SlideShare a Scribd company logo
1 of 8
Download to read offline
Project management in a hospital: From chaos to success
At leading Hospital many projects were running at the same time. Projects that were necessary
to realize the ambitions of the hospital. The problem was that too many projects yielded too
little result too late. Hospital implemented Critical Chain Project Management,Lean & Six
Sigma (TLS) and cut the average lead time in half whilst doubling the number of completed
projects ...... with the same number of people! Now, TLS is an indispensable tool for innovation
at the hospital.
Background
In 2005, it ran into financial trouble and had to restructure completely. Since then, Hospital has made
a strong come back. It grows faster than the market and is financially healthy again. So healthy, that it
confidently invested in a new hospital that it just moved into in spring 2011.
In early 2008, the recovery was in full swing and one of the problems that the management and its
employees ran into was the long lead times and poor delivery performance of many projects. A survey
by hospital staff led to a shocking conclusion: There were no less than one hundred eighty projects
running simultaneously, and a significant number of them had no clear project leader, sponsor, scope
definition, budget or due date. The Chief Innovation Officer of Hospital explains: "Projects, and a
lot of them, are inevitable for a hospital with our ambition level. But we had insufficient visibility and
control over project selection, progress and completion."
Following this sobering observation, the hospital’s board decided to invest in a project management
solution that not only had to create order in the projects, but would also raise its output. They chose
TLS because it had amply proven to improve both output and due date performance of projects
without increasing workload.
CCPM: Clear task priorities for outstanding project performance
Critical Chain Project Management (CCPM) was developed by Dr. Eli Goldratt, author of The Goal
and Critical Chain and founder of the Theory of Constraints (TOC). CCPM is the solution for project
organizations that have a low project performance in time, scope and budget.
CCPM uses the fact that project plans have more slack ("buffers") than project teams know or want to
admit: These buffers are their only means to achieve acceptable delivery performance. Or so they
think .....
During project planning, CCPM takes these buffers from the task estimates and insert them in a
project buffer at the end of the project. After all, it is not important for individual tasks to be
completed on time, as long as the overall project is finished on time.
Figure 1: CCPM: The project, instead of its tasks, is protected by a time buffer
During execution, tasks that need to be executed now are regularly updated in the CCPM
software by means of a remaining duration estimates: How many days till this task is
completed? This estimate is then used to calculate which task consumes most of the buffer.
Based on this ‘buffer consumption’ clear task priorities are calculated and depicted as green,
yellow or red tasks.
Figure 2: Colours give clear priorities within and between projects
These clear task priorities within and between projects not only end frequent discussions
about project priorities, but also result in a faster and more reliable completion of projects.
Typical CCPM implementations result in the following improvements:
• Due date performance ≥ 90%
• Lead time ≈ 30% shorter
• Productivity ≈ 30% higher
• Less stress and more focus in project teams and management
CCPM has been successfully applied on a large scale in industry, IT, pharma, infrastructure
& utilities.
Yet another project
In June 2008, yet another project commenced: "Implementation of CCPM”. But the goal of
this particular project was to significantly reduce the number of concurrently active projects
by the end of 2009, whilst assuring that 95% of the projects are finished on time, scope (what
you deliver) and budget. It was decided to focus the implementation on cross-departmental
projects which caused the bulk of the load and problems at project resources in Hospital.
To start with, the project team made an inventory of problems and discovered that they were
deep rooted and fundamental:
• Some of the projects had no plan
• Some of the projects had no clear project leader or sponsor
• Projects were launched, regardless of the availability of the required staff
• Management had insufficient understanding of problems and status of active projects
• Projects were often completed too late (if a due date was set at all)
• Project group meetings were sometimes ineffective
• Projects often went over budget (if there was a formal budget)
• Project staff were not always available when needed
• There was tension and debate on priorities within and between projects
This survey also revealed that Hospital first had to invest in basic elements of project
management, in order to be ready for the implementation of CCPM.
Basic elements of project management
In a high performing project environment, every organization needs three things: structures,
processes and templates.
Structures: Projects are temporary endeavours to achieve something unique. So, even more
than with regular work, it is important to clearly identify roles and responsibilities.
Obviously, the project leader is critical because he is responsible for the delivery of the scope
(what you deliver), on time and within budget, but the sponsor also plays a key role. Each
project must have a sponsor which is decisive and accessible for the project leader. The
sponsor is often problem owner, provider of the necessary budget and the person who needs
to approve potential deviations from the plan. Appointing decisive and accessible sponsors
and assuring frequent and constructive consultation between project leader and sponsor was
an important first step to success at Hospital.
Processes: Since projects are unique, most develop, almost by definition, in a fairly
unpredictable way. For this reason, it is important that key processes are in place to deal with
these unforeseen developments. First, we established that projects are always in one of the
following 4 phases: idea, planning, implementation and evaluation. The transition between
each phase is a formal step that requires a decision by the client or the project board (see
below). In order to maintain progress in active projects, brief weekly project meetings and
monthly meetings with the sponsor proved critical to success.
Templates: Project management has become notorious for demanding extensive project plans
that proved quite useless during execution. Hence CCPM provides plans and reports that are
very concise and focused. Hospital in Rotterdam, introduced no fewer than six templates for
project ideas, project plans, project meeting notes, project status reporting, escalation, and
completion reports. At first, some of these templates received some skepticism, but now they
are all used extensively because they help project teams and sponsors to focus and save time.
Project Board
Besides implementing structures, processes and templates a so called Project Board was set
up. The Project Board is a tightly structured meeting of the hospital’s board that included all
sponsors of the cross-departmental projects. The objective of the project board is threefold:
First, selection of valuable project ideas. Second, ensure effective intervention by sponsors in
struggling (so called “red”) projects, and finally evaluation of completed projects.
Figure 3: Transparancy about active projects and their status; green, yellow or red
A project selection was simplified by means of a 1 page potential sponsor before proposing it to the
Project Board. The Chairman of the Board then lead the discussion: "In no more than fifteen minutes,
we often have five or more project ideas to discuss. I ask only three questions: Who is excited about
this idea? What problem does it solve? And: What is the direction of the solution? Through question 1
and 2 we lost quite a few ideas, and normally only 1 or 2 get approved for planning, provided that at
least 2 projects were completed as well. Otherwise they must wait to prevent overloading of the
project resources. "
The advantage of this method is twofold. Firstly, management now is fully aware of, and committed
to, all ongoing cross-departmental projects. But more importantly: During the first phase of
implementation significantly less projects were started, thus reducing the work load on the scarce
project resources and allowing them to focus on finishing already running projects effectively.
Besides focusing on project selection, execution and evaluation the project board also monitors the
depletion of the project budget. In many organizations, projects need to be financed from
departmental budgets, often leading to heated discussions at the end of the year when the overall
budget appears to have been exceeded. To stop this once and for all, Hospital took a fraction of all
relevant operating budgets and inserted them into one central project budget, aimed at covering the
out of pocket expenses of all cross-departmental projects. Every month, the project board monitored
the real and expected exhaustion of this budget vs time using a simple report. This way the project
board could monitor the budget depletion per project, but more importantly found that the inevitable
budget overruns and under spends tend to offset one another provided they are financed for a single
source; the cross-departmental project budget.
Finally .....
In the fall of 2008, the situation in Hospital had significantly improved: All the projects had
clear project leaders, sponsors and consensus over time (due date), scope (what they will
deliver), budget (out of pocket expenses only) and goal (desired outcome). Because the
project board was quite reluctant to approve new projects and even some struggling projects
were stopped, the pressure on the project resources declined. It was time to introduce TLS to
further reduce lead times and increase completion.
Software can never be the aim of an improvement project, but, increasingly, it is becoming a
necessary precondition. CCPM software distinguishes itself from other project management
software in the sense that it is focused on execution rather than planning. After all, it is during
execution that the project almost inevitably starts to deviate from the plan and more often
than not, in traditional project management the plan is abandoned altogether. The solution is a
robust high level plan that doesn’t detail actions, but lists deliverables, intermediate
objectives necessary for achieving the project objective. Plans usually consist of no more than
ten to fifteen deliverables. During execution the responsible resource can add actions to the
deliverable that are deemed necessary to generate the desired outcome.
Project plans are not created by a person sitting at a computer. One of the key success factors
of this CCPM implementation is the so called planning session: After approval of the project
idea by the Project Board, the proposed project team gets together for a four hour meeting. In
a closely facilitated meeting they go through the key elements of the project plan template in
such a way, that the draft plan is filled in and ready to be sent to the sponsor for approval by
the end of the meeting. At Hospital projects are no longer started without such a planning
session. In very little time it generates a focused plan with maximum buy-in that contains all
elements the project team needs to execute the project successfully.
Once a project is in progress, frequent (weekly) short project team meetings are critical for
success. In the weekly meetings, the project leader updates the project real time in the CCPM
software, based on the input of the team members. Hospital has even invested in a number
of "CCPM-rooms" with computer and flatscreen TV’s on the wall where project teams can
meet and update their project.
What is unique about this? CCPM makes very clear which project deliverables need to be
worked on now and in what order of priority both and between projects. This leads to calm
and focus as well as a better flow of projects. Per active deliverable, the tasks are updated by
entering the estimated number of days until completion. CCPM is always forward looking:
Do not spend time on what has been done, but focus on what needs to be done to finish a
deliverable. And even more importantly, avoid blame if tasks were completed late. Accept
windfalls and setbacks as a fact of life in a project environment and focus continually on
corrective actions and decisions that lead to completion of the project on time, scope and
budget.
Through the CCPM implementation, Hospital learnt that project management is a vital but
often underestimated craft. For that reason, it secured the continuation and development of
CCPM knowledge in an in-house project office. The project office provides training courses
for project teams and leaders, facilitates planning sessions, prepares project board meetings
and gives (un)solicited assistance to projects that are in red.
Results: Doubling the output and halving the lead time
Between late 2008 and spring 2009, all the old projects were finished and new projects under
CCPM principles introduced. Due to its success, the management has decided to add a group
of existing projects related to the construction of the new hospital to the CCPM portfolio (see
the increase in the summer of 2009 in Figure 4 below). Nevertheless, the number of cross-
departmental projects that ran simultaneously in Hospital remained fairly stable with
approximately 30, versus over 40 at the start in mid 2008. This decrease is critical to the
focus of project resources and the flow of projects.
Figure 4: Number of concurrent cross-departmental projects declined from around 40 to under 30
despite growing the portfolio
The fact that Hospital could add a significant number of projects to its portfolio was due to
the fact that they finished much faster than before. Figure 5 shows that the average lead time
of cross-departmental projects has decreased from over 2 years in 2008 to approximately 10
months in 2009 and 2010. This is less than half the lead time!
Figure 5: Average lead time (in # of months) of cross-departmental projects was cut in less than half
This brings us to the last and most important achievement: In 2008, on average 1 cross-departmental
project was finished per month. The Chairman of the Board concludes: "By introducing project
management principles and TLS, the productivity of our project resources nearly tripled. Currently
we finish about 3 cross-departmental projects per month. Project management has become a core
competency of Hospital towards achieving our ambition; making Rotterdam the healthiest city in the
Netherlands."
Figure 6: Number of projects finished per month tripled (6-month rolling average)
Lessons for successful implementation
What is critical to achieving success?
1. Implement simple structures, processes and templates for all projects
2. Install a Project Board at board level to select projects and evaluate and monitor progress
3. Create a central budget for all out of pocket expenses and avoid planning and monitoring of internal
hours
4. CCPM project management is a craft: Use an experienced implementer and retain the knowledge
and skills in a project office
5. Accept windfalls and setbacks as a "fact of life” and keep project teams focused on completing
projects on time, scope and budget

More Related Content

What's hot

Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementBarun_agnihotri
 
Overview of Project management lecture 2
Overview of Project management lecture 2Overview of Project management lecture 2
Overview of Project management lecture 2Abeera Malik
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)Tony
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Introduction To Project Management Megat
Introduction To Project Management MegatIntroduction To Project Management Megat
Introduction To Project Management Megatmegat zainurul anuar
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project ManagementJohn Goodpasture
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Mena M. Eissa
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementWorkfront
 
Project management part 3
Project management part 3Project management part 3
Project management part 3hkbhadraa
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 
2. characteristics of a projec
2. characteristics of a projec2. characteristics of a projec
2. characteristics of a projecDr. Johnson Mavole
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Khan Project Scope Creep Presentationin Pdf
Khan   Project Scope Creep Presentationin PdfKhan   Project Scope Creep Presentationin Pdf
Khan Project Scope Creep Presentationin PdfZahidKhan007
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1Abeera Malik
 
PROJECT MANAGEMENT.pptx
PROJECT MANAGEMENT.pptxPROJECT MANAGEMENT.pptx
PROJECT MANAGEMENT.pptxNimra zaman
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Introduction to-project-management
Introduction to-project-managementIntroduction to-project-management
Introduction to-project-managementPinta Florin
 

What's hot (20)

Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project Management for the Accidental Project Manager
Project Management for the Accidental Project ManagerProject Management for the Accidental Project Manager
Project Management for the Accidental Project Manager
 
Overview of Project management lecture 2
Overview of Project management lecture 2Overview of Project management lecture 2
Overview of Project management lecture 2
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Introduction To Project Management Megat
Introduction To Project Management MegatIntroduction To Project Management Megat
Introduction To Project Management Megat
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project Management
 
01 introduction
01  introduction01  introduction
01 introduction
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
A Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project ManagementA Beginner's Guide to IT Project Management
A Beginner's Guide to IT Project Management
 
Project management part 3
Project management part 3Project management part 3
Project management part 3
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
2. characteristics of a projec
2. characteristics of a projec2. characteristics of a projec
2. characteristics of a projec
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Khan Project Scope Creep Presentationin Pdf
Khan   Project Scope Creep Presentationin PdfKhan   Project Scope Creep Presentationin Pdf
Khan Project Scope Creep Presentationin Pdf
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1
 
PROJECT MANAGEMENT.pptx
PROJECT MANAGEMENT.pptxPROJECT MANAGEMENT.pptx
PROJECT MANAGEMENT.pptx
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
Introduction to-project-management
Introduction to-project-managementIntroduction to-project-management
Introduction to-project-management
 

Viewers also liked

Mongol ulsiin undsen huuliin erh zui.lekts
Mongol ulsiin undsen huuliin erh zui.lektsMongol ulsiin undsen huuliin erh zui.lekts
Mongol ulsiin undsen huuliin erh zui.lektsAltangerel Bilguun
 
Hospital management
Hospital managementHospital management
Hospital managementSmit Patel
 
Hospital management final report presentation
Hospital management final report presentationHospital management final report presentation
Hospital management final report presentationMd Abul Kalam Azad
 
Hospital Management System
Hospital Management SystemHospital Management System
Hospital Management SystemPranil Dukare
 
[PPT] Hospital management system - Quanta-his
[PPT] Hospital management system - Quanta-his[PPT] Hospital management system - Quanta-his
[PPT] Hospital management system - Quanta-hisBirlamedisoft Pvt. Ltd
 
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4NICHOLAS RATEMO
 
Hospital management system project
Hospital management system projectHospital management system project
Hospital management system projectHimani Chopra
 

Viewers also liked (8)

Mongol ulsiin undsen huuliin erh zui.lekts
Mongol ulsiin undsen huuliin erh zui.lektsMongol ulsiin undsen huuliin erh zui.lekts
Mongol ulsiin undsen huuliin erh zui.lekts
 
Hospital management
Hospital managementHospital management
Hospital management
 
Hospital management final report presentation
Hospital management final report presentationHospital management final report presentation
Hospital management final report presentation
 
Hospital Management System
Hospital Management SystemHospital Management System
Hospital Management System
 
[PPT] Hospital management system - Quanta-his
[PPT] Hospital management system - Quanta-his[PPT] Hospital management system - Quanta-his
[PPT] Hospital management system - Quanta-his
 
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
 
Hospital management system project
Hospital management system projectHospital management system project
Hospital management system project
 
Hospital management system
Hospital management systemHospital management system
Hospital management system
 

Similar to Project management in a hospital

Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptxMIANMNADEEM
 
Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)ferozpatowary
 
Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)ferozpatowary
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementsdbhosale860
 
Chapter 1 Modern Project Management
Chapter 1 Modern Project ManagementChapter 1 Modern Project Management
Chapter 1 Modern Project ManagementKristina Badec
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsTa Ngoc
 
Presentation of project management synopsis 1
Presentation of project management synopsis 1Presentation of project management synopsis 1
Presentation of project management synopsis 1ferozpatowary
 
Project Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptxProject Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptxAhmedMuuse6
 
UCISA Toolkit - Establishing a PMO in an HE Environment
UCISA Toolkit - Establishing a PMO in an HE Environment UCISA Toolkit - Establishing a PMO in an HE Environment
UCISA Toolkit - Establishing a PMO in an HE Environment Mark Ritchie
 
2014 Fire Rescue - Project Managment 101 training
2014 Fire Rescue - Project Managment 101 training2014 Fire Rescue - Project Managment 101 training
2014 Fire Rescue - Project Managment 101 trainingIan Robertson
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final RptEd Kozak
 
Project Management
Project ManagementProject Management
Project ManagementMayanSardana
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management DiplomaTheunis Venter
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 

Similar to Project management in a hospital (20)

briefing2
briefing2briefing2
briefing2
 
Estimate budget and project crashing.pptx
Estimate budget and project crashing.pptxEstimate budget and project crashing.pptx
Estimate budget and project crashing.pptx
 
Project management
Project managementProject management
Project management
 
Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)Presentation of project management (905, scm. rajib ahashan rashel)
Presentation of project management (905, scm. rajib ahashan rashel)
 
1 ch1
1 ch11 ch1
1 ch1
 
Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)Presentation of project management (907, scm. mir mohammed shorab hossein)
Presentation of project management (907, scm. mir mohammed shorab hossein)
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project management
 
Chapter 1 Modern Project Management
Chapter 1 Modern Project ManagementChapter 1 Modern Project Management
Chapter 1 Modern Project Management
 
Why projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfallsWhy projects fail avoiding the classic pitfalls
Why projects fail avoiding the classic pitfalls
 
Presentation of project management synopsis 1
Presentation of project management synopsis 1Presentation of project management synopsis 1
Presentation of project management synopsis 1
 
Project Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptxProject Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptx
 
project managementUnit 1.pdf
project managementUnit 1.pdfproject managementUnit 1.pdf
project managementUnit 1.pdf
 
UCISA Toolkit - Establishing a PMO in an HE Environment
UCISA Toolkit - Establishing a PMO in an HE Environment UCISA Toolkit - Establishing a PMO in an HE Environment
UCISA Toolkit - Establishing a PMO in an HE Environment
 
2014 Fire Rescue - Project Managment 101 training
2014 Fire Rescue - Project Managment 101 training2014 Fire Rescue - Project Managment 101 training
2014 Fire Rescue - Project Managment 101 training
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management Diploma
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 

Project management in a hospital

  • 1. Project management in a hospital: From chaos to success At leading Hospital many projects were running at the same time. Projects that were necessary to realize the ambitions of the hospital. The problem was that too many projects yielded too little result too late. Hospital implemented Critical Chain Project Management,Lean & Six Sigma (TLS) and cut the average lead time in half whilst doubling the number of completed projects ...... with the same number of people! Now, TLS is an indispensable tool for innovation at the hospital. Background In 2005, it ran into financial trouble and had to restructure completely. Since then, Hospital has made a strong come back. It grows faster than the market and is financially healthy again. So healthy, that it confidently invested in a new hospital that it just moved into in spring 2011. In early 2008, the recovery was in full swing and one of the problems that the management and its employees ran into was the long lead times and poor delivery performance of many projects. A survey by hospital staff led to a shocking conclusion: There were no less than one hundred eighty projects running simultaneously, and a significant number of them had no clear project leader, sponsor, scope definition, budget or due date. The Chief Innovation Officer of Hospital explains: "Projects, and a lot of them, are inevitable for a hospital with our ambition level. But we had insufficient visibility and control over project selection, progress and completion." Following this sobering observation, the hospital’s board decided to invest in a project management solution that not only had to create order in the projects, but would also raise its output. They chose TLS because it had amply proven to improve both output and due date performance of projects without increasing workload. CCPM: Clear task priorities for outstanding project performance Critical Chain Project Management (CCPM) was developed by Dr. Eli Goldratt, author of The Goal and Critical Chain and founder of the Theory of Constraints (TOC). CCPM is the solution for project organizations that have a low project performance in time, scope and budget. CCPM uses the fact that project plans have more slack ("buffers") than project teams know or want to admit: These buffers are their only means to achieve acceptable delivery performance. Or so they think ..... During project planning, CCPM takes these buffers from the task estimates and insert them in a project buffer at the end of the project. After all, it is not important for individual tasks to be completed on time, as long as the overall project is finished on time.
  • 2. Figure 1: CCPM: The project, instead of its tasks, is protected by a time buffer During execution, tasks that need to be executed now are regularly updated in the CCPM software by means of a remaining duration estimates: How many days till this task is completed? This estimate is then used to calculate which task consumes most of the buffer. Based on this ‘buffer consumption’ clear task priorities are calculated and depicted as green, yellow or red tasks. Figure 2: Colours give clear priorities within and between projects These clear task priorities within and between projects not only end frequent discussions about project priorities, but also result in a faster and more reliable completion of projects.
  • 3. Typical CCPM implementations result in the following improvements: • Due date performance ≥ 90% • Lead time ≈ 30% shorter • Productivity ≈ 30% higher • Less stress and more focus in project teams and management CCPM has been successfully applied on a large scale in industry, IT, pharma, infrastructure & utilities. Yet another project In June 2008, yet another project commenced: "Implementation of CCPM”. But the goal of this particular project was to significantly reduce the number of concurrently active projects by the end of 2009, whilst assuring that 95% of the projects are finished on time, scope (what you deliver) and budget. It was decided to focus the implementation on cross-departmental projects which caused the bulk of the load and problems at project resources in Hospital. To start with, the project team made an inventory of problems and discovered that they were deep rooted and fundamental: • Some of the projects had no plan • Some of the projects had no clear project leader or sponsor • Projects were launched, regardless of the availability of the required staff • Management had insufficient understanding of problems and status of active projects • Projects were often completed too late (if a due date was set at all) • Project group meetings were sometimes ineffective • Projects often went over budget (if there was a formal budget) • Project staff were not always available when needed • There was tension and debate on priorities within and between projects This survey also revealed that Hospital first had to invest in basic elements of project management, in order to be ready for the implementation of CCPM. Basic elements of project management In a high performing project environment, every organization needs three things: structures, processes and templates. Structures: Projects are temporary endeavours to achieve something unique. So, even more than with regular work, it is important to clearly identify roles and responsibilities. Obviously, the project leader is critical because he is responsible for the delivery of the scope (what you deliver), on time and within budget, but the sponsor also plays a key role. Each project must have a sponsor which is decisive and accessible for the project leader. The sponsor is often problem owner, provider of the necessary budget and the person who needs to approve potential deviations from the plan. Appointing decisive and accessible sponsors and assuring frequent and constructive consultation between project leader and sponsor was an important first step to success at Hospital. Processes: Since projects are unique, most develop, almost by definition, in a fairly unpredictable way. For this reason, it is important that key processes are in place to deal with these unforeseen developments. First, we established that projects are always in one of the following 4 phases: idea, planning, implementation and evaluation. The transition between
  • 4. each phase is a formal step that requires a decision by the client or the project board (see below). In order to maintain progress in active projects, brief weekly project meetings and monthly meetings with the sponsor proved critical to success. Templates: Project management has become notorious for demanding extensive project plans that proved quite useless during execution. Hence CCPM provides plans and reports that are very concise and focused. Hospital in Rotterdam, introduced no fewer than six templates for project ideas, project plans, project meeting notes, project status reporting, escalation, and completion reports. At first, some of these templates received some skepticism, but now they are all used extensively because they help project teams and sponsors to focus and save time. Project Board Besides implementing structures, processes and templates a so called Project Board was set up. The Project Board is a tightly structured meeting of the hospital’s board that included all sponsors of the cross-departmental projects. The objective of the project board is threefold: First, selection of valuable project ideas. Second, ensure effective intervention by sponsors in struggling (so called “red”) projects, and finally evaluation of completed projects. Figure 3: Transparancy about active projects and their status; green, yellow or red A project selection was simplified by means of a 1 page potential sponsor before proposing it to the Project Board. The Chairman of the Board then lead the discussion: "In no more than fifteen minutes, we often have five or more project ideas to discuss. I ask only three questions: Who is excited about this idea? What problem does it solve? And: What is the direction of the solution? Through question 1 and 2 we lost quite a few ideas, and normally only 1 or 2 get approved for planning, provided that at least 2 projects were completed as well. Otherwise they must wait to prevent overloading of the project resources. " The advantage of this method is twofold. Firstly, management now is fully aware of, and committed to, all ongoing cross-departmental projects. But more importantly: During the first phase of implementation significantly less projects were started, thus reducing the work load on the scarce project resources and allowing them to focus on finishing already running projects effectively.
  • 5. Besides focusing on project selection, execution and evaluation the project board also monitors the depletion of the project budget. In many organizations, projects need to be financed from departmental budgets, often leading to heated discussions at the end of the year when the overall budget appears to have been exceeded. To stop this once and for all, Hospital took a fraction of all relevant operating budgets and inserted them into one central project budget, aimed at covering the out of pocket expenses of all cross-departmental projects. Every month, the project board monitored the real and expected exhaustion of this budget vs time using a simple report. This way the project board could monitor the budget depletion per project, but more importantly found that the inevitable budget overruns and under spends tend to offset one another provided they are financed for a single source; the cross-departmental project budget. Finally ..... In the fall of 2008, the situation in Hospital had significantly improved: All the projects had clear project leaders, sponsors and consensus over time (due date), scope (what they will deliver), budget (out of pocket expenses only) and goal (desired outcome). Because the project board was quite reluctant to approve new projects and even some struggling projects were stopped, the pressure on the project resources declined. It was time to introduce TLS to further reduce lead times and increase completion. Software can never be the aim of an improvement project, but, increasingly, it is becoming a necessary precondition. CCPM software distinguishes itself from other project management software in the sense that it is focused on execution rather than planning. After all, it is during execution that the project almost inevitably starts to deviate from the plan and more often than not, in traditional project management the plan is abandoned altogether. The solution is a robust high level plan that doesn’t detail actions, but lists deliverables, intermediate objectives necessary for achieving the project objective. Plans usually consist of no more than ten to fifteen deliverables. During execution the responsible resource can add actions to the deliverable that are deemed necessary to generate the desired outcome. Project plans are not created by a person sitting at a computer. One of the key success factors of this CCPM implementation is the so called planning session: After approval of the project idea by the Project Board, the proposed project team gets together for a four hour meeting. In a closely facilitated meeting they go through the key elements of the project plan template in such a way, that the draft plan is filled in and ready to be sent to the sponsor for approval by the end of the meeting. At Hospital projects are no longer started without such a planning session. In very little time it generates a focused plan with maximum buy-in that contains all elements the project team needs to execute the project successfully. Once a project is in progress, frequent (weekly) short project team meetings are critical for success. In the weekly meetings, the project leader updates the project real time in the CCPM software, based on the input of the team members. Hospital has even invested in a number of "CCPM-rooms" with computer and flatscreen TV’s on the wall where project teams can meet and update their project. What is unique about this? CCPM makes very clear which project deliverables need to be worked on now and in what order of priority both and between projects. This leads to calm and focus as well as a better flow of projects. Per active deliverable, the tasks are updated by entering the estimated number of days until completion. CCPM is always forward looking: Do not spend time on what has been done, but focus on what needs to be done to finish a deliverable. And even more importantly, avoid blame if tasks were completed late. Accept
  • 6. windfalls and setbacks as a fact of life in a project environment and focus continually on corrective actions and decisions that lead to completion of the project on time, scope and budget. Through the CCPM implementation, Hospital learnt that project management is a vital but often underestimated craft. For that reason, it secured the continuation and development of CCPM knowledge in an in-house project office. The project office provides training courses for project teams and leaders, facilitates planning sessions, prepares project board meetings and gives (un)solicited assistance to projects that are in red. Results: Doubling the output and halving the lead time Between late 2008 and spring 2009, all the old projects were finished and new projects under CCPM principles introduced. Due to its success, the management has decided to add a group of existing projects related to the construction of the new hospital to the CCPM portfolio (see the increase in the summer of 2009 in Figure 4 below). Nevertheless, the number of cross- departmental projects that ran simultaneously in Hospital remained fairly stable with approximately 30, versus over 40 at the start in mid 2008. This decrease is critical to the focus of project resources and the flow of projects. Figure 4: Number of concurrent cross-departmental projects declined from around 40 to under 30 despite growing the portfolio The fact that Hospital could add a significant number of projects to its portfolio was due to the fact that they finished much faster than before. Figure 5 shows that the average lead time
  • 7. of cross-departmental projects has decreased from over 2 years in 2008 to approximately 10 months in 2009 and 2010. This is less than half the lead time! Figure 5: Average lead time (in # of months) of cross-departmental projects was cut in less than half This brings us to the last and most important achievement: In 2008, on average 1 cross-departmental project was finished per month. The Chairman of the Board concludes: "By introducing project management principles and TLS, the productivity of our project resources nearly tripled. Currently we finish about 3 cross-departmental projects per month. Project management has become a core competency of Hospital towards achieving our ambition; making Rotterdam the healthiest city in the Netherlands."
  • 8. Figure 6: Number of projects finished per month tripled (6-month rolling average) Lessons for successful implementation What is critical to achieving success? 1. Implement simple structures, processes and templates for all projects 2. Install a Project Board at board level to select projects and evaluate and monitor progress 3. Create a central budget for all out of pocket expenses and avoid planning and monitoring of internal hours 4. CCPM project management is a craft: Use an experienced implementer and retain the knowledge and skills in a project office 5. Accept windfalls and setbacks as a "fact of life” and keep project teams focused on completing projects on time, scope and budget