SlideShare a Scribd company logo
1 of 10
Download to read offline
Project Background
   Case Study of a
                                                  227 acre parcel in north central Kane
Successful SESC Plan                              County, Illinois
                                                  Agricultural  Residential Subdivision
                                                  291 Homes, Developed in Six Units
                                                      H         D   l    d i Si U it
         Jonathan Koepke, CPESC                   Curb and Gutter
          Resource Conservationist
         Kane-
         Kane-DuPage Soil & Water                 5 Detention Basins
            Conservation District




  Project Background (cont.)                                      Aerial
Three Planned Creek Crossings—Two
                      Crossings—
Permanent, One Temporary
One Drainageway Permanently Impacted
Obtained Corps of Engineers Permit which
requires SWCD review and i
     i              i     d inspection of S il
                                  ti     f Soil
Erosion and Sediment Control
Article 3-Erosion and Sediment Control-of the
        3-                      Control-
Kane County Stormwater Ordinance is
administered by the City
NPDES Permit Coverage




                                                                                           1
Topography Map       Water Features




  Soil Erosion and
Sediment Control Plan
     Total of 7 Sheets




                                          2
SWCD Standard Notes



Key Components
  y    p




                                       3
Legend of Practices    Scheduling Information




Perimeter Silt Fence   Stabilization Information




                                                   4
Stockpile Stabilization and
       Stabilization
                                           Protection




Early Completion of Basins     Other Stabilization Driving Force
                             Kane County Ordinance states that “[t]he area of
                               disturbance onsite at any one time shall be
                               limited to 20 acres. An additional 20 acres (a
                               maximum of 40 acres of disturbance at any one
                               time) may be stripped in order to balance cut
                               and fill onsite”.
                             Developer was told by City that he could not mass
                               grade another phase until the existing disturbed
                               areas were being stabilized




                                                                                  5
Diversion of Offsite Flow/Runoff      Sediment Traps/Basins




Erosion Control Blanket Location   Protection of Detention Basins




                                                                    6
Specific Instructions for Work in
           Critical Areas                  Work in Critical Areas
                                     Instructions resulted
                                     in an area-specific
                                           area-
                                     preconstruction
                                     meeting with the
                                     contractor, engineer,
                                     City, developer, and
                                     SWCD.
                                     Specific Plan was
                                     developed after
                                     meeting




Drawings for Temporary Practices     Drawings for Permanent Practices



                                                 Note: See IUM for
                                                  correct formula




                                                                        7
Stabilized Entrances       Clean Streets




                          Inlet Protection   Check Dams
       Not Recommended.
Other practices/products available.




                                                             8
Energy Dissipation           Energy Dissipation

   Note: See IUM for
    correct formula




Dewatering Notes       Inspection and Maintenance Notes




                                                          9
NPDES Signatory Requirements              Looking Back
                               Downstream end of diversion was
                               constructed as a swale. Keeping it as
                               confined channel all the way to the basin
                               may have worked better.
                                                  better
                               Stockpile location shown on plans




      Questions??




                                                                           10

More Related Content

What's hot

Full Cycle Tailings Management - Fosterville Gold Mine
Full Cycle Tailings Management - Fosterville Gold MineFull Cycle Tailings Management - Fosterville Gold Mine
Full Cycle Tailings Management - Fosterville Gold MineAdvisian
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Honolulu Civil Beat
 
Moffett RAB Site 14 Update
Moffett RAB Site 14 UpdateMoffett RAB Site 14 Update
Moffett RAB Site 14 UpdateSteve Williams
 
[Day 2] Center Presentation: IWMI
[Day 2] Center Presentation: IWMI[Day 2] Center Presentation: IWMI
[Day 2] Center Presentation: IWMIcsi2009
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Terry Aylward
 
Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportHonolulu Civil Beat
 
Kent Peterson Gulf Coast Green 2010
Kent Peterson Gulf Coast Green 2010Kent Peterson Gulf Coast Green 2010
Kent Peterson Gulf Coast Green 2010Hayley Pallister
 
Sand2016 7941 pe nea salt club presentation 082216 hansen llm
Sand2016 7941 pe nea salt club presentation 082216 hansen llmSand2016 7941 pe nea salt club presentation 082216 hansen llm
Sand2016 7941 pe nea salt club presentation 082216 hansen llmleann_mays
 
Nyc hard assets_conference_pdf_with_nan_symbol
Nyc hard assets_conference_pdf_with_nan_symbolNyc hard assets_conference_pdf_with_nan_symbol
Nyc hard assets_conference_pdf_with_nan_symbolVMS Ventures
 
March 2013 Newletter
March 2013 NewletterMarch 2013 Newletter
March 2013 Newlettercwright67
 
Prasad Modak Presentation at First Multistakholder Workshop
Prasad Modak Presentation at First Multistakholder WorkshopPrasad Modak Presentation at First Multistakholder Workshop
Prasad Modak Presentation at First Multistakholder WorkshopEkonnect
 
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS Projects
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS ProjectsGlobal CCS Institute - Day 1 - Panel 1 - International Progress on CCS Projects
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS ProjectsGlobal CCS Institute
 
CL:AIRE Research Bulletin RB3
CL:AIRE Research Bulletin RB3CL:AIRE Research Bulletin RB3
CL:AIRE Research Bulletin RB3chrisberryman
 

What's hot (20)

Full Cycle Tailings Management - Fosterville Gold Mine
Full Cycle Tailings Management - Fosterville Gold MineFull Cycle Tailings Management - Fosterville Gold Mine
Full Cycle Tailings Management - Fosterville Gold Mine
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report
 
Moffett RAB Site 14 Update
Moffett RAB Site 14 UpdateMoffett RAB Site 14 Update
Moffett RAB Site 14 Update
 
ORP FY13 Budget Workshop
ORP FY13 Budget WorkshopORP FY13 Budget Workshop
ORP FY13 Budget Workshop
 
[Day 2] Center Presentation: IWMI
[Day 2] Center Presentation: IWMI[Day 2] Center Presentation: IWMI
[Day 2] Center Presentation: IWMI
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
 
Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress report
 
Kent Peterson Gulf Coast Green 2010
Kent Peterson Gulf Coast Green 2010Kent Peterson Gulf Coast Green 2010
Kent Peterson Gulf Coast Green 2010
 
SDE Brochure
SDE BrochureSDE Brochure
SDE Brochure
 
Water Talks : Regional Seawater Desalination
Water Talks : Regional Seawater DesalinationWater Talks : Regional Seawater Desalination
Water Talks : Regional Seawater Desalination
 
Sand2016 7941 pe nea salt club presentation 082216 hansen llm
Sand2016 7941 pe nea salt club presentation 082216 hansen llmSand2016 7941 pe nea salt club presentation 082216 hansen llm
Sand2016 7941 pe nea salt club presentation 082216 hansen llm
 
Nyc hard assets_conference_pdf_with_nan_symbol
Nyc hard assets_conference_pdf_with_nan_symbolNyc hard assets_conference_pdf_with_nan_symbol
Nyc hard assets_conference_pdf_with_nan_symbol
 
311576 DD Inserts
311576 DD Inserts311576 DD Inserts
311576 DD Inserts
 
Praire creek
Praire creekPraire creek
Praire creek
 
March 2013 Newletter
March 2013 NewletterMarch 2013 Newletter
March 2013 Newletter
 
Integrating biophysical and socioeconomic model outputs
Integrating biophysical and socioeconomic model outputs Integrating biophysical and socioeconomic model outputs
Integrating biophysical and socioeconomic model outputs
 
Prasad Modak Presentation at First Multistakholder Workshop
Prasad Modak Presentation at First Multistakholder WorkshopPrasad Modak Presentation at First Multistakholder Workshop
Prasad Modak Presentation at First Multistakholder Workshop
 
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS Projects
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS ProjectsGlobal CCS Institute - Day 1 - Panel 1 - International Progress on CCS Projects
Global CCS Institute - Day 1 - Panel 1 - International Progress on CCS Projects
 
Deepwater
DeepwaterDeepwater
Deepwater
 
CL:AIRE Research Bulletin RB3
CL:AIRE Research Bulletin RB3CL:AIRE Research Bulletin RB3
CL:AIRE Research Bulletin RB3
 

Viewers also liked

Programma Elisa Innovazione di Sistema negli Enti Locali
Programma Elisa Innovazione di Sistema negli Enti LocaliProgramma Elisa Innovazione di Sistema negli Enti Locali
Programma Elisa Innovazione di Sistema negli Enti LocaliProgettoELI4U
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmKelseyMusich
 
Introduction To Swc Ds 5.27.09
Introduction To Swc Ds 5.27.09Introduction To Swc Ds 5.27.09
Introduction To Swc Ds 5.27.09KelseyMusich
 
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec España
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec EspañaPresentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec España
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec EspañaFIAB
 

Viewers also liked (6)

Programma Elisa Innovazione di Sistema negli Enti Locali
Programma Elisa Innovazione di Sistema negli Enti LocaliProgramma Elisa Innovazione di Sistema negli Enti Locali
Programma Elisa Innovazione di Sistema negli Enti Locali
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.Km
 
Morchok
MorchokMorchok
Morchok
 
Introduction To Swc Ds 5.27.09
Introduction To Swc Ds 5.27.09Introduction To Swc Ds 5.27.09
Introduction To Swc Ds 5.27.09
 
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec España
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec EspañaPresentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec España
Presentación VIII Cotec Europa 2012 - Juan Mulet, Director General Cotec España
 
Mythology and Geography
Mythology and GeographyMythology and Geography
Mythology and Geography
 

Similar to Successful Kane County Residential Development SESC Case Study

Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationUniversity of Wisconsin-Madison
 
NE Construction & Environment
NE Construction & EnvironmentNE Construction & Environment
NE Construction & EnvironmentCaspianwetsci
 
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...Healthy Lakes, Healthy Lives
 
Sustainable Site Design
Sustainable Site DesignSustainable Site Design
Sustainable Site Designemilydean
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisDan Arthur
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect
 
Mine closure and sustainable water management by prof carolyn oldham
Mine closure and sustainable water management by prof carolyn oldhamMine closure and sustainable water management by prof carolyn oldham
Mine closure and sustainable water management by prof carolyn oldhamEngineers Australia
 
8. Ricardo Monsivais - AES lac (parte 2)
8. Ricardo Monsivais - AES  lac (parte 2)8. Ricardo Monsivais - AES  lac (parte 2)
8. Ricardo Monsivais - AES lac (parte 2)Fundación Chile
 
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...D4Z
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Leed consultant review
Leed consultant reviewLeed consultant review
Leed consultant reviewJ C
 
A GIS based framework for assessing and mapping potential irrigation areas in...
A GIS based framework for assessing and mapping potential irrigation areas in...A GIS based framework for assessing and mapping potential irrigation areas in...
A GIS based framework for assessing and mapping potential irrigation areas in...World Agroforestry (ICRAF)
 
A gis based framework for assessing and mapping potential irrigation areas in...
A gis based framework for assessing and mapping potential irrigation areas in...A gis based framework for assessing and mapping potential irrigation areas in...
A gis based framework for assessing and mapping potential irrigation areas in...World Agroforestry (ICRAF)
 

Similar to Successful Kane County Residential Development SESC Case Study (20)

Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research Station
 
NE Construction & Environment
NE Construction & EnvironmentNE Construction & Environment
NE Construction & Environment
 
March 14, 2013
March 14, 2013March 14, 2013
March 14, 2013
 
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...
Cleveland Harbor Sustainable Sediment Management Strategies-White, Carter-Cor...
 
Savannah Harbor Expansion Project Update - March 14, 2013
Savannah Harbor Expansion Project Update - March 14, 2013Savannah Harbor Expansion Project Update - March 14, 2013
Savannah Harbor Expansion Project Update - March 14, 2013
 
Sustainable Site Design
Sustainable Site DesignSustainable Site Design
Sustainable Site Design
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 
Mine closure and sustainable water management by prof carolyn oldham
Mine closure and sustainable water management by prof carolyn oldhamMine closure and sustainable water management by prof carolyn oldham
Mine closure and sustainable water management by prof carolyn oldham
 
NFBWA Reuse and Conservation Considerations
NFBWA Reuse and Conservation ConsiderationsNFBWA Reuse and Conservation Considerations
NFBWA Reuse and Conservation Considerations
 
T s2 gh3_richard price
T s2 gh3_richard priceT s2 gh3_richard price
T s2 gh3_richard price
 
Civil Works Transformation
Civil Works TransformationCivil Works Transformation
Civil Works Transformation
 
8. Ricardo Monsivais - AES lac (parte 2)
8. Ricardo Monsivais - AES  lac (parte 2)8. Ricardo Monsivais - AES  lac (parte 2)
8. Ricardo Monsivais - AES lac (parte 2)
 
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...
Designing Bioretention with an Internal Water Storage Layer - NC Cooperative ...
 
Global Solar Summit
Global Solar SummitGlobal Solar Summit
Global Solar Summit
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
February 9, 2012
February 9, 2012February 9, 2012
February 9, 2012
 
Leed consultant review
Leed consultant reviewLeed consultant review
Leed consultant review
 
A GIS based framework for assessing and mapping potential irrigation areas in...
A GIS based framework for assessing and mapping potential irrigation areas in...A GIS based framework for assessing and mapping potential irrigation areas in...
A GIS based framework for assessing and mapping potential irrigation areas in...
 
A gis based framework for assessing and mapping potential irrigation areas in...
A gis based framework for assessing and mapping potential irrigation areas in...A gis based framework for assessing and mapping potential irrigation areas in...
A gis based framework for assessing and mapping potential irrigation areas in...
 

Successful Kane County Residential Development SESC Case Study

  • 1. Project Background Case Study of a 227 acre parcel in north central Kane Successful SESC Plan County, Illinois Agricultural  Residential Subdivision 291 Homes, Developed in Six Units H D l d i Si U it Jonathan Koepke, CPESC Curb and Gutter Resource Conservationist Kane- Kane-DuPage Soil & Water 5 Detention Basins Conservation District Project Background (cont.) Aerial Three Planned Creek Crossings—Two Crossings— Permanent, One Temporary One Drainageway Permanently Impacted Obtained Corps of Engineers Permit which requires SWCD review and i i i d inspection of S il ti f Soil Erosion and Sediment Control Article 3-Erosion and Sediment Control-of the 3- Control- Kane County Stormwater Ordinance is administered by the City NPDES Permit Coverage 1
  • 2. Topography Map Water Features Soil Erosion and Sediment Control Plan Total of 7 Sheets 2
  • 3. SWCD Standard Notes Key Components y p 3
  • 4. Legend of Practices Scheduling Information Perimeter Silt Fence Stabilization Information 4
  • 5. Stockpile Stabilization and Stabilization Protection Early Completion of Basins Other Stabilization Driving Force Kane County Ordinance states that “[t]he area of disturbance onsite at any one time shall be limited to 20 acres. An additional 20 acres (a maximum of 40 acres of disturbance at any one time) may be stripped in order to balance cut and fill onsite”. Developer was told by City that he could not mass grade another phase until the existing disturbed areas were being stabilized 5
  • 6. Diversion of Offsite Flow/Runoff Sediment Traps/Basins Erosion Control Blanket Location Protection of Detention Basins 6
  • 7. Specific Instructions for Work in Critical Areas Work in Critical Areas Instructions resulted in an area-specific area- preconstruction meeting with the contractor, engineer, City, developer, and SWCD. Specific Plan was developed after meeting Drawings for Temporary Practices Drawings for Permanent Practices Note: See IUM for correct formula 7
  • 8. Stabilized Entrances Clean Streets Inlet Protection Check Dams Not Recommended. Other practices/products available. 8
  • 9. Energy Dissipation Energy Dissipation Note: See IUM for correct formula Dewatering Notes Inspection and Maintenance Notes 9
  • 10. NPDES Signatory Requirements Looking Back Downstream end of diversion was constructed as a swale. Keeping it as confined channel all the way to the basin may have worked better. better Stockpile location shown on plans Questions?? 10