SlideShare a Scribd company logo
1 of 9
Download to read offline
Order in Case No 129 of 2018 Page 1
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005
Tel. 022 22163964/65/69 Fax 22163976
Email: mercindia@merc.gov.in
Website: www.mercindia.org.in / www. merc.gov.in
Case No. 129 of 2018
In the matter of
Petition for seeking approval on adaption of Tariff for long term procurement of 500
MW Wind Power under Section 63 of the Electricity Act 2003 for meeting the Non-
Solar Renewable Purchase Obligations
Coram
Shri. Anand B. Kulkarni, Chairperson
Shri. Mukesh Khullar, Member
Maharashtra State Electricity Distribution Company Limited (MSEDCL).......... Petitioner
M/s Torrent Power Limited …..… Impleded Party
Appearance
For MSEDCL : Shri. Satish Chavan (Rep.)
For M/s Torrent Power Limited : None
For Consumer Representative : None
ORDER
Date: 14 June, 2018
1. Maharashtra State Electricity Distribution Co. Ltd (MSEDCL) Plot No G-9, 5th
Floor,
Prakashgad, Station Road, Bandra (East), Mumbai - 400 051, has filed a Petition on 4
June,2018 seeking approval on adaption of Tariff for long term procurement of 500
MW Wind Power under Section 63 of the Electricity Act, 2003(EA, 2003) for
meeting the Non- Solar Renewable Purchase Obligations.
2. MSEDCL’s prayers are as follows:
(a) To admit the Petition as per the provisions under Section 63 of the Electricity Act
(EA), 2003.
Order in Case No 129 of 2018 Page 2
(b) To accord approval for adoption of tariff as discovered in the e-reverse auction
conducted on 06.03.2018 and the same to be made eligible for meeting the Non-
solar RPO requirement of MSEDCL.
(c) To accord approval for signing of Power Purchase Agreement with the last
selected bidder (i. e. M/s Torrent Power Limited) for its full offered capacity of
146 MW.
(d) To consider the submission made by the Petitioner and consider the same
positively while deciding the Petition as well as for further actions;
(e) To pass any other order/relief as the Hon’ble Commission may deem fit and
appropriate under the circumstances of the case and in the interest of justice;
(f) To condone any error/omission and to give opportunity to rectify the same;
(g) To permit the Petitioner to make further submissions, addition and alteration to
this Petition as may be necessary from time to time.
3. MSEDCL in its Petition has stated as follows:
Procurement of long term 500 MW Wind power through competitive bidding:-
a) MSEDCL planned to procure 500 MW Wind Power on long term basis from the
existing as well as proposed Wind Power Projects through competitive bidding
process to meet its RPO requirement.
b) The Ministry of Power (MoP), vide its Notification dated 8 December,2017, has
issued Guidelines under Section 63 of the Electricity Act (EA),2003 for long
term procurement of power through Tariff- based Competitive Bidding from
grid-connected Wind Power Projects.
c) The Commission in its order dated 6 December, 2017 in Case No. 157 of 2017;
in the matter of seeking approval of Long/Medium/Short term procurement of
Renewable Energy through Competitive Bidding has ruled that MSEDCL shall
come before the Commission through specific Petition prior to the bidding
process only if MSEDCL requires any deviation with respect to the bidding
documents.
d) Also, as per the provision mentioned in MoP guidelines at clause no. 5.1 (b),
procurer shall inform the initiation of bidding process to the Commission.
MSEDCL has submitted its Petition on 20 December, 2017 in Case No.192 of
Order in Case No 129 of 2018 Page 3
2017 for approval of deviation in standard bidding document for long term
procurement of 500 MW Wind power to meet non-Solar RPO target.
e) MSEDCL initiated the bidding process on 21 December, 2017 by publishing the
RfS and PPA on TCIL portal. The bidding documents i.e. the RfS was prepared
in line with the MoP guidelines dated 8 December,2017 except for minimum
bid capacity of intra-state already commissioned wind generators. The clauses in
line with MoP guidelines were incorporated in the PPA as well.
f) The hearing in Case No. 192 of 2017 was held on 16 January, 2018 before the
Commission. The Commission was apprised with status of the tender process.
g) The Pre-bid meeting was conducted on 8 January, 2018 wherein queries of the
prospective bidders were discussed. Considering the queries raised by the
bidders in pre-bid meeting and possibility of delay in passing order by the
Commission, MSEDCL decided to go with standard MoP guidelines and carry
out tender process without deviating MoP guidelines. Thereafter, the RfS and
PPA were revised and prepared without any deviation from MoP guidelines
dated 8 December,2017
h) The last date of bid submission was 22 February, 2018. Seven (7) bidders had
submitted their bids. The Technical bid opening was conducted on 22 February,
2018 at 15.00 hrs. Thereafter the Technical Bids were evaluated and out of the 7
(seven) bidders, 6 (six) emerged as technically and financially qualified bidders
and 1 (one) bidder was disqualified for not meeting the minimum bid capacity
as specified in the tender document.
i) Subsequently the technically qualified bidders were informed about their
qualification for the next stage. Also, training was organized on 5 March, 2018
for the qualified bidders for using the TCIL portal for participating in the
reverse auction. The Financial Bids of the qualified bidders were opened on 6
March, 2018.
j) The e-reverse auction started from 14.00 Hrs on 6 March ,2018 in which all the
6 qualified bidders had participated and it was successfully completed the same
day.
k) The final tariff discovered from the e-reverse auction conducted on 6 March,
2018 is as presented below:
Order in Case No 129 of 2018 Page 4
S.
No.
Name of the Bidder Capacity
(MW)
IPO
Rate
Rs/kWh
E-RA
result
Rs/kWh
Bucket
Filled
Capacity in
MW
Intra/
Inter
1
Adani Green Energy
(MP) Limited
100 2.88 2.85 75
Inter State
Project
2
KCT Renewable
Energy Private
Limited
100 2.96 2.85 75
Intra State
Project
3 Inox Wind Limited 50 2.99 2.86 50
Inter State
Project
4
Mytrah Energy
(India) Private
Limited
200 2.97 2.86 100
Intra State
Project
5
Hero Wind Energy
Private Limited
100.8 2.96 2.86 75.6
Intra State
Project
6
Torrent Power
Limited
271 2.98 2.87 146*
Intra State
Project
Total 821.8 - - 521.6
* 124.6 MW from the bucket filled and 21.4 MW from the out of bucket.
l) The Commission in its order dated 6 December, 2017 for Case No. 157 of 2017
directed that…
In case the standard bidding document is used by MSEDCL then a specific
petition shall be filed by MSEDCL after bidding process for adoption of tariff as
is mandated under Sec-63 of EA 2003. The said Petition shall cover the
following, for approval of the Commission. (i) quantum of power , (ii) Period of
power flow, Tariff rate of the RE power to be procured, under Tariff Based
Competitive Bidding Process for Short term/ Medium term /Long term basis for
adoption under Section 63 of the Act.
MSEDCL has approached the Commission for adoption of tariff offered under
Section 63 of the EA, 2003 after completion of bidding process.
m) MSEDCL submits to the Commission to approve the tariff as discovered in the
e-reverse auction for procurement of wind power. Also, the last successful
bidder (i.e. M/s Torrent Power Limited) has offered capacity of 146 MW,
whereas the allotted capacity in bucket filling of 500 MW as per the e-reverse
auction is 124.6 MW. It is requested to the Commission to allow the Petitioner
Order in Case No 129 of 2018 Page 5
to execute the Power Purchase Agreement for a capacity of 146 MW with M/s
Torrent Power Limited.
n) MSEDCL requests the Commission to approve the above tariffs discovered in
the e-reverse auction for further signing of PPA with the Successful Bidders.
The agreement will for a period of 25 years from the Commercial Operation
Date in case of proposed/new wind power project or for a period of 25 years
from the date of execution of PPA in case of existing wind power projects.
4. M/s Torrent Power Limited in its written submission received on 9 June, 2018 has
stated that it has no objection in accepting the offered project capacity of 146 MW
pursuant to the E-Reverse Auction held under the Rfs No.MSEDCL/Competitive/500
Wind dated 21 December, 2017 at the tariff of Rs.2.87 per unit.
5. Adani Green Energy (MP) Limited in its written submission received on 9 June,2018
has stated as follows:
a) Adani Green Energy (MP) Limited is selected as successful bidder and allocated
75 MW Wind Power Project.MSEDCL has filed the Petition in Case No 129 of
2018 before the Commission for adoption of tariff. One of the prayer in the said
Petition to accord approval of signing of PPA with last selected bidder (i.e. M/s
Torrent Power Limited who has submitted bid for 271 MW) for additional
capacity of 146 MW at the tariff of Rs 2.87 per unit as against 124.4 MW own
under the bid.
b) Adani Green Energy (MP) Limited who is one of the successful bidder is ready
and willing to execute the Wind Power Project for additional capacity at the bid
out tariff/L1 tariff i.e. at Rs.2.85 per unit, which is lower than the one offered to
M/s Torrent Power Ltd. for additional capacity of 146 MW. Incremental capacity
if any should be offered to lower price bidder who is willing to take additional
capacity at L1 tariff, instead of allocation to last bidder that too at higher rate.
Adani Green Energy (MP) Limited have capacity to execute the additional Wind
power project as may be offered to it in the currently provided in the tender.
6. The proceedings of the hearing held on 9 June, 2018 are summarized as follows:
i. The representative of MSEDCL has stated that, MSEDCL has floated the tenders
as per MoP standard bidding guidelines and carried out tender process without
deviating MoP guidelines. Out of the 7 bidders, 6 were technically and financially
qualified and 1 bidder was disqualified for not meeting the minimum bid capacity
as specified in the tender document. The final tariff discovered from the e-reverse
auction conducted on 6 March, 2018 are between Rs.2.85 to Rs.2.87 per unit. The
last successful bidder M/s Torrent Power Limited has offered capacity of 146
MW, whereas the allotted capacity in bucket filling of 500 MW as per the e-
Order in Case No 129 of 2018 Page 6
reverse auction is 124.6 MW. MSEDCL requests the Commission to approve the
discovered tariff and to allow it to execute the Power Purchase Agreement for a
capacity of 146 MW with M/s Torrent Power Limited. Energy purchased through
the tendering process shall be considered eligible for meeting the Non-solar RPO
requirement of MSEDCL
ii. The representative of Adani Green Energy (MP) Limited has stated that it has
submitted its reply on 9 June, 2018 and reiterated its submission and requested the
Commission to consider its request for willing to execute the Wind Power Project
for additional capacity at the bid out tariff i.e. at Rs.2.85 per unit, which is lower
than Rs.2.87 per unit offered by M/s Torrent Power Ltd.
7. Adani Green Energy (MP) Limited in its subsequent submission dated 13 June,2018
has stated that it is withdrawing its letter dated 9 June,2018.
8. MSEDCL in its subsequent submission dated 13 June,2018, in reply to the issue
raised by Adani Green Energy (MP) Limited vide letter dated 9 June,2018 has stated
as follows:
a) M/s Adani Green Energy (MP) Limited, vide letter dated 9 June, 2018, has
submitted their reply to the Commission and stated that, they are ready to execute
the wind power project for additional capacity at the bid out tariff i.e L1 Tariff i.e
@Rs.2.85 p.u. which is lower than the one offered to M/s. Torrent Power Ltd
additional capacity.
b) On 10 April, 2018, SECI approached MSEDCL for consent for purchase of Wind
power from the projects under 2000 MW Wind ISTS connected scheme (Tranche
IV) at discovered tariff of Rs. 2.52 per kWh plus SECI trading margin of Rs.0.07
per kWh. Accordingly, MSEDCL has given consent on 7 May, 2018 for
procurement of 500 MW and filed petition with the Commission for approval and
adoption of tariff on 5 June, 2018.
c) In view of above developments, MSEDCL has decided to restrict it bucket to 500
MW after completion of reverse auction process in the said tender.
d) Accordingly, MSEDCL requests the Commission to approve adoption of tariff for
long term procurement of 500 MW wind power under Section 63 of the Electricity
Act 2003 for meeting the Non-Solar Renewable Purchase Obligations as under:
S.
No.
Name of the Bidder Capacity
(MW)
IPO
Rate
Rs/kWh
E-RA
result
Rs/kWh
Bucket
Filled
Capacity in
MW
Intra/
Inter
1 Adani Green Energy 100 2.88 2.85 75 Inter State
Order in Case No 129 of 2018 Page 7
(MP) Limited Project
2
KCT Renewable
Energy Private
Limited
100 2.96 2.85 75
Intra State
Project
3 Inox Wind Limited 50 2.99 2.86 50
Inter State
Project
4
Mytrah Energy
(India) Private
Limited
200 2.97 2.86 100
Intra State
Project
5
Hero Wind Energy
Private Limited
100.8 2.96 2.86 75.6
Intra State
Project
6
Torrent Power
Limited
271 2.98 2.87 124.4
Intra State
Project
Total 821.8 - - 500
In view of the above the MSEDCL prays to the Commission:
i) To admit the Petition as per the provisions under Section 63 of the Electricity Act
(EA), 2003.
ii) To accord approval for adoption of tariff as discovered in the e-reverse auction
conducted on 6 March, 2018 and the same to be made eligible for meeting the
Non-solar RPO requirement of MSEDCL.
iii) To accord approval for signing of Power Purchase Agreement with the last
selected bidder (i. e. M/s Torrent Power Limited) for its bucket filling capacity of
124.4 MW only instead of full offered capacity of 146 MW.
Commission’s Analysis and Rulings
9. MSEDCL under the present Petition has sought approval for i) adoption of tariff
as discovered in the e-reverse auction conducted on 6 March, 2018 and the same
to be made eligible for meeting the Non-solar RPO requirement of MSEDCL ii)
signing of Power Purchase Agreement with the last selected bidder M/s Torrent
Power Limited for its full offered capacity of 146 MW. However MSEDCL in its
subsequent submission dated 13 June,2018 has requested the Commission to
accord approval for signing of Power Purchase Agreement with the last selected
bidder M/s Torrent Power Limited for its bucket filling capacity of 124.4 MW
only instead of full offered capacity of 146 MW.
Order in Case No 129 of 2018 Page 8
10. The Commission in its Order dated 6 December, 2017 in Case No. 157 of 2017
had permitted MSEDCL to procure Wind, Solar and Bagasse based cogeneration
RE power on Short Term, Medium term and Long term basis at the rate
discovered through Tariff based Competitive Bidding (e-reverse auction).
Further, the Commission in that Order dated 6 December, 2017 had also ruled
that in case the standard bidding document is used by MSEDCL then a specific
petition shall be filed by MSEDCL after bidding process for adoption of tariff as
is mandated under Sec-63 of EA 2003. The said Petition shall cover the following,
for approval of the Commission. (i) quantum of power , (ii) Period of power flow,
Tariff rate of the RE power to be procured, under Tariff Based Competitive
Bidding Process for Short term/ Medium term /Long term basis for adoption
under Section 63 of the Act.
11. The Commission notes that MSEDCL has prepared Rfs document without any
deviation in line with the MoP Guidelines dated 8 December,2017 for Tariff
Based Competitive Bidding Process for Procurement of Power from grid
connected Wind power Projects and floated the tender. The final tariff
discovered from the e-reverse auction conducted on 6 March, 2018 is between Rs
2.85 to Rs 2.87 per unit. The last successful bidder M/s Torrent Power Limited
has offered capacity of 146 MW, whereas the allotted capacity in bucket filling of
500 MW as per the e-reverse auction is 124.6 MW i.e. 21.40 MW capacity is out
of the bucket. However, the Commission notes that MSEDCL in its submission
dated 13 June, 2018 has stated that it has decided to restrict bucket filling
capacity of M/s Torrent Power Limited for its of 124.4 MW only instead of full
offered capacity of 146 MW.
12. The Commission notes that the M/s Adani Green Energy (MP) Limited has also
withdrawn vide its letter dated 13 June, 2018 about its contention made in its
submission dated 9 June, 2018 and during the proceeding of the hearing held on
9 June, 2018.
13. In view of foregoing, in line with the mandate u/s 63 of the EA, 2003 the
following procurement and rates are approved by the Commission as proposed
by MSEDCL. Also, the Commission accords approval to consider the proposed
Wind Power generation to count towards fulfilment of its non-Solar RPO for the
respective periods.
Order in Case No 129 of 2018 Page 9
Sr.
No.
Name of the
supplier
Quantum of
procurement
approved
(MW)
PPA Period Time
period of
supply
Rate
(Rs./kWh)
1
Adani Green
Energy (MP)
Limited
75
25 Years
from the date
of COD for
new Wind
projects
or
25 years from
date of
signing of
EPA for
existing
Wind
Projects
As per
availability
2.85
2
KCT
Renewable
Energy Private
Limited
75 2.85
3
Inox Wind
Limited
50 2.86
4
Mytrah Energy
(India) Private
Limited
100 2.86
5
Hero Wind
Energy Private
Limited
75.6 2.86
6
Torrent Power
Limited
124.5 2.87
Total 500 -
The Petition of Maharashtra State Electricity Distribution Co. Ltd. in Case No.129 of 2018
stands disposed of accordingly.
Sd/ Sd/
(Mukesh Khullar) (Anand B. Kulkarni)
Member Chairperson

More Related Content

What's hot

Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanHeadway Solar
 
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftHeadway Solar
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015Headway Solar
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftHeadway Solar
 
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...Bhalindra Bath - projects & M&A law
 
Coal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomCoal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomSoumya Ranjan Parida
 
Rational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentRational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentSoumya Ranjan Parida
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?IPPAI
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaBhargav Parmar
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...Harish Sharma
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projectsshivraj negi
 
Issue in Renewable Energy
Issue in Renewable EnergyIssue in Renewable Energy
Issue in Renewable EnergyIPPAI
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Gurparvesh kaur
 
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?madhavanvee
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorIPPAI
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?IPPAI
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
 

What's hot (20)

Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project Rajasthan
 
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
 
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
 
Coal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomCoal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a Boom
 
Rational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentRational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO document
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?Competitive Bidding in the Power Sector : Is It Working?
Competitive Bidding in the Power Sector : Is It Working?
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
 
Issue in Renewable Energy
Issue in Renewable EnergyIssue in Renewable Energy
Issue in Renewable Energy
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )
 
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
Will Renewable Energy Certificates(RECs) drive the growth of Solar in India?
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Tariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power SectorTariff-based Competitive Bidding in the Power Sector
Tariff-based Competitive Bidding in the Power Sector
 
Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?Competitive bidding in the Power Sector: Is it working or not?
Competitive bidding in the Power Sector: Is it working or not?
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
 

Similar to MSEDCL seeks approval of wind power tariff under Section 63

Order 131 of 2018-12062018
Order 131 of 2018-12062018Order 131 of 2018-12062018
Order 131 of 2018-12062018Jay Ranvir
 
Rerc order ppa cancellation petition no 265
Rerc order ppa cancellation petition no 265Rerc order ppa cancellation petition no 265
Rerc order ppa cancellation petition no 265Pinkesh Kumar
 
Order 163 of 2017-12062018
Order 163 of 2017-12062018Order 163 of 2017-12062018
Order 163 of 2017-12062018Jay Ranvir
 
Madhya pradesh solar policy 2012
Madhya pradesh solar policy 2012Madhya pradesh solar policy 2012
Madhya pradesh solar policy 2012Headway Solar
 
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...Dr. Oliver Massmann
 
CESTAT Ruling Power Equipment 2022.pdf
CESTAT Ruling Power Equipment 2022.pdfCESTAT Ruling Power Equipment 2022.pdf
CESTAT Ruling Power Equipment 2022.pdfHindenburg Research
 
Tendernotice_1 (1).pdf
Tendernotice_1 (1).pdfTendernotice_1 (1).pdf
Tendernotice_1 (1).pdfssusera91051
 
Tendernotice_1.pdf
Tendernotice_1.pdfTendernotice_1.pdf
Tendernotice_1.pdfssusera91051
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Amitava Nag
 
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....Das A. K.
 
Day-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASDay-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASIPPAI
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Spark Network
 
Procedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata PowerProcedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata PowerJay Ranvir
 
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdfKrishnaKG4
 
Solar Tenders by Maven PK
Solar Tenders by Maven PK Solar Tenders by Maven PK
Solar Tenders by Maven PK Maven PK
 
Renewables will shape Argentina’s new energy matrix
Renewables will shape Argentina’s new	energy matrixRenewables will shape Argentina’s new	energy matrix
Renewables will shape Argentina’s new energy matrixDoris Capurro
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
 

Similar to MSEDCL seeks approval of wind power tariff under Section 63 (20)

Order 131 of 2018-12062018
Order 131 of 2018-12062018Order 131 of 2018-12062018
Order 131 of 2018-12062018
 
Rerc order ppa cancellation petition no 265
Rerc order ppa cancellation petition no 265Rerc order ppa cancellation petition no 265
Rerc order ppa cancellation petition no 265
 
Order 163 of 2017-12062018
Order 163 of 2017-12062018Order 163 of 2017-12062018
Order 163 of 2017-12062018
 
Madhya pradesh solar policy 2012
Madhya pradesh solar policy 2012Madhya pradesh solar policy 2012
Madhya pradesh solar policy 2012
 
C.09-11 CS: "All generators can participate"
C.09-11 CS: "All generators can participate"C.09-11 CS: "All generators can participate"
C.09-11 CS: "All generators can participate"
 
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
 
CESTAT Ruling Power Equipment 2022.pdf
CESTAT Ruling Power Equipment 2022.pdfCESTAT Ruling Power Equipment 2022.pdf
CESTAT Ruling Power Equipment 2022.pdf
 
Tendernotice_1 (1).pdf
Tendernotice_1 (1).pdfTendernotice_1 (1).pdf
Tendernotice_1 (1).pdf
 
Tendernotice_1.pdf
Tendernotice_1.pdfTendernotice_1.pdf
Tendernotice_1.pdf
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
CW / 18587 / 2018 INDIAN WIND POWER ASSOCIATION (RAJASTHAN STATE COUNCIL) Vs....
 
Day-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASDay-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IAS
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
 
Draft Feed-In Tariffs
Draft Feed-In TariffsDraft Feed-In Tariffs
Draft Feed-In Tariffs
 
Procedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata PowerProcedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata Power
 
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
5. AL QAHTANI PIPE COATING TERMINAL V. MINERAL SALES.pdf
 
Solar Tenders by Maven PK
Solar Tenders by Maven PK Solar Tenders by Maven PK
Solar Tenders by Maven PK
 
Renewables will shape Argentina’s new energy matrix
Renewables will shape Argentina’s new	energy matrixRenewables will shape Argentina’s new	energy matrix
Renewables will shape Argentina’s new energy matrix
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
Nit wardha-river
Nit wardha-riverNit wardha-river
Nit wardha-river
 

More from Jay Ranvir

Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policyJay Ranvir
 
Open access mp
Open access mpOpen access mp
Open access mpJay Ranvir
 
Profile on the production retreaded tyre
Profile on the production retreaded tyreProfile on the production retreaded tyre
Profile on the production retreaded tyreJay Ranvir
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessJay Ranvir
 
Open Access Charges Rajasthan
Open Access Charges RajasthanOpen Access Charges Rajasthan
Open Access Charges RajasthanJay Ranvir
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demandsJay Ranvir
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015Jay Ranvir
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draftJay Ranvir
 
Notified f &s regulations 2018
Notified f &s  regulations 2018Notified f &s  regulations 2018
Notified f &s regulations 2018Jay Ranvir
 
Detailed comparison of capex vs opex
Detailed comparison of capex vs opexDetailed comparison of capex vs opex
Detailed comparison of capex vs opexJay Ranvir
 
Plastics to oil report
Plastics to oil reportPlastics to oil report
Plastics to oil reportJay Ranvir
 
Detail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantDetail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantJay Ranvir
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sourcesJay Ranvir
 
Verification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationVerification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationJay Ranvir
 
Short term open access status for march 17
Short term open access status for march 17Short term open access status for march 17
Short term open access status for march 17Jay Ranvir
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)Jay Ranvir
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)Jay Ranvir
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyJay Ranvir
 
Ppa model presentation
Ppa model presentationPpa model presentation
Ppa model presentationJay Ranvir
 

More from Jay Ranvir (20)

Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policy
 
Open access mp
Open access mpOpen access mp
Open access mp
 
Profile on the production retreaded tyre
Profile on the production retreaded tyreProfile on the production retreaded tyre
Profile on the production retreaded tyre
 
Tyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading ProcessTyre Retreading by Hot Retreading Process
Tyre Retreading by Hot Retreading Process
 
Ch21
Ch21Ch21
Ch21
 
Open Access Charges Rajasthan
Open Access Charges RajasthanOpen Access Charges Rajasthan
Open Access Charges Rajasthan
 
Response to msedcl demands
Response to msedcl demandsResponse to msedcl demands
Response to msedcl demands
 
Practice directions rts net metering regulations 2015
Practice directions  rts  net metering regulations 2015Practice directions  rts  net metering regulations 2015
Practice directions rts net metering regulations 2015
 
Ppa agreement draft
Ppa agreement draftPpa agreement draft
Ppa agreement draft
 
Notified f &s regulations 2018
Notified f &s  regulations 2018Notified f &s  regulations 2018
Notified f &s regulations 2018
 
Detailed comparison of capex vs opex
Detailed comparison of capex vs opexDetailed comparison of capex vs opex
Detailed comparison of capex vs opex
 
Plastics to oil report
Plastics to oil reportPlastics to oil report
Plastics to oil report
 
Detail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plantDetail information of 5 t pyrolysis plant
Detail information of 5 t pyrolysis plant
 
Model ppa for renewable energy sources
Model ppa for renewable energy sourcesModel ppa for renewable energy sources
Model ppa for renewable energy sources
 
Verification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligationVerification of compliance of renewable purchase obligation
Verification of compliance of renewable purchase obligation
 
Short term open access status for march 17
Short term open access status for march 17Short term open access status for march 17
Short term open access status for march 17
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)
 
The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)The indian-sunshine-the-solar-energy-landscape-in-india (1)
The indian-sunshine-the-solar-energy-landscape-in-india (1)
 
Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind Energy
 
Ppa model presentation
Ppa model presentationPpa model presentation
Ppa model presentation
 

Recently uploaded

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Recently uploaded (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

MSEDCL seeks approval of wind power tariff under Section 63

  • 1. Order in Case No 129 of 2018 Page 1 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in / www. merc.gov.in Case No. 129 of 2018 In the matter of Petition for seeking approval on adaption of Tariff for long term procurement of 500 MW Wind Power under Section 63 of the Electricity Act 2003 for meeting the Non- Solar Renewable Purchase Obligations Coram Shri. Anand B. Kulkarni, Chairperson Shri. Mukesh Khullar, Member Maharashtra State Electricity Distribution Company Limited (MSEDCL).......... Petitioner M/s Torrent Power Limited …..… Impleded Party Appearance For MSEDCL : Shri. Satish Chavan (Rep.) For M/s Torrent Power Limited : None For Consumer Representative : None ORDER Date: 14 June, 2018 1. Maharashtra State Electricity Distribution Co. Ltd (MSEDCL) Plot No G-9, 5th Floor, Prakashgad, Station Road, Bandra (East), Mumbai - 400 051, has filed a Petition on 4 June,2018 seeking approval on adaption of Tariff for long term procurement of 500 MW Wind Power under Section 63 of the Electricity Act, 2003(EA, 2003) for meeting the Non- Solar Renewable Purchase Obligations. 2. MSEDCL’s prayers are as follows: (a) To admit the Petition as per the provisions under Section 63 of the Electricity Act (EA), 2003.
  • 2. Order in Case No 129 of 2018 Page 2 (b) To accord approval for adoption of tariff as discovered in the e-reverse auction conducted on 06.03.2018 and the same to be made eligible for meeting the Non- solar RPO requirement of MSEDCL. (c) To accord approval for signing of Power Purchase Agreement with the last selected bidder (i. e. M/s Torrent Power Limited) for its full offered capacity of 146 MW. (d) To consider the submission made by the Petitioner and consider the same positively while deciding the Petition as well as for further actions; (e) To pass any other order/relief as the Hon’ble Commission may deem fit and appropriate under the circumstances of the case and in the interest of justice; (f) To condone any error/omission and to give opportunity to rectify the same; (g) To permit the Petitioner to make further submissions, addition and alteration to this Petition as may be necessary from time to time. 3. MSEDCL in its Petition has stated as follows: Procurement of long term 500 MW Wind power through competitive bidding:- a) MSEDCL planned to procure 500 MW Wind Power on long term basis from the existing as well as proposed Wind Power Projects through competitive bidding process to meet its RPO requirement. b) The Ministry of Power (MoP), vide its Notification dated 8 December,2017, has issued Guidelines under Section 63 of the Electricity Act (EA),2003 for long term procurement of power through Tariff- based Competitive Bidding from grid-connected Wind Power Projects. c) The Commission in its order dated 6 December, 2017 in Case No. 157 of 2017; in the matter of seeking approval of Long/Medium/Short term procurement of Renewable Energy through Competitive Bidding has ruled that MSEDCL shall come before the Commission through specific Petition prior to the bidding process only if MSEDCL requires any deviation with respect to the bidding documents. d) Also, as per the provision mentioned in MoP guidelines at clause no. 5.1 (b), procurer shall inform the initiation of bidding process to the Commission. MSEDCL has submitted its Petition on 20 December, 2017 in Case No.192 of
  • 3. Order in Case No 129 of 2018 Page 3 2017 for approval of deviation in standard bidding document for long term procurement of 500 MW Wind power to meet non-Solar RPO target. e) MSEDCL initiated the bidding process on 21 December, 2017 by publishing the RfS and PPA on TCIL portal. The bidding documents i.e. the RfS was prepared in line with the MoP guidelines dated 8 December,2017 except for minimum bid capacity of intra-state already commissioned wind generators. The clauses in line with MoP guidelines were incorporated in the PPA as well. f) The hearing in Case No. 192 of 2017 was held on 16 January, 2018 before the Commission. The Commission was apprised with status of the tender process. g) The Pre-bid meeting was conducted on 8 January, 2018 wherein queries of the prospective bidders were discussed. Considering the queries raised by the bidders in pre-bid meeting and possibility of delay in passing order by the Commission, MSEDCL decided to go with standard MoP guidelines and carry out tender process without deviating MoP guidelines. Thereafter, the RfS and PPA were revised and prepared without any deviation from MoP guidelines dated 8 December,2017 h) The last date of bid submission was 22 February, 2018. Seven (7) bidders had submitted their bids. The Technical bid opening was conducted on 22 February, 2018 at 15.00 hrs. Thereafter the Technical Bids were evaluated and out of the 7 (seven) bidders, 6 (six) emerged as technically and financially qualified bidders and 1 (one) bidder was disqualified for not meeting the minimum bid capacity as specified in the tender document. i) Subsequently the technically qualified bidders were informed about their qualification for the next stage. Also, training was organized on 5 March, 2018 for the qualified bidders for using the TCIL portal for participating in the reverse auction. The Financial Bids of the qualified bidders were opened on 6 March, 2018. j) The e-reverse auction started from 14.00 Hrs on 6 March ,2018 in which all the 6 qualified bidders had participated and it was successfully completed the same day. k) The final tariff discovered from the e-reverse auction conducted on 6 March, 2018 is as presented below:
  • 4. Order in Case No 129 of 2018 Page 4 S. No. Name of the Bidder Capacity (MW) IPO Rate Rs/kWh E-RA result Rs/kWh Bucket Filled Capacity in MW Intra/ Inter 1 Adani Green Energy (MP) Limited 100 2.88 2.85 75 Inter State Project 2 KCT Renewable Energy Private Limited 100 2.96 2.85 75 Intra State Project 3 Inox Wind Limited 50 2.99 2.86 50 Inter State Project 4 Mytrah Energy (India) Private Limited 200 2.97 2.86 100 Intra State Project 5 Hero Wind Energy Private Limited 100.8 2.96 2.86 75.6 Intra State Project 6 Torrent Power Limited 271 2.98 2.87 146* Intra State Project Total 821.8 - - 521.6 * 124.6 MW from the bucket filled and 21.4 MW from the out of bucket. l) The Commission in its order dated 6 December, 2017 for Case No. 157 of 2017 directed that… In case the standard bidding document is used by MSEDCL then a specific petition shall be filed by MSEDCL after bidding process for adoption of tariff as is mandated under Sec-63 of EA 2003. The said Petition shall cover the following, for approval of the Commission. (i) quantum of power , (ii) Period of power flow, Tariff rate of the RE power to be procured, under Tariff Based Competitive Bidding Process for Short term/ Medium term /Long term basis for adoption under Section 63 of the Act. MSEDCL has approached the Commission for adoption of tariff offered under Section 63 of the EA, 2003 after completion of bidding process. m) MSEDCL submits to the Commission to approve the tariff as discovered in the e-reverse auction for procurement of wind power. Also, the last successful bidder (i.e. M/s Torrent Power Limited) has offered capacity of 146 MW, whereas the allotted capacity in bucket filling of 500 MW as per the e-reverse auction is 124.6 MW. It is requested to the Commission to allow the Petitioner
  • 5. Order in Case No 129 of 2018 Page 5 to execute the Power Purchase Agreement for a capacity of 146 MW with M/s Torrent Power Limited. n) MSEDCL requests the Commission to approve the above tariffs discovered in the e-reverse auction for further signing of PPA with the Successful Bidders. The agreement will for a period of 25 years from the Commercial Operation Date in case of proposed/new wind power project or for a period of 25 years from the date of execution of PPA in case of existing wind power projects. 4. M/s Torrent Power Limited in its written submission received on 9 June, 2018 has stated that it has no objection in accepting the offered project capacity of 146 MW pursuant to the E-Reverse Auction held under the Rfs No.MSEDCL/Competitive/500 Wind dated 21 December, 2017 at the tariff of Rs.2.87 per unit. 5. Adani Green Energy (MP) Limited in its written submission received on 9 June,2018 has stated as follows: a) Adani Green Energy (MP) Limited is selected as successful bidder and allocated 75 MW Wind Power Project.MSEDCL has filed the Petition in Case No 129 of 2018 before the Commission for adoption of tariff. One of the prayer in the said Petition to accord approval of signing of PPA with last selected bidder (i.e. M/s Torrent Power Limited who has submitted bid for 271 MW) for additional capacity of 146 MW at the tariff of Rs 2.87 per unit as against 124.4 MW own under the bid. b) Adani Green Energy (MP) Limited who is one of the successful bidder is ready and willing to execute the Wind Power Project for additional capacity at the bid out tariff/L1 tariff i.e. at Rs.2.85 per unit, which is lower than the one offered to M/s Torrent Power Ltd. for additional capacity of 146 MW. Incremental capacity if any should be offered to lower price bidder who is willing to take additional capacity at L1 tariff, instead of allocation to last bidder that too at higher rate. Adani Green Energy (MP) Limited have capacity to execute the additional Wind power project as may be offered to it in the currently provided in the tender. 6. The proceedings of the hearing held on 9 June, 2018 are summarized as follows: i. The representative of MSEDCL has stated that, MSEDCL has floated the tenders as per MoP standard bidding guidelines and carried out tender process without deviating MoP guidelines. Out of the 7 bidders, 6 were technically and financially qualified and 1 bidder was disqualified for not meeting the minimum bid capacity as specified in the tender document. The final tariff discovered from the e-reverse auction conducted on 6 March, 2018 are between Rs.2.85 to Rs.2.87 per unit. The last successful bidder M/s Torrent Power Limited has offered capacity of 146 MW, whereas the allotted capacity in bucket filling of 500 MW as per the e-
  • 6. Order in Case No 129 of 2018 Page 6 reverse auction is 124.6 MW. MSEDCL requests the Commission to approve the discovered tariff and to allow it to execute the Power Purchase Agreement for a capacity of 146 MW with M/s Torrent Power Limited. Energy purchased through the tendering process shall be considered eligible for meeting the Non-solar RPO requirement of MSEDCL ii. The representative of Adani Green Energy (MP) Limited has stated that it has submitted its reply on 9 June, 2018 and reiterated its submission and requested the Commission to consider its request for willing to execute the Wind Power Project for additional capacity at the bid out tariff i.e. at Rs.2.85 per unit, which is lower than Rs.2.87 per unit offered by M/s Torrent Power Ltd. 7. Adani Green Energy (MP) Limited in its subsequent submission dated 13 June,2018 has stated that it is withdrawing its letter dated 9 June,2018. 8. MSEDCL in its subsequent submission dated 13 June,2018, in reply to the issue raised by Adani Green Energy (MP) Limited vide letter dated 9 June,2018 has stated as follows: a) M/s Adani Green Energy (MP) Limited, vide letter dated 9 June, 2018, has submitted their reply to the Commission and stated that, they are ready to execute the wind power project for additional capacity at the bid out tariff i.e L1 Tariff i.e @Rs.2.85 p.u. which is lower than the one offered to M/s. Torrent Power Ltd additional capacity. b) On 10 April, 2018, SECI approached MSEDCL for consent for purchase of Wind power from the projects under 2000 MW Wind ISTS connected scheme (Tranche IV) at discovered tariff of Rs. 2.52 per kWh plus SECI trading margin of Rs.0.07 per kWh. Accordingly, MSEDCL has given consent on 7 May, 2018 for procurement of 500 MW and filed petition with the Commission for approval and adoption of tariff on 5 June, 2018. c) In view of above developments, MSEDCL has decided to restrict it bucket to 500 MW after completion of reverse auction process in the said tender. d) Accordingly, MSEDCL requests the Commission to approve adoption of tariff for long term procurement of 500 MW wind power under Section 63 of the Electricity Act 2003 for meeting the Non-Solar Renewable Purchase Obligations as under: S. No. Name of the Bidder Capacity (MW) IPO Rate Rs/kWh E-RA result Rs/kWh Bucket Filled Capacity in MW Intra/ Inter 1 Adani Green Energy 100 2.88 2.85 75 Inter State
  • 7. Order in Case No 129 of 2018 Page 7 (MP) Limited Project 2 KCT Renewable Energy Private Limited 100 2.96 2.85 75 Intra State Project 3 Inox Wind Limited 50 2.99 2.86 50 Inter State Project 4 Mytrah Energy (India) Private Limited 200 2.97 2.86 100 Intra State Project 5 Hero Wind Energy Private Limited 100.8 2.96 2.86 75.6 Intra State Project 6 Torrent Power Limited 271 2.98 2.87 124.4 Intra State Project Total 821.8 - - 500 In view of the above the MSEDCL prays to the Commission: i) To admit the Petition as per the provisions under Section 63 of the Electricity Act (EA), 2003. ii) To accord approval for adoption of tariff as discovered in the e-reverse auction conducted on 6 March, 2018 and the same to be made eligible for meeting the Non-solar RPO requirement of MSEDCL. iii) To accord approval for signing of Power Purchase Agreement with the last selected bidder (i. e. M/s Torrent Power Limited) for its bucket filling capacity of 124.4 MW only instead of full offered capacity of 146 MW. Commission’s Analysis and Rulings 9. MSEDCL under the present Petition has sought approval for i) adoption of tariff as discovered in the e-reverse auction conducted on 6 March, 2018 and the same to be made eligible for meeting the Non-solar RPO requirement of MSEDCL ii) signing of Power Purchase Agreement with the last selected bidder M/s Torrent Power Limited for its full offered capacity of 146 MW. However MSEDCL in its subsequent submission dated 13 June,2018 has requested the Commission to accord approval for signing of Power Purchase Agreement with the last selected bidder M/s Torrent Power Limited for its bucket filling capacity of 124.4 MW only instead of full offered capacity of 146 MW.
  • 8. Order in Case No 129 of 2018 Page 8 10. The Commission in its Order dated 6 December, 2017 in Case No. 157 of 2017 had permitted MSEDCL to procure Wind, Solar and Bagasse based cogeneration RE power on Short Term, Medium term and Long term basis at the rate discovered through Tariff based Competitive Bidding (e-reverse auction). Further, the Commission in that Order dated 6 December, 2017 had also ruled that in case the standard bidding document is used by MSEDCL then a specific petition shall be filed by MSEDCL after bidding process for adoption of tariff as is mandated under Sec-63 of EA 2003. The said Petition shall cover the following, for approval of the Commission. (i) quantum of power , (ii) Period of power flow, Tariff rate of the RE power to be procured, under Tariff Based Competitive Bidding Process for Short term/ Medium term /Long term basis for adoption under Section 63 of the Act. 11. The Commission notes that MSEDCL has prepared Rfs document without any deviation in line with the MoP Guidelines dated 8 December,2017 for Tariff Based Competitive Bidding Process for Procurement of Power from grid connected Wind power Projects and floated the tender. The final tariff discovered from the e-reverse auction conducted on 6 March, 2018 is between Rs 2.85 to Rs 2.87 per unit. The last successful bidder M/s Torrent Power Limited has offered capacity of 146 MW, whereas the allotted capacity in bucket filling of 500 MW as per the e-reverse auction is 124.6 MW i.e. 21.40 MW capacity is out of the bucket. However, the Commission notes that MSEDCL in its submission dated 13 June, 2018 has stated that it has decided to restrict bucket filling capacity of M/s Torrent Power Limited for its of 124.4 MW only instead of full offered capacity of 146 MW. 12. The Commission notes that the M/s Adani Green Energy (MP) Limited has also withdrawn vide its letter dated 13 June, 2018 about its contention made in its submission dated 9 June, 2018 and during the proceeding of the hearing held on 9 June, 2018. 13. In view of foregoing, in line with the mandate u/s 63 of the EA, 2003 the following procurement and rates are approved by the Commission as proposed by MSEDCL. Also, the Commission accords approval to consider the proposed Wind Power generation to count towards fulfilment of its non-Solar RPO for the respective periods.
  • 9. Order in Case No 129 of 2018 Page 9 Sr. No. Name of the supplier Quantum of procurement approved (MW) PPA Period Time period of supply Rate (Rs./kWh) 1 Adani Green Energy (MP) Limited 75 25 Years from the date of COD for new Wind projects or 25 years from date of signing of EPA for existing Wind Projects As per availability 2.85 2 KCT Renewable Energy Private Limited 75 2.85 3 Inox Wind Limited 50 2.86 4 Mytrah Energy (India) Private Limited 100 2.86 5 Hero Wind Energy Private Limited 75.6 2.86 6 Torrent Power Limited 124.5 2.87 Total 500 - The Petition of Maharashtra State Electricity Distribution Co. Ltd. in Case No.129 of 2018 stands disposed of accordingly. Sd/ Sd/ (Mukesh Khullar) (Anand B. Kulkarni) Member Chairperson