SlideShare a Scribd company logo
1 of 6
Download to read offline
IEEE AFRICON 2009

23 - 25 September 2009, Nairobi, Kenya

Effect of Converter DC fault on the Transient
Stability of a Multi-Machine Power System with
HVDC Transmission lines
1

D.T. Oyedokun MIEEE, 2K. A. Folly MIEEE, 3S.P. Chowdhury MIEEE
Department of Electrical Engineering
University of Cape Town
Cape Town, South Africa.

1

davoyedokun@ieee.org, 2komla.folly@uct.ac.za, 3sp.chowdhury@uct.ac.za

Abstract—This paper deals with the effect of DC faults on the
transient stability of a Multi-Machine Power System with two
transmission line configurations; HVDC and a hybrid HVACHVDC transmission line. The faults are located at the DC
terminals of the HVDC converter station. In order to carry out
this study, two case studies are presented. In the first case study a
double HVDC transmission line is used to transmit 2000MW to
an area of the power system called Pookland which has a total
load demand of 2440MW. In case two, a parallel hybrid HVACHVDC transmission line is used to transmit the same amount of
power to Pookland. In both cases, the impact of a short term
converter DC fault on the transient stability of the entire system
was investigated. This was done by studying the response of the
rotor angle of G2 in Pookland, G3 in the Bing Coal plant and the
voltage profile at the terminals of the generators to the DC fault
at the HVDC converter station. Amongst other results, it was
established that in case 1 which has a double HVDC transmission
line, the rectifier side (in the Bing coal plant) has less rotor angle
oscillations when compared to the inverter side (in Pookland),
but the rectifier side took longer than the inverter side for the
rotor angle of the generators to stabilize. In case 2, the voltage at
G2 in Pookland took six times the amount of time it took G3 in
the Bing coal plant to stabilize while the voltage in the Bing Coal
plant dipped by 0.35pu (smaller than case 1 which dipped by
0.4pu). In conclusion, the converter DC fault had a smaller
impact on the transient stability of the Multi-Machine power
system when the hybrid HVAC-HVDC transmission line was
adopted.

Keywords-component; HVDC, HVAC, Hybrid HVAC-HVDC
transient stability, transmisison, rotor angle

I.

INTRODUCTION

The ability of a power system to withstand and recover
from system faults in a fast and successfully manner is critical
to the stability of the power system. According to [1], the use
of High Voltage Direct Current (HVDC) transmission for long
distance applications has seen an increase due to the following
reasons:

•

It is a more economical mode of power transfer as
compared to HVAC over long distances exceeding
500km [2].

•

HVDC
transmission
lines
(i.e.
submarine,
underground and overhead transmission lines) do not
make use of the three phase cables used in HVAC
transmission therefore, the power losses incurred in
the DC lines are lower than that of AC lines.

•

HVDC can be used to interconnect asynchronous
systems. Examples of such connections are in North
America, between the South-West Power Pool (SPP)
and also between Quebec and its neighbors (New
England and the Maritimes) [3].

Large HVDC schemes exist worldwide. These include the
pacific intertie which has a total of 3100MW over a distance of
1360km and the Hydro Quebec New England link [4]. Itaipu in
Brazil has an HVDC scheme of 6300MW, the cross channel
UK- France scheme has a capacity of 2000MW, Wybord in
Russia has a capacity of 1050MW. The scheme between North
and south Islands of New Zealand is 1240MW and the CahoraBassa Hydro scheme between Mozambique and South Africa
has a Capacity of 1920MW [5]. As of 2005, the worldwide
installed HVDC capacity was 55GW which is 1.4% of the
worldwide installed generation capacity [6].
HVDC is obtained directly from High Voltage Alternating
Current (HVAC) through the use of HVDC converters and
their associated devices like filters, reactors and capacitor
banks which provide reactive power support for the HVDC
converters. In most HVDC schemes around the world, the 12
pulse thyristor converter configuration has been adopted to
reduce the requirements for smoothing the DC waveform [7].
With regards to power system stability, it has been stated that
the use of HVDC transmission lines in parallel with HVAC
transmission lines increases the strength and the stability of the
system. An example of such an interconnection is the Pacific
Intertie in California and Oregon [8].

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

1
IEEE AFRICON 2009

23 - 25 September 2009, Nairobi, Kenya

As faults on HVDC converter stations could lead to instability
in the power system, this paper looks at the effect of converter
DC faults on the rotor angle of the generators for a multimachine power system. This is done by looking at two
transmission line configurations between the Bing Coal plant
and Pookland as indicated in fig.2 while a DC fault is induced
in the converter station.
Firstly, a double HVDC transmission line is considered for
transmission and secondly, parallel transmission using hybrid
HVAC-HVDC is considered. In each of the configurations, a
50msec fault is applied on the rectifier DC terminal. The effect
of this fault on the rotor angle of the generator G1 in Pookland
and generator G3 in the Bing coal plant are investigated.

II.

CONVERTER FAULTS AND EQUATIONS

A. Converter Equations
Fig.1 shows the schematics of the rectifier side of a HVDC
scheme.

Fig.1 Rectifier side of a HVDC scheme

V DC =

3 2

π

VS BT cos α

VDC ( I ) =

I DC =

3 2

π
3 2

π

From (3) and (4), the DC power output from the rectifier is
given as follows:

PDC = V DC ( R ) ⋅ I DC

(5)

QR = PDC ⋅ tan(α )

(6)

Where QR is the reactive power absorbed by the rectifier.
Similarly

QI is the reactive power absorbed by the inverter

B. Converter faults
Natural or line commutation is the process through which
rectifiers convert AC to DC and inverters convert DC to AC.
This process can further be described as the transfer of current
between two converter valves with both valves carrying
current simultaneously. When this process is interrupted by
e.g. faults in the converter station, instability may arise in the
system which can affect the AC side of the HVAC scheme
depending on the duration of the fault and the protection
scheme adopted [9]. Possible location of fault within the
converter station are across a non-conducting valve, across the
bridge DC terminals, ground faults on the Bridge DC
terminals and also ground faults at the DC bus [10].
III.

(1)

SYSTEM MODEL AND RESULTS

V SR BT cos α

(2)

VSI BT cos γ

(3)

DigSILENT power factory was used in the simulations.
From fig.2, the Bing coal plant has two generating stations G3
and G4 which are connected to bus 12 and bus 13 respectively.
Each of the generating stations has a capacity of 1080MW.
Pookland which is on the left side of the network has a total
local generating capacity of 600MW of which 400 is from G2
and the rest if from G1. Furthermore Pookland has two
distribution centers. The first distribution center is at bus 7
which is connected to bus 6 via a 1600MVA 500/11 kV step
down transformer.

(4)

The second distribution center in Pookland is at bus 8 which is
connected to bus 6 via a 1600MVA 500/11 kV step down
transformer. The load at bus 7 is 1064MW while the load at
bus 8 is 1379MW.

Where: B = Number of converter bridges
T = Transformer turns ratio

VDC ( R ) =

RI is the resistance of the Inverter
RL is the resistance of the HVDC Line
IDC is the DC line current
α is the firing angle

VDC ( R ) −V DC ( I )
RR + RL + RI

Where: VDC(R) is the rectifier DC voltage
VSR is the rectifier AC Voltage
VDC(I) is the inverter DC voltage
VSI is the Inverter AC Voltage
γ is the inverter extinction angle
RR is the resistance of the Rectifier

The details of the transmission line data are given in the
appendix. Capacitor banks are connected to Bus 5 and Bus 9
contributing a total reactive power compensation of 1000Mvar.
For the HVDC scheme in fig.3, series rectors each of 0.86H are
connected to each end of the HVDC transmission line. A
combination of two 6-pulse converters is used for the rectifier
end in the Bing coal plant and at the inverter end of the HVDC
transmission line which is in Pookland

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

2
IEEE AFRICON 2009

23 - 25 September 2009, Nairobi, Kenya

In the simulations, generator G1 in Pookland is a slack bus, G2
in Pookland is a PV bus, G3 and G4 in the Bing coal plant are
both set as PV buses.
The converter transformers in fig.3 are connected via remote to
buses 5 and 9 in fig.2.

Fig.4 Case 1: G3 Rotor Angle

Fig. 2 The Entire power network excluding the HVDC scheme

Fig.5 Case 1: G3 Terminal Voltage
The following fig.6 and fig.7 shows the results obtained from
the generator (G2) in Pookland.

Fig. 3 The remote HVDC scheme between the Bing coal
plant (bus 9) and Pookland (Bus 5)

A. Case 1: HVDC Transmission to Pookland
The HVDC transmission line is scheduled to deliver about
2000MW over 500km to Pookland with current control at the
rectifier and extinction angle control at the inverter. The
current order of the rectifier was set at 3.6kA. A 50ms fault
was applied at the DC terminal of the rectifier. The effect of the
DC fault on the rotor angle stability as well as the recovery of
the voltage level at the generating stations in Pookland and the
Bing coal plant is investigated.

Fig.6 Case 1: G2 Rotor Angle

The simulation results obtained for case 1 are given in fig.4 to
fig.7.
Fig.4 and fig.5 show the results obtained from G3.

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

3
IEEE AFRICON 2009

23 - 25 September 2009, Nairobi, Kenya

Fig.8 Case 2: G3 Rotor Angle

Fig.7 Case 1: G2 Voltage
During the 50ms fault applied at the DC side of the terminal,
the two inverters in Pookland went automatically into
blocking mode. This was done to prevent forward current
flowing through the inverter. During this time the rotor angle
of G3 the Bing coal plant increased from -85º to 160º in figure
4 while the terminal voltage dropped to 0.63pu from 1.0 pu in
figure 5. After the fault was cleared, inverter 1 returned to
normal operation and 7ms later, inverter 2 returned to normal
operation while the two rectifiers in the Bing coal plant went
into blocking mode for 5ms and then a commutation failure
lasting for 2msec.
Following this, the rectifier returned to normal operation while
the voltage level at G3 in the Bing coal plant and G2 in
Pookland normalized. It took about 70secs for the rotor angle
of G3 to return to a stable value of -52º with the largest swing
between 170º to
-170º as opposed to G2 in Pookland which
had the largest swing between -86.97º and -86.74º in figure 6
whose oscillations damped out in about 7.5 seconds.

Fig.9 Case 2: G3 Voltage
The following fig.10 and fig.11 shows the results obtained
from the generator in Pookland.

B. Case 2: HVAC/HVDC Transmission to Pookland
The HVDC transmission line is scheduled to deliver about
1000MW over 500km to Pookland with current control at the
rectifier and extinction angle control at the inverter. The
current order of the rectifier was set at 1.8 kA. The HVAC line
transmitted the rest 1000MW.A 50ms fault at the DC terminal
of the rectifier was applied. The effect of the fault on the rotor
angle stability and the recovery of the voltage at the generating
stations are investigated.
The results obtained from the simulation using HVAC/HVDC
transmission to Pookland are given in fig.8 to fig.11.
The following fig.8 and fig.9 show the results obtained from
the generator in the Bing coal Plant.
Fig.10 Case 2: G2 Rotor Angle

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

4
IEEE AFRICON 2009

23 - 25 September 2009, Nairobi, Kenya

Furthermore, the effect of the DC fault was more prominent in
the Bing coal plant as the pu voltage at G3 reduced to 0.63 in
fig. 5 but retuned to its prefault value at 0.3sec after the fault.
In Pookland, there was a sharp increase of the voltage level at
G2 from 1.0pu to 1.025pu which took 1.2sec to drop to a post
fault level of 0.995pu.

Fig.11 Case 2: G2 Voltage
During the 50ms fault induced at the DC side of the terminal,
the two inverters at Pookland went into blocking mode.
During this time, the rotor angle of G3 in the Bing coal plant
decreased from -31º to -54º while the terminal voltage dropped
to 0.64 pu from 1.0 pu. After the fault was cleared, inverter 1
returned to normal operation and 7ms later, inverter 2 returned
to normal operation while the two rectifiers went into blocking
mode for 5ms and then a commutation failure lasting for 2ms
based on the control scheme in operation.
Following this, the two rectifiers returned to normal operation
while the voltage level at G3 in the Bing coal plant and G2 in
Pookland normalized. During this time there was a repeated
return to blocking mode by both rectifier 1 and inverter1. This
occurred six times.
From fig.4 and fig. 8 it can be seen that it took 38sec (almost
half when compared to case 1) for the rotor angle of G3 to
return to its pre fault angle of -44º with the largest swing
between -31º to -54º as opposed to G2 in Pookland which had
the largest swing between -86.96º and -86.81º whose
oscillations damped out in about 30 seconds.
IV.

ANALYSIS AND DISCUSIONS

From the simulation of DC faults on the rectifier end of the
HVDC scheme for the HVDC transmission and HVDCHVAC transmission the following analysis are made:
For the HVDC transmission scheme in case 1, the rectifier DC
fault had a large impact on the generator close to the rectifier
end at the Bing coal plant. The rotor angle of G3 had only one
large step change between 160º and -160º and returned to its
pre fault angle of -80º after 70sec. On the contrary, the
rectifier DC fault had a smaller impact on the rotor angle
displacement of generator G2 which is in Pookland (the
inverter end if the HVDC scheme). G2 had smaller
oscillations between -86.97º and -86.74º which is a very small
range.

For the HVAC-HVDC scheme in case 2, the rectifier DC fault
had a different impact on the generator close to the rectifier
end in the Bing coal plant as compared to case 1. The rotor
angle of G3 had more oscillations with the largest between
-31º and -55º returning to its prefault angle of -44º after 45sec.
On the contrary, the rectifier DC fault had a smaller impact on
the rotor angle displacement of generator G2 which is in
Pookland (the inverter end if the HVDC scheme). G2 had
lesser oscillations between -86.83º and -86.99º which is a very
small range and returned to its prefault angle of -86.89º in
32sec.
Regarding the effect of the DC fault on the voltage profile, G3
in the Bing coal plant had a greater voltage dip of 0.4pu with
few oscillations which stabilized after 5.7sec. In Pookland,
there was a slight increase of the voltage level at G2 from
1.0pu to 1.01pu with large oscillations which took 34sec to
drop to a post fault level of 1.0pu.

V.

OBSERVATIONS

In case 1, the rectifier side has less rotor angle oscillations
when compared to the inverter side, but rectifier side takes
longer than the inverter side for the rotor angle of the relevant
generators to stabilize. The peak to peak amplitude of the rotor
angle oscillation in the Bing coal plant is 300º and that of
Pookland has a high of 0.23º The voltage at G2 in Pookland
(the inverter end) took twice the amount of time it took G3 in
the Bing coal plant to stabilize.
In case 2, the rectifier side had more rotor angle oscillations
when compared to the inverter side and the rectifier side also
takes longer (13sec more than the inverter side) to stabilize
The largest peak to peak amplitude of the multiple rotor angle
oscillation in the Bing coal plant is 24º and that of Pookland
has a high of 0.16º which is 9 times damper than case 1.
Hence when these values are compared with case 1, it can be
seen that the oscillations have been damped in case 2.The
voltage at G2 in Pookland (the inverter end) took six times the
amount of time it took G3 in the Bing coal plant (rectifier end)
to stabilize while the voltage in the Bing coal plant dipped by
0.35pu (smaller than case 1 which dipped by 0.4pu).The
voltage rise in Pookland was about 0.01pu but with 14
oscillations. When compared to case 1, the oscillations are
more but the amplitude of the oscillations is smaller.

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

5
IEEE AFRICON 2009

VI.

23 - 25 September 2009, Nairobi, Kenya

CONCLUSION

From the simulation result, analysis and observations, the
following conclusions are made:Firstly, the rectifier DC faults when a hybrid HVAC-HVDC
transmission line is used for transmission has a smaller impact
on the generators closer to the inverter end as the rotor angle
of the generator has fewer oscillations with reduced
amplitudes. Secondly, the hybrid HVAC- HVDC transmission
line induces more oscillations with lower amplitudes in the
terminal voltage of the generator at the inverter end in
Pookland.

APPENDIX
Table A1: Transmision line Parameters

Line
HVAC
HVDC

Resistance
(Ω/km)
0.028
0.015

Reactance
(Ω/km)
0.325
0.025

Susceptance
(μS/km)
4.35
0.45

Length
(km)
500
500

ACKNOWLEDGMENTS
Munificent thanks to God for sustained life and wisdom, to
our colleagues at the UCT Power System Research Group, to
family and friends for their support, to Eskom for their
financial support and to the beautiful City of Cape Town for
her pseudo-random weather conditions.

REFERENCES
[1]

D T Oyedokun, K.A Folly, “Power Flow studies in HVAC and HVDC
Transmision Lines” , IASTED AfricaPES 2008, Garborone,Botswana,
2008
[2] P Kundar, Power System Stability and Control (McGraw-Hill, Inc,
1993).
[3] Brian K. Johnson, The ABCs of HVDC Transmission Technologies,
IEEE power and energy magazine, March/April 2007.
[4] M Hausler, “Multi terminal HVDC for High Power transmission in
Europe”, Presented at CWPEX99, Pozan, Poland, March 1999.
[5] N.G Hingorani, “High- Voltage DC Transmision: A power electronic
workhorse”, IEEE Spectrun, April 1996.
[6] JM Perez de Andres et all, “Prospects for HVDC- Getting more power
out of the grid”, Jornadas Tecnicas sobre la "Sesion Plenaria Cigre
2006”, Madrid, 29-30 November, 2006
[7] D. T .Oyedokun, “Using DigSILENT and PSCAD for planning and
operation of HVAC-HVDC interconnections”, Bsc (Elec Eng) Thesis,
UCT, 2007.
[8] F. F Wu, “ Technical Considerations for Power Grid Interconnecxtion in
Northeast Asia”, University of Hong Kong and California at Berkely,
http://www.nautilus.org/archives/energy/grid/abstracts/wu_technical.pdf
April 27th, 2009.
[9] D. A. Woodford, “HVDC Transmission”, Manitoba HVDC research
center, Canada, 1998
[10] J Arillaga , “High Voltage Direct Current Transmission”, Peter
Peregrinus Ltd. London, UK, 1983, pp 158-173.

978-1-4244-3919-5/09/$25.00 ©2009 IEEE

6

More Related Content

What's hot

Chapter 6 dc motor speed control
Chapter 6 dc motor speed controlChapter 6 dc motor speed control
Chapter 6 dc motor speed control
Hattori Sidek
 
doubley fed induction motor
doubley fed induction motordoubley fed induction motor
doubley fed induction motor
usic123
 

What's hot (19)

Chapter 6 dc motor speed control
Chapter 6 dc motor speed controlChapter 6 dc motor speed control
Chapter 6 dc motor speed control
 
Traction Motors and Control
Traction Motors and ControlTraction Motors and Control
Traction Motors and Control
 
Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
RGPV DIPLOMA EX305 UNIT III
RGPV DIPLOMA EX305 UNIT IIIRGPV DIPLOMA EX305 UNIT III
RGPV DIPLOMA EX305 UNIT III
 
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
Power Factor Correction with Current Controlled Buck Converter for BLDC Motor...
 
Ijertv2 is2554
Ijertv2 is2554Ijertv2 is2554
Ijertv2 is2554
 
Drives lec 11_12_Braking of DC Motors
Drives lec 11_12_Braking of DC MotorsDrives lec 11_12_Braking of DC Motors
Drives lec 11_12_Braking of DC Motors
 
Modelling and Simulation of DFIG for Wind Energy Generation Using Stator Volt...
Modelling and Simulation of DFIG for Wind Energy Generation Using Stator Volt...Modelling and Simulation of DFIG for Wind Energy Generation Using Stator Volt...
Modelling and Simulation of DFIG for Wind Energy Generation Using Stator Volt...
 
Commanding Doubly-Fed Induction Generator (DFIG) to Decouple Active and React...
Commanding Doubly-Fed Induction Generator (DFIG) to Decouple Active and React...Commanding Doubly-Fed Induction Generator (DFIG) to Decouple Active and React...
Commanding Doubly-Fed Induction Generator (DFIG) to Decouple Active and React...
 
load test on dc compound generator (long shunt)
load test on dc compound generator (long shunt)load test on dc compound generator (long shunt)
load test on dc compound generator (long shunt)
 
Synchronous generator
Synchronous generatorSynchronous generator
Synchronous generator
 
RGPV EX503 UNIT II
RGPV EX503 UNIT IIRGPV EX503 UNIT II
RGPV EX503 UNIT II
 
Infinite bus bar in power system
Infinite bus bar in power systemInfinite bus bar in power system
Infinite bus bar in power system
 
Improvement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK ConverterImprovement In Pre-Regulation For Power Factor Using CUK Converter
Improvement In Pre-Regulation For Power Factor Using CUK Converter
 
Drives lec 15_16_Armature Voltage based Speed Control Methods
Drives lec 15_16_Armature Voltage based Speed Control MethodsDrives lec 15_16_Armature Voltage based Speed Control Methods
Drives lec 15_16_Armature Voltage based Speed Control Methods
 
Electrical Drive & Traction (Their Control)
Electrical Drive & Traction (Their Control)Electrical Drive & Traction (Their Control)
Electrical Drive & Traction (Their Control)
 
doubley fed induction motor
doubley fed induction motordoubley fed induction motor
doubley fed induction motor
 
ENERGY EFFICIENT VARIABLE SPEED HIGH POWER FACTOR THREE PHASE INDUCTION MOTOR...
ENERGY EFFICIENT VARIABLE SPEED HIGH POWER FACTOR THREE PHASE INDUCTION MOTOR...ENERGY EFFICIENT VARIABLE SPEED HIGH POWER FACTOR THREE PHASE INDUCTION MOTOR...
ENERGY EFFICIENT VARIABLE SPEED HIGH POWER FACTOR THREE PHASE INDUCTION MOTOR...
 

Viewers also liked

Unit 1 prinsip dasar listrik
Unit 1 prinsip dasar listrikUnit 1 prinsip dasar listrik
Unit 1 prinsip dasar listrik
Indra S Wahyudi
 
PowerWorld 15. Transient Stability Quickstart
PowerWorld 15. Transient Stability QuickstartPowerWorld 15. Transient Stability Quickstart
PowerWorld 15. Transient Stability Quickstart
J. FR
 
Dasar pembangkit dan pengukuran teknik tegangan tinggi
Dasar pembangkit dan pengukuran teknik tegangan tinggiDasar pembangkit dan pengukuran teknik tegangan tinggi
Dasar pembangkit dan pengukuran teknik tegangan tinggi
Indra S Wahyudi
 
Voltage regulation
Voltage regulationVoltage regulation
Voltage regulation
popet
 

Viewers also liked (20)

Instalasi motor 3 fasa
Instalasi motor 3 fasaInstalasi motor 3 fasa
Instalasi motor 3 fasa
 
Proteus Project : Arduino programming for LED
Proteus Project : Arduino programming for LEDProteus Project : Arduino programming for LED
Proteus Project : Arduino programming for LED
 
petunjuk praktis penelitian ilmiah
petunjuk praktis penelitian ilmiahpetunjuk praktis penelitian ilmiah
petunjuk praktis penelitian ilmiah
 
Impact of dynamic system modelling on the power stability of hvdc systems
Impact of dynamic system modelling on the power stability of hvdc systemsImpact of dynamic system modelling on the power stability of hvdc systems
Impact of dynamic system modelling on the power stability of hvdc systems
 
Unit 5 daya ac
Unit 5  daya acUnit 5  daya ac
Unit 5 daya ac
 
ADR34xx Micro-Power, High-Accuracy Voltage References
ADR34xx Micro-Power, High-Accuracy Voltage ReferencesADR34xx Micro-Power, High-Accuracy Voltage References
ADR34xx Micro-Power, High-Accuracy Voltage References
 
Elektronika Daya - Statcom
Elektronika Daya - StatcomElektronika Daya - Statcom
Elektronika Daya - Statcom
 
PROTEUS - ARDUNIO PROGRAMMING FOR LCD
PROTEUS - ARDUNIO PROGRAMMING FOR LCDPROTEUS - ARDUNIO PROGRAMMING FOR LCD
PROTEUS - ARDUNIO PROGRAMMING FOR LCD
 
Unit 1 prinsip dasar listrik
Unit 1 prinsip dasar listrikUnit 1 prinsip dasar listrik
Unit 1 prinsip dasar listrik
 
Teknologi sistem pengendalian tenaga listrik berbasis scada
Teknologi sistem pengendalian tenaga listrik berbasis scadaTeknologi sistem pengendalian tenaga listrik berbasis scada
Teknologi sistem pengendalian tenaga listrik berbasis scada
 
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVECTRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVEC
 
Power quality 5
Power quality 5Power quality 5
Power quality 5
 
PowerWorld 15. Transient Stability Quickstart
PowerWorld 15. Transient Stability QuickstartPowerWorld 15. Transient Stability Quickstart
PowerWorld 15. Transient Stability Quickstart
 
Presentation
PresentationPresentation
Presentation
 
Power System Stablity
Power System StablityPower System Stablity
Power System Stablity
 
Transient stability analysis and enhancement of ieee 9 bus system
Transient stability analysis and enhancement of ieee  9 bus system Transient stability analysis and enhancement of ieee  9 bus system
Transient stability analysis and enhancement of ieee 9 bus system
 
Control of hvdc system 1
Control of hvdc system 1Control of hvdc system 1
Control of hvdc system 1
 
Circuit analysis i with matlab computing and simulink sim powersystems modeling
Circuit analysis i with matlab computing and simulink sim powersystems modelingCircuit analysis i with matlab computing and simulink sim powersystems modeling
Circuit analysis i with matlab computing and simulink sim powersystems modeling
 
Dasar pembangkit dan pengukuran teknik tegangan tinggi
Dasar pembangkit dan pengukuran teknik tegangan tinggiDasar pembangkit dan pengukuran teknik tegangan tinggi
Dasar pembangkit dan pengukuran teknik tegangan tinggi
 
Voltage regulation
Voltage regulationVoltage regulation
Voltage regulation
 

Similar to Effect of converter dc fault on the transient stability of a multi machine power system with hvdc transmission lines

Modelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission SystemModelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission System
ijtsrd
 

Similar to Effect of converter dc fault on the transient stability of a multi machine power system with hvdc transmission lines (20)

Jz3517311738
Jz3517311738Jz3517311738
Jz3517311738
 
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
Improving Fault Ride ThroughCapabilities For Offshore PMSG Wind Farms Connect...
 
seminar report on vsc-hvdc poornima college of engineering
seminar report on vsc-hvdc poornima college of engineeringseminar report on vsc-hvdc poornima college of engineering
seminar report on vsc-hvdc poornima college of engineering
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid GenerationPerformance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
 
A ZVS Interleaved Boost AC/DC Converter Using Super Capacitor Power for Hybri...
A ZVS Interleaved Boost AC/DC Converter Using Super Capacitor Power for Hybri...A ZVS Interleaved Boost AC/DC Converter Using Super Capacitor Power for Hybri...
A ZVS Interleaved Boost AC/DC Converter Using Super Capacitor Power for Hybri...
 
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
The Operation of the GCCIA HVDC Project and Its Potential Impacts on the Elec...
 
220v gss working modelFinal report
220v gss working modelFinal report220v gss working modelFinal report
220v gss working modelFinal report
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Modelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission SystemModelling and Operation of HVDC Based Power Transmission System
Modelling and Operation of HVDC Based Power Transmission System
 
Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...Autonomous microgrid based parallel inverters using droop controller for impr...
Autonomous microgrid based parallel inverters using droop controller for impr...
 
Conceptual study on Grid-to-Vehicle (G2V) wireless power transfer using singl...
Conceptual study on Grid-to-Vehicle (G2V) wireless power transfer using singl...Conceptual study on Grid-to-Vehicle (G2V) wireless power transfer using singl...
Conceptual study on Grid-to-Vehicle (G2V) wireless power transfer using singl...
 
Hvdc
HvdcHvdc
Hvdc
 
Modeling and Analysis of Transformerless High Gain Buck-boost DC-DC Converters
Modeling and Analysis of Transformerless High Gain Buck-boost DC-DC ConvertersModeling and Analysis of Transformerless High Gain Buck-boost DC-DC Converters
Modeling and Analysis of Transformerless High Gain Buck-boost DC-DC Converters
 
Source-load-variable voltage regulated cascaded DC/DC converter for a DC mic...
Source-load-variable voltage regulated cascaded DC/DC  converter for a DC mic...Source-load-variable voltage regulated cascaded DC/DC  converter for a DC mic...
Source-load-variable voltage regulated cascaded DC/DC converter for a DC mic...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
 
azadar_training
azadar_trainingazadar_training
azadar_training
 
Hvdc transmission
Hvdc transmissionHvdc transmission
Hvdc transmission
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 

More from Indra S Wahyudi (8)

Power system and communication network co simulation for smart grid applications
Power system and communication network co simulation for smart grid applicationsPower system and communication network co simulation for smart grid applications
Power system and communication network co simulation for smart grid applications
 
vsc hvdc fuzzy controller for improving the stability of acdc power system
vsc hvdc fuzzy controller for improving the stability of acdc power systemvsc hvdc fuzzy controller for improving the stability of acdc power system
vsc hvdc fuzzy controller for improving the stability of acdc power system
 
teknik tenaga listrik
teknik tenaga listrikteknik tenaga listrik
teknik tenaga listrik
 
Unit 6 rangkaian tiga fase
Unit 6  rangkaian tiga faseUnit 6  rangkaian tiga fase
Unit 6 rangkaian tiga fase
 
Unit 6 rangkaian tiga fase
Unit 6  rangkaian tiga faseUnit 6  rangkaian tiga fase
Unit 6 rangkaian tiga fase
 
Unit 4 rangkaian satu fase
Unit 4  rangkaian satu faseUnit 4  rangkaian satu fase
Unit 4 rangkaian satu fase
 
Unit 3 dasar listrik ac
Unit 3  dasar listrik acUnit 3  dasar listrik ac
Unit 3 dasar listrik ac
 
Unit 2 rangkaian dc
Unit 2  rangkaian dcUnit 2  rangkaian dc
Unit 2 rangkaian dc
 

Recently uploaded

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 

Effect of converter dc fault on the transient stability of a multi machine power system with hvdc transmission lines

  • 1. IEEE AFRICON 2009 23 - 25 September 2009, Nairobi, Kenya Effect of Converter DC fault on the Transient Stability of a Multi-Machine Power System with HVDC Transmission lines 1 D.T. Oyedokun MIEEE, 2K. A. Folly MIEEE, 3S.P. Chowdhury MIEEE Department of Electrical Engineering University of Cape Town Cape Town, South Africa. 1 davoyedokun@ieee.org, 2komla.folly@uct.ac.za, 3sp.chowdhury@uct.ac.za Abstract—This paper deals with the effect of DC faults on the transient stability of a Multi-Machine Power System with two transmission line configurations; HVDC and a hybrid HVACHVDC transmission line. The faults are located at the DC terminals of the HVDC converter station. In order to carry out this study, two case studies are presented. In the first case study a double HVDC transmission line is used to transmit 2000MW to an area of the power system called Pookland which has a total load demand of 2440MW. In case two, a parallel hybrid HVACHVDC transmission line is used to transmit the same amount of power to Pookland. In both cases, the impact of a short term converter DC fault on the transient stability of the entire system was investigated. This was done by studying the response of the rotor angle of G2 in Pookland, G3 in the Bing Coal plant and the voltage profile at the terminals of the generators to the DC fault at the HVDC converter station. Amongst other results, it was established that in case 1 which has a double HVDC transmission line, the rectifier side (in the Bing coal plant) has less rotor angle oscillations when compared to the inverter side (in Pookland), but the rectifier side took longer than the inverter side for the rotor angle of the generators to stabilize. In case 2, the voltage at G2 in Pookland took six times the amount of time it took G3 in the Bing coal plant to stabilize while the voltage in the Bing Coal plant dipped by 0.35pu (smaller than case 1 which dipped by 0.4pu). In conclusion, the converter DC fault had a smaller impact on the transient stability of the Multi-Machine power system when the hybrid HVAC-HVDC transmission line was adopted. Keywords-component; HVDC, HVAC, Hybrid HVAC-HVDC transient stability, transmisison, rotor angle I. INTRODUCTION The ability of a power system to withstand and recover from system faults in a fast and successfully manner is critical to the stability of the power system. According to [1], the use of High Voltage Direct Current (HVDC) transmission for long distance applications has seen an increase due to the following reasons: • It is a more economical mode of power transfer as compared to HVAC over long distances exceeding 500km [2]. • HVDC transmission lines (i.e. submarine, underground and overhead transmission lines) do not make use of the three phase cables used in HVAC transmission therefore, the power losses incurred in the DC lines are lower than that of AC lines. • HVDC can be used to interconnect asynchronous systems. Examples of such connections are in North America, between the South-West Power Pool (SPP) and also between Quebec and its neighbors (New England and the Maritimes) [3]. Large HVDC schemes exist worldwide. These include the pacific intertie which has a total of 3100MW over a distance of 1360km and the Hydro Quebec New England link [4]. Itaipu in Brazil has an HVDC scheme of 6300MW, the cross channel UK- France scheme has a capacity of 2000MW, Wybord in Russia has a capacity of 1050MW. The scheme between North and south Islands of New Zealand is 1240MW and the CahoraBassa Hydro scheme between Mozambique and South Africa has a Capacity of 1920MW [5]. As of 2005, the worldwide installed HVDC capacity was 55GW which is 1.4% of the worldwide installed generation capacity [6]. HVDC is obtained directly from High Voltage Alternating Current (HVAC) through the use of HVDC converters and their associated devices like filters, reactors and capacitor banks which provide reactive power support for the HVDC converters. In most HVDC schemes around the world, the 12 pulse thyristor converter configuration has been adopted to reduce the requirements for smoothing the DC waveform [7]. With regards to power system stability, it has been stated that the use of HVDC transmission lines in parallel with HVAC transmission lines increases the strength and the stability of the system. An example of such an interconnection is the Pacific Intertie in California and Oregon [8]. 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 1
  • 2. IEEE AFRICON 2009 23 - 25 September 2009, Nairobi, Kenya As faults on HVDC converter stations could lead to instability in the power system, this paper looks at the effect of converter DC faults on the rotor angle of the generators for a multimachine power system. This is done by looking at two transmission line configurations between the Bing Coal plant and Pookland as indicated in fig.2 while a DC fault is induced in the converter station. Firstly, a double HVDC transmission line is considered for transmission and secondly, parallel transmission using hybrid HVAC-HVDC is considered. In each of the configurations, a 50msec fault is applied on the rectifier DC terminal. The effect of this fault on the rotor angle of the generator G1 in Pookland and generator G3 in the Bing coal plant are investigated. II. CONVERTER FAULTS AND EQUATIONS A. Converter Equations Fig.1 shows the schematics of the rectifier side of a HVDC scheme. Fig.1 Rectifier side of a HVDC scheme V DC = 3 2 π VS BT cos α VDC ( I ) = I DC = 3 2 π 3 2 π From (3) and (4), the DC power output from the rectifier is given as follows: PDC = V DC ( R ) ⋅ I DC (5) QR = PDC ⋅ tan(α ) (6) Where QR is the reactive power absorbed by the rectifier. Similarly QI is the reactive power absorbed by the inverter B. Converter faults Natural or line commutation is the process through which rectifiers convert AC to DC and inverters convert DC to AC. This process can further be described as the transfer of current between two converter valves with both valves carrying current simultaneously. When this process is interrupted by e.g. faults in the converter station, instability may arise in the system which can affect the AC side of the HVAC scheme depending on the duration of the fault and the protection scheme adopted [9]. Possible location of fault within the converter station are across a non-conducting valve, across the bridge DC terminals, ground faults on the Bridge DC terminals and also ground faults at the DC bus [10]. III. (1) SYSTEM MODEL AND RESULTS V SR BT cos α (2) VSI BT cos γ (3) DigSILENT power factory was used in the simulations. From fig.2, the Bing coal plant has two generating stations G3 and G4 which are connected to bus 12 and bus 13 respectively. Each of the generating stations has a capacity of 1080MW. Pookland which is on the left side of the network has a total local generating capacity of 600MW of which 400 is from G2 and the rest if from G1. Furthermore Pookland has two distribution centers. The first distribution center is at bus 7 which is connected to bus 6 via a 1600MVA 500/11 kV step down transformer. (4) The second distribution center in Pookland is at bus 8 which is connected to bus 6 via a 1600MVA 500/11 kV step down transformer. The load at bus 7 is 1064MW while the load at bus 8 is 1379MW. Where: B = Number of converter bridges T = Transformer turns ratio VDC ( R ) = RI is the resistance of the Inverter RL is the resistance of the HVDC Line IDC is the DC line current α is the firing angle VDC ( R ) −V DC ( I ) RR + RL + RI Where: VDC(R) is the rectifier DC voltage VSR is the rectifier AC Voltage VDC(I) is the inverter DC voltage VSI is the Inverter AC Voltage γ is the inverter extinction angle RR is the resistance of the Rectifier The details of the transmission line data are given in the appendix. Capacitor banks are connected to Bus 5 and Bus 9 contributing a total reactive power compensation of 1000Mvar. For the HVDC scheme in fig.3, series rectors each of 0.86H are connected to each end of the HVDC transmission line. A combination of two 6-pulse converters is used for the rectifier end in the Bing coal plant and at the inverter end of the HVDC transmission line which is in Pookland 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 2
  • 3. IEEE AFRICON 2009 23 - 25 September 2009, Nairobi, Kenya In the simulations, generator G1 in Pookland is a slack bus, G2 in Pookland is a PV bus, G3 and G4 in the Bing coal plant are both set as PV buses. The converter transformers in fig.3 are connected via remote to buses 5 and 9 in fig.2. Fig.4 Case 1: G3 Rotor Angle Fig. 2 The Entire power network excluding the HVDC scheme Fig.5 Case 1: G3 Terminal Voltage The following fig.6 and fig.7 shows the results obtained from the generator (G2) in Pookland. Fig. 3 The remote HVDC scheme between the Bing coal plant (bus 9) and Pookland (Bus 5) A. Case 1: HVDC Transmission to Pookland The HVDC transmission line is scheduled to deliver about 2000MW over 500km to Pookland with current control at the rectifier and extinction angle control at the inverter. The current order of the rectifier was set at 3.6kA. A 50ms fault was applied at the DC terminal of the rectifier. The effect of the DC fault on the rotor angle stability as well as the recovery of the voltage level at the generating stations in Pookland and the Bing coal plant is investigated. Fig.6 Case 1: G2 Rotor Angle The simulation results obtained for case 1 are given in fig.4 to fig.7. Fig.4 and fig.5 show the results obtained from G3. 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 3
  • 4. IEEE AFRICON 2009 23 - 25 September 2009, Nairobi, Kenya Fig.8 Case 2: G3 Rotor Angle Fig.7 Case 1: G2 Voltage During the 50ms fault applied at the DC side of the terminal, the two inverters in Pookland went automatically into blocking mode. This was done to prevent forward current flowing through the inverter. During this time the rotor angle of G3 the Bing coal plant increased from -85º to 160º in figure 4 while the terminal voltage dropped to 0.63pu from 1.0 pu in figure 5. After the fault was cleared, inverter 1 returned to normal operation and 7ms later, inverter 2 returned to normal operation while the two rectifiers in the Bing coal plant went into blocking mode for 5ms and then a commutation failure lasting for 2msec. Following this, the rectifier returned to normal operation while the voltage level at G3 in the Bing coal plant and G2 in Pookland normalized. It took about 70secs for the rotor angle of G3 to return to a stable value of -52º with the largest swing between 170º to -170º as opposed to G2 in Pookland which had the largest swing between -86.97º and -86.74º in figure 6 whose oscillations damped out in about 7.5 seconds. Fig.9 Case 2: G3 Voltage The following fig.10 and fig.11 shows the results obtained from the generator in Pookland. B. Case 2: HVAC/HVDC Transmission to Pookland The HVDC transmission line is scheduled to deliver about 1000MW over 500km to Pookland with current control at the rectifier and extinction angle control at the inverter. The current order of the rectifier was set at 1.8 kA. The HVAC line transmitted the rest 1000MW.A 50ms fault at the DC terminal of the rectifier was applied. The effect of the fault on the rotor angle stability and the recovery of the voltage at the generating stations are investigated. The results obtained from the simulation using HVAC/HVDC transmission to Pookland are given in fig.8 to fig.11. The following fig.8 and fig.9 show the results obtained from the generator in the Bing coal Plant. Fig.10 Case 2: G2 Rotor Angle 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 4
  • 5. IEEE AFRICON 2009 23 - 25 September 2009, Nairobi, Kenya Furthermore, the effect of the DC fault was more prominent in the Bing coal plant as the pu voltage at G3 reduced to 0.63 in fig. 5 but retuned to its prefault value at 0.3sec after the fault. In Pookland, there was a sharp increase of the voltage level at G2 from 1.0pu to 1.025pu which took 1.2sec to drop to a post fault level of 0.995pu. Fig.11 Case 2: G2 Voltage During the 50ms fault induced at the DC side of the terminal, the two inverters at Pookland went into blocking mode. During this time, the rotor angle of G3 in the Bing coal plant decreased from -31º to -54º while the terminal voltage dropped to 0.64 pu from 1.0 pu. After the fault was cleared, inverter 1 returned to normal operation and 7ms later, inverter 2 returned to normal operation while the two rectifiers went into blocking mode for 5ms and then a commutation failure lasting for 2ms based on the control scheme in operation. Following this, the two rectifiers returned to normal operation while the voltage level at G3 in the Bing coal plant and G2 in Pookland normalized. During this time there was a repeated return to blocking mode by both rectifier 1 and inverter1. This occurred six times. From fig.4 and fig. 8 it can be seen that it took 38sec (almost half when compared to case 1) for the rotor angle of G3 to return to its pre fault angle of -44º with the largest swing between -31º to -54º as opposed to G2 in Pookland which had the largest swing between -86.96º and -86.81º whose oscillations damped out in about 30 seconds. IV. ANALYSIS AND DISCUSIONS From the simulation of DC faults on the rectifier end of the HVDC scheme for the HVDC transmission and HVDCHVAC transmission the following analysis are made: For the HVDC transmission scheme in case 1, the rectifier DC fault had a large impact on the generator close to the rectifier end at the Bing coal plant. The rotor angle of G3 had only one large step change between 160º and -160º and returned to its pre fault angle of -80º after 70sec. On the contrary, the rectifier DC fault had a smaller impact on the rotor angle displacement of generator G2 which is in Pookland (the inverter end if the HVDC scheme). G2 had smaller oscillations between -86.97º and -86.74º which is a very small range. For the HVAC-HVDC scheme in case 2, the rectifier DC fault had a different impact on the generator close to the rectifier end in the Bing coal plant as compared to case 1. The rotor angle of G3 had more oscillations with the largest between -31º and -55º returning to its prefault angle of -44º after 45sec. On the contrary, the rectifier DC fault had a smaller impact on the rotor angle displacement of generator G2 which is in Pookland (the inverter end if the HVDC scheme). G2 had lesser oscillations between -86.83º and -86.99º which is a very small range and returned to its prefault angle of -86.89º in 32sec. Regarding the effect of the DC fault on the voltage profile, G3 in the Bing coal plant had a greater voltage dip of 0.4pu with few oscillations which stabilized after 5.7sec. In Pookland, there was a slight increase of the voltage level at G2 from 1.0pu to 1.01pu with large oscillations which took 34sec to drop to a post fault level of 1.0pu. V. OBSERVATIONS In case 1, the rectifier side has less rotor angle oscillations when compared to the inverter side, but rectifier side takes longer than the inverter side for the rotor angle of the relevant generators to stabilize. The peak to peak amplitude of the rotor angle oscillation in the Bing coal plant is 300º and that of Pookland has a high of 0.23º The voltage at G2 in Pookland (the inverter end) took twice the amount of time it took G3 in the Bing coal plant to stabilize. In case 2, the rectifier side had more rotor angle oscillations when compared to the inverter side and the rectifier side also takes longer (13sec more than the inverter side) to stabilize The largest peak to peak amplitude of the multiple rotor angle oscillation in the Bing coal plant is 24º and that of Pookland has a high of 0.16º which is 9 times damper than case 1. Hence when these values are compared with case 1, it can be seen that the oscillations have been damped in case 2.The voltage at G2 in Pookland (the inverter end) took six times the amount of time it took G3 in the Bing coal plant (rectifier end) to stabilize while the voltage in the Bing coal plant dipped by 0.35pu (smaller than case 1 which dipped by 0.4pu).The voltage rise in Pookland was about 0.01pu but with 14 oscillations. When compared to case 1, the oscillations are more but the amplitude of the oscillations is smaller. 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 5
  • 6. IEEE AFRICON 2009 VI. 23 - 25 September 2009, Nairobi, Kenya CONCLUSION From the simulation result, analysis and observations, the following conclusions are made:Firstly, the rectifier DC faults when a hybrid HVAC-HVDC transmission line is used for transmission has a smaller impact on the generators closer to the inverter end as the rotor angle of the generator has fewer oscillations with reduced amplitudes. Secondly, the hybrid HVAC- HVDC transmission line induces more oscillations with lower amplitudes in the terminal voltage of the generator at the inverter end in Pookland. APPENDIX Table A1: Transmision line Parameters Line HVAC HVDC Resistance (Ω/km) 0.028 0.015 Reactance (Ω/km) 0.325 0.025 Susceptance (μS/km) 4.35 0.45 Length (km) 500 500 ACKNOWLEDGMENTS Munificent thanks to God for sustained life and wisdom, to our colleagues at the UCT Power System Research Group, to family and friends for their support, to Eskom for their financial support and to the beautiful City of Cape Town for her pseudo-random weather conditions. REFERENCES [1] D T Oyedokun, K.A Folly, “Power Flow studies in HVAC and HVDC Transmision Lines” , IASTED AfricaPES 2008, Garborone,Botswana, 2008 [2] P Kundar, Power System Stability and Control (McGraw-Hill, Inc, 1993). [3] Brian K. Johnson, The ABCs of HVDC Transmission Technologies, IEEE power and energy magazine, March/April 2007. [4] M Hausler, “Multi terminal HVDC for High Power transmission in Europe”, Presented at CWPEX99, Pozan, Poland, March 1999. [5] N.G Hingorani, “High- Voltage DC Transmision: A power electronic workhorse”, IEEE Spectrun, April 1996. [6] JM Perez de Andres et all, “Prospects for HVDC- Getting more power out of the grid”, Jornadas Tecnicas sobre la "Sesion Plenaria Cigre 2006”, Madrid, 29-30 November, 2006 [7] D. T .Oyedokun, “Using DigSILENT and PSCAD for planning and operation of HVAC-HVDC interconnections”, Bsc (Elec Eng) Thesis, UCT, 2007. [8] F. F Wu, “ Technical Considerations for Power Grid Interconnecxtion in Northeast Asia”, University of Hong Kong and California at Berkely, http://www.nautilus.org/archives/energy/grid/abstracts/wu_technical.pdf April 27th, 2009. [9] D. A. Woodford, “HVDC Transmission”, Manitoba HVDC research center, Canada, 1998 [10] J Arillaga , “High Voltage Direct Current Transmission”, Peter Peregrinus Ltd. London, UK, 1983, pp 158-173. 978-1-4244-3919-5/09/$25.00 ©2009 IEEE 6