The Project Charter
The most Important and Powerful Document to
use for Initiating, Controlling and Preparing a
Project in order to ensure Project Quality
Presented by Mark Troncone, MBA, PMP®, ITILv3, CSM®
Agenda
 Why do you need a Project Charter?
 When is a Project Charter Created?
 Why is a Project Charter Important?
 When should a Project Charter be used?
 How to Create a Project Charter
 The Traditional Sections to Include
 The New Sections that Must be included for Quality
 When should it be Updated?
 Who Should Sign Off?
About Me
 PMP® Certified – Project Management Institute
 CRM Certified SCRUM Master® – SCRUM Alliance
 ITILv3 Foundations® Certified -
 Certified IT Business Analyst – IFS State of Connecticut
 MT Associates - Active career transition mentor
 MBA – Management, BS – Marketing, AS – Accounting
 Work Experience:
• Save the Children
• Transact Technologies
• Starwood Hotels
• Affinion Group
• Hewitt Associates
• Wachovia Bank
• Bayer Pharmaceuticals
• Reader’s Digest
• James River Corporation
Why do you need a Project Charter
 As a Project Manager – it is your “Power Document” to use
throughout the life of a project
 You cannot start nor run a Project without one
 The Project Charter formally recognizes /authorizes the existence of
the Project
 A project does not exist without a Project Charter
 The Project Charter gives the Project Manager authority to spend
money and commit corporate resources
 The Project Charter provides “high-level” requirements and scope
for the Project
 The Project Charter links the Project to the on-going work of the
organization
 Any changes to the Project Charter after “Sign-Off” will necessitate
questioning whether or not the Project should continue
When is a Project Charter Created
Tasks developed during the Initiating Phase:
 Select a Project Manager
 Determine company culture and existing systems
 Divide large projects into Phases
 Understand the Business Case
 Uncover “Initial” requirements and risks
 Create Measurable Objectives
 Identify Stakeholders (I would do this before the Project Charter)
 Develop Stakeholder Management Strategy
 Create Project Charter
Why is a Project Charter Important
 Defines how success will be measured
 Defines Deliverables/Scope (Project and Product)
 Defines the Project Manager Authority Level
 Defines Project Team roles and responsibilities
 Defines the Business Case
 Defines the Stakeholders and their Expectations
 Defines Measurable Objectives
 Defines Project Approval Requirements
 Defines “High Level” Project Risks
 I will define other areas to add later in the presentation
When should a Project Charter be used
 As mentioned, the Project Charter should be developed
during the Initiation Phase of the Project
 The Project Charter should be reviewed after the Project
“Kick-Off” meeting with:
• The Stakeholder(s)
• Key Business User(s)
• Subject Matter Expert(s)
• 3rd Party Vendor lead(s)
• Project Team
• Project Sponsor(s)
 The Project Charter should also be referenced throughout
the project conflict resolutions concerning any area of
dispute of how the project should be run. This then
becomes the Project Manager’s Power Document -
to say “This is what we agreed on”
How to Create a Project Charter
 You should have a template document created with
all of the sections included in this presentation to
quickly - fill out / update / amend
 Also include:
• Revision History (in the front)
• Table of contents (in the front after the Revision History)
 Sign Off Section (last page of the document)
 Sign Off Section to include:
• Project Sponsor(s)
• Key Stakeholder(s)
• Project Manager
• Other Representatives as determined
The Traditional Sections of the Project
Charter to Include
 Cover Page:
• Company Name/Logo
• Project Name and Project Number
• Date Created (MM/DD/YYY)
• Version Number
 Revision History (Type / Date / Change and Section / By Whom)
 Table of Contents
 Project Title and Description
 Project Scope (High Level Deliverables and end result of the project)
 Business Case (Why is the Project being done)
 Project Manager Assigned and their Authority Level
 Stakeholders and Stakeholder Requirements
The Traditional Sections of the Project
Charter to Include
 Project Agreements:
• What your business will provide
• What the other entity will provide (if necessary)
• What a 3rd Party Vendor will provide (if necessary)
• Responsibilities of any entity or 3rd Party Vendor Project Manager
• Products to be Installed/Upgraded
• Exclusions (What the company is excluded from delivering)
• Assumptions / Constraints
• Acceptance Criteria
 Measurable Project Objectives (measurable strategic goals)
 Project Approval Requirements (items needing approval)
 High Level Business Risks (potential risks and opportunities)
The New Project Charter Sections that
Must be included for Quality
I suggest adding the sections mentioned on the following
slides to ensure quality is delivered throughout the
project:
• For larger projects (> one year, > $$$ Budget and > X amount of
resources) you may want to have separate documents addressing
these areas with separate meetings and sign-offs. This can be
time consuming but necessary.
• For smaller projects it will improve the process to have all of these
sections combined in one document (Project Charter) that can be
referenced and updated easily.
• Also all topics within this Project Charter can be reviewed,
discussed and agreed upon in one meeting with all of the
significant team members present.
The New Project Charter Sections that
Must be included for Quality
 Project Plan and Milestones (without dates)
• Describes how the project will be run and managed
• Names the Milestone Tasks to achieve for each phase
 Project Communications Plan
◦ Describes how the project team will communicate:
• To Stakeholders, Project Sponsors, Key Business Users
• To the Project Team, Partnering Entity, 3rd Prty Vendor
• To any other resource needing updates
• How the Project Team will communicate Project Tasks updates
• Contains a Visual Project Task Spreadsheet
• Project Meetings – Structure / Agenda / How Often / Schedules
• Weekly Project Dashboard and Status Reports – Schedules
The New Project Charter Sections that
Must be included for Quality
• Communications of any “Sub-Teams” – Structure and agenda
• Chart for Scheduled Meetings (meeting name, method,
attendees, leader, frequency)
• Contacts Lists (Name, Title, Phone, Email Address)
• Email Subject Line Structure
 Project Name
 Project Categories
 Project Level (1= High Must Read, 2 = medium Be Informed, 3 = Low FYI)
 Subject Line Message
• Requirements Plan
• High level plan describing how requirements will be gathered
• Estimates Business Analyst effort and Business Commitment
The New Project Charter Sections that
Must be included for Quality
 Requirements
• How they will be gathered (Functional and Non-Functional)
• Method for Reviewing Requirements with business
• Commitments of time from the business to ensure requirements
are delivered on time
• How Sign-Offs will be obtained
 Project Risk Management Plan
• How Risks will be Captured / Scored / Responded To
• Contingency Plans developed here
 Project Issues Management Plan
• How Issues will be Categorized / Rated for Severity / Monitored
and resolved – then communicated back to all Team Members
The New Project Charter Sections that
Must be included for Quality
 Project Change Control Management Plan
• To Log a Requested Change / Prioritize / Note Effects / Approve
• Change Approval while project is in-flight
• Change Enhancement after Project Closure
• Change Dismissed as Not Needed
 Project Training Plan
• Training Plan including system modules and written manuals
• Training Plan Schedule and who will need to be trained
 Project Testing Plan
• Unit Testing – by developers and review with the business
• QA Testing – Test Scripts and Sign-Off
• UAT Testing – Test Scripts and Sign-Off
The New Project Charter Sections that
Must be included for Quality
 Project Implementation Plan
• Technical Cut Over – High Level Tasks – incl. Non-Functionals
 Project “Go Live” Plan
• Go Live Plan (duration) and Monitoring
 Project Closure
• Project Closing Plan
 Project Lessons Learned Management Plan
• Identify Type / Severity / Escalation Process / where to keep
 Project – Application Support Plan
• How will the application be supported (Customer Service and
Help Desk) – who will need training
When to Update the Project Charter
 Update up and to the final presentation to the:
• Stakeholders
• Project Sponsors
• Key Business Users and Subject Matter experts
• Project Team
 Can be updated after reviewed and signed-off only
if all Team Members agree to the amendment
 But if continually changed or questioned after Sign-
Off the question should be raised “Do we continue
with the project?”
Who should Sign-Off on the Project
Charter
 At a minimum the Project Charter should be signed off by:
• Stakeholder(s)
• Project Sponsor(s)
• Project Manager / Tech Lead / Business SME(s)
 Can be updated after reviewed
• Key Business Users and Subject Matter experts
• Other Key Department Stakeholders that this project may effect
• Key Project Team Members:
• DBA
• QA Lead
• Lead Developer
• Network or Technical Leads
QUESTIONS?
Tell me what you think
mtroncone73@yahoo.com

More Related Content

What's hot

Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
Nithin Dev
 

What's hot (20)

The Project Management Process - Week 6 Leadership
The Project Management Process - Week 6   LeadershipThe Project Management Process - Week 6   Leadership
The Project Management Process - Week 6 Leadership
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptx
 
Project Management PowerPoint Presentation Slides
Project Management PowerPoint Presentation SlidesProject Management PowerPoint Presentation Slides
Project Management PowerPoint Presentation Slides
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Project management
Project managementProject management
Project management
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project manager
Project managerProject manager
Project manager
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Viewers also liked

Orgb Team Charter[1]
Orgb   Team Charter[1]Orgb   Team Charter[1]
Orgb Team Charter[1]
guest30696ca8
 
The Groop Project Checklist
The Groop Project Checklist The Groop Project Checklist
The Groop Project Checklist
thegroop
 

Viewers also liked (14)

Roles responsabilities-jc
Roles responsabilities-jcRoles responsabilities-jc
Roles responsabilities-jc
 
Qa exploratory test charter template
Qa exploratory test charter templateQa exploratory test charter template
Qa exploratory test charter template
 
Orgb Team Charter[1]
Orgb   Team Charter[1]Orgb   Team Charter[1]
Orgb Team Charter[1]
 
Project charter sample
Project charter sampleProject charter sample
Project charter sample
 
GoodData: The DevOps Story @ FIT CVUT October 16 2013
GoodData: The DevOps Story @ FIT CVUT October 16 2013GoodData: The DevOps Story @ FIT CVUT October 16 2013
GoodData: The DevOps Story @ FIT CVUT October 16 2013
 
Quality Assurance
Quality AssuranceQuality Assurance
Quality Assurance
 
[Srijan Wednesday Webinars] Building a High Performance QA Team
[Srijan Wednesday Webinars] Building a High Performance QA Team[Srijan Wednesday Webinars] Building a High Performance QA Team
[Srijan Wednesday Webinars] Building a High Performance QA Team
 
Why Everyone Needs DevOps Now: 15 Year Study Of High Performing Technology Orgs
Why Everyone Needs DevOps Now: 15 Year Study Of High Performing Technology OrgsWhy Everyone Needs DevOps Now: 15 Year Study Of High Performing Technology Orgs
Why Everyone Needs DevOps Now: 15 Year Study Of High Performing Technology Orgs
 
Role of QA in Continuous Delivery
Role of QA in Continuous DeliveryRole of QA in Continuous Delivery
Role of QA in Continuous Delivery
 
The Groop Project Checklist
The Groop Project Checklist The Groop Project Checklist
The Groop Project Checklist
 
My Personal CORE Strategy: Brand, Customers, Goals
My Personal CORE Strategy: Brand, Customers, Goals My Personal CORE Strategy: Brand, Customers, Goals
My Personal CORE Strategy: Brand, Customers, Goals
 
The Prime Directive. How To Charter Your Team Best (With LEGO Serious Play)
The Prime Directive. How To Charter Your Team Best (With LEGO Serious Play)The Prime Directive. How To Charter Your Team Best (With LEGO Serious Play)
The Prime Directive. How To Charter Your Team Best (With LEGO Serious Play)
 
Project Metrics & Measures
Project Metrics & MeasuresProject Metrics & Measures
Project Metrics & Measures
 
Developing Metrics and KPI (Key Performance Indicators
Developing Metrics and KPI (Key Performance IndicatorsDeveloping Metrics and KPI (Key Performance Indicators
Developing Metrics and KPI (Key Performance Indicators
 

Similar to The Project Charter Ensuring Quality

Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012
satish526
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
apoorvaguptaspn27
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
Sharad Srivastava
 
Plan_QualityManagement
Plan_QualityManagementPlan_QualityManagement
Plan_QualityManagement
Fahad Saleem
 
Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0
lee_anderson40
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
Goutama Bachtiar
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
gatecomro
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
Noman Aftab
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
sombat nirund
 

Similar to The Project Charter Ensuring Quality (20)

The project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project successThe project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project success
 
Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012Do it, sf state project lifecycle management (plm) v1.19 091012
Do it, sf state project lifecycle management (plm) v1.19 091012
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
Plan_QualityManagement
Plan_QualityManagementPlan_QualityManagement
Plan_QualityManagement
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0Project Management Toolkit_Final v1.0
Project Management Toolkit_Final v1.0
 
Effective Project Integration Management
Effective Project Integration ManagementEffective Project Integration Management
Effective Project Integration Management
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
My resume
My resumeMy resume
My resume
 
6396901
63969016396901
6396901
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 

More from Mark Troncone MBA, PMP, CBAP, ITILv3, CSM

More from Mark Troncone MBA, PMP, CBAP, ITILv3, CSM (15)

Networking - Everything That You Wanted to Know
Networking - Everything That You Wanted to KnowNetworking - Everything That You Wanted to Know
Networking - Everything That You Wanted to Know
 
The 10 Questions you must ask Before you start your Job Search
The 10 Questions you must ask Before you start your Job SearchThe 10 Questions you must ask Before you start your Job Search
The 10 Questions you must ask Before you start your Job Search
 
QUIKSOLVER
QUIKSOLVERQUIKSOLVER
QUIKSOLVER
 
Mark Troncone Value Proposition_Color v 5.0
Mark Troncone Value Proposition_Color v 5.0Mark Troncone Value Proposition_Color v 5.0
Mark Troncone Value Proposition_Color v 5.0
 
Knowing your Interviewer’s Personality Type – Answering their Questions the R...
Knowing your Interviewer’s Personality Type – Answering their Questions the R...Knowing your Interviewer’s Personality Type – Answering their Questions the R...
Knowing your Interviewer’s Personality Type – Answering their Questions the R...
 
How to Create an Effective Marketing Plan
How to Create an Effective Marketing PlanHow to Create an Effective Marketing Plan
How to Create an Effective Marketing Plan
 
It Business Analyst Consultative Skills
It Business Analyst Consultative SkillsIt Business Analyst Consultative Skills
It Business Analyst Consultative Skills
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
How the change control process affects project quality
How the change control process affects project qualityHow the change control process affects project quality
How the change control process affects project quality
 
Creating An Elevator Speech That Wow’s
Creating An Elevator Speech That Wow’sCreating An Elevator Speech That Wow’s
Creating An Elevator Speech That Wow’s
 
Everything That You Wanted To Know About Networking
Everything That You Wanted To Know About NetworkingEverything That You Wanted To Know About Networking
Everything That You Wanted To Know About Networking
 
How To Plan And Lead A Meeting For Maximum Results
How To Plan And Lead A Meeting For Maximum ResultsHow To Plan And Lead A Meeting For Maximum Results
How To Plan And Lead A Meeting For Maximum Results
 
10 Questions You Must Ask Before You Start Your Job Search
10 Questions You Must Ask Before You Start Your Job Search10 Questions You Must Ask Before You Start Your Job Search
10 Questions You Must Ask Before You Start Your Job Search
 
Implementing Dr Demings Quality Philosophy Within An It Area
Implementing Dr Demings Quality Philosophy Within An It AreaImplementing Dr Demings Quality Philosophy Within An It Area
Implementing Dr Demings Quality Philosophy Within An It Area
 
How To Prepare For A Phone Interview
How To Prepare For A Phone InterviewHow To Prepare For A Phone Interview
How To Prepare For A Phone Interview
 

Recently uploaded

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 

Recently uploaded (16)

Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 

The Project Charter Ensuring Quality

  • 1. The Project Charter The most Important and Powerful Document to use for Initiating, Controlling and Preparing a Project in order to ensure Project Quality Presented by Mark Troncone, MBA, PMP®, ITILv3, CSM®
  • 2. Agenda  Why do you need a Project Charter?  When is a Project Charter Created?  Why is a Project Charter Important?  When should a Project Charter be used?  How to Create a Project Charter  The Traditional Sections to Include  The New Sections that Must be included for Quality  When should it be Updated?  Who Should Sign Off?
  • 3. About Me  PMP® Certified – Project Management Institute  CRM Certified SCRUM Master® – SCRUM Alliance  ITILv3 Foundations® Certified -  Certified IT Business Analyst – IFS State of Connecticut  MT Associates - Active career transition mentor  MBA – Management, BS – Marketing, AS – Accounting  Work Experience: • Save the Children • Transact Technologies • Starwood Hotels • Affinion Group • Hewitt Associates • Wachovia Bank • Bayer Pharmaceuticals • Reader’s Digest • James River Corporation
  • 4. Why do you need a Project Charter  As a Project Manager – it is your “Power Document” to use throughout the life of a project  You cannot start nor run a Project without one  The Project Charter formally recognizes /authorizes the existence of the Project  A project does not exist without a Project Charter  The Project Charter gives the Project Manager authority to spend money and commit corporate resources  The Project Charter provides “high-level” requirements and scope for the Project  The Project Charter links the Project to the on-going work of the organization  Any changes to the Project Charter after “Sign-Off” will necessitate questioning whether or not the Project should continue
  • 5. When is a Project Charter Created Tasks developed during the Initiating Phase:  Select a Project Manager  Determine company culture and existing systems  Divide large projects into Phases  Understand the Business Case  Uncover “Initial” requirements and risks  Create Measurable Objectives  Identify Stakeholders (I would do this before the Project Charter)  Develop Stakeholder Management Strategy  Create Project Charter
  • 6. Why is a Project Charter Important  Defines how success will be measured  Defines Deliverables/Scope (Project and Product)  Defines the Project Manager Authority Level  Defines Project Team roles and responsibilities  Defines the Business Case  Defines the Stakeholders and their Expectations  Defines Measurable Objectives  Defines Project Approval Requirements  Defines “High Level” Project Risks  I will define other areas to add later in the presentation
  • 7. When should a Project Charter be used  As mentioned, the Project Charter should be developed during the Initiation Phase of the Project  The Project Charter should be reviewed after the Project “Kick-Off” meeting with: • The Stakeholder(s) • Key Business User(s) • Subject Matter Expert(s) • 3rd Party Vendor lead(s) • Project Team • Project Sponsor(s)  The Project Charter should also be referenced throughout the project conflict resolutions concerning any area of dispute of how the project should be run. This then becomes the Project Manager’s Power Document - to say “This is what we agreed on”
  • 8. How to Create a Project Charter  You should have a template document created with all of the sections included in this presentation to quickly - fill out / update / amend  Also include: • Revision History (in the front) • Table of contents (in the front after the Revision History)  Sign Off Section (last page of the document)  Sign Off Section to include: • Project Sponsor(s) • Key Stakeholder(s) • Project Manager • Other Representatives as determined
  • 9. The Traditional Sections of the Project Charter to Include  Cover Page: • Company Name/Logo • Project Name and Project Number • Date Created (MM/DD/YYY) • Version Number  Revision History (Type / Date / Change and Section / By Whom)  Table of Contents  Project Title and Description  Project Scope (High Level Deliverables and end result of the project)  Business Case (Why is the Project being done)  Project Manager Assigned and their Authority Level  Stakeholders and Stakeholder Requirements
  • 10. The Traditional Sections of the Project Charter to Include  Project Agreements: • What your business will provide • What the other entity will provide (if necessary) • What a 3rd Party Vendor will provide (if necessary) • Responsibilities of any entity or 3rd Party Vendor Project Manager • Products to be Installed/Upgraded • Exclusions (What the company is excluded from delivering) • Assumptions / Constraints • Acceptance Criteria  Measurable Project Objectives (measurable strategic goals)  Project Approval Requirements (items needing approval)  High Level Business Risks (potential risks and opportunities)
  • 11. The New Project Charter Sections that Must be included for Quality I suggest adding the sections mentioned on the following slides to ensure quality is delivered throughout the project: • For larger projects (> one year, > $$$ Budget and > X amount of resources) you may want to have separate documents addressing these areas with separate meetings and sign-offs. This can be time consuming but necessary. • For smaller projects it will improve the process to have all of these sections combined in one document (Project Charter) that can be referenced and updated easily. • Also all topics within this Project Charter can be reviewed, discussed and agreed upon in one meeting with all of the significant team members present.
  • 12. The New Project Charter Sections that Must be included for Quality  Project Plan and Milestones (without dates) • Describes how the project will be run and managed • Names the Milestone Tasks to achieve for each phase  Project Communications Plan ◦ Describes how the project team will communicate: • To Stakeholders, Project Sponsors, Key Business Users • To the Project Team, Partnering Entity, 3rd Prty Vendor • To any other resource needing updates • How the Project Team will communicate Project Tasks updates • Contains a Visual Project Task Spreadsheet • Project Meetings – Structure / Agenda / How Often / Schedules • Weekly Project Dashboard and Status Reports – Schedules
  • 13. The New Project Charter Sections that Must be included for Quality • Communications of any “Sub-Teams” – Structure and agenda • Chart for Scheduled Meetings (meeting name, method, attendees, leader, frequency) • Contacts Lists (Name, Title, Phone, Email Address) • Email Subject Line Structure  Project Name  Project Categories  Project Level (1= High Must Read, 2 = medium Be Informed, 3 = Low FYI)  Subject Line Message • Requirements Plan • High level plan describing how requirements will be gathered • Estimates Business Analyst effort and Business Commitment
  • 14. The New Project Charter Sections that Must be included for Quality  Requirements • How they will be gathered (Functional and Non-Functional) • Method for Reviewing Requirements with business • Commitments of time from the business to ensure requirements are delivered on time • How Sign-Offs will be obtained  Project Risk Management Plan • How Risks will be Captured / Scored / Responded To • Contingency Plans developed here  Project Issues Management Plan • How Issues will be Categorized / Rated for Severity / Monitored and resolved – then communicated back to all Team Members
  • 15. The New Project Charter Sections that Must be included for Quality  Project Change Control Management Plan • To Log a Requested Change / Prioritize / Note Effects / Approve • Change Approval while project is in-flight • Change Enhancement after Project Closure • Change Dismissed as Not Needed  Project Training Plan • Training Plan including system modules and written manuals • Training Plan Schedule and who will need to be trained  Project Testing Plan • Unit Testing – by developers and review with the business • QA Testing – Test Scripts and Sign-Off • UAT Testing – Test Scripts and Sign-Off
  • 16. The New Project Charter Sections that Must be included for Quality  Project Implementation Plan • Technical Cut Over – High Level Tasks – incl. Non-Functionals  Project “Go Live” Plan • Go Live Plan (duration) and Monitoring  Project Closure • Project Closing Plan  Project Lessons Learned Management Plan • Identify Type / Severity / Escalation Process / where to keep  Project – Application Support Plan • How will the application be supported (Customer Service and Help Desk) – who will need training
  • 17. When to Update the Project Charter  Update up and to the final presentation to the: • Stakeholders • Project Sponsors • Key Business Users and Subject Matter experts • Project Team  Can be updated after reviewed and signed-off only if all Team Members agree to the amendment  But if continually changed or questioned after Sign- Off the question should be raised “Do we continue with the project?”
  • 18. Who should Sign-Off on the Project Charter  At a minimum the Project Charter should be signed off by: • Stakeholder(s) • Project Sponsor(s) • Project Manager / Tech Lead / Business SME(s)  Can be updated after reviewed • Key Business Users and Subject Matter experts • Other Key Department Stakeholders that this project may effect • Key Project Team Members: • DBA • QA Lead • Lead Developer • Network or Technical Leads
  • 19. QUESTIONS? Tell me what you think mtroncone73@yahoo.com