SlideShare a Scribd company logo
1 of 1
Download to read offline
ID3190
Edited2008
www.vsl.com
Water tank duplication, Harvey – Australia
Provision of a new precast tank to double available water storage
OWNER
Water Corporation of WA
MAIN CONTRACTOR
VSL - AJ Lucas JV
VSL ENTITY
VSL Australia
DATE
2011/2012
▲ The project involved doubling the Water Corporation's water storage capacity at the Harvey site.
The Southern Seawater Desalination
Plant (SSDP) is Western Australia's
second major desalination project.
The plant is located at Taranto Road,
north of Binningup, approximately
150km south of Perth.
Water Corporation received
conditional environmental approval
for the plant in June 2009.
Construction of the new plant began
the following month, once full project
approval had been received from the
Federal Government.
The plant is being built in two stages,
each with a maximum capacity of 50
giga litres (GL) a year.
Initially, VSL worked as a
subcontractor on the first tank at
Binningup, with a scope of work that
included design and construction of
the tank base slab, walls and the
roof. VSL has since been appointed
to work on a second tank, under a
sub-contract to AJ Lucas.
The first stage of the scheme was
officially opened in September 2011
and is expected to reach its full
capacity of 50GL/year within a year.
It was completed three months
ahead of schedule and required an
investment of AU$955 million.
A second stage of the project was
announced in August 2011. It will
involve expansion of the plant's
capacity from 50GL/year to
100GL/year.
The project involves construction of
a 28km-long underground pipeline
from Binningup to a storage facility
comprising four summit tanks
located northeast of Harvey. The
pipeline will facilitate the transfer of
potable water from the plant to the
integrated water supply scheme.
Scope of works performed
Design, manufacture, supply,
construction and testing of a
second precast, post-tensioned
concrete, circular, roofed water
storage tank at the Water
Corporation’s Harvey summit tank
site.
The plant is owned by Water
Corporation which is the main
provider of water, wastewater and
drainage services in Western
Australia.
The new plant has the potential to
deliver 30% of the state's water
supply from climate-independent
water sources.
It is expected to deliver total potable
water savings of up to 1,200GL a
year.

More Related Content

What's hot

Bridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_UgandaBridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_UgandaJavad Akhtar
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage ProjectAndrew Motycka
 
fact-sheet-wheatstone-project-overview
fact-sheet-wheatstone-project-overviewfact-sheet-wheatstone-project-overview
fact-sheet-wheatstone-project-overviewDevan Gopal
 
PIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases IPIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases ISven Maedler
 
Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation VDOT Northern Virginia
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
 
Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Fairfax County
 
Federal Projects - USFW Region 3
Federal Projects - USFW Region 3Federal Projects - USFW Region 3
Federal Projects - USFW Region 3jschelkoph
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectFairfax County
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Crosstown TO
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationFairfax County
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
urban design Makoko digital version
urban design Makoko digital versionurban design Makoko digital version
urban design Makoko digital versionIsmaila Aro
 

What's hot (18)

Bridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_UgandaBridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_Uganda
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Waterman Drainage Project
Waterman Drainage ProjectWaterman Drainage Project
Waterman Drainage Project
 
fact-sheet-wheatstone-project-overview
fact-sheet-wheatstone-project-overviewfact-sheet-wheatstone-project-overview
fact-sheet-wheatstone-project-overview
 
PIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases IPIS Uyo - Ring Road Phases I
PIS Uyo - Ring Road Phases I
 
Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 
site proj 1
site proj 1site proj 1
site proj 1
 
Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013
 
Ad
AdAd
Ad
 
Federal Projects - USFW Region 3
Federal Projects - USFW Region 3Federal Projects - USFW Region 3
Federal Projects - USFW Region 3
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement Project
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream Restoration
 
Dowling Road High Service Pump Station
Dowling Road High Service Pump StationDowling Road High Service Pump Station
Dowling Road High Service Pump Station
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
urban design Makoko digital version
urban design Makoko digital versionurban design Makoko digital version
urban design Makoko digital version
 
Hydraulic ppt
Hydraulic pptHydraulic ppt
Hydraulic ppt
 

Similar to Water tank duplication project in Harvey, Australia

Kenworth Trucks saving water case study
Kenworth Trucks saving water case studyKenworth Trucks saving water case study
Kenworth Trucks saving water case studyNEXTDC
 
Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report Honolulu Civil Beat
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Honolulu Civil Beat
 
Mackay Bluewater Trail Projects
Mackay Bluewater Trail Projects Mackay Bluewater Trail Projects
Mackay Bluewater Trail Projects guest387c76
 
Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project Deshan Arachchige
 
Feb. 24 Waste Management Daily Progress Report
Feb. 24 Waste Management Daily Progress Report Feb. 24 Waste Management Daily Progress Report
Feb. 24 Waste Management Daily Progress Report Honolulu Civil Beat
 
1282927519Leaflet-204
1282927519Leaflet-2041282927519Leaflet-204
1282927519Leaflet-204Obada Alsaqqa
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015Blase Townsing
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Honolulu Civil Beat
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
MedupiFactSheetSept2013
MedupiFactSheetSept2013MedupiFactSheetSept2013
MedupiFactSheetSept2013Matthew Wright
 
Cronulla wastewater treatment plant
Cronulla wastewater treatment plantCronulla wastewater treatment plant
Cronulla wastewater treatment plantRick Nabett
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Ryan Johnson
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationFairfax County
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportHonolulu Civil Beat
 
March 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress ReportMarch 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportHonolulu Civil Beat
 

Similar to Water tank duplication project in Harvey, Australia (20)

Kenworth Trucks saving water case study
Kenworth Trucks saving water case studyKenworth Trucks saving water case study
Kenworth Trucks saving water case study
 
Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report
 
SFPUC-#377404v1.PDF
SFPUC-#377404v1.PDFSFPUC-#377404v1.PDF
SFPUC-#377404v1.PDF
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report
 
Mackay Bluewater Trail Projects
Mackay Bluewater Trail Projects Mackay Bluewater Trail Projects
Mackay Bluewater Trail Projects
 
Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project
 
Feb. 24 Waste Management Daily Progress Report
Feb. 24 Waste Management Daily Progress Report Feb. 24 Waste Management Daily Progress Report
Feb. 24 Waste Management Daily Progress Report
 
1282927519Leaflet-204
1282927519Leaflet-2041282927519Leaflet-204
1282927519Leaflet-204
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
 
Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
MedupiFactSheetSept2013
MedupiFactSheetSept2013MedupiFactSheetSept2013
MedupiFactSheetSept2013
 
Swansea lagoon presentation by ioan jenkins
Swansea lagoon presentation by ioan jenkinsSwansea lagoon presentation by ioan jenkins
Swansea lagoon presentation by ioan jenkins
 
Cronulla wastewater treatment plant
Cronulla wastewater treatment plantCronulla wastewater treatment plant
Cronulla wastewater treatment plant
 
Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15Town of Scitutate job story Underground Construction 10-1-15
Town of Scitutate job story Underground Construction 10-1-15
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall Restoration
 
Abergeldie Marine
Abergeldie MarineAbergeldie Marine
Abergeldie Marine
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress Report
 
March 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress ReportMarch 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress Report
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress Report
 

Water tank duplication project in Harvey, Australia

  • 1. ID3190 Edited2008 www.vsl.com Water tank duplication, Harvey – Australia Provision of a new precast tank to double available water storage OWNER Water Corporation of WA MAIN CONTRACTOR VSL - AJ Lucas JV VSL ENTITY VSL Australia DATE 2011/2012 ▲ The project involved doubling the Water Corporation's water storage capacity at the Harvey site. The Southern Seawater Desalination Plant (SSDP) is Western Australia's second major desalination project. The plant is located at Taranto Road, north of Binningup, approximately 150km south of Perth. Water Corporation received conditional environmental approval for the plant in June 2009. Construction of the new plant began the following month, once full project approval had been received from the Federal Government. The plant is being built in two stages, each with a maximum capacity of 50 giga litres (GL) a year. Initially, VSL worked as a subcontractor on the first tank at Binningup, with a scope of work that included design and construction of the tank base slab, walls and the roof. VSL has since been appointed to work on a second tank, under a sub-contract to AJ Lucas. The first stage of the scheme was officially opened in September 2011 and is expected to reach its full capacity of 50GL/year within a year. It was completed three months ahead of schedule and required an investment of AU$955 million. A second stage of the project was announced in August 2011. It will involve expansion of the plant's capacity from 50GL/year to 100GL/year. The project involves construction of a 28km-long underground pipeline from Binningup to a storage facility comprising four summit tanks located northeast of Harvey. The pipeline will facilitate the transfer of potable water from the plant to the integrated water supply scheme. Scope of works performed Design, manufacture, supply, construction and testing of a second precast, post-tensioned concrete, circular, roofed water storage tank at the Water Corporation’s Harvey summit tank site. The plant is owned by Water Corporation which is the main provider of water, wastewater and drainage services in Western Australia. The new plant has the potential to deliver 30% of the state's water supply from climate-independent water sources. It is expected to deliver total potable water savings of up to 1,200GL a year.