SlideShare a Scribd company logo
1 of 30
CP3 Start Data
Directions
General assignment:
For CP3 you will set your CP2 project and document deliverable
aside and start fresh. This is a new project. Your task is to use
this document and the data provided to create a project file
using Microsoft Project. The data below will establish a project
budget and schedule baseline with Budget = $4,449,920.00 and
a highly desired completion date of 12/17/08.
Next we will create a scenario for a time that is 'out in the
future' here. We are fast forwarding the project and loading
some fictional information to create a scenario for you to
analyze using Earned Value and then provide course corrections
to the project.
The project at this future date shows that our project is not
performing very well. However, you are given the opportunity
to make some changes to the project to still complete it on the
desired date of 12/17/08.
These directions help you to input and establish a baseline
project plan. You should check the plan to see that it agrees
with the budget and completion date given above before
proceeding.
Once that plan is set we will then check the project status as of
10/1/08. We will set the Gantt to represent the anticipated 50%
completion 'date' of 10/1/08. This is the date where the project
'should be' 50% complete. You do NOT set the project to 50%
complete; you set it to 40%. These are two different things and
these 2 parameters set up the scenario for you to generate EV
data and tell me about how the project is doing. Details of how
to set these will be give later in these directions..
Basic Setup:
First, change the project start date to Mon 4/14/08. Next are
provided some detailed steps to help you with the Microsoft
Project data input and then in progress monitoring and analysis.
The next step is to look at the options that are set for your
Microsoft Project software. If you have not changed them
before they will need some adjustments.
To make your reports easier to read you need to eliminate the
display of cents in your cost numbers. Go to File – Options –
Display – Decimal Digits and change this to “0”.
Set the default to have new tasks “Auto Scheduled”. The
Microsoft Project default is manual and we do not want that for
this project.
Getting started with our project, we will input the initial project
plan.
Check to be sure the project start date is Mon 4/14/08.Use the
following data to setup your baseline project file. Adjust
indenting to match WBS coding provided. In MSP right mouse
click the header row and insert a WBS Column as shown. Do
not add durations or dates for the Summary Tasks because these
will populate for you when you enter the lower task
information. The others should automatically generate. All
start and finish dates will be generated automatically.
Hint: You can cut and paste the basic task names, durations, and
predecessor data into Microsoft Project. You will have to
indent the lower sub tasks as you enter the data so that this will
work. Do not paste the start and finish dates in as Microsoft
Project will generate most of them automatically. Be sure to
verify your work as some of the formats in the word document
may not exactly match what Microsoft Project expects.
WBS
Task Name
Duration
Start
Finish
Predecessors
1
Theme Park Project
178 days
4/14/08
12/17/08
1.1
Site Layout & Site Grading
10 days
4/14/08
4/25/08
1.2
Footings & Foundations
55 days
4/28/08
7/11/08
2
1.3
Masonry
60 days
5/19/08
8/8/08
3SS+15 days
1.4
Frames, Columns and Beams
40 days
7/7/08
8/29/08
4SS+35 days
1.5
Joists & Roof Deck
30 days
9/1/08
10/10/08
5
1.6
Slab on Grade
35 days
7/14/08
8/29/08
3
1.7
Rough Carpentry
35 days
9/1/08
10/17/08
7
1.8
Interior Studs
20 days
9/1/08
9/26/08
7
1.9
Interior Drywall
30 days
10/13/08
11/21/08
9,6
1.10
Painting
35 days
10/27/08
12/12/08
10FS-20 days
1.11
Elevator
30 days
9/1/08
10/10/08
7
1.12
Doors
5 days
10/20/08
10/24/08
8
1.13
Custom Theme Painting
15 days
11/3/08
11/21/08
11SS+5 days
1.14
Flooring
15 days
11/17/08
12/5/08
10FS-5 days
1.15
Finish Carpentry
15 days
11/17/08
12/5/08
10FS-5 days
1.16
Bathroom Compartments/Accessories
3 days
12/8/08
Wed 12/10/08
16
1.17
Plumbing
85 days
7/28/08
11/21/08
1.17.1
Hangers & Supports
40 days
7/28/08
9/19/08
3FS+10 days
1.17.2
Pipes & Fittings
40 days
9/22/08
11/14/08
19
1.17.3
Test
5 days
11/17/08
11/21/08
20
1.18
HVAC
95 days
7/28/08
12/5/08
1.18.1
Stacks & Vents
30 days
7/28/08
9/5/08
3FS+10 days
1.18.2
Hangers & Supports
30 days
9/8/08
10/17/08
23
1.18.3
Ductwork & Piping
30 days
10/20/08
11/28/08
24
1.18.4
Test
5 days
12/1/08
12/5/08
25
1.19
Electrical
95 days
7/28/08
12/5/08
1.19.1
Boxes
25 days
7/28/08
8/29/08
3FS+10 days
1.19.2
Conduit
25 days
9/1/08
10/3/08
28
1.19.3
Wiring Devices/Switches/Receptacles
20 days
10/6/08
10/31/08
29
1.19.4
Light Fixtures
20 days
11/3/08
11/28/08
30
1.19.5
Test
5 days
12/1/08
12/5/08
31
1.20
Mechanicals Complete
1 day
12/8/08
12/8/08
21,26,32
1.21
Attraction Install and Training
146 days
4/14/08
11/3/08
1.21.1
Ferris Wheel
137 days
4/14/08
10/21/08
1.21.1.1
Ferris Wheel to ship
3 days
4/14/08
4/16/08
1.21.1.2
Ferris Wheel Legs & fan install
6 days
9/1/08
9/8/08
36,7
1.21.1.3
Ferris Wheel gondola install
6 days
9/9/08
9/16/08
37
1.21.1.4
Ferris Wheel MEP install
6 days
9/17/08
9/24/08
38
1.21.1.5
Ferris wheel platform design
2 days
9/25/08
9/26/08
39
1.21.1.6
Ferris Wheel Platform
6 days
9/29/08
10/6/08
40
1.21.1.7
Ferris Wheel Railing
6 days
10/7/08
10/14/08
41
1.21.1.8
Ferris wheel turnstile
3 days
10/15/08
10/17/08
42
1.21.1.9
Ferris wheel Training
1 day
10/20/08
10/20/08
43
1.21.1.10
Ferris Wheel Certification
1 day
10/21/08
10/21/08
44
1.21.2
Ropes course install & Training
30 days
9/1/08
10/10/08
7
1.21.3
Climbing wall install & Training
10 days
9/1/08
9/12/08
7
1.21.4
Carousel install & Training
13 days
9/1/08
9/17/08
7
1.21.5
Bowling install & Training
40 days
9/1/08
10/24/08
7
1.21.6
Go Cart install & Training
45 days
9/1/08
10/31/08
7
1.21.7
Mini Golf install & Training
15 days
9/1/08
9/19/08
7
1.21.8
Attraction install and training complete
1 day
11/3/08
11/03/08
45,46,47,48,49,50,51
1.22
Furniture Installation
5 days
12/9/08
12/15/08
33
1.23
System and Security Training
3 days
11/4/08
11/6/08
52
1.24
Final Walkthrough
1 day
12/16/08
12/16/08
12,14,15,16,17,52,53,54
1.25
Grand Opening
1 day
12/17/2008
12/17/2008
55
Next enter the Working Resource data below into the project
Resource Sheet [View  Resource Sheet]. You may use cut and
paste here also. You may have to work a column at a time.
Resource Name
Type
Initials
Max Units
Std. Rate
Accrue At
Customer
Work
C
400%
$0.00/hr
Prorated
Architect
Work
A
300%
$125.00/hr
Prorated
Engineer
Work
E
500%
$125.00/hr
Prorated
Electrician
Work
E
200%
$80.00/hr
Prorated
Electrician 2
Work
E
100%
$300.00/hr
Prorated
Builder
Work
B
600%
$65.00/hr
Prorated
Landscaper
Work
L
100%
$50.00/hr
Prorated
Builder 1
Work
B
100%
$85.00/hr
Prorated
Builder 2
Work
B
100%
$85.00/hr
Prorated
Builder 3
Work
B
100%
$85.00/hr
Prorated
Builder 4
Work
B
100%
$85.00/hr
Prorated
Painter
Work
P
300%
$200.00/hr
Prorated
Plumber
Work
P
100%
$150.00/hr
Prorated
Plumber 2
Work
P
100%
$225.00/hr
Prorated
Steamfitter
Work
S
100%
$125.00/hr
Prorated
Steamfitter 2
Work
S
100%
$200.00/hr
Prorated
FW Supplier
Work
F
100%
$100.00/hr
Prorated
Ride Supplier
Work
R
600%
$100.00/hr
Prorated
Now assign the resources to the project tasks as described
below.
WBS
Task Name
Resources
1
Theme Park Project
1.1
Site Layout & Site Grading
Architect
1.2
Footings & Foundations
Builder
1.3
Masonry
Builder
1.4
Frames, Columns and Beams
Builder
1.5
Joists & Roof Deck
Builder
1.6
Slab on Grade
Builder
1.7
Rough Carpentry
Builder
1.8
Interior Studs
Builder
1.9
Interior Drywall
Builder
1.10
Painting
Painter
1.11
Elevator
Builder
1.12
Doors
Builder
1.13
Theme Painting
Painter
1.14
Flooring
Builder 1
1.15
Finish Carpentry
Builder 2
1.16
Bathroom Compartments/Accessories
Builder
1.17
Plumbing
1.17.1
Hangers & Supports
Plumber
1.17.2
Pipes & Fittings
Plumber
1.17.3
Test
Plumber
1.18
HVAC
1.18.1
Stacks & Vents
Steamfitter
1.18.2
Hangers & Supports
Steamfitter
1.18.3
Ductwork & Piping
Steamfitter
1.18.4
Test
Steamfitter
1.19
Electrical
1.19.1
Boxes
Electrician
1.19.2
Conduit
Electrician
1.19.3
Wiring Devices/Switches/Receptacles
Electrician
1.19.4
Light Fixtures
Electrician
1.19.5
Test
Electrician
1.20
Mechanicals Complete
1.21
Attraction Install and Training
1.21.1
Ferris Wheel
1.21.1.1
Ferris Wheel to ship
FW Supplier
1.21.1.2
Ferris Wheel Legs & fan install
FW Supplier
1.21.1.3
Ferris Wheel gondola install
FW Supplier
1.21.1.4
Ferris Wheel MEP install
FW Supplier
1.21.1.5
Ferris wheel platform design
FW Supplier
1.21.1.6
Ferris Wheel Platform
FW Supplier
1.21.1.7
Ferris Wheel Railing
FW Supplier
1.21.1.8
Ferris wheel turnstyle
FW Supplier
1.21.1.9
Ferris wheel Training
FW Supplier
1.21.1.10
Ferris Wheel Certification
FW Supplier
1.21.2
Ropes course install & Training
Ride Supplier
1.21.3
Climbing wall install & Training
Ride Supplier
1.21.4
Carousel install & Training
Ride Supplier
1.21.5
Bowling install & Training
Ride Supplier
1.21.6
Go Cart install & Training
Ride Supplier
1.21.7
Mini Golf install & Training
Ride Supplier
1.21.8
Attraction install and training complete
1.22
Furniture Installation
Builder 3
1.23
System and Security Training
Builder 4
1.24
Final Walkthrough
Builder,Customer
1.25
Grand Opening
Customer
Now we have to add the material costs for each task. In MSP we
do this by adding a Prorated Fixed Cost in the Detail Gantt
View, Table/Cost View.
WBS
Task Name
Fixed Cost
1
Theme Park Project
$0.00
1.1
Site Layout & Site Grading
$10,000.00
1.2
Footings & Foundations
$30,000.00
1.3
Masonry
$150,000.00
1.4
Frames, Columns and Beams
$85,000.00
1.5
Joists & Roof Deck
$200,000.00
1.6
Slab on Grade
$250,000.00
1.7
Rough Carpentry
$175,000.00
1.8
Interior Studs
$20,000.00
1.9
Interior Drywall
$30,000.00
1.10
Painting
$45,000.00
1.11
Elevator
$80,000.00
1.12
Doors
$25,000.00
1.13
Theme Painting
$30,000.00
1.14
Flooring
$150,000.00
1.15
Finish Carpentry
$125,000.00
1.16
Bathroom Compartments/Accessories
$15,000.00
1.17
Plumbing
$0.00
1.17.1
Hangers & Supports
$30,000.00
1.17.2
Pipes & Fittings
$40,000.00
1.17.3
Test
$2,000.00
1.18
HVAC
$0.00
1.18.1
Stacks & Vents
$25,000.00
1.18.2
Hangers & Supports
$10,000.00
1.18.3
Ductwork & Piping
$40,000.00
1.18.4
Test
$5,000.00
1.19
Electrical
$0.00
1.19.1
Boxes
$35,000.00
1.19.2
Conduit
$15,000.00
1.19.3
Wiring Devices/Switches/Receptacles
$20,000.00
1.19.4
Light Fixtures
$40,000.00
1.19.5
Test
$10,000.00
1.20
Mechanicals Complete
$0.00
1.21
Attraction Install and Training
$0.00
1.21.1
Ferris Wheel
$0.00
1.21.1.1
Ferris Wheel to ship
$250,000.00
1.21.1.2
Ferris Wheel Legs & fan install
$4,000.00
1.21.1.3
Ferris Wheel gondola install
$3,000.00
1.21.1.4
Ferris Wheel MEP install
$5,000.00
1.21.1.5
Ferris wheel platform design
$1,000.00
1.21.1.6
Ferris Wheel Platform
$15,000.00
1.21.1.7
Ferris Wheel Railing
$5,000.00
1.21.1.8
Ferris wheel turnstyle
$2,000.00
1.21.1.9
Ferris wheel Training
$5,000.00
1.21.1.10
Ferris Wheel Certification
$1,000.00
1.21.2
Ropes course install & Training
$180,000.00
1.21.3
Climbing wall install & Training
$80,000.00
1.21.4
Carousel install & Training
$30,000.00
1.21.5
Bowling install & Training
$350,000.00
1.21.6
Go Cart install & Training
$890,000.00
1.21.7
Mini Golf install & Training
$65,000.00
1.21.8
Attraction install and training complete
$0.00
1.22
Furniture Installation
$110,000.00
1.23
System and Security Training
$10,000.00
1.24
Final Walkthrough
$15,000.00
1.25
Grand Opening
$30,000.00
At this point you will have all the data entered and your project
plan completed in MS Project.
There will be a picture showing what your file and Gantt chart
should look like posted in doc sharing so you can be sure you
are on track at this point.
It is very important to save a copy of your file at this point with
a unique name so it something goes wrong in the next step you
can start here again not at the beginning.
From this point we will progress to the monitoring and control.
CRITICAL STEP!!!
We now are ‘OUT IN THE FUTURE’ on the 10/1/08 day. Let’s
see how the project is doing!
The plan must be set up so that it will remain visible as
approved and show variances. This is setting the baseline.
Change the “View” to “Tracking Gantt”. This will show the
baseline plan and the actual progress on the same chart. It is
required that you use the tracking Gantt in this section of the
assignment.
Next, start tracking the project by setting the project baseline.
In 2007 the sequence is: Project Tools  Set Baseline  Set
Baseline  Set Baseline  OK. In Project 2010 the sequence is:
Project  Set Baseline  Set Baseline  Set Baseline for entire
project.
Now it is necessary to update the project data to where the
project actually is on the status date.
% Complete (The Reality)
The 40% project complete should be set by you by setting the
top level task (Theme Park Project) to 40%. This will adjust all
task completions to a % complete based on the baseline
schedule. This is how 'done' we are saying we actually are with
the project at this point in time.
% Scheduled (The Plan)
The date (i.e. point in time) provided for the review fast
forwards the project to the 'anticipated' 50% project scheduled
date. This is the date on the calendar when we 'wanted' to be
50% complete.
Next, adjust the Project Current Date to 10/1/08 AND adjust the
Project Status Date to 10/1/08.
Project  Project Information  status date.
Now we have to adjust a few task fixed costs because we have
spent more on materials than we had estimated. In MSP we do
this by adjusting the Prorated Fixed Cost in the Detail Gantt
View, Table  Cost View. This is will set the “Actual Costs,
AC” for those tasks in the project. All other actual costs are
calculated by MS Project to be exactly what was planned.
WBS
Task Name
Fixed Cost
1.2
Footings & Foundations
$100,000.00
1.6
Slab on Grade
$300,000.00
1.14
Flooring
$200,000.00
1.18.1
Stacks & Vents
$50,000.00
We now are we know the status as of 10/1/08 day. Let’s see
what to do next!
CRITICAL STEP!!!
The executives of the company have said that we must maintain
the finish date for this project even if it requires additional
resources and money.
Because we are behind, we need to move all the incomplete
work into the future to get a true look at the estimated
completion date. Select to Reschedule Incomplete Work to start
date after: 10/1/08.
Project  Update Project Select  OK
What’s the new projected completion date? After we look at
Earned Value below, we will have to do something about this
issue.
In the Tracking Gantt – Earned Value view, use the project file
to perform your Earned Value Analysis as described on the
Project Tab under Course Home. You should insert columns for
CPI and SPI to this view so you will have them to help you
evaluate the project. Use the project file and your analysis to
complete the Project Status Report which you will be submitting
to the CP3 DropBox.
View  Tables  More Views  Earned Value
As mentioned above, the project at this future date shows that
our project is not performing very well. Analyze the project and
report on it.
Make your changes to bring the project back on schedule
The good news is you are given the opportunity to make some
changes to the project to still complete it on the desired date of
12/17/08. You can do this by analyzing the critical path
activities and then making changes to the project to pull the
date in. Make your changes, for example to resources. Analyze
the result of these changes to the project dates and the project
costs (i.e. the date should improve and then cost may increase.
Assume you need to do something proactive to catch up and
then explain the impact of those changes.
This is an important part of the project and is not scripted. You
need to act as the project manager and make the decision that
will get your project back on schedule. You will also need to
communicate and justify them to your management in the
report.
Crashing and fast tracking are two methods of schedule
compression you may consider but are not limited to these. If
you use crashing by adding resources to an activity you MUST
make the cost of the added resources 150% of the cost of the
initially assigned resources. This will mean setting up an
additional resource with a higher per hour cost. This is a
practical decision because increasing the amount of resources
on a task is NOT as efficient at the initial allocations.
Integration into WORD for your report.
There are several simple formatting tricks to get the MSP data
into the WORD document.
1) Change the time scale to shrink down the MSP Gantt chart.
Right click on the timeline to open a screen which lists Top,
Middle and Bottom tabs. On the Middle tab select Quarters. On
the Bottom Tab, select Months.
2) Print the MSP file. For a printer driver select Microsoft
Office Document Image Writer (If you have this driver
available to you). Save the file somewhere you can find it on
your C drive. Insert as a picture file (Tif) into your Word
Document. If this doesn't work you may need to use print screen
or some other screen capture tool like SnipIt.
Another way is to use the “Copy Picture” function under the
“Copy” command on the Ribbon. There is a document in doc
sharing that gives details on how this works.
You can also use the “Print Screen” function on your computer.
An even better screen capture tool is the “Snipping Tool”. The
“Snipping Tool” that is a part of MS Office 2010 is a refined
version of “Print Screen” that allows you to select only the part
of the screen you want to use. It is available in Accessories
under All Programs.
If you do so be sure to crop your images so that only the
pertinent parts of the images are pasted into your report. When
you use screen shots from MSP you need to crop them to show
only the parts with project information and not the menus and
etc from the software.
To present the tables associated with the Gantt charts in your
report you can cut and paste these from MSP into MS Word.
Sometimes it works to paste them first into Excel and adjust the
formatting and then paste them into MS Word.
PROJ592_CourseHome_CP3_Start_Data_-_PROPOSED.docx
Page 1
Homework
Investment Decisions
Please respond to the following:
--From Case 4, imagine you are the consultant who has to make
the recommendation on whether or not to purchase Anheuser-
Busch. Determine the rate of return you could expect from your
investment and the method you would use to evaluate the
investment decision. Assess the disadvantages and advantages
of each investment method located in Chapter 4, and choose the
one that would provide the most accurate measure for your
anticipated rate of return requirement. Justify your
recommendation.
--Capital budgeting decisions are among the most important
decisions facing business entities. Suggest specific milestones
needed to evaluate the performance of capital projects, and
suggest some ways to hold managers accountable for spending
overruns. Recommend when capital projects should be
abandoned due to subsequent cost overruns. Support your
position. (1-2 references 350 words)
Inventory Costing Methods
Please respond to the following:
--Complete the e-Activity. Next, imagine that you have been
hired as the production manager of a manufacturing company
and must determine the best inventory costing system to
implement. Discuss the key factors that must be considered
before making the determination. Provide specific details and a
rationale for your decision.
--As a production manager, one of your key tasks is to improve
efficiencies by either increasing productivity or reducing cost.
Determine whether the responsibility reports needed to track
performance should be created by department, function, or
manager, using a costing method of your choice. Based on the
costing method you selected, determine the type of data needed
to track and evaluate performance to control costs such as cost
per unit, cost per hour, etc. Be specific with your examples. (1-
2 references 350 words)

More Related Content

Similar to CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx

Industrial Designer
Industrial DesignerIndustrial Designer
Industrial DesignerAshton B
 
Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides SlideTeam
 
Project management
Project managementProject management
Project managementervinod
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...Kuldeep Kumar
 
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxadampcarr67227
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentationKhem Singh
 
Website Handling And Maintenance Proposal PowerPoint Presentation Slides
Website Handling And Maintenance Proposal PowerPoint Presentation SlidesWebsite Handling And Maintenance Proposal PowerPoint Presentation Slides
Website Handling And Maintenance Proposal PowerPoint Presentation SlidesSlideTeam
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Nzar Braim
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsSachin Melwani
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
So you want to build an app? The HeirList Dev kickoff deck
So you want to build an app?   The HeirList Dev kickoff deckSo you want to build an app?   The HeirList Dev kickoff deck
So you want to build an app? The HeirList Dev kickoff deckChief Innovation
 
Module 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptModule 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptvaibhavkarnwal5
 
Module 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptModule 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptFaisalRafique27
 
Project Assessment PowerPoint Presentation Slides
Project Assessment PowerPoint Presentation SlidesProject Assessment PowerPoint Presentation Slides
Project Assessment PowerPoint Presentation SlidesSlideTeam
 
A project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxA project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxblondellchancy
 
Project Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesProject Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesSlideTeam
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Website Editing Proposal PowerPoint Presentation Slides
Website Editing Proposal PowerPoint Presentation SlidesWebsite Editing Proposal PowerPoint Presentation Slides
Website Editing Proposal PowerPoint Presentation SlidesSlideTeam
 
Project Deliverables PowerPoint Presentation Slides
Project Deliverables PowerPoint Presentation SlidesProject Deliverables PowerPoint Presentation Slides
Project Deliverables PowerPoint Presentation SlidesSlideTeam
 

Similar to CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx (20)

Industrial Designer
Industrial DesignerIndustrial Designer
Industrial Designer
 
Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides
 
Project management
Project managementProject management
Project management
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
 
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
 
Website Handling And Maintenance Proposal PowerPoint Presentation Slides
Website Handling And Maintenance Proposal PowerPoint Presentation SlidesWebsite Handling And Maintenance Proposal PowerPoint Presentation Slides
Website Handling And Maintenance Proposal PowerPoint Presentation Slides
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisons
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
So you want to build an app? The HeirList Dev kickoff deck
So you want to build an app?   The HeirList Dev kickoff deckSo you want to build an app?   The HeirList Dev kickoff deck
So you want to build an app? The HeirList Dev kickoff deck
 
Module 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptModule 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.ppt
 
Module 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.pptModule 2 rev - Proejct Management Overview.ppt
Module 2 rev - Proejct Management Overview.ppt
 
Project Assessment PowerPoint Presentation Slides
Project Assessment PowerPoint Presentation SlidesProject Assessment PowerPoint Presentation Slides
Project Assessment PowerPoint Presentation Slides
 
A project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docxA project plan is a document created at the beginning of the proje.docx
A project plan is a document created at the beginning of the proje.docx
 
Schedule Training
Schedule TrainingSchedule Training
Schedule Training
 
Project Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation SlidesProject Deliverables Powerpoint Presentation Slides
Project Deliverables Powerpoint Presentation Slides
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Website Editing Proposal PowerPoint Presentation Slides
Website Editing Proposal PowerPoint Presentation SlidesWebsite Editing Proposal PowerPoint Presentation Slides
Website Editing Proposal PowerPoint Presentation Slides
 
Project Deliverables PowerPoint Presentation Slides
Project Deliverables PowerPoint Presentation SlidesProject Deliverables PowerPoint Presentation Slides
Project Deliverables PowerPoint Presentation Slides
 

More from faithxdunce63732

Assignment DetailsScenario You are member of a prisoner revie.docx
Assignment DetailsScenario You are member of a prisoner revie.docxAssignment DetailsScenario You are member of a prisoner revie.docx
Assignment DetailsScenario You are member of a prisoner revie.docxfaithxdunce63732
 
Assignment DetailsScenario You are an investigator for Child .docx
Assignment DetailsScenario You are an investigator for Child .docxAssignment DetailsScenario You are an investigator for Child .docx
Assignment DetailsScenario You are an investigator for Child .docxfaithxdunce63732
 
Assignment DetailsScenario You are a new patrol officer in a .docx
Assignment DetailsScenario You are a new patrol officer in a .docxAssignment DetailsScenario You are a new patrol officer in a .docx
Assignment DetailsScenario You are a new patrol officer in a .docxfaithxdunce63732
 
Assignment DetailsScenario Generally, we have considered sexual.docx
Assignment DetailsScenario Generally, we have considered sexual.docxAssignment DetailsScenario Generally, we have considered sexual.docx
Assignment DetailsScenario Generally, we have considered sexual.docxfaithxdunce63732
 
Assignment DetailsPower’s on, Power’s Off!How convenient is.docx
Assignment DetailsPower’s on, Power’s Off!How convenient is.docxAssignment DetailsPower’s on, Power’s Off!How convenient is.docx
Assignment DetailsPower’s on, Power’s Off!How convenient is.docxfaithxdunce63732
 
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docx
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docxAssignment DetailsIn 1908, playwright Israel Zangwill referred to .docx
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docxfaithxdunce63732
 
Assignment DetailsPart IRespond to the following.docx
Assignment DetailsPart IRespond to the following.docxAssignment DetailsPart IRespond to the following.docx
Assignment DetailsPart IRespond to the following.docxfaithxdunce63732
 
Assignment DetailsPlease discuss the following in your main post.docx
Assignment DetailsPlease discuss the following in your main post.docxAssignment DetailsPlease discuss the following in your main post.docx
Assignment DetailsPlease discuss the following in your main post.docxfaithxdunce63732
 
Assignment DetailsPennsylvania was the leader in sentencing and .docx
Assignment DetailsPennsylvania was the leader in sentencing and .docxAssignment DetailsPennsylvania was the leader in sentencing and .docx
Assignment DetailsPennsylvania was the leader in sentencing and .docxfaithxdunce63732
 
Assignment DetailsPart IRespond to the followingReview .docx
Assignment DetailsPart IRespond to the followingReview .docxAssignment DetailsPart IRespond to the followingReview .docx
Assignment DetailsPart IRespond to the followingReview .docxfaithxdunce63732
 
Assignment DetailsPart IRespond to the following questio.docx
Assignment DetailsPart IRespond to the following questio.docxAssignment DetailsPart IRespond to the following questio.docx
Assignment DetailsPart IRespond to the following questio.docxfaithxdunce63732
 
Assignment DetailsPart IRespond to the following questions.docx
Assignment DetailsPart IRespond to the following questions.docxAssignment DetailsPart IRespond to the following questions.docx
Assignment DetailsPart IRespond to the following questions.docxfaithxdunce63732
 
Assignment DetailsOne thing that unites all humans—despite cultu.docx
Assignment DetailsOne thing that unites all humans—despite cultu.docxAssignment DetailsOne thing that unites all humans—despite cultu.docx
Assignment DetailsOne thing that unites all humans—despite cultu.docxfaithxdunce63732
 
Assignment DetailsMN551Develop cooperative relationships with.docx
Assignment DetailsMN551Develop cooperative relationships with.docxAssignment DetailsMN551Develop cooperative relationships with.docx
Assignment DetailsMN551Develop cooperative relationships with.docxfaithxdunce63732
 
Assignment DetailsInfluence ProcessesYou have been encourag.docx
Assignment DetailsInfluence ProcessesYou have been encourag.docxAssignment DetailsInfluence ProcessesYou have been encourag.docx
Assignment DetailsInfluence ProcessesYou have been encourag.docxfaithxdunce63732
 
Assignment DetailsIn this assignment, you will identify and .docx
Assignment DetailsIn this assignment, you will identify and .docxAssignment DetailsIn this assignment, you will identify and .docx
Assignment DetailsIn this assignment, you will identify and .docxfaithxdunce63732
 
Assignment DetailsFinancial statements are the primary means of .docx
Assignment DetailsFinancial statements are the primary means of .docxAssignment DetailsFinancial statements are the primary means of .docx
Assignment DetailsFinancial statements are the primary means of .docxfaithxdunce63732
 
Assignment DetailsIn this assignment, you will identify a pr.docx
Assignment DetailsIn this assignment, you will identify a pr.docxAssignment DetailsIn this assignment, you will identify a pr.docx
Assignment DetailsIn this assignment, you will identify a pr.docxfaithxdunce63732
 
Assignment DetailsHealth information technology (health IT) .docx
Assignment DetailsHealth information technology (health IT) .docxAssignment DetailsHealth information technology (health IT) .docx
Assignment DetailsHealth information technology (health IT) .docxfaithxdunce63732
 
Assignment DetailsDiscuss the followingWhat were some of .docx
Assignment DetailsDiscuss the followingWhat were some of .docxAssignment DetailsDiscuss the followingWhat were some of .docx
Assignment DetailsDiscuss the followingWhat were some of .docxfaithxdunce63732
 

More from faithxdunce63732 (20)

Assignment DetailsScenario You are member of a prisoner revie.docx
Assignment DetailsScenario You are member of a prisoner revie.docxAssignment DetailsScenario You are member of a prisoner revie.docx
Assignment DetailsScenario You are member of a prisoner revie.docx
 
Assignment DetailsScenario You are an investigator for Child .docx
Assignment DetailsScenario You are an investigator for Child .docxAssignment DetailsScenario You are an investigator for Child .docx
Assignment DetailsScenario You are an investigator for Child .docx
 
Assignment DetailsScenario You are a new patrol officer in a .docx
Assignment DetailsScenario You are a new patrol officer in a .docxAssignment DetailsScenario You are a new patrol officer in a .docx
Assignment DetailsScenario You are a new patrol officer in a .docx
 
Assignment DetailsScenario Generally, we have considered sexual.docx
Assignment DetailsScenario Generally, we have considered sexual.docxAssignment DetailsScenario Generally, we have considered sexual.docx
Assignment DetailsScenario Generally, we have considered sexual.docx
 
Assignment DetailsPower’s on, Power’s Off!How convenient is.docx
Assignment DetailsPower’s on, Power’s Off!How convenient is.docxAssignment DetailsPower’s on, Power’s Off!How convenient is.docx
Assignment DetailsPower’s on, Power’s Off!How convenient is.docx
 
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docx
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docxAssignment DetailsIn 1908, playwright Israel Zangwill referred to .docx
Assignment DetailsIn 1908, playwright Israel Zangwill referred to .docx
 
Assignment DetailsPart IRespond to the following.docx
Assignment DetailsPart IRespond to the following.docxAssignment DetailsPart IRespond to the following.docx
Assignment DetailsPart IRespond to the following.docx
 
Assignment DetailsPlease discuss the following in your main post.docx
Assignment DetailsPlease discuss the following in your main post.docxAssignment DetailsPlease discuss the following in your main post.docx
Assignment DetailsPlease discuss the following in your main post.docx
 
Assignment DetailsPennsylvania was the leader in sentencing and .docx
Assignment DetailsPennsylvania was the leader in sentencing and .docxAssignment DetailsPennsylvania was the leader in sentencing and .docx
Assignment DetailsPennsylvania was the leader in sentencing and .docx
 
Assignment DetailsPart IRespond to the followingReview .docx
Assignment DetailsPart IRespond to the followingReview .docxAssignment DetailsPart IRespond to the followingReview .docx
Assignment DetailsPart IRespond to the followingReview .docx
 
Assignment DetailsPart IRespond to the following questio.docx
Assignment DetailsPart IRespond to the following questio.docxAssignment DetailsPart IRespond to the following questio.docx
Assignment DetailsPart IRespond to the following questio.docx
 
Assignment DetailsPart IRespond to the following questions.docx
Assignment DetailsPart IRespond to the following questions.docxAssignment DetailsPart IRespond to the following questions.docx
Assignment DetailsPart IRespond to the following questions.docx
 
Assignment DetailsOne thing that unites all humans—despite cultu.docx
Assignment DetailsOne thing that unites all humans—despite cultu.docxAssignment DetailsOne thing that unites all humans—despite cultu.docx
Assignment DetailsOne thing that unites all humans—despite cultu.docx
 
Assignment DetailsMN551Develop cooperative relationships with.docx
Assignment DetailsMN551Develop cooperative relationships with.docxAssignment DetailsMN551Develop cooperative relationships with.docx
Assignment DetailsMN551Develop cooperative relationships with.docx
 
Assignment DetailsInfluence ProcessesYou have been encourag.docx
Assignment DetailsInfluence ProcessesYou have been encourag.docxAssignment DetailsInfluence ProcessesYou have been encourag.docx
Assignment DetailsInfluence ProcessesYou have been encourag.docx
 
Assignment DetailsIn this assignment, you will identify and .docx
Assignment DetailsIn this assignment, you will identify and .docxAssignment DetailsIn this assignment, you will identify and .docx
Assignment DetailsIn this assignment, you will identify and .docx
 
Assignment DetailsFinancial statements are the primary means of .docx
Assignment DetailsFinancial statements are the primary means of .docxAssignment DetailsFinancial statements are the primary means of .docx
Assignment DetailsFinancial statements are the primary means of .docx
 
Assignment DetailsIn this assignment, you will identify a pr.docx
Assignment DetailsIn this assignment, you will identify a pr.docxAssignment DetailsIn this assignment, you will identify a pr.docx
Assignment DetailsIn this assignment, you will identify a pr.docx
 
Assignment DetailsHealth information technology (health IT) .docx
Assignment DetailsHealth information technology (health IT) .docxAssignment DetailsHealth information technology (health IT) .docx
Assignment DetailsHealth information technology (health IT) .docx
 
Assignment DetailsDiscuss the followingWhat were some of .docx
Assignment DetailsDiscuss the followingWhat were some of .docxAssignment DetailsDiscuss the followingWhat were some of .docx
Assignment DetailsDiscuss the followingWhat were some of .docx
 

Recently uploaded

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 

Recently uploaded (20)

Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 

CP3 Start DataDirectionsGeneral assignmentFor CP3 you wil.docx

  • 1. CP3 Start Data Directions General assignment: For CP3 you will set your CP2 project and document deliverable aside and start fresh. This is a new project. Your task is to use this document and the data provided to create a project file using Microsoft Project. The data below will establish a project budget and schedule baseline with Budget = $4,449,920.00 and a highly desired completion date of 12/17/08. Next we will create a scenario for a time that is 'out in the future' here. We are fast forwarding the project and loading some fictional information to create a scenario for you to analyze using Earned Value and then provide course corrections to the project. The project at this future date shows that our project is not performing very well. However, you are given the opportunity to make some changes to the project to still complete it on the desired date of 12/17/08. These directions help you to input and establish a baseline project plan. You should check the plan to see that it agrees with the budget and completion date given above before proceeding. Once that plan is set we will then check the project status as of 10/1/08. We will set the Gantt to represent the anticipated 50% completion 'date' of 10/1/08. This is the date where the project 'should be' 50% complete. You do NOT set the project to 50% complete; you set it to 40%. These are two different things and these 2 parameters set up the scenario for you to generate EV data and tell me about how the project is doing. Details of how to set these will be give later in these directions.. Basic Setup: First, change the project start date to Mon 4/14/08. Next are
  • 2. provided some detailed steps to help you with the Microsoft Project data input and then in progress monitoring and analysis. The next step is to look at the options that are set for your Microsoft Project software. If you have not changed them before they will need some adjustments. To make your reports easier to read you need to eliminate the display of cents in your cost numbers. Go to File – Options – Display – Decimal Digits and change this to “0”. Set the default to have new tasks “Auto Scheduled”. The Microsoft Project default is manual and we do not want that for this project. Getting started with our project, we will input the initial project plan. Check to be sure the project start date is Mon 4/14/08.Use the following data to setup your baseline project file. Adjust indenting to match WBS coding provided. In MSP right mouse click the header row and insert a WBS Column as shown. Do not add durations or dates for the Summary Tasks because these will populate for you when you enter the lower task information. The others should automatically generate. All start and finish dates will be generated automatically. Hint: You can cut and paste the basic task names, durations, and predecessor data into Microsoft Project. You will have to indent the lower sub tasks as you enter the data so that this will work. Do not paste the start and finish dates in as Microsoft Project will generate most of them automatically. Be sure to verify your work as some of the formats in the word document may not exactly match what Microsoft Project expects. WBS Task Name Duration Start Finish Predecessors 1 Theme Park Project
  • 3. 178 days 4/14/08 12/17/08 1.1 Site Layout & Site Grading 10 days 4/14/08 4/25/08 1.2 Footings & Foundations 55 days 4/28/08 7/11/08 2 1.3 Masonry 60 days 5/19/08 8/8/08 3SS+15 days 1.4 Frames, Columns and Beams 40 days 7/7/08 8/29/08 4SS+35 days 1.5 Joists & Roof Deck 30 days 9/1/08 10/10/08 5 1.6 Slab on Grade
  • 4. 35 days 7/14/08 8/29/08 3 1.7 Rough Carpentry 35 days 9/1/08 10/17/08 7 1.8 Interior Studs 20 days 9/1/08 9/26/08 7 1.9 Interior Drywall 30 days 10/13/08 11/21/08 9,6 1.10 Painting 35 days 10/27/08 12/12/08 10FS-20 days 1.11 Elevator 30 days 9/1/08 10/10/08 7 1.12 Doors
  • 5. 5 days 10/20/08 10/24/08 8 1.13 Custom Theme Painting 15 days 11/3/08 11/21/08 11SS+5 days 1.14 Flooring 15 days 11/17/08 12/5/08 10FS-5 days 1.15 Finish Carpentry 15 days 11/17/08 12/5/08 10FS-5 days 1.16 Bathroom Compartments/Accessories 3 days 12/8/08 Wed 12/10/08 16 1.17 Plumbing 85 days 7/28/08 11/21/08 1.17.1 Hangers & Supports
  • 6. 40 days 7/28/08 9/19/08 3FS+10 days 1.17.2 Pipes & Fittings 40 days 9/22/08 11/14/08 19 1.17.3 Test 5 days 11/17/08 11/21/08 20 1.18 HVAC 95 days 7/28/08 12/5/08 1.18.1 Stacks & Vents 30 days 7/28/08 9/5/08 3FS+10 days 1.18.2 Hangers & Supports 30 days 9/8/08 10/17/08 23 1.18.3 Ductwork & Piping
  • 7. 30 days 10/20/08 11/28/08 24 1.18.4 Test 5 days 12/1/08 12/5/08 25 1.19 Electrical 95 days 7/28/08 12/5/08 1.19.1 Boxes 25 days 7/28/08 8/29/08 3FS+10 days 1.19.2 Conduit 25 days 9/1/08 10/3/08 28 1.19.3 Wiring Devices/Switches/Receptacles 20 days 10/6/08 10/31/08 29 1.19.4 Light Fixtures
  • 8. 20 days 11/3/08 11/28/08 30 1.19.5 Test 5 days 12/1/08 12/5/08 31 1.20 Mechanicals Complete 1 day 12/8/08 12/8/08 21,26,32 1.21 Attraction Install and Training 146 days 4/14/08 11/3/08 1.21.1 Ferris Wheel 137 days 4/14/08 10/21/08 1.21.1.1 Ferris Wheel to ship 3 days 4/14/08 4/16/08 1.21.1.2 Ferris Wheel Legs & fan install
  • 9. 6 days 9/1/08 9/8/08 36,7 1.21.1.3 Ferris Wheel gondola install 6 days 9/9/08 9/16/08 37 1.21.1.4 Ferris Wheel MEP install 6 days 9/17/08 9/24/08 38 1.21.1.5 Ferris wheel platform design 2 days 9/25/08 9/26/08 39 1.21.1.6 Ferris Wheel Platform 6 days 9/29/08 10/6/08 40 1.21.1.7 Ferris Wheel Railing 6 days 10/7/08 10/14/08 41 1.21.1.8 Ferris wheel turnstile
  • 10. 3 days 10/15/08 10/17/08 42 1.21.1.9 Ferris wheel Training 1 day 10/20/08 10/20/08 43 1.21.1.10 Ferris Wheel Certification 1 day 10/21/08 10/21/08 44 1.21.2 Ropes course install & Training 30 days 9/1/08 10/10/08 7 1.21.3 Climbing wall install & Training 10 days 9/1/08 9/12/08 7 1.21.4 Carousel install & Training 13 days 9/1/08 9/17/08 7 1.21.5 Bowling install & Training
  • 11. 40 days 9/1/08 10/24/08 7 1.21.6 Go Cart install & Training 45 days 9/1/08 10/31/08 7 1.21.7 Mini Golf install & Training 15 days 9/1/08 9/19/08 7 1.21.8 Attraction install and training complete 1 day 11/3/08 11/03/08 45,46,47,48,49,50,51 1.22 Furniture Installation 5 days 12/9/08 12/15/08 33 1.23 System and Security Training 3 days 11/4/08 11/6/08 52 1.24 Final Walkthrough
  • 12. 1 day 12/16/08 12/16/08 12,14,15,16,17,52,53,54 1.25 Grand Opening 1 day 12/17/2008 12/17/2008 55 Next enter the Working Resource data below into the project Resource Sheet [View Resource Sheet]. You may use cut and paste here also. You may have to work a column at a time. Resource Name Type Initials Max Units Std. Rate Accrue At Customer Work C 400% $0.00/hr Prorated Architect Work A 300% $125.00/hr Prorated Engineer Work E 500% $125.00/hr
  • 15. Prorated Steamfitter 2 Work S 100% $200.00/hr Prorated FW Supplier Work F 100% $100.00/hr Prorated Ride Supplier Work R 600% $100.00/hr Prorated Now assign the resources to the project tasks as described below. WBS Task Name Resources 1 Theme Park Project 1.1 Site Layout & Site Grading Architect 1.2 Footings & Foundations Builder 1.3
  • 16. Masonry Builder 1.4 Frames, Columns and Beams Builder 1.5 Joists & Roof Deck Builder 1.6 Slab on Grade Builder 1.7 Rough Carpentry Builder 1.8 Interior Studs Builder 1.9 Interior Drywall Builder 1.10 Painting Painter 1.11 Elevator Builder 1.12 Doors Builder 1.13 Theme Painting Painter 1.14 Flooring Builder 1 1.15
  • 17. Finish Carpentry Builder 2 1.16 Bathroom Compartments/Accessories Builder 1.17 Plumbing 1.17.1 Hangers & Supports Plumber 1.17.2 Pipes & Fittings Plumber 1.17.3 Test Plumber 1.18 HVAC 1.18.1 Stacks & Vents Steamfitter 1.18.2 Hangers & Supports Steamfitter 1.18.3 Ductwork & Piping Steamfitter 1.18.4 Test Steamfitter 1.19 Electrical 1.19.1
  • 18. Boxes Electrician 1.19.2 Conduit Electrician 1.19.3 Wiring Devices/Switches/Receptacles Electrician 1.19.4 Light Fixtures Electrician 1.19.5 Test Electrician 1.20 Mechanicals Complete 1.21 Attraction Install and Training 1.21.1 Ferris Wheel 1.21.1.1 Ferris Wheel to ship FW Supplier 1.21.1.2 Ferris Wheel Legs & fan install FW Supplier 1.21.1.3 Ferris Wheel gondola install FW Supplier 1.21.1.4 Ferris Wheel MEP install FW Supplier 1.21.1.5
  • 19. Ferris wheel platform design FW Supplier 1.21.1.6 Ferris Wheel Platform FW Supplier 1.21.1.7 Ferris Wheel Railing FW Supplier 1.21.1.8 Ferris wheel turnstyle FW Supplier 1.21.1.9 Ferris wheel Training FW Supplier 1.21.1.10 Ferris Wheel Certification FW Supplier 1.21.2 Ropes course install & Training Ride Supplier 1.21.3 Climbing wall install & Training Ride Supplier 1.21.4 Carousel install & Training Ride Supplier 1.21.5 Bowling install & Training Ride Supplier 1.21.6 Go Cart install & Training Ride Supplier 1.21.7 Mini Golf install & Training Ride Supplier 1.21.8
  • 20. Attraction install and training complete 1.22 Furniture Installation Builder 3 1.23 System and Security Training Builder 4 1.24 Final Walkthrough Builder,Customer 1.25 Grand Opening Customer Now we have to add the material costs for each task. In MSP we do this by adding a Prorated Fixed Cost in the Detail Gantt View, Table/Cost View. WBS Task Name Fixed Cost 1 Theme Park Project $0.00 1.1 Site Layout & Site Grading $10,000.00 1.2 Footings & Foundations $30,000.00 1.3 Masonry $150,000.00 1.4 Frames, Columns and Beams $85,000.00 1.5
  • 21. Joists & Roof Deck $200,000.00 1.6 Slab on Grade $250,000.00 1.7 Rough Carpentry $175,000.00 1.8 Interior Studs $20,000.00 1.9 Interior Drywall $30,000.00 1.10 Painting $45,000.00 1.11 Elevator $80,000.00 1.12 Doors $25,000.00 1.13 Theme Painting $30,000.00 1.14 Flooring $150,000.00 1.15 Finish Carpentry $125,000.00 1.16 Bathroom Compartments/Accessories $15,000.00 1.17
  • 22. Plumbing $0.00 1.17.1 Hangers & Supports $30,000.00 1.17.2 Pipes & Fittings $40,000.00 1.17.3 Test $2,000.00 1.18 HVAC $0.00 1.18.1 Stacks & Vents $25,000.00 1.18.2 Hangers & Supports $10,000.00 1.18.3 Ductwork & Piping $40,000.00 1.18.4 Test $5,000.00 1.19 Electrical $0.00 1.19.1 Boxes $35,000.00 1.19.2 Conduit $15,000.00 1.19.3
  • 23. Wiring Devices/Switches/Receptacles $20,000.00 1.19.4 Light Fixtures $40,000.00 1.19.5 Test $10,000.00 1.20 Mechanicals Complete $0.00 1.21 Attraction Install and Training $0.00 1.21.1 Ferris Wheel $0.00 1.21.1.1 Ferris Wheel to ship $250,000.00 1.21.1.2 Ferris Wheel Legs & fan install $4,000.00 1.21.1.3 Ferris Wheel gondola install $3,000.00 1.21.1.4 Ferris Wheel MEP install $5,000.00 1.21.1.5 Ferris wheel platform design $1,000.00 1.21.1.6 Ferris Wheel Platform $15,000.00 1.21.1.7
  • 24. Ferris Wheel Railing $5,000.00 1.21.1.8 Ferris wheel turnstyle $2,000.00 1.21.1.9 Ferris wheel Training $5,000.00 1.21.1.10 Ferris Wheel Certification $1,000.00 1.21.2 Ropes course install & Training $180,000.00 1.21.3 Climbing wall install & Training $80,000.00 1.21.4 Carousel install & Training $30,000.00 1.21.5 Bowling install & Training $350,000.00 1.21.6 Go Cart install & Training $890,000.00 1.21.7 Mini Golf install & Training $65,000.00 1.21.8 Attraction install and training complete $0.00 1.22 Furniture Installation $110,000.00 1.23
  • 25. System and Security Training $10,000.00 1.24 Final Walkthrough $15,000.00 1.25 Grand Opening $30,000.00 At this point you will have all the data entered and your project plan completed in MS Project. There will be a picture showing what your file and Gantt chart should look like posted in doc sharing so you can be sure you are on track at this point. It is very important to save a copy of your file at this point with a unique name so it something goes wrong in the next step you can start here again not at the beginning. From this point we will progress to the monitoring and control. CRITICAL STEP!!! We now are ‘OUT IN THE FUTURE’ on the 10/1/08 day. Let’s see how the project is doing! The plan must be set up so that it will remain visible as approved and show variances. This is setting the baseline. Change the “View” to “Tracking Gantt”. This will show the baseline plan and the actual progress on the same chart. It is required that you use the tracking Gantt in this section of the assignment. Next, start tracking the project by setting the project baseline. In 2007 the sequence is: Project Tools Set Baseline Set Baseline Set Baseline OK. In Project 2010 the sequence is: Project Set Baseline Set Baseline Set Baseline for entire project. Now it is necessary to update the project data to where the project actually is on the status date. % Complete (The Reality) The 40% project complete should be set by you by setting the top level task (Theme Park Project) to 40%. This will adjust all
  • 26. task completions to a % complete based on the baseline schedule. This is how 'done' we are saying we actually are with the project at this point in time. % Scheduled (The Plan) The date (i.e. point in time) provided for the review fast forwards the project to the 'anticipated' 50% project scheduled date. This is the date on the calendar when we 'wanted' to be 50% complete. Next, adjust the Project Current Date to 10/1/08 AND adjust the Project Status Date to 10/1/08. Project Project Information status date. Now we have to adjust a few task fixed costs because we have spent more on materials than we had estimated. In MSP we do this by adjusting the Prorated Fixed Cost in the Detail Gantt View, Table Cost View. This is will set the “Actual Costs, AC” for those tasks in the project. All other actual costs are calculated by MS Project to be exactly what was planned. WBS Task Name Fixed Cost 1.2 Footings & Foundations $100,000.00 1.6 Slab on Grade $300,000.00 1.14 Flooring $200,000.00 1.18.1 Stacks & Vents $50,000.00 We now are we know the status as of 10/1/08 day. Let’s see what to do next! CRITICAL STEP!!! The executives of the company have said that we must maintain
  • 27. the finish date for this project even if it requires additional resources and money. Because we are behind, we need to move all the incomplete work into the future to get a true look at the estimated completion date. Select to Reschedule Incomplete Work to start date after: 10/1/08. Project Update Project Select OK What’s the new projected completion date? After we look at Earned Value below, we will have to do something about this issue. In the Tracking Gantt – Earned Value view, use the project file to perform your Earned Value Analysis as described on the Project Tab under Course Home. You should insert columns for CPI and SPI to this view so you will have them to help you evaluate the project. Use the project file and your analysis to complete the Project Status Report which you will be submitting to the CP3 DropBox. View Tables More Views Earned Value As mentioned above, the project at this future date shows that our project is not performing very well. Analyze the project and report on it. Make your changes to bring the project back on schedule The good news is you are given the opportunity to make some changes to the project to still complete it on the desired date of 12/17/08. You can do this by analyzing the critical path activities and then making changes to the project to pull the date in. Make your changes, for example to resources. Analyze the result of these changes to the project dates and the project costs (i.e. the date should improve and then cost may increase. Assume you need to do something proactive to catch up and then explain the impact of those changes. This is an important part of the project and is not scripted. You need to act as the project manager and make the decision that will get your project back on schedule. You will also need to
  • 28. communicate and justify them to your management in the report. Crashing and fast tracking are two methods of schedule compression you may consider but are not limited to these. If you use crashing by adding resources to an activity you MUST make the cost of the added resources 150% of the cost of the initially assigned resources. This will mean setting up an additional resource with a higher per hour cost. This is a practical decision because increasing the amount of resources on a task is NOT as efficient at the initial allocations. Integration into WORD for your report. There are several simple formatting tricks to get the MSP data into the WORD document. 1) Change the time scale to shrink down the MSP Gantt chart. Right click on the timeline to open a screen which lists Top, Middle and Bottom tabs. On the Middle tab select Quarters. On the Bottom Tab, select Months. 2) Print the MSP file. For a printer driver select Microsoft Office Document Image Writer (If you have this driver available to you). Save the file somewhere you can find it on your C drive. Insert as a picture file (Tif) into your Word Document. If this doesn't work you may need to use print screen or some other screen capture tool like SnipIt. Another way is to use the “Copy Picture” function under the “Copy” command on the Ribbon. There is a document in doc sharing that gives details on how this works. You can also use the “Print Screen” function on your computer. An even better screen capture tool is the “Snipping Tool”. The “Snipping Tool” that is a part of MS Office 2010 is a refined version of “Print Screen” that allows you to select only the part of the screen you want to use. It is available in Accessories under All Programs. If you do so be sure to crop your images so that only the
  • 29. pertinent parts of the images are pasted into your report. When you use screen shots from MSP you need to crop them to show only the parts with project information and not the menus and etc from the software. To present the tables associated with the Gantt charts in your report you can cut and paste these from MSP into MS Word. Sometimes it works to paste them first into Excel and adjust the formatting and then paste them into MS Word. PROJ592_CourseHome_CP3_Start_Data_-_PROPOSED.docx Page 1 Homework Investment Decisions Please respond to the following: --From Case 4, imagine you are the consultant who has to make the recommendation on whether or not to purchase Anheuser- Busch. Determine the rate of return you could expect from your investment and the method you would use to evaluate the investment decision. Assess the disadvantages and advantages of each investment method located in Chapter 4, and choose the one that would provide the most accurate measure for your anticipated rate of return requirement. Justify your recommendation. --Capital budgeting decisions are among the most important decisions facing business entities. Suggest specific milestones needed to evaluate the performance of capital projects, and suggest some ways to hold managers accountable for spending overruns. Recommend when capital projects should be abandoned due to subsequent cost overruns. Support your position. (1-2 references 350 words) Inventory Costing Methods Please respond to the following:
  • 30. --Complete the e-Activity. Next, imagine that you have been hired as the production manager of a manufacturing company and must determine the best inventory costing system to implement. Discuss the key factors that must be considered before making the determination. Provide specific details and a rationale for your decision. --As a production manager, one of your key tasks is to improve efficiencies by either increasing productivity or reducing cost. Determine whether the responsibility reports needed to track performance should be created by department, function, or manager, using a costing method of your choice. Based on the costing method you selected, determine the type of data needed to track and evaluate performance to control costs such as cost per unit, cost per hour, etc. Be specific with your examples. (1- 2 references 350 words)