SlideShare a Scribd company logo
1 of 5
Problem Background
Your project consists of six activities shown in the table below,
along with: (1) planned start and finish dates; (2) activity
budgets; and (3) earned value (EV) accrual rules from you
project cost management plan.
Activity
Planned Start
Planned Finish
Budget
EV Accrual Rule
Activity One
Mon - 10/13/14
Fri - 10/31/14 (
10,000
Percent Complete with Gates
Activity Two
Mon - 10/20/14
Fri -11/28/14
30,000
Fixed Formula -50/50
Activity Three
Mon -11/3/14
Fri -11/14/14
7,000
Fixed Formula -20/80
Activity Four
Mon -10/13/14
Fri -11/14/14
20,000
Weighted Milestones
Activity Five
Mon 11/17/14
Fri - 12/5/14
10,000
Fixed Formula – 0/100
Activity Six
Mon -12/8/14
Fri -12/19/14
7,000
Fixed Formula – 0/100
Activity Two has a start-to-start relationship (one week lag
time) with Activity One. Activity Three has a finish-to-start
relationship with Activity One. Activity Five has finish-to-start
relationships with activities Three and Four. Activity Six has
finish-to-start relationships with activities Two and Five.
Assumptions
1. Assume a five-day work week.
2. For all activities (except Activity Four), assume the
expenditure rate is constant over the duration of the activity,
i.e.:
For Activity Four, assume the expenditure profile shown below:
The project sponsor wants you (the PM) to present a project
cost and schedule performance assessment using data through
Friday, Nov 7, 2014. You have collected the following
information:
Activity
Actual Start
Actual Finish
Actual Cost
Activity One
Mon - 10/13/14
Fri - 11/3/14
12,000
Activity Two
Mon - 10/20/14
12,000
Activity Three
Mon -11/4/14
4,000
Activity Four
Mon -10/13/14
20,000
Activity Five
0
Activity Six
0
For Activity One, three equally-valued gates have been
established and all gates are complete as of 11/7/14.
For Activity Four, four milestones have been established with
the following values: (1) milestone 1 – 30%; milestone 2- 30%;
milestone 3 – 10%; milestone 4 -30%. Three of the milestones
are complete as of 11/7/14.
Show all work. Round dollar values to the nearest dollar.
Calculate all other variables to three decimal places.
1. Earned Value Measures
a. Calculate earned value measures for each activity and for the
cumulative project as of 11/7/14; fill in the table below:
Activity
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Activity One
12,000
Activity Two
12,000
Activity Three
4,000
Activity Four
20,000
Activity Five
0
Activity Six
0
Entire Project
48,000
ExpendituresTime
ExpendituresWeeks123455.5K3.0K
Problem BackgroundYour project consists of six activities show.docx

More Related Content

Similar to Problem BackgroundYour project consists of six activities show.docx

160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
SUM104-Topic6 - MS Project2013 - Murat Islam
SUM104-Topic6 - MS Project2013 - Murat IslamSUM104-Topic6 - MS Project2013 - Murat Islam
SUM104-Topic6 - MS Project2013 - Murat Islam
Murat Islam CEng MIMechE
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docxACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
annetnash8266
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
EngrMuhammadJavidNaw
 
MGT 150. Project ManagementCourse AssignmentsAssignment .docx
MGT 150. Project ManagementCourse AssignmentsAssignment .docxMGT 150. Project ManagementCourse AssignmentsAssignment .docx
MGT 150. Project ManagementCourse AssignmentsAssignment .docx
bunnyfinney
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
khenry4
 
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docxCP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
faithxdunce63732
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
NASAPMC
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
NASAPMC
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 

Similar to Problem BackgroundYour project consists of six activities show.docx (20)

Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
Assignment 1 Principles Of Project Management Mthabisi Sibanda MANCOSA 130635
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
SUM104-Topic6 - MS Project2013 - Murat Islam
SUM104-Topic6 - MS Project2013 - Murat IslamSUM104-Topic6 - MS Project2013 - Murat Islam
SUM104-Topic6 - MS Project2013 - Murat Islam
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docxACCT 241 - 04  Principles of Managerial AccountingFall 2014 S.docx
ACCT 241 - 04 Principles of Managerial AccountingFall 2014 S.docx
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
 
mehmet tanlak - 3
mehmet tanlak - 3mehmet tanlak - 3
mehmet tanlak - 3
 
Project management
Project managementProject management
Project management
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
MGT 150. Project ManagementCourse AssignmentsAssignment .docx
MGT 150. Project ManagementCourse AssignmentsAssignment .docxMGT 150. Project ManagementCourse AssignmentsAssignment .docx
MGT 150. Project ManagementCourse AssignmentsAssignment .docx
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docxCP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 

More from elishaoatway

PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docxPROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
elishaoatway
 
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docxProblem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
elishaoatway
 
Problem descriptionThe Jim Thornton Coffee House chain is .docx
Problem descriptionThe Jim Thornton Coffee House chain is .docxProblem descriptionThe Jim Thornton Coffee House chain is .docx
Problem descriptionThe Jim Thornton Coffee House chain is .docx
elishaoatway
 
Problem 5The probability distributions for inter-arrival a.docx
Problem 5The probability distributions for inter-arrival a.docxProblem 5The probability distributions for inter-arrival a.docx
Problem 5The probability distributions for inter-arrival a.docx
elishaoatway
 
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docxProblem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
elishaoatway
 
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docxPROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
elishaoatway
 
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docxPROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
elishaoatway
 
Problem 8-2B(a) Journalize the transactions, including explanati.docx
Problem 8-2B(a) Journalize the transactions, including explanati.docxProblem 8-2B(a) Journalize the transactions, including explanati.docx
Problem 8-2B(a) Journalize the transactions, including explanati.docx
elishaoatway
 
Problem B Regulatory Compliance 1 No.docx
Problem B Regulatory Compliance     1  No.docxProblem B Regulatory Compliance     1  No.docx
Problem B Regulatory Compliance 1 No.docx
elishaoatway
 
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docxPROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
elishaoatway
 
Problem 3 15 pointsThe following items were taken from the po.docx
Problem 3 15 pointsThe following items were taken from the po.docxProblem 3 15 pointsThe following items were taken from the po.docx
Problem 3 15 pointsThe following items were taken from the po.docx
elishaoatway
 
Problem 3-1A Identifying adjusting entries with explanations LO C3.docx
Problem 3-1A Identifying adjusting entries with explanations LO C3.docxProblem 3-1A Identifying adjusting entries with explanations LO C3.docx
Problem 3-1A Identifying adjusting entries with explanations LO C3.docx
elishaoatway
 
Essay #2 addresses some topic in the broad scope of Transcendentalis.docx
Essay #2 addresses some topic in the broad scope of Transcendentalis.docxEssay #2 addresses some topic in the broad scope of Transcendentalis.docx
Essay #2 addresses some topic in the broad scope of Transcendentalis.docx
elishaoatway
 

More from elishaoatway (20)

PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docxPROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
PROBLEM IDENTIFICATION AND RECOMMENDATIONS FOR SFK ORGANIZATION .docx
 
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docxProblem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
Problem Set #2 SCOR470 Fall 2015 Topics Soil water pote.docx
 
Problem descriptionThe Jim Thornton Coffee House chain is .docx
Problem descriptionThe Jim Thornton Coffee House chain is .docxProblem descriptionThe Jim Thornton Coffee House chain is .docx
Problem descriptionThe Jim Thornton Coffee House chain is .docx
 
Problem 5The probability distributions for inter-arrival a.docx
Problem 5The probability distributions for inter-arrival a.docxProblem 5The probability distributions for inter-arrival a.docx
Problem 5The probability distributions for inter-arrival a.docx
 
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docxProblem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
Problem 4-6 Calculating Internal Growth [LO3]The most recent fin.docx
 
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docxPROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
PROBLEM 8-18a. Fill in the worksheet with the appropriate value.docx
 
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docxPROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
PROBLEM 5-5BPrepare a correct detailed multiple-step income st.docx
 
Problem 8-2B(a) Journalize the transactions, including explanati.docx
Problem 8-2B(a) Journalize the transactions, including explanati.docxProblem 8-2B(a) Journalize the transactions, including explanati.docx
Problem 8-2B(a) Journalize the transactions, including explanati.docx
 
Problem B Regulatory Compliance 1 No.docx
Problem B Regulatory Compliance     1  No.docxProblem B Regulatory Compliance     1  No.docx
Problem B Regulatory Compliance 1 No.docx
 
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docxPROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
PROBLEM 3-22EventProduct CostsPeriod Costsa.b..docx
 
Problem 3 15 pointsThe following items were taken from the po.docx
Problem 3 15 pointsThe following items were taken from the po.docxProblem 3 15 pointsThe following items were taken from the po.docx
Problem 3 15 pointsThe following items were taken from the po.docx
 
Problem 3-1A Identifying adjusting entries with explanations LO C3.docx
Problem 3-1A Identifying adjusting entries with explanations LO C3.docxProblem 3-1A Identifying adjusting entries with explanations LO C3.docx
Problem 3-1A Identifying adjusting entries with explanations LO C3.docx
 
Essay 21) Describe the opportunities and challenges posed by the d.docx
Essay 21) Describe the opportunities and challenges posed by the d.docxEssay 21) Describe the opportunities and challenges posed by the d.docx
Essay 21) Describe the opportunities and challenges posed by the d.docx
 
Essay 11) Evaluate the Articles of Confederation as a guide for su.docx
Essay 11) Evaluate the Articles of Confederation as a guide for su.docxEssay 11) Evaluate the Articles of Confederation as a guide for su.docx
Essay 11) Evaluate the Articles of Confederation as a guide for su.docx
 
Essay (1) QuestionWhat is the so-called Machine Age How was it .docx
Essay (1) QuestionWhat is the so-called Machine Age How was it .docxEssay (1) QuestionWhat is the so-called Machine Age How was it .docx
Essay (1) QuestionWhat is the so-called Machine Age How was it .docx
 
Essay #2 addresses some topic in the broad scope of Transcendentalis.docx
Essay #2 addresses some topic in the broad scope of Transcendentalis.docxEssay #2 addresses some topic in the broad scope of Transcendentalis.docx
Essay #2 addresses some topic in the broad scope of Transcendentalis.docx
 
Essay # 2 The Tempest Prompt4-5 pages (MLA format)Char.docx
Essay # 2 The Tempest Prompt4-5 pages (MLA format)Char.docxEssay # 2 The Tempest Prompt4-5 pages (MLA format)Char.docx
Essay # 2 The Tempest Prompt4-5 pages (MLA format)Char.docx
 
Es la actividad que hacemos con pecesEs un animal blanco y negro q.docx
Es la actividad que hacemos con pecesEs un animal blanco y negro q.docxEs la actividad que hacemos con pecesEs un animal blanco y negro q.docx
Es la actividad que hacemos con pecesEs un animal blanco y negro q.docx
 
Erving Goffman is one of the most important sociological thinkers in.docx
Erving Goffman is one of the most important sociological thinkers in.docxErving Goffman is one of the most important sociological thinkers in.docx
Erving Goffman is one of the most important sociological thinkers in.docx
 
Eric seeks to trademark the name McJobs for his international compan.docx
Eric seeks to trademark the name McJobs for his international compan.docxEric seeks to trademark the name McJobs for his international compan.docx
Eric seeks to trademark the name McJobs for his international compan.docx
 

Recently uploaded

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 

Recently uploaded (20)

ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 

Problem BackgroundYour project consists of six activities show.docx

  • 1. Problem Background Your project consists of six activities shown in the table below, along with: (1) planned start and finish dates; (2) activity budgets; and (3) earned value (EV) accrual rules from you project cost management plan. Activity Planned Start Planned Finish Budget EV Accrual Rule Activity One Mon - 10/13/14 Fri - 10/31/14 ( 10,000 Percent Complete with Gates Activity Two Mon - 10/20/14 Fri -11/28/14 30,000 Fixed Formula -50/50 Activity Three Mon -11/3/14 Fri -11/14/14 7,000 Fixed Formula -20/80 Activity Four Mon -10/13/14 Fri -11/14/14 20,000 Weighted Milestones Activity Five Mon 11/17/14 Fri - 12/5/14
  • 2. 10,000 Fixed Formula – 0/100 Activity Six Mon -12/8/14 Fri -12/19/14 7,000 Fixed Formula – 0/100 Activity Two has a start-to-start relationship (one week lag time) with Activity One. Activity Three has a finish-to-start relationship with Activity One. Activity Five has finish-to-start relationships with activities Three and Four. Activity Six has finish-to-start relationships with activities Two and Five. Assumptions 1. Assume a five-day work week. 2. For all activities (except Activity Four), assume the expenditure rate is constant over the duration of the activity, i.e.: For Activity Four, assume the expenditure profile shown below: The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through Friday, Nov 7, 2014. You have collected the following information: Activity Actual Start Actual Finish Actual Cost Activity One Mon - 10/13/14
  • 3. Fri - 11/3/14 12,000 Activity Two Mon - 10/20/14 12,000 Activity Three Mon -11/4/14 4,000 Activity Four Mon -10/13/14 20,000 Activity Five 0 Activity Six 0 For Activity One, three equally-valued gates have been established and all gates are complete as of 11/7/14. For Activity Four, four milestones have been established with the following values: (1) milestone 1 – 30%; milestone 2- 30%; milestone 3 – 10%; milestone 4 -30%. Three of the milestones are complete as of 11/7/14. Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places. 1. Earned Value Measures a. Calculate earned value measures for each activity and for the cumulative project as of 11/7/14; fill in the table below:
  • 4. Activity Planned Value (PV) Earned Value (EV) Actual Cost (AC) Activity One 12,000 Activity Two 12,000 Activity Three 4,000 Activity Four 20,000 Activity Five 0 Activity Six 0 Entire Project 48,000 ExpendituresTime ExpendituresWeeks123455.5K3.0K