Jeffrey D. Mansfield
Project Management/Program Management/Portfolio Management Professional
jeffreydmansfield#@gmail.com
http://www.linkedin.com/in/jeffreydmansfield/
December 2018
Answering these questions are a challenge as changes
in scope and priority will occur during development.
The following Agile planning and tracking process can
help answer these questions.
1. Break backlog into epics/stories
2. Assign story points
Part of prioritization process
Use Fibonacci numbers (1, 2, 3, 5, 8, 13, 21) for t-shirt sizing of effort
3. Define MinimumViable Product - MVP
Product Owner defines the minimum functionality to be released
4. Add additional story point contingency to account for:
Changes in requirement (new functionality)
Resolving technical debt (rework)
5. Estimate team capacity in story points
Estimate number of story points (velocity) to be completed for each sprint
▪ Velocity will improve as team matures
▪ Velocity will change as team changes
6. Develop an initial sprint plan
Number of sprints required until MVP + Contingency < sum of velocity
Sprint 1 2 3 4 5 6 7 8 9 10
Sprint End Date 2/15/19 3/1/19 3/15/19 3/29/19 4/12/19 4/26/19 5/10/19 5/24/19 6/7/19 6/21/19
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story
Points 600 600 600 600 600 600 600 600 600 600 600
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
1. After every sprint, assess the following:
What was the actual velocity of the team?
The number of story points the team completed
Is the planned velocity too high or too low based on actual?
Can any changes be made to increase velocity?
Has the story points required to meet MVP changed?
Does the contingency need to be adjusted?
Has the team capacity changed?
Have people been added or removed?
2. Reforecast the sprint plan based on the assessment
1. First 3 sprints on plan, additional stories added to
backlog, but backlog is less than MVP and
Contingency planned.
Sprint 1 2 3 4 5 6 7 8 9 10
Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story
Points 600 600 600 600 600 600 600 600 600 600 600
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Original Remaining Story Points (Incl
Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
Actual/Forecast
Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600
Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600
Actual Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Actual Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Actual Remaining Story Points (Incl Backlog) 450 440 430 360 290 220 150 80 40
Actual Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
Adjusted total story points based on backlog.
Total story points still within team capacity.
Still on target for 10 sprints.
1. First 3 sprints on plan, additional stories added to
backlog, but backlog is less than MVP and
Contingency planned.
2. Loss of team member for 3 sprints reducing velocity
and MVP cannot be met as originally planned.
Sprint 1 2 3 4 5 6 7 8 9 10
Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story
Points 600 600 600 600 600 600 600 600 600 600 600
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
Actual/Forecast
Actual Team Capacity Story Points 570 570 570 570 570 570 570 570 570 570 570
Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600
Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600
Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 40 40
Actual Total Completed Story Points 50 110 170 230 290 350 420 490 530 570
Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 250 180 110 70 30
Actual Remaining MVP & Contingency Story
Points 550 490 430 370 310 250 180 110 70 30
Adjusted team velocity to reflect loss of team member.
Team velocity will no longer cover MVP.
1. First 3 sprints on plan, additional stories added to
backlog, but backlog is less than MVP and
Contingency planned.
2. Lose team member for 3 sprints reducing velocity
and MVP cannot be met as originally planned.
3. Added additional velocity to later sprints to keep to
current sprint plan.
Sprint 1 2 3 4 5 6 7 8 9 10
Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story
Points 600 600 600 600 600 600 600 600 600 600 600
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
Actual/Forecast
Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600
Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600
Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 55 55
Actual Total Completed Story Points 50 110 170 230 290 350 420 490 545 600
Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 250 180 110 55
Actual Remaining MVP & Contingency Story
Points 550 490 430 370 310 250 180 110 55
Decision taken to reduce number of team members planned to be released for
sprint 9 and 10.
Increased forecasted velocity to reflect additional team members for these
sprints.
MVP is now being met.
1. First 3 sprints on plan, additional stories added to
backlog, but backlog is less than MVP and
Contingency planned.
2. Lose team member for 3 sprints reducing velocity
and MVP cannot be met as originally planned.
3. Added additional velocity to later sprints to keep to
current sprint plan.
4. Product Owner adds additional stories to MVP.
Sprint 1 2 3 4 5 6 7 8 9 10
Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600
Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency Story
Points 550 490 430 360 290 220 150 80 40
Actual/Forecast
Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600
Actual Total Story Points (Incl Backlog) 500 550 600 600 600 650 735 735 735 735
Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 700 700
Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 55 55
Actual Total Completed Story Points 50 110 170 230 290 350 420 490 545 600
Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 300 315 245 190 135
Actual Remaining MVP & Contingency Story
Points 550 490 430 370 310 250 180 110 155 100
Product Owner adds 100 story points to MVP.
MVP now exceeds team capacity.
MVP can no longer be delivered within current sprint plan.
1. First 3 sprints on plan, additional stories added to
backlog, but backlog is less than MVP and
Contingency planned.
2. Lose team member for 3 sprints reducing velocity
and MVP cannot be met as originally planned.
3. Added additional velocity to later sprints to keep to
current sprint plan.
4. Product Owner adds additional stories to MVP
5. Additional Sprint is added to complete MVP.
Sprint 1 2 3 4 5 6 7 8 9 10 11 12
Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 7/5/2019 7/19/2019
Plan
Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 600 600
Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 500 500
Original Total MVP & Contingency Story
Points 600 600 600 600 600 600 600 600 600 600 600 630 700
Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40
Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 600 600
Original Remaining Story Points (Incl
Backlog) 450 390 330 260 190 120 50
Original Remaining MVP & Contingency
Story Points 550 490 430 360 290 220 150 80 40
Actual/Forecast
Actual Team Capacity Story Points 700 700 700 700 700 700 700 700 700 700 700 700 700
Actual Total Story Points (Incl Backlog) 500 550 600 600 600 650 735 735 735 735 735 735
Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 700 700 700 700
Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 70 70 70
Actual Total Completed Story Points 50 110 170 230 290 350 420 490 560 630 700 700
Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 300 315 245 175 105 35 35
Actual Remaining MVP & Contingency Story
Points 550 490 430 370 310 250 180 110 140 70
Decision taken to keep team fully staffed and to add an additional sprint.
Updated forecasted velocity based on decision.
MVP is now being met.
Some additional backlog items will not be delivered (35 story points).
Jeffrey D. Mansfield
Project Management/Program
Management/Portfolio Management Professional
Driving Business Strategy Implementation
through Projects
http://www.linkedin.com/in/jeffreydmansfield/
http://www.twitter.com/jeffmansfld
Resume -
http://www.slideshare.net/jeffreydmansfield/resume
-mansfield-jeffrey-ppm-jan272014-31143481

More Related Content

Recently uploaded

Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
FIDO Alliance
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
FIDO Alliance
 

Recently uploaded (20)

ERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage IntacctERP Contender Series: Acumatica vs. Sage Intacct
ERP Contender Series: Acumatica vs. Sage Intacct
 
Portal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russePortal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russe
 
State of the Smart Building Startup Landscape 2024!
State of the Smart Building Startup Landscape 2024!State of the Smart Building Startup Landscape 2024!
State of the Smart Building Startup Landscape 2024!
 
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
Event-Driven Architecture Masterclass: Integrating Distributed Data Stores Ac...
 
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
TEST BANK For, Information Technology Project Management 9th Edition Kathy Sc...
 
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
Event-Driven Architecture Masterclass: Engineering a Robust, High-performance...
 
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptxHarnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
Harnessing Passkeys in the Battle Against AI-Powered Cyber Threats.pptx
 
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on ThanabotsContinuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
 
Intro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptxIntro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptx
 
Event-Driven Architecture Masterclass: Challenges in Stream Processing
Event-Driven Architecture Masterclass: Challenges in Stream ProcessingEvent-Driven Architecture Masterclass: Challenges in Stream Processing
Event-Driven Architecture Masterclass: Challenges in Stream Processing
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
Introduction to FIDO Authentication and Passkeys.pptx
Introduction to FIDO Authentication and Passkeys.pptxIntroduction to FIDO Authentication and Passkeys.pptx
Introduction to FIDO Authentication and Passkeys.pptx
 
How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cf
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM Performance
 
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdfFrisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
Frisco Automating Purchase Orders with MuleSoft IDP- May 10th, 2024.pptx.pdf
 
WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024WebRTC and SIP not just audio and video @ OpenSIPS 2024
WebRTC and SIP not just audio and video @ OpenSIPS 2024
 
2024 May Patch Tuesday
2024 May Patch Tuesday2024 May Patch Tuesday
2024 May Patch Tuesday
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
 
Top 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development CompaniesTop 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development Companies
 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptx
 

Featured

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Agile estimating

  • 1. Jeffrey D. Mansfield Project Management/Program Management/Portfolio Management Professional jeffreydmansfield#@gmail.com http://www.linkedin.com/in/jeffreydmansfield/ December 2018
  • 2. Answering these questions are a challenge as changes in scope and priority will occur during development. The following Agile planning and tracking process can help answer these questions.
  • 3. 1. Break backlog into epics/stories 2. Assign story points Part of prioritization process Use Fibonacci numbers (1, 2, 3, 5, 8, 13, 21) for t-shirt sizing of effort 3. Define MinimumViable Product - MVP Product Owner defines the minimum functionality to be released 4. Add additional story point contingency to account for: Changes in requirement (new functionality) Resolving technical debt (rework) 5. Estimate team capacity in story points Estimate number of story points (velocity) to be completed for each sprint ▪ Velocity will improve as team matures ▪ Velocity will change as team changes 6. Develop an initial sprint plan Number of sprints required until MVP + Contingency < sum of velocity
  • 4. Sprint 1 2 3 4 5 6 7 8 9 10 Sprint End Date 2/15/19 3/1/19 3/15/19 3/29/19 4/12/19 4/26/19 5/10/19 5/24/19 6/7/19 6/21/19 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40
  • 5. 1. After every sprint, assess the following: What was the actual velocity of the team? The number of story points the team completed Is the planned velocity too high or too low based on actual? Can any changes be made to increase velocity? Has the story points required to meet MVP changed? Does the contingency need to be adjusted? Has the team capacity changed? Have people been added or removed? 2. Reforecast the sprint plan based on the assessment
  • 6. 1. First 3 sprints on plan, additional stories added to backlog, but backlog is less than MVP and Contingency planned.
  • 7. Sprint 1 2 3 4 5 6 7 8 9 10 Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Actual/Forecast Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600 Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 Actual Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Actual Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Actual Remaining Story Points (Incl Backlog) 450 440 430 360 290 220 150 80 40 Actual Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Adjusted total story points based on backlog. Total story points still within team capacity. Still on target for 10 sprints.
  • 8. 1. First 3 sprints on plan, additional stories added to backlog, but backlog is less than MVP and Contingency planned. 2. Loss of team member for 3 sprints reducing velocity and MVP cannot be met as originally planned.
  • 9. Sprint 1 2 3 4 5 6 7 8 9 10 Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Actual/Forecast Actual Team Capacity Story Points 570 570 570 570 570 570 570 570 570 570 570 Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600 Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 40 40 Actual Total Completed Story Points 50 110 170 230 290 350 420 490 530 570 Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 250 180 110 70 30 Actual Remaining MVP & Contingency Story Points 550 490 430 370 310 250 180 110 70 30 Adjusted team velocity to reflect loss of team member. Team velocity will no longer cover MVP.
  • 10. 1. First 3 sprints on plan, additional stories added to backlog, but backlog is less than MVP and Contingency planned. 2. Lose team member for 3 sprints reducing velocity and MVP cannot be met as originally planned. 3. Added additional velocity to later sprints to keep to current sprint plan.
  • 11. Sprint 1 2 3 4 5 6 7 8 9 10 Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Actual/Forecast Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Actual Total Story Points (Incl Backlog) 500 550 600 600 600 600 600 600 600 600 Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 55 55 Actual Total Completed Story Points 50 110 170 230 290 350 420 490 545 600 Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 250 180 110 55 Actual Remaining MVP & Contingency Story Points 550 490 430 370 310 250 180 110 55 Decision taken to reduce number of team members planned to be released for sprint 9 and 10. Increased forecasted velocity to reflect additional team members for these sprints. MVP is now being met.
  • 12. 1. First 3 sprints on plan, additional stories added to backlog, but backlog is less than MVP and Contingency planned. 2. Lose team member for 3 sprints reducing velocity and MVP cannot be met as originally planned. 3. Added additional velocity to later sprints to keep to current sprint plan. 4. Product Owner adds additional stories to MVP.
  • 13. Sprint 1 2 3 4 5 6 7 8 9 10 Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Actual/Forecast Actual Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 Actual Total Story Points (Incl Backlog) 500 550 600 600 600 650 735 735 735 735 Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 700 700 Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 55 55 Actual Total Completed Story Points 50 110 170 230 290 350 420 490 545 600 Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 300 315 245 190 135 Actual Remaining MVP & Contingency Story Points 550 490 430 370 310 250 180 110 155 100 Product Owner adds 100 story points to MVP. MVP now exceeds team capacity. MVP can no longer be delivered within current sprint plan.
  • 14. 1. First 3 sprints on plan, additional stories added to backlog, but backlog is less than MVP and Contingency planned. 2. Lose team member for 3 sprints reducing velocity and MVP cannot be met as originally planned. 3. Added additional velocity to later sprints to keep to current sprint plan. 4. Product Owner adds additional stories to MVP 5. Additional Sprint is added to complete MVP.
  • 15. Sprint 1 2 3 4 5 6 7 8 9 10 11 12 Sprint End Date 2/15/19 3/1/2019 3/15/2019 3/29/2019 4/12/2019 4/26/2019 5/10/2019 5/24/2019 6/7/2019 6/21/2019 7/5/2019 7/19/2019 Plan Original Team Capacity Story Points 600 600 600 600 600 600 600 600 600 600 600 600 600 Original Total Story Points (incl Backlog) 500 500 500 500 500 500 500 500 500 500 500 500 500 Original Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 600 600 600 630 700 Original Planned Team Velocity for Sprint 50 60 60 70 70 70 70 70 40 40 Original Total Completed Story Points 50 110 170 240 310 380 450 520 560 600 600 600 Original Remaining Story Points (Incl Backlog) 450 390 330 260 190 120 50 Original Remaining MVP & Contingency Story Points 550 490 430 360 290 220 150 80 40 Actual/Forecast Actual Team Capacity Story Points 700 700 700 700 700 700 700 700 700 700 700 700 700 Actual Total Story Points (Incl Backlog) 500 550 600 600 600 650 735 735 735 735 735 735 Actual Total MVP & Contingency Story Points 600 600 600 600 600 600 600 600 700 700 700 700 Actual Team Velocity for Sprint 50 60 60 60 60 60 70 70 70 70 70 Actual Total Completed Story Points 50 110 170 230 290 350 420 490 560 630 700 700 Actual Remaining Story Points (Incl Backlog) 450 440 430 370 310 300 315 245 175 105 35 35 Actual Remaining MVP & Contingency Story Points 550 490 430 370 310 250 180 110 140 70 Decision taken to keep team fully staffed and to add an additional sprint. Updated forecasted velocity based on decision. MVP is now being met. Some additional backlog items will not be delivered (35 story points).
  • 16.
  • 17.
  • 18. Jeffrey D. Mansfield Project Management/Program Management/Portfolio Management Professional Driving Business Strategy Implementation through Projects http://www.linkedin.com/in/jeffreydmansfield/ http://www.twitter.com/jeffmansfld Resume - http://www.slideshare.net/jeffreydmansfield/resume -mansfield-jeffrey-ppm-jan272014-31143481