SlideShare a Scribd company logo
1 of 9
Download to read offline
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[528]
ANALYSIS OF GRID CONNECTED INDEPENDENT POWER PLANT
CAPABILITIES ON ELECTRICITY GENERATION SPECTRUM IN NIGERIA
C.U. Okoye*1, I.A. Adejumobi*2, I. Bitrus*3, N.O. Adelakun*4
*1,3,4Department of electrical/Electronic Engineering, The Federal Polytechnic Ilaro,
Ogun State Nigeria.
*2Federal University of Agriculture Abeokuta, Ogun State Nigeria.
ABSTRACT
At the core of any meaningful economic activity is electric power. Absence or inadequacy of it in a nation
stalls development in that nation. In Nigeria, there is a wide gap between forecast power and actual
power generation needed for productive endeavours. For instance in July 2017, the generation peak load
forecast was 14190MW while the actual generation peak load was 4567MW. In July 2018 it was again
14190MW (forecast) but 5110MW (actual). This paper uses descriptive statistics to analyse Independent
Power Plant (IPP) capabilities spread across ten years (2009-2018). The results show that there is need
to encourage more private investors to build additional IPPs in order to increase adequate power
generation in Nigeria – especially in post-COVID-19 socio-economic crisis. Consequently, it is expected
that the wide gap between generation peak load peak load forecast and actual peak load would be
narrowed.
Keywords: Independent Power Plants (IPPs), forecast, generation, installed capacity, available capacity.
I. INTRODUCTION
Nigeria’s power sector is a huge machine, comprising mainly generation, transmission and distribution
sub-systems. Unfortunately, all these sub-systems are bedeviled with much challenges. Consequently,
electricity consumers are daily faced with acute lack of power for productive activities. The nations power
generation capacity as at December, 2018 was 12910.40MW and this was just the installed (nameplate)
capacity of the grid-connected power plants [1]. Typically, in July, 2018, the generation peak load forecast
was 14190MW while the actual generation peak load was 5110MW which was just 36% of the generation
peak load forecast. It is difficult to estimate the actual electricity generated and consumed in Nigeria
because most consumers now rely on petrol and diesel generating units for own power. In a study [2], it
was revealed that Nigerians expend over ₦179 billion annually on fuel for dedicated generators; the
highest the world over. Dangote Cement, Ibese, Nigeria was said to spend ₦250 million daily before
embarking on generating its own power [3].
When more power is drawn by the load beyond the total electricity generated, the system frequency
begins to fall from the ideal 50Hz level. Without additional generation or load-shedding, the power
system will experience under frequency collapse (loss of stability and fall out of step).and this is one of
the causes of the power outage in a power system [4],[5]. To increase the total installed capacity and
available generation capacity there is need to encourage the development Independent Power Plants
(IPPs). This must be taken seriously because year 2020 is here with us and Nigeria is far from achieving
the much orchestrated Vision 20: 2020 power target. The target of Nigeria’s Vision 20: 2020 is to increase
the installed generation capacity from the 2009 figure (6000MW) to 20,000MW by 2015 and 35,000MW
by 2020. This poor state of affair has been emphasized several times in literature [6],[7],[8],[9].
Most industries in Nigeria generate their own electricity due to the unreliability of grid electricity.
According to [10], 86% of firms in the country use diesel fuel to generate power for their own use. Some
others such as Dangote Cement, Ibese, Nigeria utilizes natural gas to achieve the same purpose. Yet, a few
other Independent Power Producers, produce electricity in excess of their need and thus sell the excess
through national grid network. Some notable IPPs connected to the national grid are Okpai gas plant,
Afam VI, Azura, A.E.S., ASCO, Paras, Ibom and Omoku gas plant [1],[11],[12]. Their total installed capacity
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[529]
as at December, 2018 was 2652.00MW which is 20.5% of the total national grid installed capacity of
12910.40MW (Thermal and Hydro).
Since the reason for licensing the IPPs by the Nigerian Electricity Regulatory Commission (NERC) is
mainly to compliment the aggregate energy generation and to help in reducing gas flaring, more investors
should be encouraged to build capacity in this area to mitigate energy crises in post-COVID-19 socio-
economic development. Table 1.0 shows some licensed IPPs in Nigeria and their site ratings/capacities.
Table-1: A typical Licensed IPPs in Nigeria
S/N Power Station Capacity (MW) Status
1. Index thermal power Ltd 1800 Licence granted
2. Agbara shoeline power co. Ltd 1800 Licence granted
3. Shell Distribution co. Ltd 100 Licence granted
4. Ibafo power station Ltd 640 Licence granted
5. Hadson Power Station Ltd 200 Licence granted
6. First Independent Power Co. Ltd 150 Licence granted
7. Anita Energy Ltd 136 Licence granted
8. Lotust Bresson Nig. Ltd 60 Licence granted
9. Weston Tech & Energy Services Ltd 1000 Licence granted
10. Ethiope Energy Ltd 2800 Approved Licence
11. Farm Electric Supply Ltd 150 Approved Licence
12. ICS power 624 Approved Licence
13. Supertech Ltd 1000 Approved Licence
14. Mabon Ltd 39 Approved Licence
15. Geometric Ltd 140 Approved Licence
Total 10,639
Source: [13]
In 2009 about 29 IPPs were licensed by the NERC to build power plants in Nigeria. However, many have
not utilised this opportunity made available to them due to constraints such as harsh economic
environment and gas shortage, [14],[15]. [16] reports that 90% of power licenses were unused due to
inadequacy of natural gas, the major fuel for the proposed plants.
II. METHODOLOGY
Data were collected periodically from the National Control Centre (NCC), Osogbo, Nigeria and the
Transmission Company of Nigeria (TCN), respectively. Visits were also made to Olorunsogo I and
Olorunsogo NIPP thermal power stations which are a few kilometers from the Federal Polytechnic Ilaro,
Nigeria where the researchers live and work.
Dangote Cement, Ibese is about five-minute drive from Ilaro and its thermal IPP was also visited.
Numerous journals, textbooks and other literature sources crucial to the work were adequately consulted
also and information classified as follows:
 Installed capacity, IPP (MW): 2009 – 2018.
 Average availability (average available capacity) MW: 2009 – 2018
 Installed capacity; all other grid-connected plants (MW): 2009 – 2018
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[530]
 Available capacity, all other grid-connected plants (MW): 2009-2018
 Grid-connected IPPs in Nigeria as at December, 2018, MW.
By all other grid-connected plants, what is meant is all the hydro and the rest of the thermal power plants
generating electricity to the grid/power network. Some of them are: Kainji hydropower plant, Jebba
hydro, Shiroro hydro, Egbin thermal, Afam (I-V), Sapele, Olorunsogo, and Omotosho thermal power plants
(among others).
As at December 2018, the total installed capacity of all the three hydro plants was 1938.40 MW with
average availability of 1253.71 MW (which is 64.7%) of the total installed hydro capacity (NCC, 2018).
For thermal, it was 8320 MW which is 53.2% of the total installed thermal plants.
Availability factor (A.F) as calculated in Table 3.0 is given as:
Thus, for Rivers IPP,
For Omoku IPP,
For Okpai IPP,
In the case of ASCO (Table 3.0), A.F = 0. This means that did not generate electricity within the period.
This means that there was no grid-connected IPP at the time; hence no electricity generation from them.
III. RESULTS AND DISCUSSION
The data collected were analysed with the aid of descriptive statistics (charts and graphs) as detailed
below.
Table-2: Installed and Available Capacities of IPPs Relative to all Other Power Plants. (2009-2018)
Year
Installed
Capacity, IPP
(MW)
Average Available
Capacity, IPP (MW)
Installed Capacity, all
other grid-connected
plants (MW)
Available Capacity,
all other grid-
connected plants
(MW)
2009 NA NA 8,702.25 4,825.17
2010 NA NA 8,425.40 4,212.70
2011 1,947.00 1,289.26 6,963.40 3,190.06
2012 2,017.00 1,384.93 7,938.40 4,131.45
2013 2,127.00 1,192.14 8,788.40 3,858.85
2014 2,127.00 1,451.54 9,038.40 4,866.16
2015 2,119.00 1,173.43 10,013.40 5,227.77
2016 2,177.00 1,243.33 10,133.40 6,634.66
2017 2,191.00 1,203.24 10,133.40 5,668.01
2018 2,652.00 1,684.23 10,258.40 5,683.71
Total 17,357.00 10,622.10 90,394.85 48,298.54
Key: NA (not available): No IPP was connected to the grid at the time. All IPPs are gas-powered.
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[531]
Source: Computed from Annual Technical Reports, 2009 – 2018, National Control Centre (NCC), Osogbo,
Nigeria.
The situation presented in Table 2.0 could be better appreciated when put in a chart.
Fig.-1: Chart illustrating installed and available capacities of IPPs (2009-2018)
From here, observe that the installed and available capacities in 2018 were the highest ever achieved in
the 10-year period.
Fig.-2: Pie chart of installed capacity of IPPs and available capacity
Fig. 2.0 illustrates the aggregated installed and available capacities in the 10 years under study. The
available capacity is clearly below the installed capacity. Hence, total electricity generation was poor.
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[532]
Fig.-3: Graphical presentation of IPP installed capacity of IPPs and available capacity (2009-2018)
In Fig. 3.0., it is depicted that between 2009 and 2010, no IPP (where it existed) was connected to the
national grid hence the flattened portion. Further observe that there is an increasing gap between the
contribution of the IPPs to the grid from 2010 when they were connected to the grid to 2018.
Fig.-4: Charted representation of IPP installed capacity in relation to all other power plants in the grid
(2009 - 2018)
In Fig. 4.0., the installed capacities of IPPs relative to all other grid-connected (hydro and thermal) power
plants are shown much more clearly.
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[533]
Fig.-5: Graphical illustration of installed capacity of IPPs and the rest of the power plants connected to the
grid network (2009 - 2018)
To further convey the same information in Fig. 4.0, in a different way, Fig. 5.0 was plotted.
Fig.-6: Pie chart of installed capacity of IPPs relative to installed capacity of all other power plants.
From Fig. 6.0, it is clear that the installed capacity of the IPPs in the 10-year period did not increase
appreciably.
Table-3: Grid-Connected Independent Power Plants (IPPs) in Nigeria as at December, 2018.
S/N Power Station/Plant Installed Capacity
(MW)
Average Available
Capacity (MW)
Availability Factor
1 Rivers IPP 180.00 135.08 0.75
2 Omoku 150.00 68.94 0.46
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[534]
3 ASCO 110.00 0.00 0.00
4 Trans-Amadi 100.00 49.15 0.49
5 Okpa 480.00 345.52 0.72
6 Ibom 155.00 95.23 0.61
7 Paras 72.00 68.31 0.95
8 Azura 461.00 335.92 0.73
9 A.E.S. 294.00 0.00 0.00
Total 2652.00 1684.23 0.57
Source: Extracted from Annual Technical Reports, National Control Centre (NCC), Osogbo, Nigeria. (2018)
Fig.-7: Chart Showing the installed and available capacities of IPPs as at Dec. 2018
From Table 3.0, the chart in Fig. 7.0 was produced. This represents fairly the IPP installed and available
capacities as they are in Nigeria as at December 2018. This argument is further advanced graphically in
Fig. 8.0. This situation in 2020 may not be any different.
Fig.-8: Graphical representation of installed and available capacities of IPPs (2018)
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[535]
Babcock University currently operates a 4.4 MW IPP that continuously supplies power to the institution
day and night [17]. The plant is even of much higher rating than many of the grid-connected IPPs listed in
Table 3.0. Similarly, Dangote Cement’s IPP, Ibese, Ogun State, Nigeria, generated 406762.33 MWH of
energy in 2013 which when compared with the 29628699.32 MWH generated by the national grid
represents 1.4% of Nigeria’s total energy generation in 2013 [7]. Both and similar promising IPPs in the
nation should be encouraged to produce more than their need and to sell the excess to grid operators.
IV. CONCLUSION
There is no doubt that Nigeria needs increasing electricity generation and availability to meet the
challenges of development worsened by the negative effect of Covid-19 pandemic. The current power
generating capacity and availability is not in any way encouraging. Even if all the 12910MW installed
generating capacity is fully utilized, this is still far below the vision 20:2020 target of 40,000MW. The
Independent Power Plants (IPPs) constitute only about 20% of the nation’s installed generating capacity.
Among other things; emphasis should be on creating an enabling environment for investors to not only
build more thermal gas-fired plants, but also to exploit Nigeria’s huge potentials in renewable energy
such as small hydropower, wind and solar technologies.
RECOMMENDATIONS
 It is high time Nigeria intensified effort at encouraging the construction and development of IPPs
across board. Apart from those connected to the national grid, some organisations/industries are
courageously breaking ground in this area. Babcock university Ilishan-Remo, Ogun State, Nigeria
sometime ago announced that its 4.4MW IPP produced 24hours of uninterrupted power [17].
Dangote cement, Ibese, Nigeria also generates its own electricity at 11KV using natural gas. If
encouraged, the industry can convincingly contribute to grid generation capacity with a minimal
power loss of about 1.2%. In a study, [7], its generation represented about 1.4%of Nigeria’s total
2013 energy generation.
 Prospective Independent Power Producers should endeavour to explore and exploit renewable
energy capacity of Nigeria. For instance, the large and small hydropower potentials are about
11,500MW and 734MW respectively [18]. Wind resource has a potential of 2-6m/s at 10m height
while solar has 3.5-7.0 Kw/m/day with corresponding sunshine of 4-8hours/day.
 All the grid-connected IPPs and even the licensed/approved ones (Tables 1.0 and 3.0) are all gas
dependent. It is expected that their huge demand for natural gas would ultimately lead to reduction
in gas flaring. However, this objective has not been realised to an extent. The reason most have not
even started operation is because of acute shortage of gas [16]. So, gas supply must be improved
upon to enhance IPP construction and deployment.
 The more power stations are built and operated; the more socio-economic activities are simulated;
hence more jobs are likely to be created for the teaming youth-especially in post-COVID era.
 Prospective IPPs should be given some financial assistance by making policies that encourage cost
reduction in their investments [19].
V. REFERENCES
[1] NCC (2018), Annual Technical Report, National Control Centre, Osogbo, Nigeria.
[2] Ebhota, W.S & Tabakov, P.Y (2018), Power Inadequacy, the thorn in Economic Growth in Nigeria,
International Journal of Applied Energy Research, Vol.13, No 16, pp 12602 -12610.
[3] AIT (2014), African Independent Television, Newspaper Review, August 18.
[4] Rao, S. (2008), Testing, Commissioning, Operation, and Maintenance of Electrical Equipment,
Khanna Publisher., New Delhi.
[5] Okoye, C.U. & Omolola, S.A (2019a), A Study and Evaluation of Power Outages on 132KV
Transmission Network in Nigeria for Grid Security, The International Journal of Engineering and
Science, Vol. 8, Issue 11, pp. 53-57.
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[536]
[6] Okoye, C,U., Omolola, S.A., Adelakun, N.O., & Bitrus, I. (2019b), Retooling Nigeria’s Electricity
Generation Sub-System for Sustainable Grid Operation, International Journal of Innovations in
Engineering Research and Technology, Vol.6, Issue 12, December. Pp.7-13
[7] Okoye, C.U., Alao M.J., Bitrus, I., Adelakun N.O., & Abdulhamid, I.G. (2018), A Study and Analysis of
Energy Generation and Consumption in Dangote Cement Plant, Ibese, Nigeria. Global Journal of
Advanced Engineering Technologies and Sciences. Vol.5 No 11.
[8] KPMG (2019), Nigeria’s Electricity Supply Industry Highlights, Power Sector Watch, Edition Q.3.
[9] CSEA (2019), Energy for Growth Hub, Power Nextier, May edition.
[10] NSE (2017), The Nigerian Infrastructure Report Card 2017, Nigerian Society of Engineers.
[11] ERGP (2017), Economic Recovery Growth Plan 2017-2020, Ministry of Budget and National
Planning, Federal Republic of Nigeria.
[12] Fashola, B.R. (2017), Power Sector Reforms: Challenges and the Way Forward, paper presented
at the 2017 Public lecture series, Department of Economics, University of Lagos, Nigeria.
[13] Sambo, A.S.; Garba, B.; Zarma, I.H. & Gaji, M.M. (2010) Electricity generation and the present
challenges in the Nigerian power sector, Energy company of Nigera, Nigeria.
[14] Gasau, A.M.& Orah, A.M (2018), Independent Power Plants: A panacea to the Growth and
Sustainability of Manufacturing Industries in Nigeria, International Conference on Mechanical,
Material and Renewable Energy.
[15] Okedu, K.E., Kenu S., Idowu K., Uhunmuwangbo R. (2018), Impact of the Independent Power
Producers and National Integrated Power Projects on the Deregulation of the Nigerian Electricity
Sector, Journal of Sustainable Development in Africa, Vol.20, No 1.
[16] Opara, S. (2014), 90% Power licenses Idle due to Gas Shortage, The Punch, June 13, p.29.
[17] Uwandu, E. (2019), How we Generate 24-hour Power Supply, Vanguard, Thursday 12, p.38.
[18] Amoda, O. (2016), Power Distribution Demand Side Management in Developing Economies, 13th
DEEEAL Distinguished Lecture, The Nigerian Institution of Electrical and Electronic Engineers.
[19] FRN (2012), Investment Opportunities in the Nigeria Power Sector, Federal Republic of Nigeria.

More Related Content

What's hot

Integrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platformIntegrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platform
Farhan Beg
 
Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010
Renganathan M G
 
Power Sector India Sample
Power Sector   India   SamplePower Sector   India   Sample
Power Sector India Sample
vandalmax
 
Electricity in india
Electricity in indiaElectricity in india
Electricity in india
Dev Garg
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
Rahul Gupta
 
Solar Energy India Sample
Solar Energy   India   SampleSolar Energy   India   Sample
Solar Energy India Sample
vandalmax
 
Solar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain NaikSolar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain Naik
hussainmaloth
 

What's hot (20)

IRJET- A Review: Overcoming of Electrical Energy Crises in Pakistan
IRJET- A Review: Overcoming of Electrical Energy Crises in PakistanIRJET- A Review: Overcoming of Electrical Energy Crises in Pakistan
IRJET- A Review: Overcoming of Electrical Energy Crises in Pakistan
 
Integrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platformIntegrating wind and solar energy in India for a Smart Grid platform
Integrating wind and solar energy in India for a Smart Grid platform
 
Awea Annual Wind Report 2009
Awea Annual Wind Report 2009Awea Annual Wind Report 2009
Awea Annual Wind Report 2009
 
Power Ppt
Power PptPower Ppt
Power Ppt
 
Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010Eai presentation investment challenges in wind energy in india delhi mar 2010
Eai presentation investment challenges in wind energy in india delhi mar 2010
 
Power Sector India Sample
Power Sector   India   SamplePower Sector   India   Sample
Power Sector India Sample
 
Power sector in india
Power sector in indiaPower sector in india
Power sector in india
 
Electricity in india
Electricity in indiaElectricity in india
Electricity in india
 
India's Wind Energy Market Potential
India's Wind Energy Market PotentialIndia's Wind Energy Market Potential
India's Wind Energy Market Potential
 
Electricity in India: Developments, Issues, & Remedies
Electricity in India: Developments, Issues, & RemediesElectricity in India: Developments, Issues, & Remedies
Electricity in India: Developments, Issues, & Remedies
 
The Next Innovation Race
The Next Innovation RaceThe Next Innovation Race
The Next Innovation Race
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
Power Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in IndiaPower Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in India
 
Electricity ppt
Electricity pptElectricity ppt
Electricity ppt
 
Opportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in IndiaOpportunities & Challenges in Developing Wind Energy in India
Opportunities & Challenges in Developing Wind Energy in India
 
Solar Energy India Sample
Solar Energy   India   SampleSolar Energy   India   Sample
Solar Energy India Sample
 
Solar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain NaikSolar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain Naik
 
Power Sector Report - March 2017
Power Sector Report - March 2017Power Sector Report - March 2017
Power Sector Report - March 2017
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in India
 
Power Sector Report July 2017
Power Sector Report July 2017Power Sector Report July 2017
Power Sector Report July 2017
 

Similar to Analysis of grid connected independent power plant capabilities on electricity generation spectrum in nigeria

Performance investigation of electricial power supply to owerri for higher pr...
Performance investigation of electricial power supply to owerri for higher pr...Performance investigation of electricial power supply to owerri for higher pr...
Performance investigation of electricial power supply to owerri for higher pr...
eSAT Journals
 
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation SystemTechno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
theijes
 
MENA nuclear decommissioning market, 2012
MENA nuclear decommissioning market, 2012MENA nuclear decommissioning market, 2012
MENA nuclear decommissioning market, 2012
piersfrench
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
irjes
 

Similar to Analysis of grid connected independent power plant capabilities on electricity generation spectrum in nigeria (20)

A Markov model of generator performance at the Kainji hydro-power station in...
A Markov model of generator performance at the Kainji  hydro-power station in...A Markov model of generator performance at the Kainji  hydro-power station in...
A Markov model of generator performance at the Kainji hydro-power station in...
 
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTSDESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
 
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaA Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
 
IRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in India
 
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
 
J0364057060
J0364057060J0364057060
J0364057060
 
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
 
Solar energy as a potential contributor to help bridge the gap between electr...
Solar energy as a potential contributor to help bridge the gap between electr...Solar energy as a potential contributor to help bridge the gap between electr...
Solar energy as a potential contributor to help bridge the gap between electr...
 
Assessment of Impact of Outages in Selected Electricity Intensive Industries ...
Assessment of Impact of Outages in Selected Electricity Intensive Industries ...Assessment of Impact of Outages in Selected Electricity Intensive Industries ...
Assessment of Impact of Outages in Selected Electricity Intensive Industries ...
 
Performance investigation of electricial power supply to owerri for higher pr...
Performance investigation of electricial power supply to owerri for higher pr...Performance investigation of electricial power supply to owerri for higher pr...
Performance investigation of electricial power supply to owerri for higher pr...
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy Scenario
 
B0314011017
B0314011017B0314011017
B0314011017
 
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation SystemTechno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
 
Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...
 
Impact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric EnergyImpact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric Energy
 
An Optimized Neuro-Fuzzy Control System for Afam Vi Power Station (IPP)
An Optimized Neuro-Fuzzy Control System for Afam Vi Power Station (IPP)An Optimized Neuro-Fuzzy Control System for Afam Vi Power Station (IPP)
An Optimized Neuro-Fuzzy Control System for Afam Vi Power Station (IPP)
 
MENA nuclear decommissioning market, 2012
MENA nuclear decommissioning market, 2012MENA nuclear decommissioning market, 2012
MENA nuclear decommissioning market, 2012
 
Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.
 
The Application of Homer Optimization Software to Investigate the Prospects o...
The Application of Homer Optimization Software to Investigate the Prospects o...The Application of Homer Optimization Software to Investigate the Prospects o...
The Application of Homer Optimization Software to Investigate the Prospects o...
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
 

More from Najeem Olawale Adelakun

A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
Najeem Olawale Adelakun
 

More from Najeem Olawale Adelakun (11)

A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...
 
Solar powered automatic wash hand basin system
Solar powered automatic wash hand basin systemSolar powered automatic wash hand basin system
Solar powered automatic wash hand basin system
 
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
 
Evaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadEvaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient Load
 
Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...
 
Development of a two link robotic manipulator
Development of a two link robotic manipulatorDevelopment of a two link robotic manipulator
Development of a two link robotic manipulator
 
Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...
 
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDINGDESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDING
 
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
 
Design and Evaluation of Electrical Services for an Energy Efficient Home
Design and Evaluation of Electrical Services for an  Energy Efficient HomeDesign and Evaluation of Electrical Services for an  Energy Efficient Home
Design and Evaluation of Electrical Services for an Energy Efficient Home
 
A Review Of Solar Energy
A Review Of Solar EnergyA Review Of Solar Energy
A Review Of Solar Energy
 

Recently uploaded

Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 

Recently uploaded (20)

UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
👉 Yavatmal Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top Class Call Girl S...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 

Analysis of grid connected independent power plant capabilities on electricity generation spectrum in nigeria

  • 1. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [528] ANALYSIS OF GRID CONNECTED INDEPENDENT POWER PLANT CAPABILITIES ON ELECTRICITY GENERATION SPECTRUM IN NIGERIA C.U. Okoye*1, I.A. Adejumobi*2, I. Bitrus*3, N.O. Adelakun*4 *1,3,4Department of electrical/Electronic Engineering, The Federal Polytechnic Ilaro, Ogun State Nigeria. *2Federal University of Agriculture Abeokuta, Ogun State Nigeria. ABSTRACT At the core of any meaningful economic activity is electric power. Absence or inadequacy of it in a nation stalls development in that nation. In Nigeria, there is a wide gap between forecast power and actual power generation needed for productive endeavours. For instance in July 2017, the generation peak load forecast was 14190MW while the actual generation peak load was 4567MW. In July 2018 it was again 14190MW (forecast) but 5110MW (actual). This paper uses descriptive statistics to analyse Independent Power Plant (IPP) capabilities spread across ten years (2009-2018). The results show that there is need to encourage more private investors to build additional IPPs in order to increase adequate power generation in Nigeria – especially in post-COVID-19 socio-economic crisis. Consequently, it is expected that the wide gap between generation peak load peak load forecast and actual peak load would be narrowed. Keywords: Independent Power Plants (IPPs), forecast, generation, installed capacity, available capacity. I. INTRODUCTION Nigeria’s power sector is a huge machine, comprising mainly generation, transmission and distribution sub-systems. Unfortunately, all these sub-systems are bedeviled with much challenges. Consequently, electricity consumers are daily faced with acute lack of power for productive activities. The nations power generation capacity as at December, 2018 was 12910.40MW and this was just the installed (nameplate) capacity of the grid-connected power plants [1]. Typically, in July, 2018, the generation peak load forecast was 14190MW while the actual generation peak load was 5110MW which was just 36% of the generation peak load forecast. It is difficult to estimate the actual electricity generated and consumed in Nigeria because most consumers now rely on petrol and diesel generating units for own power. In a study [2], it was revealed that Nigerians expend over ₦179 billion annually on fuel for dedicated generators; the highest the world over. Dangote Cement, Ibese, Nigeria was said to spend ₦250 million daily before embarking on generating its own power [3]. When more power is drawn by the load beyond the total electricity generated, the system frequency begins to fall from the ideal 50Hz level. Without additional generation or load-shedding, the power system will experience under frequency collapse (loss of stability and fall out of step).and this is one of the causes of the power outage in a power system [4],[5]. To increase the total installed capacity and available generation capacity there is need to encourage the development Independent Power Plants (IPPs). This must be taken seriously because year 2020 is here with us and Nigeria is far from achieving the much orchestrated Vision 20: 2020 power target. The target of Nigeria’s Vision 20: 2020 is to increase the installed generation capacity from the 2009 figure (6000MW) to 20,000MW by 2015 and 35,000MW by 2020. This poor state of affair has been emphasized several times in literature [6],[7],[8],[9]. Most industries in Nigeria generate their own electricity due to the unreliability of grid electricity. According to [10], 86% of firms in the country use diesel fuel to generate power for their own use. Some others such as Dangote Cement, Ibese, Nigeria utilizes natural gas to achieve the same purpose. Yet, a few other Independent Power Producers, produce electricity in excess of their need and thus sell the excess through national grid network. Some notable IPPs connected to the national grid are Okpai gas plant, Afam VI, Azura, A.E.S., ASCO, Paras, Ibom and Omoku gas plant [1],[11],[12]. Their total installed capacity
  • 2. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [529] as at December, 2018 was 2652.00MW which is 20.5% of the total national grid installed capacity of 12910.40MW (Thermal and Hydro). Since the reason for licensing the IPPs by the Nigerian Electricity Regulatory Commission (NERC) is mainly to compliment the aggregate energy generation and to help in reducing gas flaring, more investors should be encouraged to build capacity in this area to mitigate energy crises in post-COVID-19 socio- economic development. Table 1.0 shows some licensed IPPs in Nigeria and their site ratings/capacities. Table-1: A typical Licensed IPPs in Nigeria S/N Power Station Capacity (MW) Status 1. Index thermal power Ltd 1800 Licence granted 2. Agbara shoeline power co. Ltd 1800 Licence granted 3. Shell Distribution co. Ltd 100 Licence granted 4. Ibafo power station Ltd 640 Licence granted 5. Hadson Power Station Ltd 200 Licence granted 6. First Independent Power Co. Ltd 150 Licence granted 7. Anita Energy Ltd 136 Licence granted 8. Lotust Bresson Nig. Ltd 60 Licence granted 9. Weston Tech & Energy Services Ltd 1000 Licence granted 10. Ethiope Energy Ltd 2800 Approved Licence 11. Farm Electric Supply Ltd 150 Approved Licence 12. ICS power 624 Approved Licence 13. Supertech Ltd 1000 Approved Licence 14. Mabon Ltd 39 Approved Licence 15. Geometric Ltd 140 Approved Licence Total 10,639 Source: [13] In 2009 about 29 IPPs were licensed by the NERC to build power plants in Nigeria. However, many have not utilised this opportunity made available to them due to constraints such as harsh economic environment and gas shortage, [14],[15]. [16] reports that 90% of power licenses were unused due to inadequacy of natural gas, the major fuel for the proposed plants. II. METHODOLOGY Data were collected periodically from the National Control Centre (NCC), Osogbo, Nigeria and the Transmission Company of Nigeria (TCN), respectively. Visits were also made to Olorunsogo I and Olorunsogo NIPP thermal power stations which are a few kilometers from the Federal Polytechnic Ilaro, Nigeria where the researchers live and work. Dangote Cement, Ibese is about five-minute drive from Ilaro and its thermal IPP was also visited. Numerous journals, textbooks and other literature sources crucial to the work were adequately consulted also and information classified as follows:  Installed capacity, IPP (MW): 2009 – 2018.  Average availability (average available capacity) MW: 2009 – 2018  Installed capacity; all other grid-connected plants (MW): 2009 – 2018
  • 3. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [530]  Available capacity, all other grid-connected plants (MW): 2009-2018  Grid-connected IPPs in Nigeria as at December, 2018, MW. By all other grid-connected plants, what is meant is all the hydro and the rest of the thermal power plants generating electricity to the grid/power network. Some of them are: Kainji hydropower plant, Jebba hydro, Shiroro hydro, Egbin thermal, Afam (I-V), Sapele, Olorunsogo, and Omotosho thermal power plants (among others). As at December 2018, the total installed capacity of all the three hydro plants was 1938.40 MW with average availability of 1253.71 MW (which is 64.7%) of the total installed hydro capacity (NCC, 2018). For thermal, it was 8320 MW which is 53.2% of the total installed thermal plants. Availability factor (A.F) as calculated in Table 3.0 is given as: Thus, for Rivers IPP, For Omoku IPP, For Okpai IPP, In the case of ASCO (Table 3.0), A.F = 0. This means that did not generate electricity within the period. This means that there was no grid-connected IPP at the time; hence no electricity generation from them. III. RESULTS AND DISCUSSION The data collected were analysed with the aid of descriptive statistics (charts and graphs) as detailed below. Table-2: Installed and Available Capacities of IPPs Relative to all Other Power Plants. (2009-2018) Year Installed Capacity, IPP (MW) Average Available Capacity, IPP (MW) Installed Capacity, all other grid-connected plants (MW) Available Capacity, all other grid- connected plants (MW) 2009 NA NA 8,702.25 4,825.17 2010 NA NA 8,425.40 4,212.70 2011 1,947.00 1,289.26 6,963.40 3,190.06 2012 2,017.00 1,384.93 7,938.40 4,131.45 2013 2,127.00 1,192.14 8,788.40 3,858.85 2014 2,127.00 1,451.54 9,038.40 4,866.16 2015 2,119.00 1,173.43 10,013.40 5,227.77 2016 2,177.00 1,243.33 10,133.40 6,634.66 2017 2,191.00 1,203.24 10,133.40 5,668.01 2018 2,652.00 1,684.23 10,258.40 5,683.71 Total 17,357.00 10,622.10 90,394.85 48,298.54 Key: NA (not available): No IPP was connected to the grid at the time. All IPPs are gas-powered.
  • 4. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [531] Source: Computed from Annual Technical Reports, 2009 – 2018, National Control Centre (NCC), Osogbo, Nigeria. The situation presented in Table 2.0 could be better appreciated when put in a chart. Fig.-1: Chart illustrating installed and available capacities of IPPs (2009-2018) From here, observe that the installed and available capacities in 2018 were the highest ever achieved in the 10-year period. Fig.-2: Pie chart of installed capacity of IPPs and available capacity Fig. 2.0 illustrates the aggregated installed and available capacities in the 10 years under study. The available capacity is clearly below the installed capacity. Hence, total electricity generation was poor.
  • 5. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [532] Fig.-3: Graphical presentation of IPP installed capacity of IPPs and available capacity (2009-2018) In Fig. 3.0., it is depicted that between 2009 and 2010, no IPP (where it existed) was connected to the national grid hence the flattened portion. Further observe that there is an increasing gap between the contribution of the IPPs to the grid from 2010 when they were connected to the grid to 2018. Fig.-4: Charted representation of IPP installed capacity in relation to all other power plants in the grid (2009 - 2018) In Fig. 4.0., the installed capacities of IPPs relative to all other grid-connected (hydro and thermal) power plants are shown much more clearly.
  • 6. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [533] Fig.-5: Graphical illustration of installed capacity of IPPs and the rest of the power plants connected to the grid network (2009 - 2018) To further convey the same information in Fig. 4.0, in a different way, Fig. 5.0 was plotted. Fig.-6: Pie chart of installed capacity of IPPs relative to installed capacity of all other power plants. From Fig. 6.0, it is clear that the installed capacity of the IPPs in the 10-year period did not increase appreciably. Table-3: Grid-Connected Independent Power Plants (IPPs) in Nigeria as at December, 2018. S/N Power Station/Plant Installed Capacity (MW) Average Available Capacity (MW) Availability Factor 1 Rivers IPP 180.00 135.08 0.75 2 Omoku 150.00 68.94 0.46
  • 7. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [534] 3 ASCO 110.00 0.00 0.00 4 Trans-Amadi 100.00 49.15 0.49 5 Okpa 480.00 345.52 0.72 6 Ibom 155.00 95.23 0.61 7 Paras 72.00 68.31 0.95 8 Azura 461.00 335.92 0.73 9 A.E.S. 294.00 0.00 0.00 Total 2652.00 1684.23 0.57 Source: Extracted from Annual Technical Reports, National Control Centre (NCC), Osogbo, Nigeria. (2018) Fig.-7: Chart Showing the installed and available capacities of IPPs as at Dec. 2018 From Table 3.0, the chart in Fig. 7.0 was produced. This represents fairly the IPP installed and available capacities as they are in Nigeria as at December 2018. This argument is further advanced graphically in Fig. 8.0. This situation in 2020 may not be any different. Fig.-8: Graphical representation of installed and available capacities of IPPs (2018)
  • 8. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [535] Babcock University currently operates a 4.4 MW IPP that continuously supplies power to the institution day and night [17]. The plant is even of much higher rating than many of the grid-connected IPPs listed in Table 3.0. Similarly, Dangote Cement’s IPP, Ibese, Ogun State, Nigeria, generated 406762.33 MWH of energy in 2013 which when compared with the 29628699.32 MWH generated by the national grid represents 1.4% of Nigeria’s total energy generation in 2013 [7]. Both and similar promising IPPs in the nation should be encouraged to produce more than their need and to sell the excess to grid operators. IV. CONCLUSION There is no doubt that Nigeria needs increasing electricity generation and availability to meet the challenges of development worsened by the negative effect of Covid-19 pandemic. The current power generating capacity and availability is not in any way encouraging. Even if all the 12910MW installed generating capacity is fully utilized, this is still far below the vision 20:2020 target of 40,000MW. The Independent Power Plants (IPPs) constitute only about 20% of the nation’s installed generating capacity. Among other things; emphasis should be on creating an enabling environment for investors to not only build more thermal gas-fired plants, but also to exploit Nigeria’s huge potentials in renewable energy such as small hydropower, wind and solar technologies. RECOMMENDATIONS  It is high time Nigeria intensified effort at encouraging the construction and development of IPPs across board. Apart from those connected to the national grid, some organisations/industries are courageously breaking ground in this area. Babcock university Ilishan-Remo, Ogun State, Nigeria sometime ago announced that its 4.4MW IPP produced 24hours of uninterrupted power [17]. Dangote cement, Ibese, Nigeria also generates its own electricity at 11KV using natural gas. If encouraged, the industry can convincingly contribute to grid generation capacity with a minimal power loss of about 1.2%. In a study, [7], its generation represented about 1.4%of Nigeria’s total 2013 energy generation.  Prospective Independent Power Producers should endeavour to explore and exploit renewable energy capacity of Nigeria. For instance, the large and small hydropower potentials are about 11,500MW and 734MW respectively [18]. Wind resource has a potential of 2-6m/s at 10m height while solar has 3.5-7.0 Kw/m/day with corresponding sunshine of 4-8hours/day.  All the grid-connected IPPs and even the licensed/approved ones (Tables 1.0 and 3.0) are all gas dependent. It is expected that their huge demand for natural gas would ultimately lead to reduction in gas flaring. However, this objective has not been realised to an extent. The reason most have not even started operation is because of acute shortage of gas [16]. So, gas supply must be improved upon to enhance IPP construction and deployment.  The more power stations are built and operated; the more socio-economic activities are simulated; hence more jobs are likely to be created for the teaming youth-especially in post-COVID era.  Prospective IPPs should be given some financial assistance by making policies that encourage cost reduction in their investments [19]. V. REFERENCES [1] NCC (2018), Annual Technical Report, National Control Centre, Osogbo, Nigeria. [2] Ebhota, W.S & Tabakov, P.Y (2018), Power Inadequacy, the thorn in Economic Growth in Nigeria, International Journal of Applied Energy Research, Vol.13, No 16, pp 12602 -12610. [3] AIT (2014), African Independent Television, Newspaper Review, August 18. [4] Rao, S. (2008), Testing, Commissioning, Operation, and Maintenance of Electrical Equipment, Khanna Publisher., New Delhi. [5] Okoye, C.U. & Omolola, S.A (2019a), A Study and Evaluation of Power Outages on 132KV Transmission Network in Nigeria for Grid Security, The International Journal of Engineering and Science, Vol. 8, Issue 11, pp. 53-57.
  • 9. e-ISSN: 2582-5208 International Research Journal of Modernization in Engineering Technology and Science Volume:02/Issue:12/December -2020 Impact Factor- 5.354 www.irjmets.com www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science [536] [6] Okoye, C,U., Omolola, S.A., Adelakun, N.O., & Bitrus, I. (2019b), Retooling Nigeria’s Electricity Generation Sub-System for Sustainable Grid Operation, International Journal of Innovations in Engineering Research and Technology, Vol.6, Issue 12, December. Pp.7-13 [7] Okoye, C.U., Alao M.J., Bitrus, I., Adelakun N.O., & Abdulhamid, I.G. (2018), A Study and Analysis of Energy Generation and Consumption in Dangote Cement Plant, Ibese, Nigeria. Global Journal of Advanced Engineering Technologies and Sciences. Vol.5 No 11. [8] KPMG (2019), Nigeria’s Electricity Supply Industry Highlights, Power Sector Watch, Edition Q.3. [9] CSEA (2019), Energy for Growth Hub, Power Nextier, May edition. [10] NSE (2017), The Nigerian Infrastructure Report Card 2017, Nigerian Society of Engineers. [11] ERGP (2017), Economic Recovery Growth Plan 2017-2020, Ministry of Budget and National Planning, Federal Republic of Nigeria. [12] Fashola, B.R. (2017), Power Sector Reforms: Challenges and the Way Forward, paper presented at the 2017 Public lecture series, Department of Economics, University of Lagos, Nigeria. [13] Sambo, A.S.; Garba, B.; Zarma, I.H. & Gaji, M.M. (2010) Electricity generation and the present challenges in the Nigerian power sector, Energy company of Nigera, Nigeria. [14] Gasau, A.M.& Orah, A.M (2018), Independent Power Plants: A panacea to the Growth and Sustainability of Manufacturing Industries in Nigeria, International Conference on Mechanical, Material and Renewable Energy. [15] Okedu, K.E., Kenu S., Idowu K., Uhunmuwangbo R. (2018), Impact of the Independent Power Producers and National Integrated Power Projects on the Deregulation of the Nigerian Electricity Sector, Journal of Sustainable Development in Africa, Vol.20, No 1. [16] Opara, S. (2014), 90% Power licenses Idle due to Gas Shortage, The Punch, June 13, p.29. [17] Uwandu, E. (2019), How we Generate 24-hour Power Supply, Vanguard, Thursday 12, p.38. [18] Amoda, O. (2016), Power Distribution Demand Side Management in Developing Economies, 13th DEEEAL Distinguished Lecture, The Nigerian Institution of Electrical and Electronic Engineers. [19] FRN (2012), Investment Opportunities in the Nigeria Power Sector, Federal Republic of Nigeria.