IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________________
Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 279
PERFORMANCE INVESTIGATION OF ELECTRICIAL POWER
SUPPLY TO OWERRI FOR HIGHER PRODUCTIVITY
Osueke G. O1
, Emeka-Opara F. O2
1
Dept. of Mechanical Eng, Federal University of Tech, Owerri, Nigeria
2
National Productivity Centre, Abuja. Nigeria
Abstract
This research was carried out to investigate the performance of electrical power supply to Owerri, Imo State Capital. The Enugu
Electrical Distribution Company (EEDC), Owerri was the case study and sample of 10 respondents representing each unit were
used. Structured questionnaire and observations techniques were administered during this research. The data presentation tools
were tables and charts. It was found out that the major hindrances to Customer satisfaction in Power supply were: inadequate
megawatts of power availability, obsolete network and equipment that require upgrade, overload networks, poor funding, lack of
routine maintenance culture, inadequately trained manpower, logistics (vehicle, personal and material problems), psychological
and physiological problems. Although the privatization policy is believed to be a progressive step to these challenges. based on
the aforementioned, it was therefore recommended that management’s proactiveness to manage faults and equipment upgrade,
government and private sectors should actively involve positive and effective management, as well as smart metering to ensure
consumers meet up with charges, Standard Organization of Nigeria (SON) play major to ensure substandard materials and
products are not delivered, form rural cooperative society to create awareness on how to use light and serve as interface between
the company and community.
Keywords: Performance, Electric Power, Investigation, Supply, Productivity.
--------------------------------------------------------------------***------------------------------------------------------------------
1. INTRODUCTION
There has been a general and widespread agitation by the
Owerri populace and the country at large for efficient
performance by public corporations most especially those of
them that have direct and equally noticeable impact on their
lives like the National Electric Power Authority , (NEPA),
Chen (2007). It is unfortunate to note that NEPA has ended
up accumulating a huge amount of debt apparently so huge
that it could not manage effectively.
It is obviously a prevailing social and economic problem
when considering the incessant power outages in relation to
the nation’s endowment with natural resources like crude
oil, natural gas , large amount of other hydrocarbon
resources. The under-utilization of these resources,
complaints and poor management polices has affected the
performance, reliability, and even economic productivity of
this sub-sector. The public (electric consumers) allegedly
has claim of extortion and exploitation by providers of
electricity in owerri, Echeta (2012). This has adversely
posed many losses and retarded the economic growth and
development.
Against the above background, there came the need to
investigate the incidences of power outage, load shading and
epileptic power supply as well the performance of the
electricity supply within Owerri after post privatization
policy by the Federal Government in 2013, aimed at (i)
increased access to electricity services; (ii) improved
efficiency, affordability, reliability and quality of services;
and (iii) greater investment into the sector, to stimulate
Productivity growth.
1.1 Statement of Problem
Following the incidences of low performance, poor quality
service delivery, power outage, load shading and epileptic
power supply that bedevil the power sector with the
increasing consumption and population rate, Echeta (2012)
maintained that Power supply has fallen below the demand
in Owerri.
1.2 Electricity Generation Company till the
Privatisation (Birth of EEDC).
According to national-electricpowerauthority.blogspot.com,
Nigeria's Public Electricity Generating company, National
Electric Power Authority (NEPA) was created by
government Decree No. 24 of 1972. That Decree gave
NEPA the mandate to "maintain, co-ordinate an efficient
and economic system of electricity supply to all parts of the
country".
However, from year 2005, it ceased to exist and has now
been renamed Power Holding Company of Nigeria, PHCN,
with 18 business units. The country of about 160 million
people, has a total installed power generating capacity of
4,000 MW, derived from both hydro and thermal power
plants. But actual power generation is often much less,
typically between 1,500 to 2,500 MW, current actual output
in a mere 1,400 MW, at least, 1,000 MW short of the actual
demand in the country put at 2,400 MW. The Authority
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________________
Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 280
generates electricity through two major sources: Hydro and
Thermal. The Hydro Power stations are Kainji Hydro Power
station with capacity of 760MW, Jebba Hydro Power station
with 578.4MW capacity, Shiroro Hydro Power Station
600MW. The Thermal Power stations are: Afam Thermal
Power station with 696MW, Lagos thermal power station,
Delta IV thermal Power station with 600MW and Sapele
Thermal Power station 1020MW.
However, the need to reform the Electricity industry
necessitated the transformation of NEPA into Power
Holding Company of Nigeria (PHCN) in 2005. The
Electricity Reform Act of 2005, unbundled PHCN into 11
Distribution companies, 1 Transmission Company and 6
Generation companies. This Reform Act gave birth to
Enugu Electricity Distribution Company (EEDC).
According to Osueke (2013), sustainable electric power
supply is the prime mover of technological and social
development
2. METHODOLOGY
The instruments used in this research include i. development
and administration of Questionnaire, 2. Literature reviews,
3. Oral interviews, 4. Data analysis and report writing. Data
were collected through the administration and retrieval of
the questionnaire, as summarized in the analysis.
2.1 Results, Analysis and Discussions
Table 1 EEDC Power supply /day.
Hours Supplied. No.
Respondents.
Percentage
0 – 2 3 17
3 – 8 10 55
9 – 14 5 27
15 – above Nil Nil
Total 18 100
In terms of power supply , average services rendered range
from 29% to 46%. The remaining hours of the day is being
covered by use of private generators.
For the Owerri Capital Territory; Average Min Supplies =
= 29% Across
The Max hrs of supply for Owerri, = = 46% of
needed power supply.
Productivity, P = F/C; =
Where i= input hours; and x= waste or unsupplied power.
This is supported by productivity and waste equation as
shown below:
Productivity,
P =
The challenges encountered during transmission are due to
technical hitches such as flux leakage, eddy current loses.
Heat losses are also common threat encountered during
transmission. The Owerri transmission unit is on regular
transmission line inspection by its technical crew. The
installation of more transformers will create better chances
of effective power transmission Obiajulu (2012). The
private establishment plays good role in stabilization of
power in Owerri. The consumers attitude in meeting up with
service charge on power is fair. The people’s reaction to
privatization of electricity transmission is at 40% - 60% rate.
About 85 megawatts of power is transmitted daily to Owerri
and is much below the quantity demanded.
The power consumers are billed even when there is no
supply because of no meter and fixed charge placed. From
above finding and results, the research team were able to
create a statistical analysis and results represented on a bar
chart below in figure 1:
Fig. 1 Bar chart showing performance rate in Owerri
From the bar chart in figure 1, it can been seen that
performance of electric power supply has increased in the
year 2014, Enugu Electricity Distribution Company has
indeed boosted power supply in Owerri. Ever since it was
privatized, there has been technical hitches over the last 3
years which are yet to be addressed because of lack of funds
and man-power development . Recently, 330KVA line
transmission high tension yard was installed in locations like
Egbu transmission unit which has boasted power
transmission in that part of owerri. Also in the Federal
University Of Technology Owerri, two 350kva transformers
with armored cable and transmission lines were mounted in
the university and ever since then electric power supply has
improved .
Presently, in Nigeria electrical power system is facing a lot
of challenges as a whole. From generation to distribution,
the reliability of the system is far below expectation
0
2
4
6
8
10
12
14
2010 2012 2013 2014
Series 3
Series 2
Series 1
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________________
Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 281
(Popoola, 2011). Recently, the Nigeria government
announced the decision to embark on measures to promote
the use of energy saving bulbs and meters, as part of
solution to the energy crisis. Providing sustainable, adequate
, reliable and efficient electricity supply to residential,
commercial and industrial consumers is germane to national
development .
Results shows that ever since the privatization of PHCN, it
has attracted foreign investors to Nigeria and to the case
study ,Owerri, network has been upgraded in some sub
stations. This policy has affected the society because some
workers were laid off and this has posed a security risk to
the government, adding to the unemployment level. From
findings also, the Distribution manager EDDC carefully
stated that more workers in the region were also laid-off.
The research apparently concluded that it is a major
disadvantage of the privatization in the country.
Notwithstanding, Technology has also been upgraded,
computers with internet facilities provided and staff ready
and dedicated to work.
This has increased the distribution of power supply in
Owerri, management dedication has also seen a change in
EDDC which is the bedrock of effective power
performance. This is because without good management
there cannot be improved productivity.
Results gathered have also shown that the suppliers of
materials to EDDC supplied inferior and substandard
materials that prompted the low level of performance but
management is on high gear to cub further occurrence.
Many transmission line fail not because of technical hitches
but of failure of material in transmission line and stations
However, the company has taken extra measures in
increasing supply and material inspection taken a full step.
If this is done continuously, result will show that
performance of electric power supply will improve
effectively.
3. CONCLUSION
The results obtained show that the earlier disappointing
trend in Electric power supply to Owerri has taken an
improvement turnaround, by virtue of services rendered by
the EEDC. It is hoped that there will be improved
performance in transmission and distribution of power
supply in Owerri, if the above mentioned challenges,
hindrances and recommendation are efficiently followed up
with the privatization policy objectives.
REFERENCES
[1] Ayodele, A. Sesan (2011). Improving And
Sustaining Power (Electricity) Supply
[2] Chen, Kuo (2007) in Echeta, D. O., Okpara, G.I., &
Emerenini, F.M. (2012). Household Demand For
Electricity In Owerri Metropolis ;Estimating The
Alternative Supply
[3] Comparing and cost of PHCN billing
www.naijatechguide.com
[4] Echeta, D. O., Okpara, G.I., & Emerenini, F.M.
(2012). Household Demand For Electricity In
Owerri Metropolis ;Estimating The Alternative
Supply.
[5] Electricity Regulatory Authority (ERA) (2006),
Annual Journal. History of NEPA
http://nationalelectricpowerauthority.blogspot.com/2
006/10/history.html
[6] Nweke N.U (2011). Research Methodology: survey
method. pp169.
[7] Nigeria Electricity Privatisation Project
http://www.nigeriaelectricityprivatisation.com/?page
_id=2 Nigeria Electricity Privatisation (PHCN).
Retrieved 20/5/14
[8] Nweke, Njideka Uchechukwu (2011). A study of the
use of public relations in power Holding company of
nigeria (PHCN),Awka. Nnamdi Azikiwe University
Awka,
[9] Obiajulul Emejuju, Dan Chima A., Queen Njemanze
& Ijeoma Odoh et al (2012). The dynamics of
technical writing and communication .Ibadan.
Owerri. Abuja Afrika-link Books
[10] Osueke, G. O. Nwosuh, E. N. and Adenugba, A.
(2013). Performance evaluation of quality of
service offered by Power Holding Company of
Nigeria(PHCN) to coldrooms in Anambra state for
higher productivity.

More Related Content

What's hot

Power Sector - India - Sample
Power Sector - India - SamplePower Sector - India - Sample
Power Sector - India - SampleNetscribes, Inc.
 
Power Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in IndiaPower Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in IndiaAditya Goyal
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...IRJET Journal
 
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...IRJET Journal
 
J0364057060
J0364057060J0364057060
J0364057060theijes
 
Electrical power outage in nigeria history, causes and possible solutions
Electrical power outage in nigeria  history, causes and possible solutionsElectrical power outage in nigeria  history, causes and possible solutions
Electrical power outage in nigeria history, causes and possible solutionsAlexander Decker
 
Indian power sector an overview
Indian power sector an overviewIndian power sector an overview
Indian power sector an overviewJasbir Arora
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisArjun Yadav
 
Power Sector Developments in India
Power Sector Developments in IndiaPower Sector Developments in India
Power Sector Developments in IndiaIndian Energy Sector
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in Indiamohkab1
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Anshuman Batra
 
power sector issues in Haryana and in India
power sector issues in Haryana and in Indiapower sector issues in Haryana and in India
power sector issues in Haryana and in IndiaKamaljit Singh
 
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...Louie Mark Quizon
 
Power failure presentation
Power failure presentationPower failure presentation
Power failure presentationSatyendra Arora
 
Industrial Analysis on power Industry
Industrial Analysis on power IndustryIndustrial Analysis on power Industry
Industrial Analysis on power IndustrySiva Konduri
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sectorRahul Gupta
 
CO2 Reduction Measures in the Electricity Supply Chain in Libya
CO2 Reduction Measures in the Electricity Supply Chain in LibyaCO2 Reduction Measures in the Electricity Supply Chain in Libya
CO2 Reduction Measures in the Electricity Supply Chain in LibyaHusen E . Bader
 

What's hot (20)

Power Sector - India - Sample
Power Sector - India - SamplePower Sector - India - Sample
Power Sector - India - Sample
 
Power Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in IndiaPower Transmission and Distribution Sector in India
Power Transmission and Distribution Sector in India
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...
Optimal Hybrid Energy System for Rural Electrification in India using HOMER S...
 
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...
Renewable Energy Integration into Smart Grid-Energy Storage Technologies and ...
 
J0364057060
J0364057060J0364057060
J0364057060
 
Electrical power outage in nigeria history, causes and possible solutions
Electrical power outage in nigeria  history, causes and possible solutionsElectrical power outage in nigeria  history, causes and possible solutions
Electrical power outage in nigeria history, causes and possible solutions
 
F0513644
F0513644F0513644
F0513644
 
Indian power sector an overview
Indian power sector an overviewIndian power sector an overview
Indian power sector an overview
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry Analysis
 
Power Sector Developments in India
Power Sector Developments in IndiaPower Sector Developments in India
Power Sector Developments in India
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in India
 
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
Indian Power Sector- A Study of Effectiveness of Past Power Sector Reforms an...
 
power sector issues in Haryana and in India
power sector issues in Haryana and in Indiapower sector issues in Haryana and in India
power sector issues in Haryana and in India
 
India : Power Sector Report_August 2013
India : Power Sector Report_August 2013India : Power Sector Report_August 2013
India : Power Sector Report_August 2013
 
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...
The Economics of Electric Energy: IPPs, the PPA, and the Electric Power Indus...
 
Power failure presentation
Power failure presentationPower failure presentation
Power failure presentation
 
Industrial Analysis on power Industry
Industrial Analysis on power IndustryIndustrial Analysis on power Industry
Industrial Analysis on power Industry
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
CO2 Reduction Measures in the Electricity Supply Chain in Libya
CO2 Reduction Measures in the Electricity Supply Chain in LibyaCO2 Reduction Measures in the Electricity Supply Chain in Libya
CO2 Reduction Measures in the Electricity Supply Chain in Libya
 

Viewers also liked

Effect of cold swaging on the mechanical and microstructure characteristics o...
Effect of cold swaging on the mechanical and microstructure characteristics o...Effect of cold swaging on the mechanical and microstructure characteristics o...
Effect of cold swaging on the mechanical and microstructure characteristics o...eSAT Journals
 
Design and development of a novel fractal antenna for wireless applications
Design and development of a novel fractal antenna for wireless applicationsDesign and development of a novel fractal antenna for wireless applications
Design and development of a novel fractal antenna for wireless applicationseSAT Journals
 
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...A review on key aggregate cryptosystem for scalable data sharing in cloud sto...
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...eSAT Journals
 
An efficient monitoring system for sports person using wi fi communication
An efficient monitoring system for sports person using wi fi communicationAn efficient monitoring system for sports person using wi fi communication
An efficient monitoring system for sports person using wi fi communicationeSAT Journals
 
Design, development and implementation of novel idea
Design, development and implementation of novel ideaDesign, development and implementation of novel idea
Design, development and implementation of novel ideaeSAT Journals
 
Quality analysis of drinking water in bhopal city
Quality analysis of drinking water in bhopal cityQuality analysis of drinking water in bhopal city
Quality analysis of drinking water in bhopal cityeSAT Journals
 
Effect of chemical treatments on the characteristics of regular and compact c...
Effect of chemical treatments on the characteristics of regular and compact c...Effect of chemical treatments on the characteristics of regular and compact c...
Effect of chemical treatments on the characteristics of regular and compact c...eSAT Journals
 
Performance of blended corrosion inhibitors for reinforced concrete
Performance of blended corrosion inhibitors for reinforced concretePerformance of blended corrosion inhibitors for reinforced concrete
Performance of blended corrosion inhibitors for reinforced concreteeSAT Journals
 
Design and testing of automobile exhaust system
Design and testing of automobile exhaust systemDesign and testing of automobile exhaust system
Design and testing of automobile exhaust systemeSAT Journals
 
A survey of low power wallace and dadda multipliers using different logic ful...
A survey of low power wallace and dadda multipliers using different logic ful...A survey of low power wallace and dadda multipliers using different logic ful...
A survey of low power wallace and dadda multipliers using different logic ful...eSAT Journals
 
Kinematic performance analysis of 4 link planar serial manipulator
Kinematic performance analysis of 4 link planar serial manipulatorKinematic performance analysis of 4 link planar serial manipulator
Kinematic performance analysis of 4 link planar serial manipulatoreSAT Journals
 
Automated water head controller for domestic application
Automated water head controller for domestic applicationAutomated water head controller for domestic application
Automated water head controller for domestic applicationeSAT Journals
 
A new design method for low speed torus type afpm machine for hev applications
A new design method for low speed torus type afpm machine for hev applicationsA new design method for low speed torus type afpm machine for hev applications
A new design method for low speed torus type afpm machine for hev applicationseSAT Journals
 
Challenges in indian currency denomination recognition & authentication
Challenges in indian currency denomination recognition & authenticationChallenges in indian currency denomination recognition & authentication
Challenges in indian currency denomination recognition & authenticationeSAT Journals
 
Effect of pitch and nominal diameter on load distribution and efficiency in m...
Effect of pitch and nominal diameter on load distribution and efficiency in m...Effect of pitch and nominal diameter on load distribution and efficiency in m...
Effect of pitch and nominal diameter on load distribution and efficiency in m...eSAT Journals
 
Implementation of latch type sense amplifier
Implementation of latch type sense amplifierImplementation of latch type sense amplifier
Implementation of latch type sense amplifiereSAT Journals
 

Viewers also liked (16)

Effect of cold swaging on the mechanical and microstructure characteristics o...
Effect of cold swaging on the mechanical and microstructure characteristics o...Effect of cold swaging on the mechanical and microstructure characteristics o...
Effect of cold swaging on the mechanical and microstructure characteristics o...
 
Design and development of a novel fractal antenna for wireless applications
Design and development of a novel fractal antenna for wireless applicationsDesign and development of a novel fractal antenna for wireless applications
Design and development of a novel fractal antenna for wireless applications
 
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...A review on key aggregate cryptosystem for scalable data sharing in cloud sto...
A review on key aggregate cryptosystem for scalable data sharing in cloud sto...
 
An efficient monitoring system for sports person using wi fi communication
An efficient monitoring system for sports person using wi fi communicationAn efficient monitoring system for sports person using wi fi communication
An efficient monitoring system for sports person using wi fi communication
 
Design, development and implementation of novel idea
Design, development and implementation of novel ideaDesign, development and implementation of novel idea
Design, development and implementation of novel idea
 
Quality analysis of drinking water in bhopal city
Quality analysis of drinking water in bhopal cityQuality analysis of drinking water in bhopal city
Quality analysis of drinking water in bhopal city
 
Effect of chemical treatments on the characteristics of regular and compact c...
Effect of chemical treatments on the characteristics of regular and compact c...Effect of chemical treatments on the characteristics of regular and compact c...
Effect of chemical treatments on the characteristics of regular and compact c...
 
Performance of blended corrosion inhibitors for reinforced concrete
Performance of blended corrosion inhibitors for reinforced concretePerformance of blended corrosion inhibitors for reinforced concrete
Performance of blended corrosion inhibitors for reinforced concrete
 
Design and testing of automobile exhaust system
Design and testing of automobile exhaust systemDesign and testing of automobile exhaust system
Design and testing of automobile exhaust system
 
A survey of low power wallace and dadda multipliers using different logic ful...
A survey of low power wallace and dadda multipliers using different logic ful...A survey of low power wallace and dadda multipliers using different logic ful...
A survey of low power wallace and dadda multipliers using different logic ful...
 
Kinematic performance analysis of 4 link planar serial manipulator
Kinematic performance analysis of 4 link planar serial manipulatorKinematic performance analysis of 4 link planar serial manipulator
Kinematic performance analysis of 4 link planar serial manipulator
 
Automated water head controller for domestic application
Automated water head controller for domestic applicationAutomated water head controller for domestic application
Automated water head controller for domestic application
 
A new design method for low speed torus type afpm machine for hev applications
A new design method for low speed torus type afpm machine for hev applicationsA new design method for low speed torus type afpm machine for hev applications
A new design method for low speed torus type afpm machine for hev applications
 
Challenges in indian currency denomination recognition & authentication
Challenges in indian currency denomination recognition & authenticationChallenges in indian currency denomination recognition & authentication
Challenges in indian currency denomination recognition & authentication
 
Effect of pitch and nominal diameter on load distribution and efficiency in m...
Effect of pitch and nominal diameter on load distribution and efficiency in m...Effect of pitch and nominal diameter on load distribution and efficiency in m...
Effect of pitch and nominal diameter on load distribution and efficiency in m...
 
Implementation of latch type sense amplifier
Implementation of latch type sense amplifierImplementation of latch type sense amplifier
Implementation of latch type sense amplifier
 

Similar to Performance investigation of electricial power supply to owerri for higher productivity

A Markov model of generator performance at the Kainji hydro-power station in...
A Markov model of generator performance at the Kainji  hydro-power station in...A Markov model of generator performance at the Kainji  hydro-power station in...
A Markov model of generator performance at the Kainji hydro-power station in...IJECEIAES
 
B0314011017
B0314011017B0314011017
B0314011017theijes
 
Evaluation of losses in distribution networks of selected industrial cities i...
Evaluation of losses in distribution networks of selected industrial cities i...Evaluation of losses in distribution networks of selected industrial cities i...
Evaluation of losses in distribution networks of selected industrial cities i...Dr. Hachimenum Amadi
 
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...Austin Ola Oshin Zechariah
 
Power distribution system fault monitoring device for supply networks in Nigeria
Power distribution system fault monitoring device for supply networks in NigeriaPower distribution system fault monitoring device for supply networks in Nigeria
Power distribution system fault monitoring device for supply networks in NigeriaIJECEIAES
 
Evaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadEvaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadNajeem Olawale Adelakun
 
Feasibility analysis of an off-grid photovoltaic-battery energy system for a...
Feasibility analysis of an off-grid photovoltaic-battery  energy system for a...Feasibility analysis of an off-grid photovoltaic-battery  energy system for a...
Feasibility analysis of an off-grid photovoltaic-battery energy system for a...IJECEIAES
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libreAbanihi
 
D0362023027
D0362023027D0362023027
D0362023027theijes
 
A Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission NetworkA Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission Networktheijes
 
A Model for Assessment of Power System Outages on Nigerian Transmission Network
	A Model for Assessment of Power System Outages on Nigerian Transmission Network	A Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission Networktheijes
 
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaA Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaIRJET Journal
 
Development and Performance Evaluation of an Intelligent Electric Power Switc...
Development and Performance Evaluation of an Intelligent Electric Power Switc...Development and Performance Evaluation of an Intelligent Electric Power Switc...
Development and Performance Evaluation of an Intelligent Electric Power Switc...YogeshIJTSRD
 
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...IAEME Publication
 
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...Isam Shahrour
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...irjes
 
10utilizationofelectricity63 73-111118183625-phpapp01 (1)
10utilizationofelectricity63 73-111118183625-phpapp01 (1)10utilizationofelectricity63 73-111118183625-phpapp01 (1)
10utilizationofelectricity63 73-111118183625-phpapp01 (1)svsikhwal
 
10 utilization of electricity 63-73
10 utilization of electricity 63-7310 utilization of electricity 63-73
10 utilization of electricity 63-73Alexander Decker
 

Similar to Performance investigation of electricial power supply to owerri for higher productivity (20)

A Markov model of generator performance at the Kainji hydro-power station in...
A Markov model of generator performance at the Kainji  hydro-power station in...A Markov model of generator performance at the Kainji  hydro-power station in...
A Markov model of generator performance at the Kainji hydro-power station in...
 
B0314011017
B0314011017B0314011017
B0314011017
 
Evaluation of losses in distribution networks of selected industrial cities i...
Evaluation of losses in distribution networks of selected industrial cities i...Evaluation of losses in distribution networks of selected industrial cities i...
Evaluation of losses in distribution networks of selected industrial cities i...
 
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...
RELIABILITY AND IMPROVEMENT OF ELECTRIC POWER GENERATION AND DISTRIBUTION ( I...
 
Power distribution system fault monitoring device for supply networks in Nigeria
Power distribution system fault monitoring device for supply networks in NigeriaPower distribution system fault monitoring device for supply networks in Nigeria
Power distribution system fault monitoring device for supply networks in Nigeria
 
Evaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadEvaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient Load
 
Feasibility analysis of an off-grid photovoltaic-battery energy system for a...
Feasibility analysis of an off-grid photovoltaic-battery  energy system for a...Feasibility analysis of an off-grid photovoltaic-battery  energy system for a...
Feasibility analysis of an off-grid photovoltaic-battery energy system for a...
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre
 
D0362023027
D0362023027D0362023027
D0362023027
 
A Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission NetworkA Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission Network
 
A Model for Assessment of Power System Outages on Nigerian Transmission Network
	A Model for Assessment of Power System Outages on Nigerian Transmission Network	A Model for Assessment of Power System Outages on Nigerian Transmission Network
A Model for Assessment of Power System Outages on Nigerian Transmission Network
 
G0371051055
G0371051055G0371051055
G0371051055
 
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in NigeriaA Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
A Low-cost Renewable Energy Solution for Improved Energy Access in Nigeria
 
Development and Performance Evaluation of an Intelligent Electric Power Switc...
Development and Performance Evaluation of an Intelligent Electric Power Switc...Development and Performance Evaluation of an Intelligent Electric Power Switc...
Development and Performance Evaluation of an Intelligent Electric Power Switc...
 
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
 
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
 
EirGrid NATIONAL CONTROL CENTRE
EirGrid NATIONAL CONTROL CENTREEirGrid NATIONAL CONTROL CENTRE
EirGrid NATIONAL CONTROL CENTRE
 
10utilizationofelectricity63 73-111118183625-phpapp01 (1)
10utilizationofelectricity63 73-111118183625-phpapp01 (1)10utilizationofelectricity63 73-111118183625-phpapp01 (1)
10utilizationofelectricity63 73-111118183625-phpapp01 (1)
 
10 utilization of electricity 63-73
10 utilization of electricity 63-7310 utilization of electricity 63-73
10 utilization of electricity 63-73
 

More from eSAT Journals

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementseSAT Journals
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case studyeSAT Journals
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case studyeSAT Journals
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreeSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialseSAT Journals
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...eSAT Journals
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...eSAT Journals
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizereSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...eSAT Journals
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteeSAT Journals
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...eSAT Journals
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...eSAT Journals
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabseSAT Journals
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaeSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodeSAT Journals
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniqueseSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...eSAT Journals
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...eSAT Journals
 

More from eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 

Performance investigation of electricial power supply to owerri for higher productivity

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________________ Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 279 PERFORMANCE INVESTIGATION OF ELECTRICIAL POWER SUPPLY TO OWERRI FOR HIGHER PRODUCTIVITY Osueke G. O1 , Emeka-Opara F. O2 1 Dept. of Mechanical Eng, Federal University of Tech, Owerri, Nigeria 2 National Productivity Centre, Abuja. Nigeria Abstract This research was carried out to investigate the performance of electrical power supply to Owerri, Imo State Capital. The Enugu Electrical Distribution Company (EEDC), Owerri was the case study and sample of 10 respondents representing each unit were used. Structured questionnaire and observations techniques were administered during this research. The data presentation tools were tables and charts. It was found out that the major hindrances to Customer satisfaction in Power supply were: inadequate megawatts of power availability, obsolete network and equipment that require upgrade, overload networks, poor funding, lack of routine maintenance culture, inadequately trained manpower, logistics (vehicle, personal and material problems), psychological and physiological problems. Although the privatization policy is believed to be a progressive step to these challenges. based on the aforementioned, it was therefore recommended that management’s proactiveness to manage faults and equipment upgrade, government and private sectors should actively involve positive and effective management, as well as smart metering to ensure consumers meet up with charges, Standard Organization of Nigeria (SON) play major to ensure substandard materials and products are not delivered, form rural cooperative society to create awareness on how to use light and serve as interface between the company and community. Keywords: Performance, Electric Power, Investigation, Supply, Productivity. --------------------------------------------------------------------***------------------------------------------------------------------ 1. INTRODUCTION There has been a general and widespread agitation by the Owerri populace and the country at large for efficient performance by public corporations most especially those of them that have direct and equally noticeable impact on their lives like the National Electric Power Authority , (NEPA), Chen (2007). It is unfortunate to note that NEPA has ended up accumulating a huge amount of debt apparently so huge that it could not manage effectively. It is obviously a prevailing social and economic problem when considering the incessant power outages in relation to the nation’s endowment with natural resources like crude oil, natural gas , large amount of other hydrocarbon resources. The under-utilization of these resources, complaints and poor management polices has affected the performance, reliability, and even economic productivity of this sub-sector. The public (electric consumers) allegedly has claim of extortion and exploitation by providers of electricity in owerri, Echeta (2012). This has adversely posed many losses and retarded the economic growth and development. Against the above background, there came the need to investigate the incidences of power outage, load shading and epileptic power supply as well the performance of the electricity supply within Owerri after post privatization policy by the Federal Government in 2013, aimed at (i) increased access to electricity services; (ii) improved efficiency, affordability, reliability and quality of services; and (iii) greater investment into the sector, to stimulate Productivity growth. 1.1 Statement of Problem Following the incidences of low performance, poor quality service delivery, power outage, load shading and epileptic power supply that bedevil the power sector with the increasing consumption and population rate, Echeta (2012) maintained that Power supply has fallen below the demand in Owerri. 1.2 Electricity Generation Company till the Privatisation (Birth of EEDC). According to national-electricpowerauthority.blogspot.com, Nigeria's Public Electricity Generating company, National Electric Power Authority (NEPA) was created by government Decree No. 24 of 1972. That Decree gave NEPA the mandate to "maintain, co-ordinate an efficient and economic system of electricity supply to all parts of the country". However, from year 2005, it ceased to exist and has now been renamed Power Holding Company of Nigeria, PHCN, with 18 business units. The country of about 160 million people, has a total installed power generating capacity of 4,000 MW, derived from both hydro and thermal power plants. But actual power generation is often much less, typically between 1,500 to 2,500 MW, current actual output in a mere 1,400 MW, at least, 1,000 MW short of the actual demand in the country put at 2,400 MW. The Authority
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________________ Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 280 generates electricity through two major sources: Hydro and Thermal. The Hydro Power stations are Kainji Hydro Power station with capacity of 760MW, Jebba Hydro Power station with 578.4MW capacity, Shiroro Hydro Power Station 600MW. The Thermal Power stations are: Afam Thermal Power station with 696MW, Lagos thermal power station, Delta IV thermal Power station with 600MW and Sapele Thermal Power station 1020MW. However, the need to reform the Electricity industry necessitated the transformation of NEPA into Power Holding Company of Nigeria (PHCN) in 2005. The Electricity Reform Act of 2005, unbundled PHCN into 11 Distribution companies, 1 Transmission Company and 6 Generation companies. This Reform Act gave birth to Enugu Electricity Distribution Company (EEDC). According to Osueke (2013), sustainable electric power supply is the prime mover of technological and social development 2. METHODOLOGY The instruments used in this research include i. development and administration of Questionnaire, 2. Literature reviews, 3. Oral interviews, 4. Data analysis and report writing. Data were collected through the administration and retrieval of the questionnaire, as summarized in the analysis. 2.1 Results, Analysis and Discussions Table 1 EEDC Power supply /day. Hours Supplied. No. Respondents. Percentage 0 – 2 3 17 3 – 8 10 55 9 – 14 5 27 15 – above Nil Nil Total 18 100 In terms of power supply , average services rendered range from 29% to 46%. The remaining hours of the day is being covered by use of private generators. For the Owerri Capital Territory; Average Min Supplies = = 29% Across The Max hrs of supply for Owerri, = = 46% of needed power supply. Productivity, P = F/C; = Where i= input hours; and x= waste or unsupplied power. This is supported by productivity and waste equation as shown below: Productivity, P = The challenges encountered during transmission are due to technical hitches such as flux leakage, eddy current loses. Heat losses are also common threat encountered during transmission. The Owerri transmission unit is on regular transmission line inspection by its technical crew. The installation of more transformers will create better chances of effective power transmission Obiajulu (2012). The private establishment plays good role in stabilization of power in Owerri. The consumers attitude in meeting up with service charge on power is fair. The people’s reaction to privatization of electricity transmission is at 40% - 60% rate. About 85 megawatts of power is transmitted daily to Owerri and is much below the quantity demanded. The power consumers are billed even when there is no supply because of no meter and fixed charge placed. From above finding and results, the research team were able to create a statistical analysis and results represented on a bar chart below in figure 1: Fig. 1 Bar chart showing performance rate in Owerri From the bar chart in figure 1, it can been seen that performance of electric power supply has increased in the year 2014, Enugu Electricity Distribution Company has indeed boosted power supply in Owerri. Ever since it was privatized, there has been technical hitches over the last 3 years which are yet to be addressed because of lack of funds and man-power development . Recently, 330KVA line transmission high tension yard was installed in locations like Egbu transmission unit which has boasted power transmission in that part of owerri. Also in the Federal University Of Technology Owerri, two 350kva transformers with armored cable and transmission lines were mounted in the university and ever since then electric power supply has improved . Presently, in Nigeria electrical power system is facing a lot of challenges as a whole. From generation to distribution, the reliability of the system is far below expectation 0 2 4 6 8 10 12 14 2010 2012 2013 2014 Series 3 Series 2 Series 1
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________________ Volume: 03 Issue: 10 | Oct-2014, Available @ http://www.ijret.org 281 (Popoola, 2011). Recently, the Nigeria government announced the decision to embark on measures to promote the use of energy saving bulbs and meters, as part of solution to the energy crisis. Providing sustainable, adequate , reliable and efficient electricity supply to residential, commercial and industrial consumers is germane to national development . Results shows that ever since the privatization of PHCN, it has attracted foreign investors to Nigeria and to the case study ,Owerri, network has been upgraded in some sub stations. This policy has affected the society because some workers were laid off and this has posed a security risk to the government, adding to the unemployment level. From findings also, the Distribution manager EDDC carefully stated that more workers in the region were also laid-off. The research apparently concluded that it is a major disadvantage of the privatization in the country. Notwithstanding, Technology has also been upgraded, computers with internet facilities provided and staff ready and dedicated to work. This has increased the distribution of power supply in Owerri, management dedication has also seen a change in EDDC which is the bedrock of effective power performance. This is because without good management there cannot be improved productivity. Results gathered have also shown that the suppliers of materials to EDDC supplied inferior and substandard materials that prompted the low level of performance but management is on high gear to cub further occurrence. Many transmission line fail not because of technical hitches but of failure of material in transmission line and stations However, the company has taken extra measures in increasing supply and material inspection taken a full step. If this is done continuously, result will show that performance of electric power supply will improve effectively. 3. CONCLUSION The results obtained show that the earlier disappointing trend in Electric power supply to Owerri has taken an improvement turnaround, by virtue of services rendered by the EEDC. It is hoped that there will be improved performance in transmission and distribution of power supply in Owerri, if the above mentioned challenges, hindrances and recommendation are efficiently followed up with the privatization policy objectives. REFERENCES [1] Ayodele, A. Sesan (2011). Improving And Sustaining Power (Electricity) Supply [2] Chen, Kuo (2007) in Echeta, D. O., Okpara, G.I., & Emerenini, F.M. (2012). Household Demand For Electricity In Owerri Metropolis ;Estimating The Alternative Supply [3] Comparing and cost of PHCN billing www.naijatechguide.com [4] Echeta, D. O., Okpara, G.I., & Emerenini, F.M. (2012). Household Demand For Electricity In Owerri Metropolis ;Estimating The Alternative Supply. [5] Electricity Regulatory Authority (ERA) (2006), Annual Journal. History of NEPA http://nationalelectricpowerauthority.blogspot.com/2 006/10/history.html [6] Nweke N.U (2011). Research Methodology: survey method. pp169. [7] Nigeria Electricity Privatisation Project http://www.nigeriaelectricityprivatisation.com/?page _id=2 Nigeria Electricity Privatisation (PHCN). Retrieved 20/5/14 [8] Nweke, Njideka Uchechukwu (2011). A study of the use of public relations in power Holding company of nigeria (PHCN),Awka. Nnamdi Azikiwe University Awka, [9] Obiajulul Emejuju, Dan Chima A., Queen Njemanze & Ijeoma Odoh et al (2012). The dynamics of technical writing and communication .Ibadan. Owerri. Abuja Afrika-link Books [10] Osueke, G. O. Nwosuh, E. N. and Adenugba, A. (2013). Performance evaluation of quality of service offered by Power Holding Company of Nigeria(PHCN) to coldrooms in Anambra state for higher productivity.