SlideShare a Scribd company logo
1 of 3
Download to read offline
To:  "'Kabei.Arlene@epamail.epa.gov'"  <'Kabei.Arlene@epamail.epa.gov'>,  
   "'Armann.Steve@epamail.epa.gov'"  <'Armann.Steve@epamail.epa.gov'>,  
   "'Vaille.Rich@epamail.epa.gov'"  <'Vaille.Rich@epamail.epa.gov'>,  
   "'Tyahla.Stephen@epamail.epa.gov'"  <'Tyahla.Stephen@epamail.epa.gov'>,  
   "'Moxley.Bret@epamail.epa.gov'"  <'Moxley.Bret@epamail.epa.gov'>,  
   "'Helmlinger.Andrew@epamail.epa.gov'"  <'Helmlinger.Andrew@epamail.epa.gov'>,  
   "'Wall.Steve@epamail.epa.gov'"  <'Wall.Steve@epamail.epa.gov'>,  
   "'stuart.yamada@doh.hawaii.gov'"  <'stuart.yamada@doh.hawaii.gov'>,  
   "'Steven.chang@doh.hawaii.gov'"  <'Steven.chang@doh.hawaii.gov'>,  
   "'alec.wong@doh.hawaii.gov'"  <'alec.wong@doh.hawaii.gov'>  
   From:  "Frey,  Jesse"  <JFrey@wm.com>  
   Date:  03/07/2011  07:00PM  
   Subject:  Daily  Progress  Report  for  March  7,  2011  
     
     
   Greetings  all.  
                   On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today.  Please  
   find  below  the  daily  progress  report  for  work  items  contained  within  the  recently  approved  
   AOC.          
   ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED  
                   Cell  6  Assessment:  

1. The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern  portion  of  the  
   E6  liner  system  was  submitted  February  25,  2011.    We  received  notification  from  DOH  on  
   March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the  liner  
   repairs,  which  allows  WMH  to  resume  operations  in  this  area.  

       

2. The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011  
   storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system  
   where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil  
   material  generated  from  the  January  storm  event  and  the  construction  of  the  diversion  
   system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This  
   removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2  weeks,  
   weather  permitting.  

       
                   Western  Storm  water  Diversion  Project  (to  render  functional):  
   1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in  place.        
   2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box  
   culvert  invert  to  pipe  invert.    Half  of  the  concrete  for  this  structure  was  poured  on  March  1,  
   2011.  The  remainder  is  scheduled  to  be  poured  on  3/10/2011.    Rebar  work  on  box  culvert  
   walls  is  ongoing.          
   3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.  
4)    The  diversion  structure  is  functionally  complete  per  the  terms  of  Section  19.b.  of  the  
   AOC.  
                   Cell  6  Leachate  Riser  Restoration:  
1. 36,200  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and  
   transported  to  the  waste  water  treatment  plant.  
       
2. Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and  transported  to  the  
   local  waste  water  treatment  plant.  
       
3. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and  placed  within  
   the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today  from  these  
   separation  tanks.  
       
                   Sediment  Basin:  
1. Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water  which  
   prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation  
   basin.      
       
2. The  contractor  pumped  113,000  gallons  of  storm  water  from  the  sedimentation  basin  
   today  and  transported  to  the  waste  water  treatment  plant.  
                   Evaluating  possible  hydraulic  head  below  liner  system:  
1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at  temporary  
   piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during  the  drilling  
   process.  Since  no  water  was  observed,  temporary  piezometers  were  not  installed.      The  
   documentation  report  was  submitted  on  February  25,  2011.      
                   Beach  Assessment  Update:  
1. The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls  received  at  
   the  established  beach  waste  hot  line  today.  
       
   ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None  
   ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS     None  
   Please  let  me  know  if  you  have  any  questions.        
   Best  regards,  
   Jesse  Frey  
   Engineer  
   Waste  Management  of  Hawaii  
   92-­‐460  Farrington  Hwy.  
   Kapolei,  HI  96707  
   Ph:  808-­‐250-­‐0574  
Fax:  808-­‐668-­‐1366  
  

More Related Content

What's hot

Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportHonolulu Civil Beat
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Honolulu Civil Beat
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportHonolulu Civil Beat
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Honolulu Civil Beat
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportHonolulu Civil Beat
 
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectGlenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectFairfax County
 
Feb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportFeb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportHonolulu Civil Beat
 
Old Colchester Road Stream Stabilization Project January 2021
Old Colchester Road Stream Stabilization Project January 2021Old Colchester Road Stream Stabilization Project January 2021
Old Colchester Road Stream Stabilization Project January 2021Fairfax County
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationFairfax County
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall RestorationFairfax County
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationFairfax County
 
Barton Hill Sediment Removal Project
Barton Hill Sediment Removal ProjectBarton Hill Sediment Removal Project
Barton Hill Sediment Removal ProjectFairfax County
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Fairfax County
 
City Council Meeting 10.14.19 Item #6 ppt interpool inc
City Council Meeting 10.14.19 Item #6   ppt interpool incCity Council Meeting 10.14.19 Item #6   ppt interpool inc
City Council Meeting 10.14.19 Item #6 ppt interpool incahcitycouncil
 
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
 
Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Fairfax County
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectFairfax County
 
Rainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall RestorationRainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall RestorationFairfax County
 

What's hot (20)

Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress report
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress Report
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily Report
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress Report
 
Glenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement ProjectGlenbrook Road Sanitary Sewer Extension and Improvement Project
Glenbrook Road Sanitary Sewer Extension and Improvement Project
 
Feb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportFeb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress Report
 
Old Colchester Road Stream Stabilization Project January 2021
Old Colchester Road Stream Stabilization Project January 2021Old Colchester Road Stream Stabilization Project January 2021
Old Colchester Road Stream Stabilization Project January 2021
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall Restoration
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Barton Hill Sediment Removal Project
Barton Hill Sediment Removal ProjectBarton Hill Sediment Removal Project
Barton Hill Sediment Removal Project
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
City Council Meeting 10.14.19 Item #6 ppt interpool inc
City Council Meeting 10.14.19 Item #6   ppt interpool incCity Council Meeting 10.14.19 Item #6   ppt interpool inc
City Council Meeting 10.14.19 Item #6 ppt interpool inc
 
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
 
Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018Land and Tree Conservation Awards Ceremony 2018
Land and Tree Conservation Awards Ceremony 2018
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
 
Rainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall RestorationRainbow Bridge Land Outfall Restoration
Rainbow Bridge Land Outfall Restoration
 

Viewers also liked

William Aila Questionnaire and Résume
William Aila Questionnaire and RésumeWilliam Aila Questionnaire and Résume
William Aila Questionnaire and RésumeHonolulu Civil Beat
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)Honolulu Civil Beat
 
City rail Financial plan August 2009
City rail Financial plan August 2009City rail Financial plan August 2009
City rail Financial plan August 2009Honolulu Civil Beat
 
Charles Carole Letter and DTS Response
Charles Carole Letter and DTS ResponseCharles Carole Letter and DTS Response
Charles Carole Letter and DTS ResponseHonolulu Civil Beat
 
HLRB Ruling on Motion to Strike Respondents' Opposition
HLRB Ruling on Motion to Strike Respondents' OppositionHLRB Ruling on Motion to Strike Respondents' Opposition
HLRB Ruling on Motion to Strike Respondents' OppositionHonolulu Civil Beat
 
City/ORI Report to HUD: August 1, 2011
City/ORI Report to HUD: August 1, 2011City/ORI Report to HUD: August 1, 2011
City/ORI Report to HUD: August 1, 2011Honolulu Civil Beat
 
FTA Record of Decision to Honolulu 2011
FTA Record of Decision to Honolulu 2011FTA Record of Decision to Honolulu 2011
FTA Record of Decision to Honolulu 2011Honolulu Civil Beat
 
Blue Planet Foundation Testimony on SB1372
Blue Planet Foundation Testimony on SB1372 Blue Planet Foundation Testimony on SB1372
Blue Planet Foundation Testimony on SB1372 Honolulu Civil Beat
 
City Council Fact-Finding Rail Report: June 2011
City Council Fact-Finding Rail Report: June 2011City Council Fact-Finding Rail Report: June 2011
City Council Fact-Finding Rail Report: June 2011Honolulu Civil Beat
 
D yanich, local tv & shared services agreements, honolulu
D yanich, local tv & shared services agreements, honoluluD yanich, local tv & shared services agreements, honolulu
D yanich, local tv & shared services agreements, honoluluHonolulu Civil Beat
 
PHP industrialisé dans Windows Azure web sites
PHP industrialisé dans Windows Azure web sitesPHP industrialisé dans Windows Azure web sites
PHP industrialisé dans Windows Azure web sitesMicrosoft
 

Viewers also liked (20)

William Aila Questionnaire and Résume
William Aila Questionnaire and RésumeWilliam Aila Questionnaire and Résume
William Aila Questionnaire and Résume
 
American jobs act_--_final
American jobs act_--_finalAmerican jobs act_--_final
American jobs act_--_final
 
Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)Removal Action Summary Report (pages 1-1015)
Removal Action Summary Report (pages 1-1015)
 
Bombardier appeal 10.13.2011
Bombardier appeal 10.13.2011Bombardier appeal 10.13.2011
Bombardier appeal 10.13.2011
 
Waste Management Invoices
Waste Management InvoicesWaste Management Invoices
Waste Management Invoices
 
City rail Financial plan August 2009
City rail Financial plan August 2009City rail Financial plan August 2009
City rail Financial plan August 2009
 
June 27 Letter to HUD
June 27 Letter to HUDJune 27 Letter to HUD
June 27 Letter to HUD
 
Charles Carole Letter and DTS Response
Charles Carole Letter and DTS ResponseCharles Carole Letter and DTS Response
Charles Carole Letter and DTS Response
 
State of the Judiciary 1.26.11
State of the Judiciary 1.26.11State of the Judiciary 1.26.11
State of the Judiciary 1.26.11
 
HLRB Ruling on Motion to Strike Respondents' Opposition
HLRB Ruling on Motion to Strike Respondents' OppositionHLRB Ruling on Motion to Strike Respondents' Opposition
HLRB Ruling on Motion to Strike Respondents' Opposition
 
City/ORI Report to HUD: August 1, 2011
City/ORI Report to HUD: August 1, 2011City/ORI Report to HUD: August 1, 2011
City/ORI Report to HUD: August 1, 2011
 
Eis pg 21 23
Eis pg 21 23Eis pg 21 23
Eis pg 21 23
 
FTA Record of Decision to Honolulu 2011
FTA Record of Decision to Honolulu 2011FTA Record of Decision to Honolulu 2011
FTA Record of Decision to Honolulu 2011
 
Blue Planet Foundation Testimony on SB1372
Blue Planet Foundation Testimony on SB1372 Blue Planet Foundation Testimony on SB1372
Blue Planet Foundation Testimony on SB1372
 
Exhibits part 1
Exhibits part 1Exhibits part 1
Exhibits part 1
 
City Council Fact-Finding Rail Report: June 2011
City Council Fact-Finding Rail Report: June 2011City Council Fact-Finding Rail Report: June 2011
City Council Fact-Finding Rail Report: June 2011
 
Gold Coast Trial Brief
Gold Coast Trial BriefGold Coast Trial Brief
Gold Coast Trial Brief
 
Prosecutor's letter
Prosecutor's letter Prosecutor's letter
Prosecutor's letter
 
D yanich, local tv & shared services agreements, honolulu
D yanich, local tv & shared services agreements, honoluluD yanich, local tv & shared services agreements, honolulu
D yanich, local tv & shared services agreements, honolulu
 
PHP industrialisé dans Windows Azure web sites
PHP industrialisé dans Windows Azure web sitesPHP industrialisé dans Windows Azure web sites
PHP industrialisé dans Windows Azure web sites
 

Similar to March 7 Waste Management Daily Progress Report

Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportHonolulu Civil Beat
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress reportHonolulu Civil Beat
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairFairfax County
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairFairfax County
 
Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportHonolulu Civil Beat
 
020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc020711 wgsl daily progress report aoc
020711 wgsl daily progress report aocHonolulu Civil Beat
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportHonolulu Civil Beat
 
Dolphin Lane Sewer Sag Project
Dolphin Lane Sewer Sag ProjectDolphin Lane Sewer Sag Project
Dolphin Lane Sewer Sag ProjectFairfax County
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project CompletionFairfax County
 
Launcelot Way Project Completion
Launcelot Way Project CompletionLauncelot Way Project Completion
Launcelot Way Project CompletionFairfax County
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationFairfax County
 
Robey Avenue Outfall Restoration
Robey Avenue Outfall RestorationRobey Avenue Outfall Restoration
Robey Avenue Outfall RestorationFairfax County
 
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationAttleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationThomasSexton8
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond ImprovementFairfax County
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall RestorationFairfax County
 

Similar to March 7 Waste Management Daily Progress Report (20)

Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress Report
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress report
 
020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
 
Dolphin Lane Sewer Sag Project
Dolphin Lane Sewer Sag ProjectDolphin Lane Sewer Sag Project
Dolphin Lane Sewer Sag Project
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project Completion
 
Launcelot Way Project Completion
Launcelot Way Project CompletionLauncelot Way Project Completion
Launcelot Way Project Completion
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall Restoration
 
SFPUC-#377404v1.PDF
SFPUC-#377404v1.PDFSFPUC-#377404v1.PDF
SFPUC-#377404v1.PDF
 
VSL_____(3190)
VSL_____(3190)VSL_____(3190)
VSL_____(3190)
 
Robey Avenue Outfall Restoration
Robey Avenue Outfall RestorationRobey Avenue Outfall Restoration
Robey Avenue Outfall Restoration
 
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationAttleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond Improvement
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall Restoration
 
borehole_waye
borehole_wayeborehole_waye
borehole_waye
 

More from Honolulu Civil Beat

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooHonolulu Civil Beat
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Honolulu Civil Beat
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsHonolulu Civil Beat
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD Honolulu Civil Beat
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Honolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Honolulu Civil Beat
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersHonolulu Civil Beat
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Honolulu Civil Beat
 

More from Honolulu Civil Beat (20)

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna Eshoo
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10
 
NHPI COVID-19 Statement
NHPI COVID-19 StatementNHPI COVID-19 Statement
NHPI COVID-19 Statement
 
DLIR Response Language Access
DLIR Response Language AccessDLIR Response Language Access
DLIR Response Language Access
 
Language Access Letter To DLIR
Language Access Letter To DLIRLanguage Access Letter To DLIR
Language Access Letter To DLIR
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
Jane Doe v. Rehab Hospital
Jane Doe v. Rehab HospitalJane Doe v. Rehab Hospital
Jane Doe v. Rehab Hospital
 
Coronavirus HPHA
Coronavirus HPHA Coronavirus HPHA
Coronavirus HPHA
 
OHA Data Request
OHA Data RequestOHA Data Request
OHA Data Request
 
Letter from Palau to Guam
Letter from Palau to GuamLetter from Palau to Guam
Letter from Palau to Guam
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence
 
OHA Analysis by Akina
OHA Analysis by AkinaOHA Analysis by Akina
OHA Analysis by Akina
 
Case COFA Letter
Case COFA LetterCase COFA Letter
Case COFA Letter
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service Providers
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018
 
Caldwell Press Release
Caldwell Press ReleaseCaldwell Press Release
Caldwell Press Release
 

Recently uploaded

Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 

Recently uploaded (20)

Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 

March 7 Waste Management Daily Progress Report

  • 1. To:  "'Kabei.Arlene@epamail.epa.gov'"  <'Kabei.Arlene@epamail.epa.gov'>,   "'Armann.Steve@epamail.epa.gov'"  <'Armann.Steve@epamail.epa.gov'>,   "'Vaille.Rich@epamail.epa.gov'"  <'Vaille.Rich@epamail.epa.gov'>,   "'Tyahla.Stephen@epamail.epa.gov'"  <'Tyahla.Stephen@epamail.epa.gov'>,   "'Moxley.Bret@epamail.epa.gov'"  <'Moxley.Bret@epamail.epa.gov'>,   "'Helmlinger.Andrew@epamail.epa.gov'"  <'Helmlinger.Andrew@epamail.epa.gov'>,   "'Wall.Steve@epamail.epa.gov'"  <'Wall.Steve@epamail.epa.gov'>,   "'stuart.yamada@doh.hawaii.gov'"  <'stuart.yamada@doh.hawaii.gov'>,   "'Steven.chang@doh.hawaii.gov'"  <'Steven.chang@doh.hawaii.gov'>,   "'alec.wong@doh.hawaii.gov'"  <'alec.wong@doh.hawaii.gov'>   From:  "Frey,  Jesse"  <JFrey@wm.com>   Date:  03/07/2011  07:00PM   Subject:  Daily  Progress  Report  for  March  7,  2011       Greetings  all.                  On  behalf  of  Joe  Whelan,  I  am  submitting  the  daily  progress  report  for  today.  Please   find  below  the  daily  progress  report  for  work  items  contained  within  the  recently  approved   AOC.           ACTIONS  PERFORMED  AND  DEVELOPMENTS  ANTICIPATED                  Cell  6  Assessment:   1. The  QCA  report  documenting  the  evaluation  and  repair  of  the  southwestern  portion  of  the   E6  liner  system  was  submitted  February  25,  2011.    We  received  notification  from  DOH  on   March  1,  2011  concurring  that  the  CQA  report  was  adequate  documentation  of  the  liner   repairs,  which  allows  WMH  to  resume  operations  in  this  area.       2. The  northwest  section  of  the  Cell  E6  liner  was  also  damaged  in  the  January  13,  2011   storm.    This  area  is  located  directly  below  the  section  of  the  storm  water  diversion  system   where  the  open  box  culvert  ties  into  the  Hobas  pipe.    Consequently,  any  rock  and  soil   material  generated  from  the  January  storm  event  and  the  construction  of  the  diversion   system  in  this  area  must  be  removed  prior  to  the  evaluation  and  repair  of  the  liner.    This   removal  activity  is  ongoing  and  is  expected  to  be  completed  within  the  next  2  weeks,   weather  permitting.                      Western  Storm  water  Diversion  Project  (to  render  functional):   1)    Diversion  Structure:      The  final  wall  section  of  the  diversion  structure  is  now  in  place.         2)    Box  Culvert:      The  contractor  has  completed  forming  the  transition  structure  from  box   culvert  invert  to  pipe  invert.    Half  of  the  concrete  for  this  structure  was  poured  on  March  1,   2011.  The  remainder  is  scheduled  to  be  poured  on  3/10/2011.    Rebar  work  on  box  culvert   walls  is  ongoing.           3)    Pipe:      Backfilling  of  the  HOBAS  pipe  channel  is  now  complete.  
  • 2. 4)    The  diversion  structure  is  functionally  complete  per  the  terms  of  Section  19.b.  of  the   AOC.                  Cell  6  Leachate  Riser  Restoration:   1. 36,200  gallons  were  pumped  from  the  Cell  E6  leachate  riser  storage  tank  today  and   transported  to  the  waste  water  treatment  plant.     2. Zero  gallons  of  water  was  pumped  from  the  south  pond  area  today  and  transported  to  the   local  waste  water  treatment  plant.     3. Zero  gallons  of  mud/water  was  pumped  from  the  south  pond  area  today  and  placed  within   the  onsite  separation  tanks.  Zero  gallons  of  water  was  pumped  today  from  these   separation  tanks.                      Sediment  Basin:   1. Showers  this  week  have  resulted  in  the  additional  accumulation  of  storm  water  which   prevented  removal  of  silt/rock  material  from  the  northern  portion  of  the  sedimentation   basin.         2. The  contractor  pumped  113,000  gallons  of  storm  water  from  the  sedimentation  basin   today  and  transported  to  the  waste  water  treatment  plant.                  Evaluating  possible  hydraulic  head  below  liner  system:   1. Per  the  work  plan  submitted  to  EPA  on  2/1/2011,  we  have  drilled  to  depth  at  temporary   piezometer  locations  PZ-­‐1,  PZ-­‐5  and  PZ-­‐6.    No  water  was  encountered    during  the  drilling   process.  Since  no  water  was  observed,  temporary  piezometers  were  not  installed.      The   documentation  report  was  submitted  on  February  25,  2011.                      Beach  Assessment  Update:   1. The  daily  beach  assessment  phase  of  this  task  is  complete.    There  were  no  calls  received  at   the  established  beach  waste  hot  line  today.     ANALYTICAL  DATA  RECEIVED  DURING  REPORTING  PERIOD  -­  None   ANTICIPATED  PROBLEMS  AND  PLANNED  RESOLUTIONS    None   Please  let  me  know  if  you  have  any  questions.         Best  regards,   Jesse  Frey   Engineer   Waste  Management  of  Hawaii   92-­‐460  Farrington  Hwy.   Kapolei,  HI  96707   Ph:  808-­‐250-­‐0574