SlideShare a Scribd company logo
1 of 26
LINN COVE VIADUCT
CARRIES: Blue Ridge Parkway
CROSSES: Grandfather Mountain
OWNER: National Park Service
MAINTAINED BY: National Park Service
DESIGN: Segmental bridge
MATERIAL: Concrete
TOTAL LENGTH: 1,243 feet (379 m)
WIDTH: 39.5 feet (12.0 m)
LOCATION: GRANDFATHER MOUNTAIN
LONGEST SPAN:180.1 feet (54.9 m)
DESIGNER:
Figg & Muller
Engineering Group
CONSTRUCTED
BY:
Jasper Construction
Co.
CONSTRUCTION
START:
1979
CONSTRUCTION
END:
1987
CONSTRUCTION
COST:
$10 million
INAUGURATED: September 11, 1987
 Grandfather Mountain's delicate ecological system and
unusually large number of globally imperiled ecosystem was
cause for concern when plans for building this section of the
Parkway started. They had to protect the special
environment of Grandfather Mountain. The engineers were
presented with the challenge of building a road without
damaging one of the world's oldest mountains.
The viaduct was designed by Figg and Muller who
took painstaking measures to leave the smallest
ecological footprint possible when designing and
building the viaduct.
ESTABLISHING THE ROUTE
The exact route
location of this
segment, commonly
referred to as the
"MISSING LINK.”
 National Park Service landscape
architects and Federal Highway
Administration engineers agreed the
road should be elevated, or bridged,
where possible to eliminate massive
cuts and fills. Figg and Muller
Engineers, Inc. developed the bridge
design and construction method. The
result: the Linn Cove Viaduct at
milepost 304.6, the most complicated
concrete bridge ever built, snaking
around boulder-strewn Linn Cove in a
sweeping “S” curve.
CONSTRUCTION OF LINN COVE VIADUCT
In order to prevent environmental
damage and to allow construction
to continue during severe winter
weather, builders pre-cast sections
indoors a few miles from the site
using a process known as "match
casting." Each new segment was
cast against the segment
preceding it.
 The bridge's segments were precast
at an indoor facility and transported to
the bridge site, where each section
was lowered into place by a custom
crane placed on either edge of the
existing structure.
The viaduct itself was the
only access road for
construction. Each pre-cast
section was lowered by a
stiff-leg crane and epoxied
into position against the
preceding segment. Steel
cables threaded through the
segments secured the entire
bridge deck.
 The viaduct was constructed from the top
down to minimize disturbance to the
natural environment. This method
eliminated the need for a "pioneer road"
and heavy equipment on the ground. The
only construction that occurred at ground
level was the drilling of foundations for
the seven permanent piers, on which the
Viaduct rests. Exposed rock was covered
to prevent staining from concrete, epoxy,
or grout. Tinted with iron oxide, the
concrete blends in with the existing rock
outcroppings. The only trees cut were
those directly beneath the
superstructure.
Linn Cove Viaduct.
Placement of its
foundations were
determined by the
location of the numerous
boulders its built around.
TIMELINE OF COMPLETION
 Although the Blue Ridge Parkway’s construction
began in 1935, construction of the Linn Cove
Viaduct was delayed until 1979, when Congress
finally approved funding. In the meantime, other
portions of the "missing link," most of them north of
the Viaduct, were completed bit-by-bit between 1968
and 1987
LINN COVE VIADUCT:
THE MOST ENVIRONMENT FRIENDLY BRIDGE
 The Viaduct was built to minimize
the damage that a traditional cut-
and-fill road would have caused to
Grandfather Mountain.
 Supported by seven massive
pillars, the viaduct almost floats in
the air without disturbing the land
below.
 To eliminate damage to the
environment, no access roads
were built for transporting heavy
equipment on the ground.
 This seven-mile section of the
Blue Ridge Parkway was
delayed for twenty years as
environmentalists, adjacent
landowners, engineers, and
architects sought a design that
would preserve and protect the
fragile habitat of adjacent
Grandfather Mountain.
 Recognized internationally as an engineering marvel.
 The most complicated bridge ever built
 An accessible paved trail
begins at the visitor center
and leads to a beautiful view
of the Viaduct from
underneath, and gives hikers
access to the Tanawha Trail.
 Linn Cove Viaduct, sometimes called the “missing link”
 Provides not only one of the most iconic views of the
Parkway, but a rich history as well
 The Linn Cove Viaduct is a beautiful reminder of the historical
cooperation between the government and its citizens, as well
as the beginning of environmentally conscious development
and natural resource conservation as we know it today.
F O R
1. CARRIES
2. CROSSES
3. OWNER
4. MAINTAINED BY
5. DESIGN
6. MATERIAL
7. TOTAL LENGTH
8. WIDTH
9. LONGEST SPAN
10. DESIGNER
11. CONSTRUCTED BY
12. CONSTRUCTION START
13. CONSTRUCTION END
14. CONSTRUCTION COST
15. INAUGURATED
TEST I:
In order to prevent environmental damage and to allow
construction to continue during severe winter weather,
builders pre-cast sections indoors a few miles from the
site using a process known as 1.____________.
The viaduct was designed by 2._____ and 3._____ who
took painstaking measures to leave the smallest
ecological footprint possible when designing and building
the viaduct.
TEST II: FILL IN THE BLANKS (2pts each)
4._______ delicate ecological system and unusually
large number of globally imperiled ecosystem was cause
for concern when plans for building this section of the
Parkway started. They had to protect the special
environment of Grandfather Mountain. The engineers
were presented with the challenge of building a road
without damaging one of the world's oldest mountains.
5,_______ landscape architects and 6.______
engineers agreed the road should be 7.______ , or
bridged, where possible to eliminate massive 8.______
and 9.______ . Figg and Muller Engineers, Inc.
developed the bridge design and construction method.
The result: the most complicated concrete bridge ever
built, snaking around boulder-strewn LINN COVE in a
sweeping 10._______ curve.
TEST III: (15pts.)
1. EXPLAIN why the LINN COVE
VIADUCT is considered as the most
environment friendly bridge.

More Related Content

Similar to Linn Cove Viaduct

Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge constructionNouman Tahir
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Ankur Saxena
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows MeanderTony Smith
 
The Destruction and Reconstruction of a City Street: The Cork Street Corridor
The Destruction and Reconstruction of a City Street: The Cork Street CorridorThe Destruction and Reconstruction of a City Street: The Cork Street Corridor
The Destruction and Reconstruction of a City Street: The Cork Street Corridorkieran rose
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridgeBismillah Arif
 
A Comparable Study Of Station Bridge, Steel
A Comparable Study Of Station Bridge, SteelA Comparable Study Of Station Bridge, Steel
A Comparable Study Of Station Bridge, SteelSimon Lapinski
 
Case StudyManaging Projects from Start to CompletionThe Rivers.docx
Case StudyManaging Projects from Start to CompletionThe Rivers.docxCase StudyManaging Projects from Start to CompletionThe Rivers.docx
Case StudyManaging Projects from Start to CompletionThe Rivers.docxtroutmanboris
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration ProjectFairfax County
 
Akashi kaikyo bridge
Akashi kaikyo bridgeAkashi kaikyo bridge
Akashi kaikyo bridgeAhsan Tonu
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardinerEast
 
First assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfFirst assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfSalamudinSadat1
 
Ben marshman confederation bridge 20130310
Ben marshman confederation bridge 20130310Ben marshman confederation bridge 20130310
Ben marshman confederation bridge 20130310mrzislion
 
Assignment 2
Assignment 2Assignment 2
Assignment 2Lisa Cain
 
Engineering mistakes in the world
Engineering mistakes in the worldEngineering mistakes in the world
Engineering mistakes in the worldAnishaJalathota
 

Similar to Linn Cove Viaduct (20)

Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
 
Golden gate bridge
Golden gate bridgeGolden gate bridge
Golden gate bridge
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows Meander
 
The Destruction and Reconstruction of a City Street: The Cork Street Corridor
The Destruction and Reconstruction of a City Street: The Cork Street CorridorThe Destruction and Reconstruction of a City Street: The Cork Street Corridor
The Destruction and Reconstruction of a City Street: The Cork Street Corridor
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridge
 
A Comparable Study Of Station Bridge, Steel
A Comparable Study Of Station Bridge, SteelA Comparable Study Of Station Bridge, Steel
A Comparable Study Of Station Bridge, Steel
 
Virginia
VirginiaVirginia
Virginia
 
Case StudyManaging Projects from Start to CompletionThe Rivers.docx
Case StudyManaging Projects from Start to CompletionThe Rivers.docxCase StudyManaging Projects from Start to CompletionThe Rivers.docx
Case StudyManaging Projects from Start to CompletionThe Rivers.docx
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration Project
 
Akashi kaikyo bridge
Akashi kaikyo bridgeAkashi kaikyo bridge
Akashi kaikyo bridge
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panels
 
SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
First assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfFirst assignment group (2) presentation.pdf
First assignment group (2) presentation.pdf
 
golden gate bridge
golden gate bridgegolden gate bridge
golden gate bridge
 
Ben marshman confederation bridge 20130310
Ben marshman confederation bridge 20130310Ben marshman confederation bridge 20130310
Ben marshman confederation bridge 20130310
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
 
Engineering mistakes in the world
Engineering mistakes in the worldEngineering mistakes in the world
Engineering mistakes in the world
 
Removing Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a TimeRemoving Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a Time
 

Recently uploaded

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Linn Cove Viaduct

  • 1.
  • 2. LINN COVE VIADUCT CARRIES: Blue Ridge Parkway CROSSES: Grandfather Mountain OWNER: National Park Service MAINTAINED BY: National Park Service DESIGN: Segmental bridge MATERIAL: Concrete TOTAL LENGTH: 1,243 feet (379 m) WIDTH: 39.5 feet (12.0 m) LOCATION: GRANDFATHER MOUNTAIN
  • 3. LONGEST SPAN:180.1 feet (54.9 m) DESIGNER: Figg & Muller Engineering Group CONSTRUCTED BY: Jasper Construction Co. CONSTRUCTION START: 1979 CONSTRUCTION END: 1987 CONSTRUCTION COST: $10 million INAUGURATED: September 11, 1987
  • 4.
  • 5.  Grandfather Mountain's delicate ecological system and unusually large number of globally imperiled ecosystem was cause for concern when plans for building this section of the Parkway started. They had to protect the special environment of Grandfather Mountain. The engineers were presented with the challenge of building a road without damaging one of the world's oldest mountains. The viaduct was designed by Figg and Muller who took painstaking measures to leave the smallest ecological footprint possible when designing and building the viaduct.
  • 6. ESTABLISHING THE ROUTE The exact route location of this segment, commonly referred to as the "MISSING LINK.”
  • 7.
  • 8.
  • 9.  National Park Service landscape architects and Federal Highway Administration engineers agreed the road should be elevated, or bridged, where possible to eliminate massive cuts and fills. Figg and Muller Engineers, Inc. developed the bridge design and construction method. The result: the Linn Cove Viaduct at milepost 304.6, the most complicated concrete bridge ever built, snaking around boulder-strewn Linn Cove in a sweeping “S” curve.
  • 10. CONSTRUCTION OF LINN COVE VIADUCT In order to prevent environmental damage and to allow construction to continue during severe winter weather, builders pre-cast sections indoors a few miles from the site using a process known as "match casting." Each new segment was cast against the segment preceding it.
  • 11.  The bridge's segments were precast at an indoor facility and transported to the bridge site, where each section was lowered into place by a custom crane placed on either edge of the existing structure.
  • 12. The viaduct itself was the only access road for construction. Each pre-cast section was lowered by a stiff-leg crane and epoxied into position against the preceding segment. Steel cables threaded through the segments secured the entire bridge deck.
  • 13.  The viaduct was constructed from the top down to minimize disturbance to the natural environment. This method eliminated the need for a "pioneer road" and heavy equipment on the ground. The only construction that occurred at ground level was the drilling of foundations for the seven permanent piers, on which the Viaduct rests. Exposed rock was covered to prevent staining from concrete, epoxy, or grout. Tinted with iron oxide, the concrete blends in with the existing rock outcroppings. The only trees cut were those directly beneath the superstructure.
  • 14. Linn Cove Viaduct. Placement of its foundations were determined by the location of the numerous boulders its built around.
  • 15. TIMELINE OF COMPLETION  Although the Blue Ridge Parkway’s construction began in 1935, construction of the Linn Cove Viaduct was delayed until 1979, when Congress finally approved funding. In the meantime, other portions of the "missing link," most of them north of the Viaduct, were completed bit-by-bit between 1968 and 1987
  • 16. LINN COVE VIADUCT: THE MOST ENVIRONMENT FRIENDLY BRIDGE  The Viaduct was built to minimize the damage that a traditional cut- and-fill road would have caused to Grandfather Mountain.  Supported by seven massive pillars, the viaduct almost floats in the air without disturbing the land below.  To eliminate damage to the environment, no access roads were built for transporting heavy equipment on the ground.
  • 17.  This seven-mile section of the Blue Ridge Parkway was delayed for twenty years as environmentalists, adjacent landowners, engineers, and architects sought a design that would preserve and protect the fragile habitat of adjacent Grandfather Mountain.
  • 18.  Recognized internationally as an engineering marvel.  The most complicated bridge ever built  An accessible paved trail begins at the visitor center and leads to a beautiful view of the Viaduct from underneath, and gives hikers access to the Tanawha Trail.
  • 19.  Linn Cove Viaduct, sometimes called the “missing link”  Provides not only one of the most iconic views of the Parkway, but a rich history as well  The Linn Cove Viaduct is a beautiful reminder of the historical cooperation between the government and its citizens, as well as the beginning of environmentally conscious development and natural resource conservation as we know it today.
  • 20. F O R
  • 21.
  • 22. 1. CARRIES 2. CROSSES 3. OWNER 4. MAINTAINED BY 5. DESIGN 6. MATERIAL 7. TOTAL LENGTH 8. WIDTH 9. LONGEST SPAN 10. DESIGNER 11. CONSTRUCTED BY 12. CONSTRUCTION START 13. CONSTRUCTION END 14. CONSTRUCTION COST 15. INAUGURATED TEST I:
  • 23. In order to prevent environmental damage and to allow construction to continue during severe winter weather, builders pre-cast sections indoors a few miles from the site using a process known as 1.____________. The viaduct was designed by 2._____ and 3._____ who took painstaking measures to leave the smallest ecological footprint possible when designing and building the viaduct. TEST II: FILL IN THE BLANKS (2pts each)
  • 24. 4._______ delicate ecological system and unusually large number of globally imperiled ecosystem was cause for concern when plans for building this section of the Parkway started. They had to protect the special environment of Grandfather Mountain. The engineers were presented with the challenge of building a road without damaging one of the world's oldest mountains.
  • 25. 5,_______ landscape architects and 6.______ engineers agreed the road should be 7.______ , or bridged, where possible to eliminate massive 8.______ and 9.______ . Figg and Muller Engineers, Inc. developed the bridge design and construction method. The result: the most complicated concrete bridge ever built, snaking around boulder-strewn LINN COVE in a sweeping 10._______ curve.
  • 26. TEST III: (15pts.) 1. EXPLAIN why the LINN COVE VIADUCT is considered as the most environment friendly bridge.

Editor's Notes

  1. The exact route location of this segment, commonly referred to as the "missing link,” created a lengthy and heated controversy between private individuals and the National Park Service. Finally, North Carolina Governor Dan K. Moore negotiated a compromise location. A key factor in this controversy was environmental concern over Grandfather Mountain. Engineers were faced with a serious question: How do you build a road at an elevation of 4,100 feet without damaging one of the world's oldest mountains? Pictue only(discuss)
  2. National Park Service landscape architects and Federal Highway Administration engineers agreed the road should be elevated, or bridged, where possible to eliminate massive cuts and fills. Figg and Muller Engineers, Inc. developed the bridge design and construction method. The result: the most complicated concrete bridge ever built, snaking around boulder-strewn Linn Cove in a sweeping "S" curve.
  3. Construction was delayed until 1979, when Congress finally approved funding. Completed in 1983 at a cost of almost $10 million, the Linn Cove Viaduct is 1,243 feet long and contains 153 segments weighing 50 ton each. Only one segment, the southernmost, is straight
  4. In order to prevent environmental damage and to allow construction to continue during severe winter weather, builders pre-cast sections indoors a few miles from the site using a process known as "match casting." Each new segment was cast against the segment preceding it. The viaduct itself was the only access road for construction. Each pre-cast section was lowered by a stiff-leg crane and epoxied into position against the preceding segment. Steel cables threaded through the segments secured the entire bridge deck. The viaduct was constructed from the top down to minimize disturbance to the natural environment. This method eliminated the need for a "pioneer road" and heavy equipment on the ground. The only construction that occurred at ground level was the drilling of foundations for the seven permanent piers, on which the Viaduct rests. Exposed rock was covered to prevent staining from concrete, epoxy, or grout. Tinted with iron oxide, the concrete blends in with the existing rock outcroppings. The only trees cut were those directly beneath the superstructure.
  5. A primitive, temporary road built along the route of a job, to provide means for moving equipment and workers
  6. Although the Blue Ridge Parkway’s construction began in 1935, construction of the Linn Cove Viaduct was delayed until 1979, when Congress finally approved funding. In the meantime, other portions of the "missing link," most of them north of the Viaduct, were completed bit-by-bit between 1968 and 1987. In addition to 12 bridges, the 7.5 mile section includes a dozen parking overlooks and the 13.5 mile Tanawha Trail, stretching from Beacon Heights to Julian Price Park. A ribbon-cutting dedication ceremony on September 11, 1987, heralded the completion of the Parkway and the end, too, of a narrow and crooked 14-mile detour around Grandfather Mountain via the Tonahlossee Trail (U.S. 221). The final section is not only a triumph of engineering and sensitivity to the environment; it is a joy to drive, safe but thrilling. Hugging the contours and Grandfather Mountain, the road gently curves and rolls, presenting motorists with magnificent views as it sweeps toward the sky.
  7. The Blue Ridge Parkway's Linn Cove Viaduct is an engineering wonder you can drive over and explore underneath.