MAIN SOURCE :IMPROVING CONSTRUCTION LOGISTICS
Report of the Strategic Forum for Construction Logistics Group
August 2005
LOGISTICS &
PRODUCTIVITY
PART 2
Construction Productivity-Logistics
What is preventing the industry from
addressing Logistics?
There are a number of factors such as:
 There is no real incentive to tackle this
because it is difficult to identify who
benefits.
 Those who may be required to do things
differently do not necessarily benefit it.
Construction Productivity-Logistics
 Every construction job is seen as a ‘one-
off’.
 with a team built up for a short period of
time;
 then disbanded afterwards;
 it is harder to manage the system to
optimise logistics in construction;
 easier for manufacturing or retail;
Construction Productivity-Logistics
 the fragmented nature of the construction
industry;
 contractual arrangements that get in the
way of logistics;
 lack of direct employment also hinders
logistics;
 Those variables list above makes logistic
on construction site more difficult.
Construction Productivity-Logistics
 Advance planning and design of
projects is generally inadequate, as are
lead times.
 There is a lack of transparency in costs
throughout the construction process.
 Decisions are often based on cash flow.
Construction Productivity-Logistics
 The way costs are recorded does not
help identify the potential savings
from improved logistics.
 Unlike other industries, the
information provided in construction is
generally an ‘estimate’ rather than an
exact science.
Construction Productivity-Logistics
 There is a general lack of understanding of the
constraints of the supply chain.
 There is also a lack of trust and confidence that
the supply and chain will actually deliver when
required.
 Can projects rely on a ‘just in time’ delivery of
products?
 Clients (and others) believe that project cost
already allows for appropriate resources to be
committed to logistics on the project.
Construction Productivity-Logistics
Off – site manufacture and Modern Methods
of Construction
One of the reasons why logistics is so important
in construction can be described as:
 the fragmented nature of the industry;
 wide range of products;
 unpredictable outside environment needs a
well planned logistics;
Construction Productivity-Logistics
Good steps toward a better logistics
 innovative methods of construction;
 advance machinery;
 robotics;
 off site components;
 advance management softwares;
 Also, less products that need to be delivered to
and assembled on site all good step towards a
better logistics.
Construction Productivity-Logistics
Programme for improving logistics
 No one part of the construction industry can
deliver improved logistics on its own.
 The benefits will come from the different parts of
the industry.
Inter-acting in a different way such as:
 planning together
 sharing information
 exposing the real cost of activities in a way that
is currently not typical.
Construction Productivity-Logistics
Clients and logistics
 Clients have every reason to expect the
supply side to deliver their projects efficiently.
 To ensure that proper attention is given to
logistics so that the benefits referred to earlier
are delivered.
 Clients can help in this by making sure that
there is a Logistics Plan at an early stage in
their projects.
Construction Productivity-Logistics
 Client should make sure that all the key
players in the supply chain have signed up
to this Plan.
 There should be a Logistics Plan prepared
at an early stage in every project.
 A Best Practice Guide prepared to help
clients understand what they can expect
from the supply side on logistics.
Construction Productivity-Logistics
Design Professionals
 Design Professionals involvement in
good logistics.
 Particularly at the scheme design stage.
Logistics will be greatly helped if:
 The design professionals should draw
up a Process Map at an early stage in
the design.
Construction Productivity-Logistics
 Including a Bill of Materials.
This should look at:
1. The flow of materials needed on a
project
2. Ways of minimising stockholding
Construction Productivity-Logistics
Which of the professional members of the
supply chain should be responsible for this?
 This needs to be discussed among
managers.
 The quantity surveyors with their
background might have the appropriate
skills for this.
Construction Productivity-Logistics
 Alternatively, it could require the
input of logistics specialists.
 Manufacturers, suppliers and
distributors clearly need to make
an input to this Plan.
Construction Productivity-Logistics
 The various professional bodies
responsible for the design professions
in the construction industry –
 RIBA
 ICE
 IStruct E
 CIBSE on design issues
Construction Productivity-Logistics
 RICS on measurement and costing.
 They are in the best position to
highlight the importance of logistics.
 As well as in the training of those
seeking to join the profession.
Construction Productivity-Logistics
In the short term:
 This can be achieved through awareness
guidance as part of continuing professional
development.
In the medium term:
 The importance of logistics needs to feature
in the initial education and training of
University students and new members.
Construction Productivity-Logistics
 The professional team needs to
prepare a Bill of Materials as part of the
Logistics Plan.
 The professional institutions consider
ways in which the role of their
profession in project logistics can be
incorporated in initial education and
training.
Construction Productivity-Logistics
Main Contractors/specialist contractors
 Many see the construction manager as the key
player in co-ordinating the logistics on a
construction project.
 This is not a function that is being carried out as
effectively as it should be across the
construction industry.
 In some major projects logistics specialists are
being employed.
Construction Productivity-Logistics
 The responsibility for project logistics
must rest with the main contractors.
 it is essential they drew up a Logistics
Plan in consultation with the rest of
the supply chain at the outset of a
project.
Construction Productivity-Logistics
 The Bill of Materials will be an important
input to this.
 The specialist contractors should each
prepare that sub-set of the Logistics Plan
relevant to their specialist input.
 They must decide on how they will be
making optimum use of the skilled labour
on site.
Construction Productivity-Logistics
 Those responsible for the logistics on a
project must have the right skills to perform
the function.
 CITB Construction Skills is asked to
recommend how logistics skills can be
developed in the industry.
Therefore:
 Main contractors most prepare a Logistics
Plan in consultation.
 The rest of the Supply Chain at the outset of
each project must be involved.
Construction Productivity-Logistics
 This Plan should include the input to the
project from the specialist contractors.
 Also, the key manufacturers and
suppliers.
 CITB Construction Skills review the
need for logistics skills in the industry.
 CITB to recommend what needs to be
done to address this.
Construction Productivity-Logistics
Manufacturers/Suppliers/ Distributors
Key objective:
 ensure that the products and materials
arrive on site at the time;
 In the quantities that are required;
 This does not just depend on the
efficiency of the supply network.
Construction Productivity-Logistics
 it also relies on the pre-planning of those on
the construction site.
Effective communication amongst:
 those planning the project;
 those supplying the products;
 those supplying materials.
 Manufacturers and suppliers can make a
significant contribution to the efficiency.
Construction Productivity-Logistics
Manufactures involvement:
 It will help if they are involved early enough in
the process.
 If they can make an input to the Logistics
Plan through the preparation of the Bill of
Materials.
On the transport side:
 There may be an opportunity to look at ways
of developing best practice.
Construction Productivity-Logistics
Learning from other industries:
 through the Department for
Transport’s Sustainable Distribution
programme;
 This has not been given any attention
yet.
 Greater transparency of cost in the
construction process.
Construction Productivity-Logistics
Therefore:
 The Department for Transport’s
Sustainable Distribution programme
include work on transport in the
construction industry.
 Key manufacturers
 Suppliers
Construction Productivity-Logistics
 Distributors input to the Bill of
Materials being prepared as part of
the Logistics Plan for each project.
 Distributors reflect the cost of
distribution in their pricing policies.
Construction Productivity-Logistics
 distributors work with contractors
 See how lessons from the
Consolidation Centre approach
might be transferred to other
significant construction projects
and programmes.
Construction Productivity-Logistics
Information Technology
 The use of electronic communications as
effectively as other industries.
 This will to help in improve logistics
throughout the supply chain.
 The industry IS not utilising bar coding for
product ordering.
 E-tagging for tracing products throughout
the process.
 To the extent that seemed appropriate.
061 logistics and productivity
061 logistics and productivity

More Related Content

What's hot

Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Transforming Construction Innovation Hub Overview and Platform Design Competi...
Transforming Construction Innovation Hub Overview and Platform Design Competi...Transforming Construction Innovation Hub Overview and Platform Design Competi...
Transforming Construction Innovation Hub Overview and Platform Design Competi...KTN
 
Turnkey project
Turnkey projectTurnkey project
Turnkey projectzairanieto
 
Mb0049 project management
Mb0049 project managementMb0049 project management
Mb0049 project managementDevendra Kachhi
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 
A responsive satellite-industry_ka2015_lisi_v02
A responsive satellite-industry_ka2015_lisi_v02A responsive satellite-industry_ka2015_lisi_v02
A responsive satellite-industry_ka2015_lisi_v02Marco Lisi
 
Collaborative procurement methods - Investigating the impact of use of Buildi...
Collaborative procurement methods - Investigating the impact of use of Buildi...Collaborative procurement methods - Investigating the impact of use of Buildi...
Collaborative procurement methods - Investigating the impact of use of Buildi...P. Laurent de Senneville MRICS, PQS
 
Construction economic
Construction economicConstruction economic
Construction economicfauziani
 
Pezzagno & Bulferetti - input2012
Pezzagno & Bulferetti - input2012Pezzagno & Bulferetti - input2012
Pezzagno & Bulferetti - input2012INPUT 2012
 
Tarek Hassn Ibrahim Awad Alla-2-2
Tarek Hassn Ibrahim Awad Alla-2-2Tarek Hassn Ibrahim Awad Alla-2-2
Tarek Hassn Ibrahim Awad Alla-2-2tarek hassan
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 

What's hot (19)

Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
3. Mr B Coster
3. Mr B Coster3. Mr B Coster
3. Mr B Coster
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
Transforming Construction Innovation Hub Overview and Platform Design Competi...
Transforming Construction Innovation Hub Overview and Platform Design Competi...Transforming Construction Innovation Hub Overview and Platform Design Competi...
Transforming Construction Innovation Hub Overview and Platform Design Competi...
 
Turnkey project
Turnkey projectTurnkey project
Turnkey project
 
Mb0049 project management
Mb0049 project managementMb0049 project management
Mb0049 project management
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
A responsive satellite-industry_ka2015_lisi_v02
A responsive satellite-industry_ka2015_lisi_v02A responsive satellite-industry_ka2015_lisi_v02
A responsive satellite-industry_ka2015_lisi_v02
 
Innovative BIM Solution For Project Management And Quantity Surveying Mr. Ken...
Innovative BIM Solution For Project Management And Quantity Surveying Mr. Ken...Innovative BIM Solution For Project Management And Quantity Surveying Mr. Ken...
Innovative BIM Solution For Project Management And Quantity Surveying Mr. Ken...
 
Turnkey projects
Turnkey projectsTurnkey projects
Turnkey projects
 
Collaborative procurement methods - Investigating the impact of use of Buildi...
Collaborative procurement methods - Investigating the impact of use of Buildi...Collaborative procurement methods - Investigating the impact of use of Buildi...
Collaborative procurement methods - Investigating the impact of use of Buildi...
 
ECSIG (TfL) presentation 29 06-15 - final for sharing
ECSIG (TfL) presentation 29 06-15 - final for sharingECSIG (TfL) presentation 29 06-15 - final for sharing
ECSIG (TfL) presentation 29 06-15 - final for sharing
 
Construction economic
Construction economicConstruction economic
Construction economic
 
Pezzagno & Bulferetti - input2012
Pezzagno & Bulferetti - input2012Pezzagno & Bulferetti - input2012
Pezzagno & Bulferetti - input2012
 
Pathway guide quantity_surveying_construction_dwl_pt
Pathway guide quantity_surveying_construction_dwl_ptPathway guide quantity_surveying_construction_dwl_pt
Pathway guide quantity_surveying_construction_dwl_pt
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Tarek Hassn Ibrahim Awad Alla-2-2
Tarek Hassn Ibrahim Awad Alla-2-2Tarek Hassn Ibrahim Awad Alla-2-2
Tarek Hassn Ibrahim Awad Alla-2-2
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 

Similar to 061 logistics and productivity

062 logistics and productivity
062 logistics and productivity062 logistics and productivity
062 logistics and productivitydrdej19
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road ConstructionHeidi Owens
 
Supply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionSupply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionKogan Page
 
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVI
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVIPLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVI
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVIIRJET Journal
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industryAngad Partap Singh Bali
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Governance models for sustainable urban construction logistics: barriers for ...
Governance models for sustainable urban construction logistics: barriers for ...Governance models for sustainable urban construction logistics: barriers for ...
Governance models for sustainable urban construction logistics: barriers for ...Walther Ploos van Amstel
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
supply chain management with very easy case study
supply chain management with very easy case studysupply chain management with very easy case study
supply chain management with very easy case studyJayesh Gupta
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfssuser52d5d3
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015FBE Manchester
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET Journal
 
050 intergrating constructability
050 intergrating constructability050 intergrating constructability
050 intergrating constructabilitydrdej19
 
050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction 050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction Dr Fereidoun Dejahang
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesBeth Hall
 
Essay On Stage Scheduling
Essay On Stage SchedulingEssay On Stage Scheduling
Essay On Stage SchedulingJessica Lopez
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction IndustryIRJET Journal
 

Similar to 061 logistics and productivity (20)

062 logistics and productivity
062 logistics and productivity062 logistics and productivity
062 logistics and productivity
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road Construction
 
_logistics_of_construction
_logistics_of_construction_logistics_of_construction
_logistics_of_construction
 
Supply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in ConstructionSupply Chain Management and Logistics in Construction
Supply Chain Management and Logistics in Construction
 
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVI
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVIPLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVI
PLANNING AND COST ANALYSIS FOR SETTING UP OF A NEW RMCPLANT NEAR BELAGAVI
 
4
44
4
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Governance models for sustainable urban construction logistics: barriers for ...
Governance models for sustainable urban construction logistics: barriers for ...Governance models for sustainable urban construction logistics: barriers for ...
Governance models for sustainable urban construction logistics: barriers for ...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
supply chain management with very easy case study
supply chain management with very easy case studysupply chain management with very easy case study
supply chain management with very easy case study
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdf
 
Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015Fbe procurement event 23rd July 2015
Fbe procurement event 23rd July 2015
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
 
050 intergrating constructability
050 intergrating constructability050 intergrating constructability
050 intergrating constructability
 
050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction 050 Intergrating Constructability with Lean Construction
050 Intergrating Constructability with Lean Construction
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 
Essay On Stage Scheduling
Essay On Stage SchedulingEssay On Stage Scheduling
Essay On Stage Scheduling
 
IRJET- Importance of Proper Cost Management in Construction Industry
IRJET-  	  Importance of Proper Cost Management in Construction IndustryIRJET-  	  Importance of Proper Cost Management in Construction Industry
IRJET- Importance of Proper Cost Management in Construction Industry
 

More from drdej19

069 managing people
069 managing people069 managing people
069 managing peopledrdej19
 
070 material management
070 material management070 material management
070 material managementdrdej19
 
068 managing fundamentals
068 managing fundamentals068 managing fundamentals
068 managing fundamentalsdrdej19
 
067 management
067 management067 management
067 managementdrdej19
 
066 management structure-the design
066 management structure-the design066 management structure-the design
066 management structure-the designdrdej19
 
065 management information system
065 management information system065 management information system
065 management information systemdrdej19
 
064 management accounting
064 management accounting064 management accounting
064 management accountingdrdej19
 
063 management theory
063 management theory063 management theory
063 management theorydrdej19
 
059 lean construction
059 lean construction059 lean construction
059 lean constructiondrdej19
 
060 lean supply chain
060 lean supply chain060 lean supply chain
060 lean supply chaindrdej19
 
055 kpi's-success factor
055 kpi's-success factor055 kpi's-success factor
055 kpi's-success factordrdej19
 
057 lean and environment
057 lean and environment057 lean and environment
057 lean and environmentdrdej19
 
058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)drdej19
 
056 labour productivity
056 labour productivity056 labour productivity
056 labour productivitydrdej19
 
054 jit and quality management system
054 jit and quality management system054 jit and quality management system
054 jit and quality management systemdrdej19
 
049 integration of constructability
049 integration of constructability049 integration of constructability
049 integration of constructabilitydrdej19
 
048 integrating workers motivation
048 integrating workers motivation048 integrating workers motivation
048 integrating workers motivationdrdej19
 
047 integrating tqm-cons-ve
047 integrating tqm-cons-ve047 integrating tqm-cons-ve
047 integrating tqm-cons-vedrdej19
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqmdrdej19
 
044 integrating scm with fem and tqm
044 integrating scm with fem and tqm044 integrating scm with fem and tqm
044 integrating scm with fem and tqmdrdej19
 

More from drdej19 (20)

069 managing people
069 managing people069 managing people
069 managing people
 
070 material management
070 material management070 material management
070 material management
 
068 managing fundamentals
068 managing fundamentals068 managing fundamentals
068 managing fundamentals
 
067 management
067 management067 management
067 management
 
066 management structure-the design
066 management structure-the design066 management structure-the design
066 management structure-the design
 
065 management information system
065 management information system065 management information system
065 management information system
 
064 management accounting
064 management accounting064 management accounting
064 management accounting
 
063 management theory
063 management theory063 management theory
063 management theory
 
059 lean construction
059 lean construction059 lean construction
059 lean construction
 
060 lean supply chain
060 lean supply chain060 lean supply chain
060 lean supply chain
 
055 kpi's-success factor
055 kpi's-success factor055 kpi's-success factor
055 kpi's-success factor
 
057 lean and environment
057 lean and environment057 lean and environment
057 lean and environment
 
058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)
 
056 labour productivity
056 labour productivity056 labour productivity
056 labour productivity
 
054 jit and quality management system
054 jit and quality management system054 jit and quality management system
054 jit and quality management system
 
049 integration of constructability
049 integration of constructability049 integration of constructability
049 integration of constructability
 
048 integrating workers motivation
048 integrating workers motivation048 integrating workers motivation
048 integrating workers motivation
 
047 integrating tqm-cons-ve
047 integrating tqm-cons-ve047 integrating tqm-cons-ve
047 integrating tqm-cons-ve
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqm
 
044 integrating scm with fem and tqm
044 integrating scm with fem and tqm044 integrating scm with fem and tqm
044 integrating scm with fem and tqm
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

061 logistics and productivity

  • 1. MAIN SOURCE :IMPROVING CONSTRUCTION LOGISTICS Report of the Strategic Forum for Construction Logistics Group August 2005 LOGISTICS & PRODUCTIVITY PART 2
  • 2. Construction Productivity-Logistics What is preventing the industry from addressing Logistics? There are a number of factors such as:  There is no real incentive to tackle this because it is difficult to identify who benefits.  Those who may be required to do things differently do not necessarily benefit it.
  • 3. Construction Productivity-Logistics  Every construction job is seen as a ‘one- off’.  with a team built up for a short period of time;  then disbanded afterwards;  it is harder to manage the system to optimise logistics in construction;  easier for manufacturing or retail;
  • 4. Construction Productivity-Logistics  the fragmented nature of the construction industry;  contractual arrangements that get in the way of logistics;  lack of direct employment also hinders logistics;  Those variables list above makes logistic on construction site more difficult.
  • 5. Construction Productivity-Logistics  Advance planning and design of projects is generally inadequate, as are lead times.  There is a lack of transparency in costs throughout the construction process.  Decisions are often based on cash flow.
  • 6. Construction Productivity-Logistics  The way costs are recorded does not help identify the potential savings from improved logistics.  Unlike other industries, the information provided in construction is generally an ‘estimate’ rather than an exact science.
  • 7. Construction Productivity-Logistics  There is a general lack of understanding of the constraints of the supply chain.  There is also a lack of trust and confidence that the supply and chain will actually deliver when required.  Can projects rely on a ‘just in time’ delivery of products?  Clients (and others) believe that project cost already allows for appropriate resources to be committed to logistics on the project.
  • 8. Construction Productivity-Logistics Off – site manufacture and Modern Methods of Construction One of the reasons why logistics is so important in construction can be described as:  the fragmented nature of the industry;  wide range of products;  unpredictable outside environment needs a well planned logistics;
  • 9. Construction Productivity-Logistics Good steps toward a better logistics  innovative methods of construction;  advance machinery;  robotics;  off site components;  advance management softwares;  Also, less products that need to be delivered to and assembled on site all good step towards a better logistics.
  • 10. Construction Productivity-Logistics Programme for improving logistics  No one part of the construction industry can deliver improved logistics on its own.  The benefits will come from the different parts of the industry. Inter-acting in a different way such as:  planning together  sharing information  exposing the real cost of activities in a way that is currently not typical.
  • 11. Construction Productivity-Logistics Clients and logistics  Clients have every reason to expect the supply side to deliver their projects efficiently.  To ensure that proper attention is given to logistics so that the benefits referred to earlier are delivered.  Clients can help in this by making sure that there is a Logistics Plan at an early stage in their projects.
  • 12. Construction Productivity-Logistics  Client should make sure that all the key players in the supply chain have signed up to this Plan.  There should be a Logistics Plan prepared at an early stage in every project.  A Best Practice Guide prepared to help clients understand what they can expect from the supply side on logistics.
  • 13. Construction Productivity-Logistics Design Professionals  Design Professionals involvement in good logistics.  Particularly at the scheme design stage. Logistics will be greatly helped if:  The design professionals should draw up a Process Map at an early stage in the design.
  • 14. Construction Productivity-Logistics  Including a Bill of Materials. This should look at: 1. The flow of materials needed on a project 2. Ways of minimising stockholding
  • 15. Construction Productivity-Logistics Which of the professional members of the supply chain should be responsible for this?  This needs to be discussed among managers.  The quantity surveyors with their background might have the appropriate skills for this.
  • 16. Construction Productivity-Logistics  Alternatively, it could require the input of logistics specialists.  Manufacturers, suppliers and distributors clearly need to make an input to this Plan.
  • 17. Construction Productivity-Logistics  The various professional bodies responsible for the design professions in the construction industry –  RIBA  ICE  IStruct E  CIBSE on design issues
  • 18. Construction Productivity-Logistics  RICS on measurement and costing.  They are in the best position to highlight the importance of logistics.  As well as in the training of those seeking to join the profession.
  • 19. Construction Productivity-Logistics In the short term:  This can be achieved through awareness guidance as part of continuing professional development. In the medium term:  The importance of logistics needs to feature in the initial education and training of University students and new members.
  • 20. Construction Productivity-Logistics  The professional team needs to prepare a Bill of Materials as part of the Logistics Plan.  The professional institutions consider ways in which the role of their profession in project logistics can be incorporated in initial education and training.
  • 21. Construction Productivity-Logistics Main Contractors/specialist contractors  Many see the construction manager as the key player in co-ordinating the logistics on a construction project.  This is not a function that is being carried out as effectively as it should be across the construction industry.  In some major projects logistics specialists are being employed.
  • 22. Construction Productivity-Logistics  The responsibility for project logistics must rest with the main contractors.  it is essential they drew up a Logistics Plan in consultation with the rest of the supply chain at the outset of a project.
  • 23. Construction Productivity-Logistics  The Bill of Materials will be an important input to this.  The specialist contractors should each prepare that sub-set of the Logistics Plan relevant to their specialist input.  They must decide on how they will be making optimum use of the skilled labour on site.
  • 24. Construction Productivity-Logistics  Those responsible for the logistics on a project must have the right skills to perform the function.  CITB Construction Skills is asked to recommend how logistics skills can be developed in the industry. Therefore:  Main contractors most prepare a Logistics Plan in consultation.  The rest of the Supply Chain at the outset of each project must be involved.
  • 25. Construction Productivity-Logistics  This Plan should include the input to the project from the specialist contractors.  Also, the key manufacturers and suppliers.  CITB Construction Skills review the need for logistics skills in the industry.  CITB to recommend what needs to be done to address this.
  • 26. Construction Productivity-Logistics Manufacturers/Suppliers/ Distributors Key objective:  ensure that the products and materials arrive on site at the time;  In the quantities that are required;  This does not just depend on the efficiency of the supply network.
  • 27. Construction Productivity-Logistics  it also relies on the pre-planning of those on the construction site. Effective communication amongst:  those planning the project;  those supplying the products;  those supplying materials.  Manufacturers and suppliers can make a significant contribution to the efficiency.
  • 28. Construction Productivity-Logistics Manufactures involvement:  It will help if they are involved early enough in the process.  If they can make an input to the Logistics Plan through the preparation of the Bill of Materials. On the transport side:  There may be an opportunity to look at ways of developing best practice.
  • 29. Construction Productivity-Logistics Learning from other industries:  through the Department for Transport’s Sustainable Distribution programme;  This has not been given any attention yet.  Greater transparency of cost in the construction process.
  • 30. Construction Productivity-Logistics Therefore:  The Department for Transport’s Sustainable Distribution programme include work on transport in the construction industry.  Key manufacturers  Suppliers
  • 31. Construction Productivity-Logistics  Distributors input to the Bill of Materials being prepared as part of the Logistics Plan for each project.  Distributors reflect the cost of distribution in their pricing policies.
  • 32. Construction Productivity-Logistics  distributors work with contractors  See how lessons from the Consolidation Centre approach might be transferred to other significant construction projects and programmes.
  • 33. Construction Productivity-Logistics Information Technology  The use of electronic communications as effectively as other industries.  This will to help in improve logistics throughout the supply chain.  The industry IS not utilising bar coding for product ordering.  E-tagging for tracing products throughout the process.  To the extent that seemed appropriate.