SlideShare a Scribd company logo
1 of 14
SUBMITTED BY
JAYESH GUPTA
2020PGMFMS10
SUPPLY CHAIN
MANAGEMENT
SOLVING THE PRACTICAL PROBLEM
BY USING SUPPLY CHAIN
MANAGEMENT
SEMINAR 1
1
SUPPLY CHAIN
MANAGEMENT
• A SUPPLY CHAIN IS AN ENTIRE SYSTEM OF PRODUCING AND DELIVERING A PRODUCT
OR SERVICE, FROM THE VERY BEGINNING STAGE OF SOURCING THE RAW MATERIALS
TO THE FINAL DELIVERY OF THE PRODUCT OR SERVICE TO END-USERS
• THE SUPPLY CHAIN LAYS OUT ALL ASPECTS OF THE PRODUCTION PROCESS,
INCLUDING THE ACTIVITIES INVOLVED AT EACH STAGE, INFORMATION THAT IS BEING
COMMUNICATED, NATURAL RESOURCES THAT ARE TRANSFORMED INTO USEFUL
MATERIALS, HUMAN RESOURCES, AND OTHER COMPONENTS THAT GO INTO THE
FINISHED PRODUCT OR SERVICE.
WHY SUPPLY CHAIN IS SO
IMPORTANT?
 Mapping out a supply chain is one of the critical steps in performing
an external analysis in a strategic planning process.
 The importance of clearly laying out the supply chain is that it helps a
company define its own market and decide where it wants to be in the
future. In developing corporate-level strategies, a company often needs
to make decisions on whether to operate a single line of business or
enter into other related or unrelated industries.
 Each stage of a supply chain is essentially a different industry, for
example, raw material extraction and manufacturing
 The supply chain enables a company to understand others that are
involved in each of the stages, and thereby provides some insights on the
attractiveness or competitiveness in industries the company might want
to enter in the future.
In supply chain management all things are taken into consideration
Like:-
 How to order
 When to order
 How much to order
 Where to deliver
Problem solving using supply chain
management:
 I have taken the problem of small construction contractor here who
constructs or build the small buildings and houses
 He takes the contract of constructing the houses and buildings from their
owner, in return he is paid for that.
 so from contractor perspective he wants to earn more and more profit
and also need to maintain good quality.
 Generally, time, cost, and quality are main performance of the building construction
project. A particular project must be completed in time, within the existing budget, and
with the desired specification
 The construction supply chain begins with the business concept from the building or
project owner. Then, this concept is translated into the design. After the design is
complete, the owner chooses a building contractor to construct the buildings according
to the design.
 After than construction begins, during the construction, materials, labors, equipments
are transported to the construction site. When all the buildings are complete, they are
given or sold to the end customers.
 So the basic supply chain we have discussed is shown by block diagram below:
 But there are various problems faced by contractor which will ultimately increase project
cost and reduction in profit
 These problems are as follows
1. The buildings construction project normally locates in the urban area and numbers of
population are crowded. Consequently, work space or parking areas are very limited . It
is very difficult to frequently park the truck for a long time to load and unload
materials. When materials required are not available or come too early, ultimately
results in extra costs.
2. Sometimes, the contractor does not realize the amount of materials available or their
relevant lead time. Some materials are shortage and must be delivered to the project
urgently. Urgent requirements normally require quick delivery and result in higher
costs.
3. Further, materials must be properly stored inside the construction site. so, an planning
must be done to handle these materials.
4. In the construction project, material handling activities heavily involve in the
production phase . These activities mostly are non-value adding activities and should
be performed as least as possible.
5. Sometimes, Construction materials are transported and distributed from several
suppliers to the construction site at the right time and the right amounts. Delay in
transportation generates extra costs to the project since construction process has to
wait for materials and labors are idle
 These problem can be resolved by using proper supply chain management techniques in
the construction process which are shown below:
 Material handling activities can be minimized by planning logistics
 Prefabrication of materials can also be done as they are able to reduce inventories or
unnecessary handlings and transportations of raw materials as well as less labor are used
at the site.
 prefabrication materials are able to reduce logistics costs whereas the project can be
done in less time and lower costs with desired quality
 Also, easier purchasing or management can be achieved and the processing time at the
site is deducted
 With the limited space at the construction site, frequent material deliveries and low
inventory must be maintained, so concept of just-in-time (JIT) has been applied in the
construction supply chain.
 Contractor sends information of material requirement to relevant suppliers and requests
them to deliver required materials at the time required.
 For above the contractor must establish the long term contact with suppliers and third
party logistics providers. Information technology is used to link and share information
between all parties to monitor day-to-day progress and update latest material
requirements.
 Last but not the least distribution chaneels are made.
 some materials are directly transported to the construction site whereas other materials
are transported through DC and are sent to the site later. Most of heavy materials e.g.
sand or gravels, etc. should be handled directly to the site. To obtain the rational cost,
the right numbers of material transportations and numbers of suppliers must be
identified. Since the fuel price is rising, the costs of transportation must be effectively
managed and minimized.
 So to establish a new construction supply chain for a small building project, customer
demands must be analyzed and interpreted. Later, demands are translated into the
building design. During the design stage, building designers must discuss with suppliers
and logistics specialists regarding the impacts of design on costs incurred from materials,
material handling activities, inventories, etc. to obtain easier construction process and
less costs.
RESULT AND CONCLUSION
 After applying supply chain management to building construction process
it is observed that total construction cost will reduced (20-30%).
supply chain management with very easy case study

More Related Content

What's hot

Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5VancityInstitute
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
 
Tips on Cost optimization For Process Plants.
Tips on Cost optimization For Process Plants.Tips on Cost optimization For Process Plants.
Tips on Cost optimization For Process Plants.fxudegbu
 
maintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay methodmaintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay methodNithin Thomas Alex
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)Waqas Aslam
 
Costing of Formal Shirt
Costing of Formal ShirtCosting of Formal Shirt
Costing of Formal ShirtAbhishek Raj
 
Capacity planning
Capacity planningCapacity planning
Capacity planningAkhil Lal
 

What's hot (15)

Project life cycle costing
Project life cycle costing Project life cycle costing
Project life cycle costing
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Tips on Cost optimization For Process Plants.
Tips on Cost optimization For Process Plants.Tips on Cost optimization For Process Plants.
Tips on Cost optimization For Process Plants.
 
5. cost estimation
5. cost estimation5. cost estimation
5. cost estimation
 
maintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay methodmaintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay method
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Lecture23,24
Lecture23,24Lecture23,24
Lecture23,24
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Cost Estimate Development Sequence
Cost Estimate Development SequenceCost Estimate Development Sequence
Cost Estimate Development Sequence
 
Costing of Formal Shirt
Costing of Formal ShirtCosting of Formal Shirt
Costing of Formal Shirt
 
Ch17 scheduling
Ch17 schedulingCh17 scheduling
Ch17 scheduling
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 

Similar to supply chain management with very easy case study

CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxbjohn46
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy systempriyang2004
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in projectMukesh Doshi
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016khaja jeelani
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersReady to Train
 
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...Dr. David Mburu (PhD)
 
LOGISTICS CONTROL OVER MATERIALS OF METRO RAIL
LOGISTICS CONTROL OVER MATERIALS OF METRO RAILLOGISTICS CONTROL OVER MATERIALS OF METRO RAIL
LOGISTICS CONTROL OVER MATERIALS OF METRO RAILIAEME Publication
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning Olivia Wilson
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Aconex
 

Similar to supply chain management with very easy case study (20)

CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docxSheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
Sheet1ActivityWork (hours)Resource NameLabor RateLabor CostsMateri.docx
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...
OVERCOMING PROJECT MANAGEMENT CHALLENGES THROUGH SUSTAINABLE SUPPLY CHAIN MAN...
 
LOGISTICS CONTROL OVER MATERIALS OF METRO RAIL
LOGISTICS CONTROL OVER MATERIALS OF METRO RAILLOGISTICS CONTROL OVER MATERIALS OF METRO RAIL
LOGISTICS CONTROL OVER MATERIALS OF METRO RAIL
 
mod1.pdf
mod1.pdfmod1.pdf
mod1.pdf
 
H1303055462
H1303055462H1303055462
H1303055462
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 

Recently uploaded

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

supply chain management with very easy case study

  • 1. SUBMITTED BY JAYESH GUPTA 2020PGMFMS10 SUPPLY CHAIN MANAGEMENT SOLVING THE PRACTICAL PROBLEM BY USING SUPPLY CHAIN MANAGEMENT SEMINAR 1 1
  • 2. SUPPLY CHAIN MANAGEMENT • A SUPPLY CHAIN IS AN ENTIRE SYSTEM OF PRODUCING AND DELIVERING A PRODUCT OR SERVICE, FROM THE VERY BEGINNING STAGE OF SOURCING THE RAW MATERIALS TO THE FINAL DELIVERY OF THE PRODUCT OR SERVICE TO END-USERS • THE SUPPLY CHAIN LAYS OUT ALL ASPECTS OF THE PRODUCTION PROCESS, INCLUDING THE ACTIVITIES INVOLVED AT EACH STAGE, INFORMATION THAT IS BEING COMMUNICATED, NATURAL RESOURCES THAT ARE TRANSFORMED INTO USEFUL MATERIALS, HUMAN RESOURCES, AND OTHER COMPONENTS THAT GO INTO THE FINISHED PRODUCT OR SERVICE.
  • 3.
  • 4. WHY SUPPLY CHAIN IS SO IMPORTANT?  Mapping out a supply chain is one of the critical steps in performing an external analysis in a strategic planning process.  The importance of clearly laying out the supply chain is that it helps a company define its own market and decide where it wants to be in the future. In developing corporate-level strategies, a company often needs to make decisions on whether to operate a single line of business or enter into other related or unrelated industries.  Each stage of a supply chain is essentially a different industry, for example, raw material extraction and manufacturing  The supply chain enables a company to understand others that are involved in each of the stages, and thereby provides some insights on the attractiveness or competitiveness in industries the company might want to enter in the future.
  • 5. In supply chain management all things are taken into consideration Like:-  How to order  When to order  How much to order  Where to deliver
  • 6. Problem solving using supply chain management:  I have taken the problem of small construction contractor here who constructs or build the small buildings and houses  He takes the contract of constructing the houses and buildings from their owner, in return he is paid for that.  so from contractor perspective he wants to earn more and more profit and also need to maintain good quality.
  • 7.  Generally, time, cost, and quality are main performance of the building construction project. A particular project must be completed in time, within the existing budget, and with the desired specification  The construction supply chain begins with the business concept from the building or project owner. Then, this concept is translated into the design. After the design is complete, the owner chooses a building contractor to construct the buildings according to the design.  After than construction begins, during the construction, materials, labors, equipments are transported to the construction site. When all the buildings are complete, they are given or sold to the end customers.
  • 8.  So the basic supply chain we have discussed is shown by block diagram below:  But there are various problems faced by contractor which will ultimately increase project cost and reduction in profit  These problems are as follows 1. The buildings construction project normally locates in the urban area and numbers of population are crowded. Consequently, work space or parking areas are very limited . It is very difficult to frequently park the truck for a long time to load and unload materials. When materials required are not available or come too early, ultimately results in extra costs.
  • 9. 2. Sometimes, the contractor does not realize the amount of materials available or their relevant lead time. Some materials are shortage and must be delivered to the project urgently. Urgent requirements normally require quick delivery and result in higher costs. 3. Further, materials must be properly stored inside the construction site. so, an planning must be done to handle these materials. 4. In the construction project, material handling activities heavily involve in the production phase . These activities mostly are non-value adding activities and should be performed as least as possible. 5. Sometimes, Construction materials are transported and distributed from several suppliers to the construction site at the right time and the right amounts. Delay in transportation generates extra costs to the project since construction process has to wait for materials and labors are idle
  • 10.  These problem can be resolved by using proper supply chain management techniques in the construction process which are shown below:  Material handling activities can be minimized by planning logistics  Prefabrication of materials can also be done as they are able to reduce inventories or unnecessary handlings and transportations of raw materials as well as less labor are used at the site.  prefabrication materials are able to reduce logistics costs whereas the project can be done in less time and lower costs with desired quality  Also, easier purchasing or management can be achieved and the processing time at the site is deducted  With the limited space at the construction site, frequent material deliveries and low inventory must be maintained, so concept of just-in-time (JIT) has been applied in the construction supply chain.
  • 11.  Contractor sends information of material requirement to relevant suppliers and requests them to deliver required materials at the time required.  For above the contractor must establish the long term contact with suppliers and third party logistics providers. Information technology is used to link and share information between all parties to monitor day-to-day progress and update latest material requirements.  Last but not the least distribution chaneels are made.  some materials are directly transported to the construction site whereas other materials are transported through DC and are sent to the site later. Most of heavy materials e.g. sand or gravels, etc. should be handled directly to the site. To obtain the rational cost, the right numbers of material transportations and numbers of suppliers must be identified. Since the fuel price is rising, the costs of transportation must be effectively managed and minimized.
  • 12.  So to establish a new construction supply chain for a small building project, customer demands must be analyzed and interpreted. Later, demands are translated into the building design. During the design stage, building designers must discuss with suppliers and logistics specialists regarding the impacts of design on costs incurred from materials, material handling activities, inventories, etc. to obtain easier construction process and less costs.
  • 13. RESULT AND CONCLUSION  After applying supply chain management to building construction process it is observed that total construction cost will reduced (20-30%).