SlideShare a Scribd company logo
1 of 54
HUAWEITECHNOLOGIES Co., Ltd.
www.huawei.com
HUAWEIConfidential
Internal Use (Only)Dec. 31 2006
GSM BSS Training Team
CNE040613040006 HUAWEI BSC6000
Software
Commissioning
ISSUE 1.0
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
This presentation describes the preparations
and process for commissioning of the
HUAWEI BSC6000. It also describes the
verification of data services for the Abis
interface, Ater interface, A interface, and Pb
interface.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Reference
 HUAWEI BSC6000 Base Station
Controller Software Installation Guide
 HUAWEI BSC6000 Base Station
Controller Commissioning Guide
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 After learning the course, you can familiarize
yourself with
 BSC6000 commissioning preparations
 BSC6000 commissioning process
 Data verification methods for BSC interfaces
 BSC6000 service verification
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Chapter 1 Overview of Commissioning
Chapter 2 Commissioning of Interface
Chapter 3 Service Verification
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Typical Networking
 The following figure shows a typical networking structure for the BSC6000:
Alarm box
LMT
MS BTS
GBAM
BSC6000
LAN Switch
MSC
PCU
LMT
Um Abis A
M2000
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Overview of Commissioning for BSC6000
 Keep the following installation disks ready before the commissioning
 OMU software installation disk of the correct version
 LMT software installation disk of the correct version
 Keep the following License file ready
 The License file that matches the office configuration has been requested
by Huawei technical support engineers
 Keep configuration data ready
According to the HUAWEI BSC6000 Base Station Controller Data
Configuration Guide, keep the following data ready and correct:
 Board data
 Abis/Ater/A/Pb interface data
 Other related commissioning data
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Overview of Commissioning for BSC6000
 Preparations for equipment
 A minimum of one BTS is connected to the BSC6000. The
commissioning of the BTS is completed and the BTS can provide the
basic functions.
 A minimum of one MSC is connected to the BSC6000. The
commissioning of the MSC is completed and the MSC can provide the
basic functions.
 A minimum of one PCU is connected to the BSC6000. The
commissioning of the PCU is completed and the PCU can provide basic
PS functions.
 Three single-mode MSs and one dual-mode MS used for testing are
ready and subscribed in the HLR.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Chapter 1 Overview of Commissioning
Chapter 2 Commissioning of Interface
Chapter 3 Service Verification
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Process of System Commissioning
 The commissioning process for the BSC6000 is as follows according
to priority:
 Load the BSC host software
 Load the BTS software
 Verify the Abis interface
 Verify the Ater interface
 Verify the A interface
 Verify the Pb interface
 Connect the BSC6000 to the M2000
 Refer to the presentation “HUAWEI BSC6000 Software Management”
for steps of loading BSC host software and BTS software.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Loading BSC Host Software
 Ensure the following condition before
loading the BSC host software:
 The BSC host software (all files in
BSC6000bscswmarea1software)
exists under the directory of LMT
Installation
DirectoryCommonSWMSoftware.
 The process of loading the BSC host
software is shown on the right.
Download software
Check GBAM version area
Load software
Activate software
Query board software
Query board information
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Loading BTS Software
 Ensure the following conditions before
loading the BTS software:
 The BTS software exists in the related
directory of the LMT.
 The BSC and the BTS are correctly
connected and the operation and
maintenance unit (OMU) of the BTS is
operational.
 The process of loading the BTS software
is shown on the right.
Download BTS software
Configure BTS software
Load BTS software
Query BTS properties
Activate BTS software
Query board information
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Commissioning for BSC
 The commissioning for the BSC comprises the following operations
without precedence:
 Perform active/standby switchover
 Query the License
 Process alarms
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the switchover function of active and standby boards is operational.
 Procedure
Choose the menu BSC Maintenance > Maintain Device > Switch Over BSC Board .
 Perform active/standby switchover tests for all boards that work in active/standby mode.
 Perform active/standby switchover once again to restore the status of the active and
standby boards.
Performing Active/Standby Switchover
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Querying License
 Purpose
To check whether the feature services based on the License file are valid.
 Procedure
Choose the menu BSC Maintenance > Maintain License > Query License and
click Query in the Query License window.
The query results are displayed in the list.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To complete the processing of real-time alarms before the interface commissioning.
 Procedure
 Choose Alarm Maintenance> Browse Alarm to query real-time alarms.
 Process each alarm according to the alarm processing steps in Online Help.
Processing Alarms
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Abis Interface
 Ensure the following conditions before
verifying the Abis interface:
 The BSC commissioning is passed.
 The physical transmission between the
BSC and the BTS is connected.
 The commissioning for the BTS used for
testing the Abis interface is completed
and the BTS is in “cell to be set up”
state.
 The process of verifying the Abis
interface is shown on the right.
Verify physical link
Verify management plane link
Verify user plane channel
Process alarms
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the physical link of the Abis interface is operational when E1/T1
bears the Abis interface.
 Procedure
Choose the menu BSC Maintenance > Maintain Transmission and Signaling >
Query Interface Board Port State .
The link information is displayed in the following figure:
Verifying Physical Link
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the management plane link (OML) between the BSC and the BTS
is operational.
 Procedure :
 Choose the menu BSC Maintenance > Maintain Transmission and Signaling
> Maintain LAPD Link.
 Query the OML of the related BTS.
Verifying Management Plane Link
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the control plane link (RSL) between the BSC and the BTS is
operational.
 Procedure
 Choose the menu BSC Maintenance > Maintain Transmission and Signaling
> Maintain LAPD Link..
 Query the RSL of the related BTS.
Verifying Control Plane Link
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the user plane
channel between the BSC and the BTS
is operational.
 Procedure
Choose the menu BSC Maintenance
> Maintain User Resource > Query
Abis Interface Timeslot State. to view
the following information.
Verifying User Plane Channel
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Ater Interface
 Ensure the following conditions
before verifying the Ater interface for
the remote GTCS:
 The BSC commissioning is passed.
 The physical transmission between
the GMPS/GEPS and the GTCS is
connected.
 The process of verifying the Ater
interface is shown on the right.
Verify management
plane link
Verify control
plane link
Verify user
plane channel
Process alarms
Verify physical link
Verify user plane
channel
Process alarms
GTCS remote configuration
GTCS local
configuration
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the physical link of the Ater interface is operational when E1/T1
bears the Ater interface (GTCS is locally configured).
 Procedure
 Search the subrack, slot, and port information for the Ater link to be verified.
 For example, Ater connection channel 0 corresponds to BM subrack 0, BM slot
16, BM port 0, TC subrack 3, TC slot 16, and TC port 0.
Verifying Physical Link
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Procedure
 Choose the menu BSC
Maintenance > Maintain
Transmission and
Signaling > Query Interface
Board Port State .
 If the status of port 1 in slot
14 of subrack 0 and the
status of port 1 in slot 14 of
subrack 5 are normal, the
Ater connection channel 0 is
operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 Purpose
To check whether the user plane channel of the Ater interface is operational when
E1/T1 bears the Ater interface (GTCS is locally configured).
 Procedure
Choose the menu BSC Maintenance > Maintain User Resource > Query Ater
Interface Timeslot State .
Type parameters in the query interface to query the timeslot status.
Verifying User Plane Channel
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Management Plane Link
 Purpose
To check whether the
management plane link of the Ater
interface is operational when the
GTCS is locally configured.
 Procedure
Choose the menu BSC
Maintenance > Maintain
Transmission and Signaling >
Query Ater OML State .
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying A Interface
 Ensure the following conditions before verifying
the A interface:
 The BSC commissioning is passed.
 The physical transmission between the BSC and
the MSC is connected.
 The MSC is operational.
 The process of verifying the A interface is shown
on the right.
Verify physical link
Verify control plane link
Verify user plane channel
Process alarms
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Purpose
To check whether the physical
link of the A interface is
operational when E1/T1 bears
the A interface.
 Procedure
 Step 1: In the main
interface, select the tab
BSC Information.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Procedure
 Step 2: Click the button E1 Interface in the previous window.
The subrack NO., slot NO., and port NO. of the A interface E1 are displayed in
the following interface.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Procedure
 Step 3: Choose the menu BSC Maintenance > Maintain Transmission and
Signaling > Query Interface Board Port State .
In the displayed interface, type the obtained subrack NO., slot NO., and port NO.
of the A interface E1.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Purpose
To check whether the control plane link of the A interface is operational.
 The control plane link indicates NO.7 transmission link. It can be categorized into
MTP2 link, MTP3 link, and SCCP link.
 The MTP2 is processed by the GEIUT board in the GEPS subrack. The MTP3
and SCCP are processed by the GXPUM board in the GEPS subrack.
 The link status is queried in the sequence of MTP2 link, MTP3 link, and SCCP
link.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 1: In the main interface, select the tab BSC information.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 2: Click the button SS7 Signaling Link in the previous window.
The obtained Ater Connection Channel Index NO. is 0. The related
MTP2 is processed by CPU 0 of the GXPUM in slot 0.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 3: In the main interface, select the tab BSC Information and click the button
Ater Connection Channel.
The Ater connection channel 0 is configured in the GEIUT board in slot 14 of the
GEPS subrack 0.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 4: Choose the menu BSC Maintenance > Maintain Transmission and
Signaling > Query MTP2 Link State.
Type 0 in Subrack NO., 14 in Slot NO., and 0 in Link NO. and then click the
button Query.
If Link Status is Service Subscribed, the MTP2 link is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 5: Choose the menu BSC Maintenance > Maintain Transmission and
Signaling > Query MTP3 Link State .
Select subrack 0, slot 14, link 0, GXPUM 0, and CPU 0 and then click the button
Query.
If the link status is available, the MTP3 link is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 6: Choose the menu BSC Maintenance > Maintain Transmission and
Signaling > Maintain SCCP .
Type 0 in DSP Index, select Query in Operation, and click the button Query.
If both DSP Status and SCCP Status are Allowed and Congestion Status is
Normal, the DSP status of the SCCP link is normal.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Procedure
 Step 7: In the tab page Subsystem Operation, type the subsystem index NO.,
select Query in Operation, and click the button Query. Query the status of
subsystems 0 to 3.
If Subsystem Status is all Normal, the SCCP link subsystem is operational. If
the MTP2, MTP3, and SCCP link status are all normal, the control plane link of
the A interface is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying User Plane Channel
 Purpose
To check whether the user plane
channel of the A interface is operational
when E1/T1 bears the A interface.
 Procedure
 Choose the menu BSC
Maintenance > Maintain User
Resource > Maintain A Interface
Circuit.
 Select the GTCS subrack NO., type
the CIC number range, and click
Query.
 If CIC status is Idle or Busy, the A
interface circuit channel is
operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Pb Interface
 Ensure the following conditions before
verifying the Pb interface:
 The BSC commissioning is passed.
 The transmission between the BSC and the
PCU is connected.
 The PCU is operational.
 The process of verifying the Pb interface is
shown on the right.
Verify physical link
Verify control plane link
Verify user plane link
Process alarms
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Purpose
To check whether the physical channel of the Pb interface is operational when E1/T1
bears the Pb interface.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Physical Link
 Procedure
Choose the menu BSC Maintenance > Maintain Transmission and Signaling >
Query Interface Board Port State .
In the displayed interface, select the subrack NO., slot NO., and port NO. for the
GEIUP board connected to the PCU.
If Port Status is Normal, the Pb interface physical link is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Control Plane Link
 Purpose
To check whether the control plane link of the Pb interface is operational.
 Procedure
Choose the menu BSC Maintenance > Maintain Transmission and Signaling >
Maintain LAPD Link .
Select PBSL under LAPD Link Range, select PCU from Candidate NE, and click the
Query button.
If PBSL link status is normal, the control plane link of the Pb interface is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying User Plane Channel
 Purpose
To check whether the user plane channel of the Pb interface is operational when
E1/T1 bears the Pb interface.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying User Plane Channel
 Procedure
Choose the menuBSC Maintenance > Maintain User Resource > Maintain Pb
Interface Circuit .
In the displayed interface, select Pb interface position, and select the subrack NO.,
PCU NO., and CIC number range.
If CIC status is Not Installed, Idle, or Busy, the user plane channel of the Pb
interface is operational.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Chapter 1 Overview of Commissioning
Chapter 2 Commissioning of Interface
Chapter 3 Service Verification
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Verifying Services
 Ensure the following conditions before verifying services:
 The BSC commissioning is passed.
 The commissioning for the Abis, Ater, A, and Pb interfaces is passed.
 The test MS is functional and already subscribed in the HLR.
 Verification services comprise
 Dialing test for basic services
 Dialing test for feature services
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Dialing Test for Basic Services
 Purpose
To check whether the BSC6000 can provide basic services.
 The basic services can be categorized into speech services, packet
services, and O&M management services.
 Before verifying the basic services, start the related interface message
tracking on the LMT.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Dialing Test for Basic Services
Basic
Service
Procedure of Dialing Test Expected Result
Speech
service
Use a test MS to dial a fixed-line phone for
50 times, and use the fixed-line phone to
dial the test MS for 50 times.
The call proceeding success ratio is
more than 90%.
Speech is clear and no evident
noise exists.
Use a test MS to dial another MS for 50
times.
The call proceeding success ratio is
more than 90%.
Speech is clear and no evident
noise exists.
Data service
Use a test MS to send fax to the fax
machine, and use the fax machine to send
a fax to the MS.
The fax file is sent and received
correctly.
Use a test MS to test GPRS or EDGE
service functions.
The data rate is consistent with the
test data rate obtained in the lab.
O&M
management
While services are running, perform
active/standby switchover 5 times for the
boards GXPU, GSCU, GTNU, GPUC,
GEIU, and GGCU.
The switchover success ratio is
more than 90%. The running
services are not affected.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Dialing Test for Feature Service
 Purpose
To check whether the BSC6000 can provide License feature services.
 Feature services vary according to offices. This presentation describes
inter-system handover service, location service, and AMR service.
 Before verifying the feature services, start the related interface message
tracking on the LMT.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Dialing Test for Feature Service
Feature
Service
Procedure of Dialing Test Requirement
Inter-
system
handover
service
Handover a dual-mode MS
from the GSM network to the
UMTS network for 50 times.
Handover the dual-mode MS
from the UMTS network to the
GSM network for 50 times.
The call proceeding success
ratio is more than 90%.
Speech is clear and no
evident noise exists.
Location
service
Use a test MS to initiate a call.
Locate the MS while the
connection is in hold.
The MS position meets the
precision requirements.
AMR
service
Use a test MS to dial a fixed-
line phone for 50 times. Select
the speech version at AMR.
The call proceeding success
ratio is more than 90%.
Speech is clear and no
evident noise exists.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
Connecting BSC6000 to M2000
 Perform the following operations on the Telnet terminal of the
BSC6000:
 Run the route command to query the configured route information.
The information about the route to the M2000 is displayed. The route
information is configured on the GBAM server.
 If route information exists, the operation is completed.
 If route information does not exist, run the route command.
Set Destination Network Address to M2000 Server IP Address, set
Destination Address Mask to M2000 Server IP Address Mask, and set
Forward Routing Address to Router IP Address.
HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential
 This presentation describes the following
information about the HUAWEI BSC6000:
 Commissioning preparations and
precautions
 System commissioning process
 Verification methods of interface data
 Service verification methods and steps
HUAWEITECHNOLOGIES Co., Ltd.
www.huawei.com
HUAWEIConfidential
Internal Use (Only)Dec. 31 2006
GSM BSS Training Team
Thank You
www.huawei.com

More Related Content

What's hot

060626 huawei umts end to-end solution
060626 huawei umts end to-end solution060626 huawei umts end to-end solution
060626 huawei umts end to-end solutionVacaba TOURE
 
Huawei wcdma ran10.0 overview
Huawei wcdma ran10.0 overviewHuawei wcdma ran10.0 overview
Huawei wcdma ran10.0 overviewRiadh Bachrouch
 
01 Bts3900 System Structure
01 Bts3900 System Structure01 Bts3900 System Structure
01 Bts3900 System StructureAtif Mahmood
 
Training wcdma rf optimization gsm to umts
Training wcdma rf optimization gsm to umtsTraining wcdma rf optimization gsm to umts
Training wcdma rf optimization gsm to umtsAbed Abed
 
Huawei node b technical-description
Huawei node b technical-descriptionHuawei node b technical-description
Huawei node b technical-descriptionYasir Jami
 
Bts3900 vii upgrade cell pp medical
Bts3900 vii upgrade cell pp medicalBts3900 vii upgrade cell pp medical
Bts3900 vii upgrade cell pp medicalsopheak086
 
83092299 rru3804-overview
83092299 rru3804-overview83092299 rru3804-overview
83092299 rru3804-overviewSerik123
 
Mobilink 2G3G Swap Guide V1.8 20150406 (1)
Mobilink 2G3G Swap Guide V1.8 20150406 (1)Mobilink 2G3G Swap Guide V1.8 20150406 (1)
Mobilink 2G3G Swap Guide V1.8 20150406 (1)Abdul Mateen Rahim
 
Huawei GGSN 9811 hardware and software
Huawei GGSN 9811 hardware and software Huawei GGSN 9811 hardware and software
Huawei GGSN 9811 hardware and software Mario Gordon
 
Huawei GGSN 9811 software management
Huawei GGSN 9811 software managementHuawei GGSN 9811 software management
Huawei GGSN 9811 software managementMario Gordon
 
Huawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopHuawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopnavaidkhan
 
Abis Over IP/Abis Optimization on-site Workshop
Abis Over IP/Abis Optimization on-site WorkshopAbis Over IP/Abis Optimization on-site Workshop
Abis Over IP/Abis Optimization on-site Workshopetkisizcom
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-trainingShelton Siziba
 
Routing over ericsson mini link
Routing over ericsson mini linkRouting over ericsson mini link
Routing over ericsson mini linkAhmed Nabeeh
 

What's hot (18)

060626 huawei umts end to-end solution
060626 huawei umts end to-end solution060626 huawei umts end to-end solution
060626 huawei umts end to-end solution
 
Huawei wcdma ran10.0 overview
Huawei wcdma ran10.0 overviewHuawei wcdma ran10.0 overview
Huawei wcdma ran10.0 overview
 
01 Bts3900 System Structure
01 Bts3900 System Structure01 Bts3900 System Structure
01 Bts3900 System Structure
 
Training wcdma rf optimization gsm to umts
Training wcdma rf optimization gsm to umtsTraining wcdma rf optimization gsm to umts
Training wcdma rf optimization gsm to umts
 
Huawei node b technical-description
Huawei node b technical-descriptionHuawei node b technical-description
Huawei node b technical-description
 
Bts3900 vii upgrade cell pp medical
Bts3900 vii upgrade cell pp medicalBts3900 vii upgrade cell pp medical
Bts3900 vii upgrade cell pp medical
 
83092299 rru3804-overview
83092299 rru3804-overview83092299 rru3804-overview
83092299 rru3804-overview
 
Ome200301 gsm bts trouble shooting issue3.0
Ome200301 gsm bts trouble shooting issue3.0Ome200301 gsm bts trouble shooting issue3.0
Ome200301 gsm bts trouble shooting issue3.0
 
Mobilink 2G3G Swap Guide V1.8 20150406 (1)
Mobilink 2G3G Swap Guide V1.8 20150406 (1)Mobilink 2G3G Swap Guide V1.8 20150406 (1)
Mobilink 2G3G Swap Guide V1.8 20150406 (1)
 
Huawei GGSN 9811 hardware and software
Huawei GGSN 9811 hardware and software Huawei GGSN 9811 hardware and software
Huawei GGSN 9811 hardware and software
 
Rtn
RtnRtn
Rtn
 
Huawei GGSN 9811 software management
Huawei GGSN 9811 software managementHuawei GGSN 9811 software management
Huawei GGSN 9811 software management
 
Huawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shopHuawei - Access failures troubleshooting work shop
Huawei - Access failures troubleshooting work shop
 
Abis Over IP/Abis Optimization on-site Workshop
Abis Over IP/Abis Optimization on-site WorkshopAbis Over IP/Abis Optimization on-site Workshop
Abis Over IP/Abis Optimization on-site Workshop
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training
 
Step by step to install tn6 p
Step by step to install tn6 pStep by step to install tn6 p
Step by step to install tn6 p
 
Huawei bts3012 hardware structure issue1.0
Huawei bts3012 hardware structure issue1.0Huawei bts3012 hardware structure issue1.0
Huawei bts3012 hardware structure issue1.0
 
Routing over ericsson mini link
Routing over ericsson mini linkRouting over ericsson mini link
Routing over ericsson mini link
 

Viewers also liked

Bts3900 gsm commissioning guide (v300 r008-03)
Bts3900 gsm commissioning guide (v300 r008-03)Bts3900 gsm commissioning guide (v300 r008-03)
Bts3900 gsm commissioning guide (v300 r008-03)ihtisham ulhaq
 
02 opti x rtn 900 v100r002 configuration guide-20100119-a
02 opti x rtn 900 v100r002 configuration guide-20100119-a02 opti x rtn 900 v100r002 configuration guide-20100119-a
02 opti x rtn 900 v100r002 configuration guide-20100119-aWaheed Ali
 
Training on microwave communication
Training on microwave communicationTraining on microwave communication
Training on microwave communicationTempus Telcosys
 
Bsc6900 gsm-site-maintenance-guide
Bsc6900 gsm-site-maintenance-guideBsc6900 gsm-site-maintenance-guide
Bsc6900 gsm-site-maintenance-guidemalikaliasadawan
 
Huawei RET alarms Troubleshooting Guide Flow Chart
Huawei RET alarms Troubleshooting Guide   Flow Chart Huawei RET alarms Troubleshooting Guide   Flow Chart
Huawei RET alarms Troubleshooting Guide Flow Chart Mohamed Abd El Razek Bakry
 
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...eieiswe
 
G2 bsc commissioning manual release b7.2
G2 bsc commissioning manual   release b7.2G2 bsc commissioning manual   release b7.2
G2 bsc commissioning manual release b7.2chungminh1108
 
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001Max Gathers
 
Wavelink Presentation(Updated)
Wavelink Presentation(Updated)Wavelink Presentation(Updated)
Wavelink Presentation(Updated)slavun
 
G2 bsc commissioning manual release b7.2 ccl
G2 bsc commissioning manual   release b7.2 cclG2 bsc commissioning manual   release b7.2 ccl
G2 bsc commissioning manual release b7.2 cclchungminh1108
 
Practical 2 g and 3g rf engineering
Practical 2 g and 3g rf engineeringPractical 2 g and 3g rf engineering
Practical 2 g and 3g rf engineeringNeonetwireless
 
Field commissioning
Field commissioningField commissioning
Field commissioningAmjad Jamil
 
Henry s software_engineer__resume _07_15_new
Henry s software_engineer__resume _07_15_newHenry s software_engineer__resume _07_15_new
Henry s software_engineer__resume _07_15_newHenry Sun
 

Viewers also liked (20)

Bts3900 gsm commissioning guide (v300 r008-03)
Bts3900 gsm commissioning guide (v300 r008-03)Bts3900 gsm commissioning guide (v300 r008-03)
Bts3900 gsm commissioning guide (v300 r008-03)
 
02 opti x rtn 900 v100r002 configuration guide-20100119-a
02 opti x rtn 900 v100r002 configuration guide-20100119-a02 opti x rtn 900 v100r002 configuration guide-20100119-a
02 opti x rtn 900 v100r002 configuration guide-20100119-a
 
Training on microwave communication
Training on microwave communicationTraining on microwave communication
Training on microwave communication
 
Microwave Antenna
Microwave AntennaMicrowave Antenna
Microwave Antenna
 
Huawei bsc 6900
Huawei bsc 6900Huawei bsc 6900
Huawei bsc 6900
 
Bsc6900 gsm-site-maintenance-guide
Bsc6900 gsm-site-maintenance-guideBsc6900 gsm-site-maintenance-guide
Bsc6900 gsm-site-maintenance-guide
 
Huawei RET alarms Troubleshooting Guide Flow Chart
Huawei RET alarms Troubleshooting Guide   Flow Chart Huawei RET alarms Troubleshooting Guide   Flow Chart
Huawei RET alarms Troubleshooting Guide Flow Chart
 
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...
Hnc2014 wan interconnection huawei new-generation ip long haul microwave solu...
 
G2 bsc commissioning manual release b7.2
G2 bsc commissioning manual   release b7.2G2 bsc commissioning manual   release b7.2
G2 bsc commissioning manual release b7.2
 
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001
US CELLULAR FLEXI LTE BTS COMMISSIONING AND INTEGRATION 4G-LTE 001
 
Wavelink Presentation(Updated)
Wavelink Presentation(Updated)Wavelink Presentation(Updated)
Wavelink Presentation(Updated)
 
CV_Devesh
CV_DeveshCV_Devesh
CV_Devesh
 
msvel
msvelmsvel
msvel
 
G2 bsc commissioning manual release b7.2 ccl
G2 bsc commissioning manual   release b7.2 cclG2 bsc commissioning manual   release b7.2 ccl
G2 bsc commissioning manual release b7.2 ccl
 
Mobiserve
MobiserveMobiserve
Mobiserve
 
Execu health, inc
Execu health, incExecu health, inc
Execu health, inc
 
177-Glimmer
177-Glimmer177-Glimmer
177-Glimmer
 
Practical 2 g and 3g rf engineering
Practical 2 g and 3g rf engineeringPractical 2 g and 3g rf engineering
Practical 2 g and 3g rf engineering
 
Field commissioning
Field commissioningField commissioning
Field commissioning
 
Henry s software_engineer__resume _07_15_new
Henry s software_engineer__resume _07_15_newHenry s software_engineer__resume _07_15_new
Henry s software_engineer__resume _07_15_new
 

Similar to 5. ene040613040006 huawei bsc6000 software commissioning 20061231-a-1.0

2gcaseanalsyishandover training
2gcaseanalsyishandover training2gcaseanalsyishandover training
2gcaseanalsyishandover trainingTerra Sacrifice
 
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp012gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01Ahabwe Brian
 
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp012gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01Rawlings Bello
 
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.ppt
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.pptOperation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.ppt
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.pptssuser0fb6a0
 
Umts access kpi troubleshooting guide rrc
Umts access kpi troubleshooting guide   rrcUmts access kpi troubleshooting guide   rrc
Umts access kpi troubleshooting guide rrcPrashant Gaurav
 
Driver in Labview (2)
Driver in Labview (2)Driver in Labview (2)
Driver in Labview (2)Mazumder Alam
 
DCS FIELDBUS Integrate hse subnet
DCS FIELDBUS Integrate hse subnet DCS FIELDBUS Integrate hse subnet
DCS FIELDBUS Integrate hse subnet Ashvani Shukla
 
DCS and Fieldbus Software installation
DCS and Fieldbus Software installation DCS and Fieldbus Software installation
DCS and Fieldbus Software installation Ashvani Shukla
 
HP_HPE6-A70_March_2023-v1.2.pdf
HP_HPE6-A70_March_2023-v1.2.pdfHP_HPE6-A70_March_2023-v1.2.pdf
HP_HPE6-A70_March_2023-v1.2.pdfCCIEHOMER
 
Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications Ashvani Shukla
 
crosstalk-monitoring
crosstalk-monitoringcrosstalk-monitoring
crosstalk-monitoringCA2009
 
400-351 Exam-CCIE Wireless
400-351 Exam-CCIE Wireless  400-351 Exam-CCIE Wireless
400-351 Exam-CCIE Wireless Isabella789
 
Aruba os 6.3.x quick start guide
Aruba os 6.3.x quick start guideAruba os 6.3.x quick start guide
Aruba os 6.3.x quick start guideDave Norris
 
Sap bpc Planning and consolidation
Sap bpc Planning and consolidationSap bpc Planning and consolidation
Sap bpc Planning and consolidationSreekanth Gogula
 
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.pptob700586
 
DetailsiBeacon_endocsSetupBeaconInIOS.pdf
DetailsiBeacon_endocsSetupBeaconInIOS.pdfDetailsiBeacon_endocsSetupBeaconInIOS.pdf
DetailsiBeacon_endocsSetupBeaconInIOS.pdfSomnathKhamaru1
 
CertsOut IBM-C1000-130 Dumps.pdf
CertsOut IBM-C1000-130 Dumps.pdfCertsOut IBM-C1000-130 Dumps.pdf
CertsOut IBM-C1000-130 Dumps.pdfJeannieHeldt
 
Dnyaneshwar_Anantwar_Resume
Dnyaneshwar_Anantwar_ResumeDnyaneshwar_Anantwar_Resume
Dnyaneshwar_Anantwar_Resumearyan9011079624
 

Similar to 5. ene040613040006 huawei bsc6000 software commissioning 20061231-a-1.0 (20)

2gcaseanalsyishandover training
2gcaseanalsyishandover training2gcaseanalsyishandover training
2gcaseanalsyishandover training
 
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp012gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
 
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp012gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
2gcaseanalsyishandover training-20060901-a-2-0-130118232643-phpapp01
 
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.ppt
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.pptOperation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.ppt
Operation_and_Maintenance_Guide_of_the_BSC6900_GSM_Based_on_the_Web_LMT.ppt
 
Umts access kpi troubleshooting guide rrc
Umts access kpi troubleshooting guide   rrcUmts access kpi troubleshooting guide   rrc
Umts access kpi troubleshooting guide rrc
 
Driver in Labview (2)
Driver in Labview (2)Driver in Labview (2)
Driver in Labview (2)
 
DCS FIELDBUS Integrate hse subnet
DCS FIELDBUS Integrate hse subnet DCS FIELDBUS Integrate hse subnet
DCS FIELDBUS Integrate hse subnet
 
DCS and Fieldbus Software installation
DCS and Fieldbus Software installation DCS and Fieldbus Software installation
DCS and Fieldbus Software installation
 
HP_HPE6-A70_March_2023-v1.2.pdf
HP_HPE6-A70_March_2023-v1.2.pdfHP_HPE6-A70_March_2023-v1.2.pdf
HP_HPE6-A70_March_2023-v1.2.pdf
 
Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications
 
crosstalk-monitoring
crosstalk-monitoringcrosstalk-monitoring
crosstalk-monitoring
 
400-351 Exam-CCIE Wireless
400-351 Exam-CCIE Wireless  400-351 Exam-CCIE Wireless
400-351 Exam-CCIE Wireless
 
ArubaOS 6.3.x Quick Start Guide
ArubaOS 6.3.x Quick Start GuideArubaOS 6.3.x Quick Start Guide
ArubaOS 6.3.x Quick Start Guide
 
Aruba os 6.3.x quick start guide
Aruba os 6.3.x quick start guideAruba os 6.3.x quick start guide
Aruba os 6.3.x quick start guide
 
Sap bpc Planning and consolidation
Sap bpc Planning and consolidationSap bpc Planning and consolidation
Sap bpc Planning and consolidation
 
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt
8- OMO211000 GSM M2000 Perfomance Management ISSUE1.0.ppt
 
DetailsiBeacon_endocsSetupBeaconInIOS.pdf
DetailsiBeacon_endocsSetupBeaconInIOS.pdfDetailsiBeacon_endocsSetupBeaconInIOS.pdf
DetailsiBeacon_endocsSetupBeaconInIOS.pdf
 
Airheads dallas 2011 rap troubleshooting
Airheads dallas 2011   rap troubleshootingAirheads dallas 2011   rap troubleshooting
Airheads dallas 2011 rap troubleshooting
 
CertsOut IBM-C1000-130 Dumps.pdf
CertsOut IBM-C1000-130 Dumps.pdfCertsOut IBM-C1000-130 Dumps.pdf
CertsOut IBM-C1000-130 Dumps.pdf
 
Dnyaneshwar_Anantwar_Resume
Dnyaneshwar_Anantwar_ResumeDnyaneshwar_Anantwar_Resume
Dnyaneshwar_Anantwar_Resume
 

Recently uploaded

SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsPrecisely
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 

Recently uploaded (20)

SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power Systems
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 

5. ene040613040006 huawei bsc6000 software commissioning 20061231-a-1.0

  • 1. HUAWEITECHNOLOGIES Co., Ltd. www.huawei.com HUAWEIConfidential Internal Use (Only)Dec. 31 2006 GSM BSS Training Team CNE040613040006 HUAWEI BSC6000 Software Commissioning ISSUE 1.0
  • 2. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential This presentation describes the preparations and process for commissioning of the HUAWEI BSC6000. It also describes the verification of data services for the Abis interface, Ater interface, A interface, and Pb interface.
  • 3. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Reference  HUAWEI BSC6000 Base Station Controller Software Installation Guide  HUAWEI BSC6000 Base Station Controller Commissioning Guide
  • 4. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  After learning the course, you can familiarize yourself with  BSC6000 commissioning preparations  BSC6000 commissioning process  Data verification methods for BSC interfaces  BSC6000 service verification
  • 5. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Chapter 1 Overview of Commissioning Chapter 2 Commissioning of Interface Chapter 3 Service Verification
  • 6. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Typical Networking  The following figure shows a typical networking structure for the BSC6000: Alarm box LMT MS BTS GBAM BSC6000 LAN Switch MSC PCU LMT Um Abis A M2000
  • 7. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Overview of Commissioning for BSC6000  Keep the following installation disks ready before the commissioning  OMU software installation disk of the correct version  LMT software installation disk of the correct version  Keep the following License file ready  The License file that matches the office configuration has been requested by Huawei technical support engineers  Keep configuration data ready According to the HUAWEI BSC6000 Base Station Controller Data Configuration Guide, keep the following data ready and correct:  Board data  Abis/Ater/A/Pb interface data  Other related commissioning data
  • 8. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Overview of Commissioning for BSC6000  Preparations for equipment  A minimum of one BTS is connected to the BSC6000. The commissioning of the BTS is completed and the BTS can provide the basic functions.  A minimum of one MSC is connected to the BSC6000. The commissioning of the MSC is completed and the MSC can provide the basic functions.  A minimum of one PCU is connected to the BSC6000. The commissioning of the PCU is completed and the PCU can provide basic PS functions.  Three single-mode MSs and one dual-mode MS used for testing are ready and subscribed in the HLR.
  • 9. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Chapter 1 Overview of Commissioning Chapter 2 Commissioning of Interface Chapter 3 Service Verification
  • 10. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Process of System Commissioning  The commissioning process for the BSC6000 is as follows according to priority:  Load the BSC host software  Load the BTS software  Verify the Abis interface  Verify the Ater interface  Verify the A interface  Verify the Pb interface  Connect the BSC6000 to the M2000  Refer to the presentation “HUAWEI BSC6000 Software Management” for steps of loading BSC host software and BTS software.
  • 11. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Loading BSC Host Software  Ensure the following condition before loading the BSC host software:  The BSC host software (all files in BSC6000bscswmarea1software) exists under the directory of LMT Installation DirectoryCommonSWMSoftware.  The process of loading the BSC host software is shown on the right. Download software Check GBAM version area Load software Activate software Query board software Query board information
  • 12. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Loading BTS Software  Ensure the following conditions before loading the BTS software:  The BTS software exists in the related directory of the LMT.  The BSC and the BTS are correctly connected and the operation and maintenance unit (OMU) of the BTS is operational.  The process of loading the BTS software is shown on the right. Download BTS software Configure BTS software Load BTS software Query BTS properties Activate BTS software Query board information
  • 13. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Commissioning for BSC  The commissioning for the BSC comprises the following operations without precedence:  Perform active/standby switchover  Query the License  Process alarms
  • 14. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the switchover function of active and standby boards is operational.  Procedure Choose the menu BSC Maintenance > Maintain Device > Switch Over BSC Board .  Perform active/standby switchover tests for all boards that work in active/standby mode.  Perform active/standby switchover once again to restore the status of the active and standby boards. Performing Active/Standby Switchover
  • 15. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Querying License  Purpose To check whether the feature services based on the License file are valid.  Procedure Choose the menu BSC Maintenance > Maintain License > Query License and click Query in the Query License window. The query results are displayed in the list.
  • 16. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To complete the processing of real-time alarms before the interface commissioning.  Procedure  Choose Alarm Maintenance> Browse Alarm to query real-time alarms.  Process each alarm according to the alarm processing steps in Online Help. Processing Alarms
  • 17. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Abis Interface  Ensure the following conditions before verifying the Abis interface:  The BSC commissioning is passed.  The physical transmission between the BSC and the BTS is connected.  The commissioning for the BTS used for testing the Abis interface is completed and the BTS is in “cell to be set up” state.  The process of verifying the Abis interface is shown on the right. Verify physical link Verify management plane link Verify user plane channel Process alarms
  • 18. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the physical link of the Abis interface is operational when E1/T1 bears the Abis interface.  Procedure Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query Interface Board Port State . The link information is displayed in the following figure: Verifying Physical Link
  • 19. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the management plane link (OML) between the BSC and the BTS is operational.  Procedure :  Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Maintain LAPD Link.  Query the OML of the related BTS. Verifying Management Plane Link
  • 20. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the control plane link (RSL) between the BSC and the BTS is operational.  Procedure  Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Maintain LAPD Link..  Query the RSL of the related BTS. Verifying Control Plane Link
  • 21. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the user plane channel between the BSC and the BTS is operational.  Procedure Choose the menu BSC Maintenance > Maintain User Resource > Query Abis Interface Timeslot State. to view the following information. Verifying User Plane Channel
  • 22. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Ater Interface  Ensure the following conditions before verifying the Ater interface for the remote GTCS:  The BSC commissioning is passed.  The physical transmission between the GMPS/GEPS and the GTCS is connected.  The process of verifying the Ater interface is shown on the right. Verify management plane link Verify control plane link Verify user plane channel Process alarms Verify physical link Verify user plane channel Process alarms GTCS remote configuration GTCS local configuration
  • 23. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the physical link of the Ater interface is operational when E1/T1 bears the Ater interface (GTCS is locally configured).  Procedure  Search the subrack, slot, and port information for the Ater link to be verified.  For example, Ater connection channel 0 corresponds to BM subrack 0, BM slot 16, BM port 0, TC subrack 3, TC slot 16, and TC port 0. Verifying Physical Link
  • 24. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Procedure  Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query Interface Board Port State .  If the status of port 1 in slot 14 of subrack 0 and the status of port 1 in slot 14 of subrack 5 are normal, the Ater connection channel 0 is operational.
  • 25. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  Purpose To check whether the user plane channel of the Ater interface is operational when E1/T1 bears the Ater interface (GTCS is locally configured).  Procedure Choose the menu BSC Maintenance > Maintain User Resource > Query Ater Interface Timeslot State . Type parameters in the query interface to query the timeslot status. Verifying User Plane Channel
  • 26. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Management Plane Link  Purpose To check whether the management plane link of the Ater interface is operational when the GTCS is locally configured.  Procedure Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query Ater OML State .
  • 27. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying A Interface  Ensure the following conditions before verifying the A interface:  The BSC commissioning is passed.  The physical transmission between the BSC and the MSC is connected.  The MSC is operational.  The process of verifying the A interface is shown on the right. Verify physical link Verify control plane link Verify user plane channel Process alarms
  • 28. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Purpose To check whether the physical link of the A interface is operational when E1/T1 bears the A interface.  Procedure  Step 1: In the main interface, select the tab BSC Information.
  • 29. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Procedure  Step 2: Click the button E1 Interface in the previous window. The subrack NO., slot NO., and port NO. of the A interface E1 are displayed in the following interface.
  • 30. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Procedure  Step 3: Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query Interface Board Port State . In the displayed interface, type the obtained subrack NO., slot NO., and port NO. of the A interface E1.
  • 31. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Purpose To check whether the control plane link of the A interface is operational.  The control plane link indicates NO.7 transmission link. It can be categorized into MTP2 link, MTP3 link, and SCCP link.  The MTP2 is processed by the GEIUT board in the GEPS subrack. The MTP3 and SCCP are processed by the GXPUM board in the GEPS subrack.  The link status is queried in the sequence of MTP2 link, MTP3 link, and SCCP link.
  • 32. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 1: In the main interface, select the tab BSC information.
  • 33. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 2: Click the button SS7 Signaling Link in the previous window. The obtained Ater Connection Channel Index NO. is 0. The related MTP2 is processed by CPU 0 of the GXPUM in slot 0.
  • 34. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 3: In the main interface, select the tab BSC Information and click the button Ater Connection Channel. The Ater connection channel 0 is configured in the GEIUT board in slot 14 of the GEPS subrack 0.
  • 35. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 4: Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query MTP2 Link State. Type 0 in Subrack NO., 14 in Slot NO., and 0 in Link NO. and then click the button Query. If Link Status is Service Subscribed, the MTP2 link is operational.
  • 36. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 5: Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query MTP3 Link State . Select subrack 0, slot 14, link 0, GXPUM 0, and CPU 0 and then click the button Query. If the link status is available, the MTP3 link is operational.
  • 37. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 6: Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Maintain SCCP . Type 0 in DSP Index, select Query in Operation, and click the button Query. If both DSP Status and SCCP Status are Allowed and Congestion Status is Normal, the DSP status of the SCCP link is normal.
  • 38. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Procedure  Step 7: In the tab page Subsystem Operation, type the subsystem index NO., select Query in Operation, and click the button Query. Query the status of subsystems 0 to 3. If Subsystem Status is all Normal, the SCCP link subsystem is operational. If the MTP2, MTP3, and SCCP link status are all normal, the control plane link of the A interface is operational.
  • 39. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying User Plane Channel  Purpose To check whether the user plane channel of the A interface is operational when E1/T1 bears the A interface.  Procedure  Choose the menu BSC Maintenance > Maintain User Resource > Maintain A Interface Circuit.  Select the GTCS subrack NO., type the CIC number range, and click Query.  If CIC status is Idle or Busy, the A interface circuit channel is operational.
  • 40. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Pb Interface  Ensure the following conditions before verifying the Pb interface:  The BSC commissioning is passed.  The transmission between the BSC and the PCU is connected.  The PCU is operational.  The process of verifying the Pb interface is shown on the right. Verify physical link Verify control plane link Verify user plane link Process alarms
  • 41. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Purpose To check whether the physical channel of the Pb interface is operational when E1/T1 bears the Pb interface.
  • 42. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Physical Link  Procedure Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Query Interface Board Port State . In the displayed interface, select the subrack NO., slot NO., and port NO. for the GEIUP board connected to the PCU. If Port Status is Normal, the Pb interface physical link is operational.
  • 43. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Control Plane Link  Purpose To check whether the control plane link of the Pb interface is operational.  Procedure Choose the menu BSC Maintenance > Maintain Transmission and Signaling > Maintain LAPD Link . Select PBSL under LAPD Link Range, select PCU from Candidate NE, and click the Query button. If PBSL link status is normal, the control plane link of the Pb interface is operational.
  • 44. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying User Plane Channel  Purpose To check whether the user plane channel of the Pb interface is operational when E1/T1 bears the Pb interface.
  • 45. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying User Plane Channel  Procedure Choose the menuBSC Maintenance > Maintain User Resource > Maintain Pb Interface Circuit . In the displayed interface, select Pb interface position, and select the subrack NO., PCU NO., and CIC number range. If CIC status is Not Installed, Idle, or Busy, the user plane channel of the Pb interface is operational.
  • 46. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Chapter 1 Overview of Commissioning Chapter 2 Commissioning of Interface Chapter 3 Service Verification
  • 47. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Verifying Services  Ensure the following conditions before verifying services:  The BSC commissioning is passed.  The commissioning for the Abis, Ater, A, and Pb interfaces is passed.  The test MS is functional and already subscribed in the HLR.  Verification services comprise  Dialing test for basic services  Dialing test for feature services
  • 48. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Dialing Test for Basic Services  Purpose To check whether the BSC6000 can provide basic services.  The basic services can be categorized into speech services, packet services, and O&M management services.  Before verifying the basic services, start the related interface message tracking on the LMT.
  • 49. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Dialing Test for Basic Services Basic Service Procedure of Dialing Test Expected Result Speech service Use a test MS to dial a fixed-line phone for 50 times, and use the fixed-line phone to dial the test MS for 50 times. The call proceeding success ratio is more than 90%. Speech is clear and no evident noise exists. Use a test MS to dial another MS for 50 times. The call proceeding success ratio is more than 90%. Speech is clear and no evident noise exists. Data service Use a test MS to send fax to the fax machine, and use the fax machine to send a fax to the MS. The fax file is sent and received correctly. Use a test MS to test GPRS or EDGE service functions. The data rate is consistent with the test data rate obtained in the lab. O&M management While services are running, perform active/standby switchover 5 times for the boards GXPU, GSCU, GTNU, GPUC, GEIU, and GGCU. The switchover success ratio is more than 90%. The running services are not affected.
  • 50. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Dialing Test for Feature Service  Purpose To check whether the BSC6000 can provide License feature services.  Feature services vary according to offices. This presentation describes inter-system handover service, location service, and AMR service.  Before verifying the feature services, start the related interface message tracking on the LMT.
  • 51. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Dialing Test for Feature Service Feature Service Procedure of Dialing Test Requirement Inter- system handover service Handover a dual-mode MS from the GSM network to the UMTS network for 50 times. Handover the dual-mode MS from the UMTS network to the GSM network for 50 times. The call proceeding success ratio is more than 90%. Speech is clear and no evident noise exists. Location service Use a test MS to initiate a call. Locate the MS while the connection is in hold. The MS position meets the precision requirements. AMR service Use a test MS to dial a fixed- line phone for 50 times. Select the speech version at AMR. The call proceeding success ratio is more than 90%. Speech is clear and no evident noise exists.
  • 52. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential Connecting BSC6000 to M2000  Perform the following operations on the Telnet terminal of the BSC6000:  Run the route command to query the configured route information. The information about the route to the M2000 is displayed. The route information is configured on the GBAM server.  If route information exists, the operation is completed.  If route information does not exist, run the route command. Set Destination Network Address to M2000 Server IP Address, set Destination Address Mask to M2000 Server IP Address Mask, and set Forward Routing Address to Router IP Address.
  • 53. HUAWEITECHNOLOGIES Co., Ltd. HUAWEIConfidential  This presentation describes the following information about the HUAWEI BSC6000:  Commissioning preparations and precautions  System commissioning process  Verification methods of interface data  Service verification methods and steps
  • 54. HUAWEITECHNOLOGIES Co., Ltd. www.huawei.com HUAWEIConfidential Internal Use (Only)Dec. 31 2006 GSM BSS Training Team Thank You www.huawei.com