SlideShare a Scribd company logo
1 of 24
Download to read offline
INTERNATIONAL RENEWABLE ENERGY
AGENCY
Grid integration for renewables in SIDS
Francisco Gafaro
King Island, 18 November 2015
This presentation
• IRENA
• The transformation of the power systems
• The challenges
• Grid modelling studies
• Case studies
2
The Voice, Advisory Resource and Knowledge Hub for 170 Governments
International Renewable Energy
Agency
IRENA work is driven by member country demand, typical questions include:
 What quality criteria should be introduce in our TOR for new VRE capacity ?
 How much VRE is feasible in our grid ?
 Should we invest in storage ?
 Can you prove that VRE makes economic sense for us ?
 What is best practice abroad in enabling policy framework design ?
Launched on 23 September 2014 at the Climate Summit
STRATEGIC OBJECTIVE:
• Enabling a sustainable energy transformation for people on the front line of climate change on
small islands around the world
• Enhancing energy independence and economic prosperity on SIDS
SIDS Lighthouses Initiative overview
4
57 (SIDS), 38 UN members
in 3 geographical zones
Over 60 million people,
90 TWh electricity
consumption per year,
29 GW of installed
generation (only in UN
members)
The global transformation
of the power systems
5
1
Competitiveness of renewables
increases continuously …
7
0%
20%
40%
60%
80%
100%
2005 2010 2014
Conventional Other renewables Wind Solar PV
VARIABLE
RENEWABLE
ENERGY
… and their share in the total electricity
production is increasing
2015:
50-55 GW solar PV 200 GW installed capacity worldwide
55-58 GW wind installed 400 GW installed capacity worldwide
Power systems don’t look the same
anymore
8
around 30.000 plants around 1.500.000 plantsaround 220.000 plants
2000 2006 2014
Wind Photovoltaics Biomass
Source: 50Hertz Source: 50Hertz Source: 50Hertz
The transformation is not only
happening in large systems …
Different sizes Different resources
Different stakeholders Different
solutions!
http://www.kingislandrenewableenergy.com.au/
The challenges
10
2
Seconds
Years
Impact
Groups.
11
Properties of VRE and challenges
Stability, Voltage,
Frequency Response
Non-Synchronous
Unit commitment
Reserves
Uncertainty
Abundance
Scarcity
Asset Utilization
Short Term Changes
Variability
Location Constraints
Modularity
VRE PROPERTIES
Voltage
Control
Frequency
Response
Frequency
Control
Generation
Adequacy
IMPACTSDEPENDONSYSTEMCHARACTERISTICS
Source: IRENA, adapted from IEA, S. Muller
T&D Grid
Adequacy
Voltage
Control
The challenges and the tools for SIDS
Planning is a key word !
Issues
Stability and reliability |
Operation
New investments: RE,
grid, storage, control
Tariffs |IPP regulation |
Standards
DIMENSIONS
Technical Economical Policy and regulation
13
Challenges for operation in islands
Each system is different and requires its own assessment! Listed characteristics and
challenges do not apply to all islands!
Non-
Synchronous
Fast variations
(sec. to min.)
Uncertainty
Longer term
variations
(daily)
Location
Low Inertia
Rapid
frequency
response
Rapid
frequency
response
Adequacy of governor
action (Capability to
deploy available
headroom)
Rapid
frequency
response
Rapid
frequency
response
Non-automated frequency
regulation (no AGC)
Regulation Regulation
Flexibility constrains on
existing generation fleet
Adequate
reserve
allocation
Adequate
reserve
allocation Load following
Load
following
Weak electrical networks
Voltage control
/ Transient
stability
Voltage control /
Power quality
Smaller geographical
area
Rapid
frequency
response
IslandSystemCharacteristics
VRE Characteristics
Grid studies
14
3
15
 Planning tools, analytical assessments,help to answer the following questions:
 How much VRE can be integrated without major system upgrades?
 Is it feasible to achieve the target shares of VRE?
 What is required to achieve the target shares of VRE?
 Depend on the characteristics of the island system and the target share of VRE
 Target medium to large size islands (MW scale) where integration takes place
gradually and mutiple stakeholders are involved
 Grid Studies are based on different type of computer simulations of the grid
operation
 To do a study requires:
 Accurate and sufficient input information
 Tools
 Engagement from authorities and the utilities
Grid modelling studies for islands
16
Grid modelling studies process
17
Grid modelling studies process
Concluded Studies
 Samoa 1
 Cook Islands (Aitutaki)
 Antigua & Barbuda
 Palau
Ongoing or coordination started
 Samoa 2
 Kiribati (collaboration with PPA)
 Fiji
Reviews requested by governments
 Barbados (April 2015), Seychelles (ongoing)
Study cases:
18
Integration studies in association with energy authorities and network operators
supporting evaluation of impacts and Operation & Expansion planning of the grid
 Peak demand around 20 MW
 Annual electricity consumption around
115 GWha
 Integration of c.a. 14 MW of PV to be
assessed
 Around 11 MW of PV under PPA with 3
different IPP
 Support identification of measures to
maximize use of hydro and PV projects
 Diesel power station provides frequency
regulation (AGC) and voltage control
 New wind projects planned, updated
studies will be required
Study case Upolu - Samoa -
background
19
19
FIAGA
F/S
L/M
TAF
4
MW
8
MW
5
MW
30
MW
DIESEL
2.7
MW
Load
3.5
MW 4
MW
TANU
33 kV
22 kV
Upolu 2014
Hydro
Map Data ©2015 Google
FIAGA
F/S
L/M
TAF
5
MW
8.5
MW
5.7
MW
6.7
MW
Load
3.5
MW
TANU
33 kV
22 kV
Upolu 2017
Hydro
5
MW
30
MW
DIESEL
4
MW
7
MW
Map Data ©2015 Google
20
Study case Upolu - Samoa - findings
Alternative
Measures to guarantee secure
operation
Security
Constraints
#1
(Minor-
Impact
Solutions)
At least two diesel units online at all times
Voltage control capabilities in all PV plants
with ±0.95 power factor
Blackout after loss
of generation or
demand, or after
fault
#2
(Mid-Impact
Solutions)
Solutions applied in #1
Adjustment of UFLS settings
Output power reduction in case of
overfrequency (new PV plants)
FRT capability (new PV plants)
All security criteria
fulfilled
#2
(Major-
Impact
Solutions)
Solutions applied in #2
3.5 Mvar reactive power compensation
2 MW power storage device
AGC control includes hydro units
All security criteria
fulfilled
Potential!
Main performance criteria steady
state:
• Voltage normal conditions
within +/- 5 % nominal
• Voltage within +/- 10 % after
contingency
Main performance criteria
dynamic:
• Avoid UFLS activation due to
fast fluctuations of PV
• Avoid activation of generator
protection (blackout) after
contingency
Antigua
 Peak load around 50 MW
 Annual electricity consumption around
350 GWha
 Over 100 MW of installed diesel
capacity
 160 GWha purchased under PPA
 Assessment impact of 9 MW of PV
and 18 MW of wind (government
projects)
 Identification of maximum capacity of
the network to host PV systems
Study case Antigua - background
21
Map Data ©2015 Google
22
Study case Antigua – findings
• Performance criteria fulfilled without major
updates in the grid
• Changes in reserve allocation practices
required
• Utility not willing to allocate contingency
reserves
• Stability of the system relays on load
shedding scheme
• Grid support functions provided by utility
scale PV and wind are crucial: Reactive
power control capability, FRT, Over
• frequency response
• Frequency range of operation of utility scale
PV and wind must be the same from
protection settings of diesel generators
• Automatic generation control recommended
Lessons learned
23
 The approach has evolved from “grid stability studies” to grid operation planning
 The deployment of high shares of variable renewables is a long journey
 Technical assessment of the grid integration is part of the journey and should
not be isolated from the other planning activities
 Each island is a unique case. Particularities define approach required for
assessments
 Grid integration assessments are a continuous / iterative process
 The biggest challenges are data collection and communication of messages
 Coordination of support activities among engaged developing partners is crucial
www.irena.org
Thank you very much!!
Francisco Gafaro
fgafaro@irena.org

More Related Content

What's hot

IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET Journal
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project AnalysisLeonardo ENERGY
 
G wiz poster
G wiz posterG wiz poster
G wiz posterJing Deng
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage Bushveld Energy
 
Cleantech America ACWA Presentation
Cleantech America ACWA PresentationCleantech America ACWA Presentation
Cleantech America ACWA PresentationMark Stout
 
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...IEA-ETSAP
 
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Implementing Agreement (IA)
 
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013New Jersey Future
 
Wind Power Overview Treasury Feb 2009
Wind Power Overview Treasury Feb 2009Wind Power Overview Treasury Feb 2009
Wind Power Overview Treasury Feb 2009Cohocton Wind Watch
 
Repurposing of west virginia strip mines for sustainable
Repurposing of west virginia strip mines for sustainableRepurposing of west virginia strip mines for sustainable
Repurposing of west virginia strip mines for sustainablemabartl
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...IEA-ETSAP
 
Applications of flow batteries in Africa
Applications of flow batteries in AfricaApplications of flow batteries in Africa
Applications of flow batteries in AfricaBushveld Energy
 
Energy Storage Opportunities and Challenges ECOFYS
Energy Storage Opportunities and Challenges ECOFYS Energy Storage Opportunities and Challenges ECOFYS
Energy Storage Opportunities and Challenges ECOFYS Andrew Gelston
 
Measuring the value of energy storage
Measuring the value of energy storageMeasuring the value of energy storage
Measuring the value of energy storageBushveld Energy
 
Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends Mirzo Ibragimov
 

What's hot (20)

IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
IRJET- Development and Comparison of an Improved Incremental Conductance Algo...
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project Analysis
 
G wiz poster
G wiz posterG wiz poster
G wiz poster
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage
 
Tale of Six Cities
Tale of Six CitiesTale of Six Cities
Tale of Six Cities
 
Cleantech America ACWA Presentation
Cleantech America ACWA PresentationCleantech America ACWA Presentation
Cleantech America ACWA Presentation
 
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
 
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
 
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
NJ Future Sandy One Year Later Design LaRossa Oct 29 2013
 
Wind Power Overview Treasury Feb 2009
Wind Power Overview Treasury Feb 2009Wind Power Overview Treasury Feb 2009
Wind Power Overview Treasury Feb 2009
 
Repurposing of west virginia strip mines for sustainable
Repurposing of west virginia strip mines for sustainableRepurposing of west virginia strip mines for sustainable
Repurposing of west virginia strip mines for sustainable
 
K-Solar Program Overview
K-Solar Program OverviewK-Solar Program Overview
K-Solar Program Overview
 
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
 
3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...
3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...
3.5_Microgrid Market Operations with Distribution System Operators_Shahidehpo...
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
 
Applications of flow batteries in Africa
Applications of flow batteries in AfricaApplications of flow batteries in Africa
Applications of flow batteries in Africa
 
Energy Storage Opportunities and Challenges ECOFYS
Energy Storage Opportunities and Challenges ECOFYS Energy Storage Opportunities and Challenges ECOFYS
Energy Storage Opportunities and Challenges ECOFYS
 
Poster Board_v8
Poster Board_v8Poster Board_v8
Poster Board_v8
 
Measuring the value of energy storage
Measuring the value of energy storageMeasuring the value of energy storage
Measuring the value of energy storage
 
Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends
 

Viewers also liked

Ips connect 2015 sohail hasnie
Ips connect 2015 sohail hasnieIps connect 2015 sohail hasnie
Ips connect 2015 sohail hasniejames_hamilton
 
Презентація об'єднаймося ж, брати мої 2003
Презентація об'єднаймося ж, брати мої 2003Презентація об'єднаймося ж, брати мої 2003
Презентація об'єднаймося ж, брати мої 2003Школа №17, Чернігів
 
Ips connect 2015 geoff stapleton
Ips connect 2015 geoff stapletonIps connect 2015 geoff stapleton
Ips connect 2015 geoff stapletonjames_hamilton
 
Esquema Construccion del Numero
Esquema Construccion del NumeroEsquema Construccion del Numero
Esquema Construccion del NumeroKatia Márquez V
 
LED_Street-lighting
LED_Street-lightingLED_Street-lighting
LED_Street-lightingLucy Record
 
Ips connect 2015 nikolasi fonua
Ips connect 2015 nikolasi fonuaIps connect 2015 nikolasi fonua
Ips connect 2015 nikolasi fonuajames_hamilton
 
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...Cristobal Mena
 
LOCAL ADMINISTRATION REFORM IN CYPRUS
LOCAL ADMINISTRATION REFORM IN CYPRUSLOCAL ADMINISTRATION REFORM IN CYPRUS
LOCAL ADMINISTRATION REFORM IN CYPRUSLean6Sigma4all
 
Design and implementation of a hospital management system
Design and implementation of a hospital management systemDesign and implementation of a hospital management system
Design and implementation of a hospital management systemOvercomer Michael
 
Matematica Transformada de Laplace
Matematica Transformada de LaplaceMatematica Transformada de Laplace
Matematica Transformada de LaplaceVictor Navarro
 

Viewers also liked (13)

Colonial kids
Colonial kidsColonial kids
Colonial kids
 
Ips connect 2015 sohail hasnie
Ips connect 2015 sohail hasnieIps connect 2015 sohail hasnie
Ips connect 2015 sohail hasnie
 
Презентація об'єднаймося ж, брати мої 2003
Презентація об'єднаймося ж, брати мої 2003Презентація об'єднаймося ж, брати мої 2003
Презентація об'єднаймося ж, брати мої 2003
 
Ips connect 2015 geoff stapleton
Ips connect 2015 geoff stapletonIps connect 2015 geoff stapleton
Ips connect 2015 geoff stapleton
 
Esquema Construccion del Numero
Esquema Construccion del NumeroEsquema Construccion del Numero
Esquema Construccion del Numero
 
LED_Street-lighting
LED_Street-lightingLED_Street-lighting
LED_Street-lighting
 
Ips connect 2015 nikolasi fonua
Ips connect 2015 nikolasi fonuaIps connect 2015 nikolasi fonua
Ips connect 2015 nikolasi fonua
 
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...
Dissertation Window of Opportunity, Disaster Public Policy Change in Chile, a...
 
Cinetica
CineticaCinetica
Cinetica
 
Wujud zat
Wujud zatWujud zat
Wujud zat
 
LOCAL ADMINISTRATION REFORM IN CYPRUS
LOCAL ADMINISTRATION REFORM IN CYPRUSLOCAL ADMINISTRATION REFORM IN CYPRUS
LOCAL ADMINISTRATION REFORM IN CYPRUS
 
Design and implementation of a hospital management system
Design and implementation of a hospital management systemDesign and implementation of a hospital management system
Design and implementation of a hospital management system
 
Matematica Transformada de Laplace
Matematica Transformada de LaplaceMatematica Transformada de Laplace
Matematica Transformada de Laplace
 

Similar to IRENA GRID INTEGRATION STUDIES HELP SIDS MAXIMIZE RENEWABLES

VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...vvfvilar
 
Renewable Energy Integration Limits
Renewable Energy Integration LimitsRenewable Energy Integration Limits
Renewable Energy Integration LimitsAnand SR
 
A Review on Integration of Wind Turbines in Distributed Generation Power System
A Review on Integration of Wind Turbines in Distributed Generation Power SystemA Review on Integration of Wind Turbines in Distributed Generation Power System
A Review on Integration of Wind Turbines in Distributed Generation Power Systemijtsrd
 
Solar PV Potential & Status.pptx
Solar PV Potential & Status.pptxSolar PV Potential & Status.pptx
Solar PV Potential & Status.pptxFaizanAli519030
 
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...Integrating Variable Renewable Energy into the Grid key issues and Emerging S...
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...Power System Operation
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyTransGrid AU
 
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEI
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEIFlinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEI
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEIjames hamilton
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimetRick Case, PMP, P.E.
 
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdfSamuelEU2
 
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...IPPAI
 
Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Daniel Schwab
 
Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...IEA-ETSAP
 
Emission impacts of marginal electricity demand in France
Emission impacts of marginal electricity demand in FranceEmission impacts of marginal electricity demand in France
Emission impacts of marginal electricity demand in FranceIEA-ETSAP
 
Best practices for Solar and Wind power system case studies
Best practices for Solar and Wind power system case studiesBest practices for Solar and Wind power system case studies
Best practices for Solar and Wind power system case studiesLeonardo ENERGY
 
Bangalore | Jul-16 | Energy Storage for Microgrids: Poised for rapid adoption
Bangalore | Jul-16 | Energy Storage for Microgrids:Poised for rapid adoptionBangalore | Jul-16 | Energy Storage for Microgrids:Poised for rapid adoption
Bangalore | Jul-16 | Energy Storage for Microgrids: Poised for rapid adoptionSmart Villages
 
IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA_RETD
 
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...Isam Shahrour
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2fboshell
 

Similar to IRENA GRID INTEGRATION STUDIES HELP SIDS MAXIMIZE RENEWABLES (20)

VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
VGEF 2015: Clean Energy - Technology (Dan Arvizu, Director, NREL & Chairman, ...
 
Renewable Energy Integration Limits
Renewable Energy Integration LimitsRenewable Energy Integration Limits
Renewable Energy Integration Limits
 
A Review on Integration of Wind Turbines in Distributed Generation Power System
A Review on Integration of Wind Turbines in Distributed Generation Power SystemA Review on Integration of Wind Turbines in Distributed Generation Power System
A Review on Integration of Wind Turbines in Distributed Generation Power System
 
Solar PV Potential & Status.pptx
Solar PV Potential & Status.pptxSolar PV Potential & Status.pptx
Solar PV Potential & Status.pptx
 
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...Integrating Variable Renewable Energy into the Grid key issues and Emerging S...
Integrating Variable Renewable Energy into the Grid key issues and Emerging S...
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEI
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEIFlinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEI
Flinders Island Isolated Power System (IPS) Connect 2016 R ROCHELEAU HNEI
 
The merits of integrating renewables with smarter grid carimet
The merits of integrating renewables with smarter grid   carimetThe merits of integrating renewables with smarter grid   carimet
The merits of integrating renewables with smarter grid carimet
 
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
+Frede-Blaabjerg-Introduction-to-renewables-systems.pdf
 
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
Session 3: Impact on U.S. Ancillary Services Markets from Variable Renewable ...
 
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro TasmaniaSecuring Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
 
Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?Clean energy microgrids - Hype or Reality?
Clean energy microgrids - Hype or Reality?
 
Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...Long-term energy system modelling with improved resolution to address short-t...
Long-term energy system modelling with improved resolution to address short-t...
 
Emission impacts of marginal electricity demand in France
Emission impacts of marginal electricity demand in FranceEmission impacts of marginal electricity demand in France
Emission impacts of marginal electricity demand in France
 
Best practices for Solar and Wind power system case studies
Best practices for Solar and Wind power system case studiesBest practices for Solar and Wind power system case studies
Best practices for Solar and Wind power system case studies
 
CaLEAP Energy Strategies Workshop June 25, 2013
CaLEAP Energy Strategies Workshop June 25, 2013CaLEAP Energy Strategies Workshop June 25, 2013
CaLEAP Energy Strategies Workshop June 25, 2013
 
Bangalore | Jul-16 | Energy Storage for Microgrids: Poised for rapid adoption
Bangalore | Jul-16 | Energy Storage for Microgrids:Poised for rapid adoptionBangalore | Jul-16 | Energy Storage for Microgrids:Poised for rapid adoption
Bangalore | Jul-16 | Energy Storage for Microgrids: Poised for rapid adoption
 
IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311
 
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...Professor Isam Shahrour Summer Course « Smart and Sustainable City »  Chapter...
Professor Isam Shahrour Summer Course « Smart and Sustainable City » Chapter...
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2
 

More from james_hamilton

James hamilton ips connect-hamilton
James hamilton   ips connect-hamiltonJames hamilton   ips connect-hamilton
James hamilton ips connect-hamiltonjames_hamilton
 
Ips connect 2015 seiapi
Ips connect 2015 seiapiIps connect 2015 seiapi
Ips connect 2015 seiapijames_hamilton
 
Ips connect 2015 deva de silva
Ips connect 2015 deva de silvaIps connect 2015 deva de silva
Ips connect 2015 deva de silvajames_hamilton
 
Ips connect 2015 andrew daka
Ips connect 2015 andrew dakaIps connect 2015 andrew daka
Ips connect 2015 andrew dakajames_hamilton
 
Ips connect 2015 kamleshwar khelawan
Ips connect 2015 kamleshwar khelawanIps connect 2015 kamleshwar khelawan
Ips connect 2015 kamleshwar khelawanjames_hamilton
 
Ips connect 2015 marc mueller stoffels
Ips connect 2015 marc mueller stoffelsIps connect 2015 marc mueller stoffels
Ips connect 2015 marc mueller stoffelsjames_hamilton
 
Ips connect 2015 simon franklin
Ips connect 2015 simon franklinIps connect 2015 simon franklin
Ips connect 2015 simon franklinjames_hamilton
 
Ips connect 2015 simon gamble
Ips connect 2015 simon gambleIps connect 2015 simon gamble
Ips connect 2015 simon gamblejames_hamilton
 
Ips connect 2015 chris smith
Ips connect 2015 chris smithIps connect 2015 chris smith
Ips connect 2015 chris smithjames_hamilton
 
Ips connect 2015 david waterhouse
Ips connect 2015 david waterhouseIps connect 2015 david waterhouse
Ips connect 2015 david waterhousejames_hamilton
 
Emergent Energy Futures
Emergent Energy FuturesEmergent Energy Futures
Emergent Energy Futuresjames_hamilton
 
Utas lld-presentation-arena oct9-final
Utas lld-presentation-arena oct9-finalUtas lld-presentation-arena oct9-final
Utas lld-presentation-arena oct9-finaljames_hamilton
 

More from james_hamilton (12)

James hamilton ips connect-hamilton
James hamilton   ips connect-hamiltonJames hamilton   ips connect-hamilton
James hamilton ips connect-hamilton
 
Ips connect 2015 seiapi
Ips connect 2015 seiapiIps connect 2015 seiapi
Ips connect 2015 seiapi
 
Ips connect 2015 deva de silva
Ips connect 2015 deva de silvaIps connect 2015 deva de silva
Ips connect 2015 deva de silva
 
Ips connect 2015 andrew daka
Ips connect 2015 andrew dakaIps connect 2015 andrew daka
Ips connect 2015 andrew daka
 
Ips connect 2015 kamleshwar khelawan
Ips connect 2015 kamleshwar khelawanIps connect 2015 kamleshwar khelawan
Ips connect 2015 kamleshwar khelawan
 
Ips connect 2015 marc mueller stoffels
Ips connect 2015 marc mueller stoffelsIps connect 2015 marc mueller stoffels
Ips connect 2015 marc mueller stoffels
 
Ips connect 2015 simon franklin
Ips connect 2015 simon franklinIps connect 2015 simon franklin
Ips connect 2015 simon franklin
 
Ips connect 2015 simon gamble
Ips connect 2015 simon gambleIps connect 2015 simon gamble
Ips connect 2015 simon gamble
 
Ips connect 2015 chris smith
Ips connect 2015 chris smithIps connect 2015 chris smith
Ips connect 2015 chris smith
 
Ips connect 2015 david waterhouse
Ips connect 2015 david waterhouseIps connect 2015 david waterhouse
Ips connect 2015 david waterhouse
 
Emergent Energy Futures
Emergent Energy FuturesEmergent Energy Futures
Emergent Energy Futures
 
Utas lld-presentation-arena oct9-final
Utas lld-presentation-arena oct9-finalUtas lld-presentation-arena oct9-final
Utas lld-presentation-arena oct9-final
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 

IRENA GRID INTEGRATION STUDIES HELP SIDS MAXIMIZE RENEWABLES

  • 1. INTERNATIONAL RENEWABLE ENERGY AGENCY Grid integration for renewables in SIDS Francisco Gafaro King Island, 18 November 2015
  • 2. This presentation • IRENA • The transformation of the power systems • The challenges • Grid modelling studies • Case studies 2
  • 3. The Voice, Advisory Resource and Knowledge Hub for 170 Governments International Renewable Energy Agency IRENA work is driven by member country demand, typical questions include:  What quality criteria should be introduce in our TOR for new VRE capacity ?  How much VRE is feasible in our grid ?  Should we invest in storage ?  Can you prove that VRE makes economic sense for us ?  What is best practice abroad in enabling policy framework design ?
  • 4. Launched on 23 September 2014 at the Climate Summit STRATEGIC OBJECTIVE: • Enabling a sustainable energy transformation for people on the front line of climate change on small islands around the world • Enhancing energy independence and economic prosperity on SIDS SIDS Lighthouses Initiative overview 4 57 (SIDS), 38 UN members in 3 geographical zones Over 60 million people, 90 TWh electricity consumption per year, 29 GW of installed generation (only in UN members)
  • 5. The global transformation of the power systems 5 1
  • 7. 7 0% 20% 40% 60% 80% 100% 2005 2010 2014 Conventional Other renewables Wind Solar PV VARIABLE RENEWABLE ENERGY … and their share in the total electricity production is increasing 2015: 50-55 GW solar PV 200 GW installed capacity worldwide 55-58 GW wind installed 400 GW installed capacity worldwide
  • 8. Power systems don’t look the same anymore 8 around 30.000 plants around 1.500.000 plantsaround 220.000 plants 2000 2006 2014 Wind Photovoltaics Biomass Source: 50Hertz Source: 50Hertz Source: 50Hertz
  • 9. The transformation is not only happening in large systems … Different sizes Different resources Different stakeholders Different solutions! http://www.kingislandrenewableenergy.com.au/
  • 11. Seconds Years Impact Groups. 11 Properties of VRE and challenges Stability, Voltage, Frequency Response Non-Synchronous Unit commitment Reserves Uncertainty Abundance Scarcity Asset Utilization Short Term Changes Variability Location Constraints Modularity VRE PROPERTIES Voltage Control Frequency Response Frequency Control Generation Adequacy IMPACTSDEPENDONSYSTEMCHARACTERISTICS Source: IRENA, adapted from IEA, S. Muller T&D Grid Adequacy Voltage Control
  • 12. The challenges and the tools for SIDS Planning is a key word ! Issues Stability and reliability | Operation New investments: RE, grid, storage, control Tariffs |IPP regulation | Standards DIMENSIONS Technical Economical Policy and regulation
  • 13. 13 Challenges for operation in islands Each system is different and requires its own assessment! Listed characteristics and challenges do not apply to all islands! Non- Synchronous Fast variations (sec. to min.) Uncertainty Longer term variations (daily) Location Low Inertia Rapid frequency response Rapid frequency response Adequacy of governor action (Capability to deploy available headroom) Rapid frequency response Rapid frequency response Non-automated frequency regulation (no AGC) Regulation Regulation Flexibility constrains on existing generation fleet Adequate reserve allocation Adequate reserve allocation Load following Load following Weak electrical networks Voltage control / Transient stability Voltage control / Power quality Smaller geographical area Rapid frequency response IslandSystemCharacteristics VRE Characteristics
  • 15. 15  Planning tools, analytical assessments,help to answer the following questions:  How much VRE can be integrated without major system upgrades?  Is it feasible to achieve the target shares of VRE?  What is required to achieve the target shares of VRE?  Depend on the characteristics of the island system and the target share of VRE  Target medium to large size islands (MW scale) where integration takes place gradually and mutiple stakeholders are involved  Grid Studies are based on different type of computer simulations of the grid operation  To do a study requires:  Accurate and sufficient input information  Tools  Engagement from authorities and the utilities Grid modelling studies for islands
  • 18. Concluded Studies  Samoa 1  Cook Islands (Aitutaki)  Antigua & Barbuda  Palau Ongoing or coordination started  Samoa 2  Kiribati (collaboration with PPA)  Fiji Reviews requested by governments  Barbados (April 2015), Seychelles (ongoing) Study cases: 18 Integration studies in association with energy authorities and network operators supporting evaluation of impacts and Operation & Expansion planning of the grid
  • 19.  Peak demand around 20 MW  Annual electricity consumption around 115 GWha  Integration of c.a. 14 MW of PV to be assessed  Around 11 MW of PV under PPA with 3 different IPP  Support identification of measures to maximize use of hydro and PV projects  Diesel power station provides frequency regulation (AGC) and voltage control  New wind projects planned, updated studies will be required Study case Upolu - Samoa - background 19 19 FIAGA F/S L/M TAF 4 MW 8 MW 5 MW 30 MW DIESEL 2.7 MW Load 3.5 MW 4 MW TANU 33 kV 22 kV Upolu 2014 Hydro Map Data ©2015 Google FIAGA F/S L/M TAF 5 MW 8.5 MW 5.7 MW 6.7 MW Load 3.5 MW TANU 33 kV 22 kV Upolu 2017 Hydro 5 MW 30 MW DIESEL 4 MW 7 MW Map Data ©2015 Google
  • 20. 20 Study case Upolu - Samoa - findings Alternative Measures to guarantee secure operation Security Constraints #1 (Minor- Impact Solutions) At least two diesel units online at all times Voltage control capabilities in all PV plants with ±0.95 power factor Blackout after loss of generation or demand, or after fault #2 (Mid-Impact Solutions) Solutions applied in #1 Adjustment of UFLS settings Output power reduction in case of overfrequency (new PV plants) FRT capability (new PV plants) All security criteria fulfilled #2 (Major- Impact Solutions) Solutions applied in #2 3.5 Mvar reactive power compensation 2 MW power storage device AGC control includes hydro units All security criteria fulfilled Potential! Main performance criteria steady state: • Voltage normal conditions within +/- 5 % nominal • Voltage within +/- 10 % after contingency Main performance criteria dynamic: • Avoid UFLS activation due to fast fluctuations of PV • Avoid activation of generator protection (blackout) after contingency
  • 21. Antigua  Peak load around 50 MW  Annual electricity consumption around 350 GWha  Over 100 MW of installed diesel capacity  160 GWha purchased under PPA  Assessment impact of 9 MW of PV and 18 MW of wind (government projects)  Identification of maximum capacity of the network to host PV systems Study case Antigua - background 21 Map Data ©2015 Google
  • 22. 22 Study case Antigua – findings • Performance criteria fulfilled without major updates in the grid • Changes in reserve allocation practices required • Utility not willing to allocate contingency reserves • Stability of the system relays on load shedding scheme • Grid support functions provided by utility scale PV and wind are crucial: Reactive power control capability, FRT, Over • frequency response • Frequency range of operation of utility scale PV and wind must be the same from protection settings of diesel generators • Automatic generation control recommended
  • 23. Lessons learned 23  The approach has evolved from “grid stability studies” to grid operation planning  The deployment of high shares of variable renewables is a long journey  Technical assessment of the grid integration is part of the journey and should not be isolated from the other planning activities  Each island is a unique case. Particularities define approach required for assessments  Grid integration assessments are a continuous / iterative process  The biggest challenges are data collection and communication of messages  Coordination of support activities among engaged developing partners is crucial
  • 24. www.irena.org Thank you very much!! Francisco Gafaro fgafaro@irena.org