfcUday Wankar
 
FACTS DEVICES
FACTS DEVICESFACTS DEVICES
FACTS DEVICESamit8847
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERNitish NIT
 

What's hot (20)

UPFC
UPFCUPFC
UPFC
 
Role of Flexible AC Transmission in Power System Contingency
Role of Flexible AC Transmission in Power System ContingencyRole of Flexible AC Transmission in Power System Contingency
Role of Flexible AC Transmission in Power System Contingency
 
An overview of FACTS devices
An overview of FACTS devicesAn overview of FACTS devices
An overview of FACTS devices
 
Pd 1995 10-2-the upfc a new approach to power transmission control
Pd 1995 10-2-the upfc a new approach to power transmission controlPd 1995 10-2-the upfc a new approach to power transmission control
Pd 1995 10-2-the upfc a new approach to power transmission control
 
Power System Control And Line Compensation
Power System Control And Line CompensationPower System Control And Line Compensation
Power System Control And Line Compensation
 
BASICS of MODERN FACTS DEVICES
BASICS of MODERN FACTS DEVICES BASICS of MODERN FACTS DEVICES
BASICS of MODERN FACTS DEVICES
 
UPFC in order to Enhance the Power System Reliability
UPFC in order to Enhance the Power System ReliabilityUPFC in order to Enhance the Power System Reliability
UPFC in order to Enhance the Power System Reliability
 
Flexible Ac Transmission Systems 2Mark Materials and Question Bank
Flexible Ac Transmission Systems 2Mark Materials and Question BankFlexible Ac Transmission Systems 2Mark Materials and Question Bank
Flexible Ac Transmission Systems 2Mark Materials and Question Bank
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
 
project report on IPFC
project report on IPFCproject report on IPFC
project report on IPFC
 
Vishws jain seminar
Vishws jain seminarVishws jain seminar
Vishws jain seminar
 
facts introducrion
facts introducrion  facts introducrion
facts introducrion
 
Upfc & fact
Upfc & factUpfc & fact
Upfc & fact
 
power quality improvement of power system network using UPFC
power quality improvement of power system network using UPFCpower quality improvement of power system network using UPFC
power quality improvement of power system network using UPFC
 
Facts lectures-2014
Facts lectures-2014Facts lectures-2014
Facts lectures-2014
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
 
Presentation On Fact Device
Presentation On Fact Device Presentation On Fact Device
Presentation On Fact Device
 
Power factor improvement using upfc
Power factor improvement using upfcPower factor improvement using upfc
Power factor improvement using upfc
 
FACTS DEVICES
FACTS DEVICESFACTS DEVICES
FACTS DEVICES
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 

Viewers also liked

Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties ahmedgoun
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sectorRahul Gupta
 
Power sector – Transmission and Distribution
Power sector – Transmission and DistributionPower sector – Transmission and Distribution
Power sector – Transmission and DistributionR Rohit Amalan
 
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015Francisco Gonzalez-Longatt
 
Sistemas proteccion
Sistemas proteccionSistemas proteccion
Sistemas proteccionEdison Rojas
 
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.Francisco Gonzalez-Longatt
 
Data Management in DIgSILENT PowerFactory 2010
Data Management in DIgSILENT PowerFactory 2010Data Management in DIgSILENT PowerFactory 2010
Data Management in DIgSILENT PowerFactory 2010Francisco Gonzalez-Longatt
 
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...Francisco Gonzalez-Longatt
 
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...PowerFactory Applications for Power System Analysis, 26th October 2015, Por...
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...Francisco Gonzalez-Longatt
 

Viewers also liked (10)

How Markets Work: The Case of Developing Countries
How Markets Work: The Case of Developing CountriesHow Markets Work: The Case of Developing Countries
How Markets Work: The Case of Developing Countries
 
Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
Power sector – Transmission and Distribution
Power sector – Transmission and DistributionPower sector – Transmission and Distribution
Power sector – Transmission and Distribution
 
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015
Future Energy System: Big-data+Uncertainties = Risk, Arequipa, Peru 6 oct2015
 
Sistemas proteccion
Sistemas proteccionSistemas proteccion
Sistemas proteccion
 
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.
Tutorial: Introduction to Transient Analysis using DIgSILENT PowerFactory.
 
Data Management in DIgSILENT PowerFactory 2010
Data Management in DIgSILENT PowerFactory 2010Data Management in DIgSILENT PowerFactory 2010
Data Management in DIgSILENT PowerFactory 2010
 
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...
Future Meshed HVDC Grids: Challenges and Opportunities, 29th October 2015, Po...
 
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...PowerFactory Applications for Power System Analysis, 26th October 2015, Por...
PowerFactory Applications for Power System Analysis, 26th October 2015, Por...
 

Similar to Planning & Designing of Distribution System

NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportAneel-k Suthar
 
Review notes power transmssion
Review notes power transmssionReview notes power transmssion
Review notes power transmssionsharique Akhtar
 
45 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_245 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_2Durga Prasada Rao M
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Living Online
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointslmnsvn
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusDrCVMOHAN
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substationShivamUpadhyay86734
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-pptLaveen Raghunam
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Designphase3-120A
 
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...IRJET Journal
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET Journal
 

Similar to Planning & Designing of Distribution System (20)

NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
Review notes power transmssion
Review notes power transmssionReview notes power transmssion
Review notes power transmssion
 
45 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_245 16255 ee543_2015_1__2_1_week_1_2
45 16255 ee543_2015_1__2_1_week_1_2
 
Vinay r epo rt
Vinay r epo rtVinay r epo rt
Vinay r epo rt
 
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
Practical Medium and High Voltage Testing of Electrical Equipment for Enginee...
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection point
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabus
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Trans distn.ppt
Trans distn.pptTrans distn.ppt
Trans distn.ppt
 
TD unit 5-1.ppt
TD unit 5-1.pptTD unit 5-1.ppt
TD unit 5-1.ppt
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
H09 Building Level Design
H09 Building Level DesignH09 Building Level Design
H09 Building Level Design
 
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...
Design and Simulation of Generation of High DC Voltage using Cockcroft Walton...
 
Hvdc
HvdcHvdc
Hvdc
 
POWER FACTOR.pptx
POWER FACTOR.pptxPOWER FACTOR.pptx
POWER FACTOR.pptx
 
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
IRJET-Comparative Analysis of Rectangular and Square Column for Axial loading...
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Planning & Designing of Distribution System

  • 1. A Presentation on: Electrification on “Malda Polytechnic”: Planning & Designing of Distribution System
  • 2. Project Members: Sourav Das Milan kr Das Santu Majee Ujjwal Maiti Santu Maiti Pratim Chakrabortty Debabrata Karmakar Subho Mondal Animesh Kanrar Jahir Mallick Manas Adak
  • 3. Planning of Distribution System A distribution system deals with the distribution of electrical energy. A good system planning should provide for an orderly development of the system to meet the power requirements for a period of about five years and to obtain optimum benefit from the available resources. The main purpose of planning is:  To make the system economical while conforming to the Indian electricity rules.  To minimize losses and maintain regulation within permissible limits. For proper Planning of a distribution system. Load survey and load forecasting of the area is necessary.
  • 4. * Load Survey * The load survey of a particular area is carried out to find present load requirement as well as the expected load growth over a period of 5 to 7 years. The following basic data should be collected for starting this work:  A detailed map of the area showing important features.  The number of houses, population and the new construction anticipated the area.  The expected number of shops post-office, rural health center Panchayat office etc.  Details of hospital s, railway stations, public health sewage systems and water supply schemes.  The cultivated area, number of wells, available irrigation facilities and irrigated area.  The type of industries and number of industries possible in these areas.  Development programs implemented and envisaged in the area.
  • 5. * Load Calculation of Hostel *  1st Year Block 10.48 kW  2nd Year Block 12.21 kW  3rd Year Block 12.21 kW  Common Room 0.883 kW  Dining Room 0.883 kW
  • 6. * Load Calculation of Nodal Office * Regional Office 9.004 kW  VET Office 2.667 kW
  • 7. * Load Calculation of College Building *  Workshops & Laboratories 153.67 kW  Classrooms 20.68 kW  Teachers’ Rooms 4.95 kW  Other Official Rooms 8.41 kW  Stadium 79.42 kW
  • 8. * Demand Factors *  Single Storied → 0.8 Public Building → 0.8  Double Storied → 0.7 Commercial Building → 0.9  Triple Storied → 0.6 Cinema Hall → 0.9  Multi Storied → 0.8 Industry → 0.8 Street Light → 1.0  Public Fan → 0.9  Domestic Fan → 0.3 to 0.6  Domestic Light → 0.3 to 0.6  Public Light → 0.8 to 0.9  Commercial Light → 0.5 to 0.75  Industrial Motor → 0.95  Pump Motor → 0.95
  • 9. * Total Load Calculation *  1st Year Block 10.48 kW  2nd + 3rd Year Block 26.136 kW  Nodal Office 9.004 kW  Workshops 37.662 kW  College 118.273 kW  Automobile 1st Yr+Mechanical 1st Yr 1.996 kW  Stadium 79.420 kW  Total Load 282.971 kW
  • 10. * Some Important Definitions *  Connected Load: It is the sum the continuous rating in KW of all electrical devices at the consumers premises and connected to the supply system.  Demand factor: Demand factor is defined as the ratio of maximum demand made by the load to the rating of the connecting load. Demand Factor= (Maximum demand made by the Load)/ (Rating of Connected Load) The value of Demand Factor determines the rating and hence the cost of power equipments to supply given connected load.  Load Factor : Load Factor is the ratio of average Demand to the Maximum Demand during a certain period of time such a month or a day or a year and is applicable to both generating equipment or receiving equipment. Load Factor = (Average Demand)/ (Maximum demand)  Connected Load Factor: It is the ratio of average power input to the connected load and related only to the receiving equipment. Connected Load Factor = (Average Power Input)/ (Connected Load)
  • 12. By back calculation the current turns negative at between e and f. hence, f point in the minimum potential point where current turns negative. Now, as per I.E rule voltage drop up to MP is 11.5 V (5% of 230v). 45𝝆 x224.09 + 125 𝝆 x 176.75 + 100 𝝆 x32.88 + 95 𝝆 x 13.9 = 11.5 V Hence 𝝆 =0.00031 ohm/ m =0.31 ohm/ km.
  • 13. * Determination of Load Centre *
  • 14. * Graphical Representation of ‘Load Centre’ *
  • 15. * Calculation for Water Works * Assume, total Population= 450. Water used by each= 25 Gallons/Head/Day. So, Water necessary= 11,250 Gallons/ Day. Now, H.P.= = 17.08 HP Here, W= Specific Gravity= 62.4 Lb/ft. Q= Discharge in cubic ft./sec. H= Total head (In ft.) Taking Efficiency of the Pump= 70% & Demand Factor= 1, we can calculate that Maximum Demand for Water Works= 18 kW
  • 16. * Prediction of Future Loads * Forecasting the future load requirement is essential part of power project design. This forecast of lone is done by two namely statically method and field survey method. Fundamental law of statistical is that every phenomenon in future obeys some mathematical law which can be represented by a smooth curve load development in any area except due to unforeseen developments such as the establishment to this low. According to this method of annual maximum demand pertaining to the area is collected for past several years. In the field survey method, existing requirement area is found out under different classes of load i.e. residential, commercial, industrial, municipal and agricultural. Future load requirement are then forecast taking into account various factors such as population growth , natural resources of the region standard of living of the people, topography and climate of the region.
  • 17. TRANSMISSION AND DISTRIBUTION SYSTEMS * (In Accordance With Indian Electricity Rules 1956 and IS: 585-1962) 1. VOLTAGE: 1.1 Declared voltage The declared voltage is the voltage at the consumers’ terminals declared by the supplier of electrical energy. It is to maintenance within the limits prescribed the Indian electricity rules. 1.2 System Voltage (Nominal Voltage) This is the line-to-line voltage for which the system is designed and installed. This is the voltage by which the system is generally designed. It is not necessarily the rated voltage of every piece of apparatus connected to the system. 1.3 Rated voltage This is the voltage at which the apparatus connected to the system is designed to operate under normal conditions. This is normally the same as the system voltage. 1.4 Low voltage A voltage not exceeding 250 V under normal conditions is considered low. 1.5 Medium Voltage A voltage exceeding 250 V but not 650 V under normal conditions are considered high. 1.6 High Voltage Voltages exceeding 650 V but not 33 KV under normal conditions are considered high. 1.7 Extra-High Voltage It is a voltage exceeding 33 KV under normal conditions.
  • 18. 2. STANDARD VOLTAGE FOR SINGLE - PHASE SYSTEM: The standard voltage system for a two-wire single-phase system is 240V. 3. STANDARD VOLTAGE FOR THREE-PHASE SYSTEM: The standard preferred voltage for three-phase systems is as follows. 415 V (Voltage to neutral=240V) 3.3 kV 66 kV 6.6 kV 132 kV 11 kV 220 kV 33 kV 400 kV Note: The above voltage refers to line-to-line voltages.
  • 19. 4. VOLTAGE LIMITS: The voltage at the point of commencement of supply under conditions should not vary from the declared voltage by more than: (i) 6% in case low or medium voltages. (ii) 6% on the higher side or by more than 9% on the lower side, in case of high voltages. (iii)12.5% In case of extra-high voltages. 5. STANDARD SYSTEM FREQUENCY: The standard system frequency is 50 Hz. The frequency of an alternating current supply should not very from the declared frequency by more than 3%.
  • 20. * INDIAN ELECTRICITY RULES, REGARDING THE CLEARANCE OF OVERHEAD LINES * IV.1 Rule- 77 CLEARENCE ABOVE GROUND OF THE LOWEST CONDUCTOR: 1. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a height less than: (i) For low and medium voltage lines 5,971 m (19 ft). (ii) For high voltage lines 6,096 m (20 ft). 2. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a height less than: (i) For low and medium voltage lines 5,486 m (18 ft). (ii) For high voltage lines 5,791 m (19 ft). 3. No conductor of an overhead line, including service lines, created a street shall at any part thereof be at a height less than: (i) For low, medium and high voltage lines up to and including 11,000 V if bare 4,572m (15 ft). (ii) For low, medium and high voltage lines up to and including 11,000 V if insulated 3,962 m (13 ft). (iii) For high voltage lines above 11,000 V 5,182 m (17 ft). (iv) For extra –high voltage lines, the clearance above ground shall not be less than 5,182 m (17 ft) plus 0.305 m (1 ft) for every 33,000 V or part thereof by which the voltage of the line exceeds 33,000 V provided that the minimum clearance along or across any street is not less than 6.096 m (20 ft).
  • 21. IV.3 Rule- 79 CLEARANCE FROM OF BUILDING OF LOW AND MEDIUM VOLTAGE LINES AND SERVICE LINES: 1. Where a low or medium voltage overhead line passes above or adjacent to or terminates on any building, the following minimum clearance from any accessible point, on the basis of maximum sag shall be observed: (i) For any flat, roof, open balcony, verandah, roof and lean to roof: (a) when the line passes above the building a vertical clearance of 2.439 m(8 ft) from the highest point, (b) when the line passes adjacent to the building, a horizontal clearance 1.219m (4 ft). (ii) For pitched roof: (a) When the line passes above the building a vertical clearance of 2.498m (8 ft), immediately under the lines and (b) When the line passes adjacent to the building, a horizontal clearance of 1.219m (4 ft). 2. Any conductor so situated as to have a clearance less than that specified in sub rule 1 shall be adequately insulated and shall be attached at suitable interval to a bare earthed bearer when having a breaking strength of not less than 377.51 kg (700ib). 3. The horizontal clearance shall be measure when the is at a maximum deflection from the vertical due to wind pressure.