This document is a commissioning manual for a telecommunications system. It provides instructions over 10 sections for installing, configuring, and testing the hardware and software components of the system. The sections cover preparing the site, checking hardware, powering up racks, installing software, conducting commissioning tests of the links and functionality, and finishing the commissioning process. The document contains detailed technical steps and is intended to guide an engineer through the full commissioning of the system.
9. XVLQJ WKH :LQGRZV HQYLURQPHQW
'RFXPHQW 6WUXFWXUH 7KLV VHFWLRQ SURYLGHV D VXPPDU RI HDFK FKDSWHU
KDSWHU *HQHUDO GHVFULSWLRQ
7KLV FKDSWHU SURYLGHV JHQHUDO LQIRUPDWLRQ
FRQFHUQLQJ WKH RSHUDWLQJ SULQFLSOH DQG
UHTXLUHPHQWV RI WKH SURFHGXUH
s +DUGZDUH GHVFULSWLRQ
s 3UHUHTXLVLWHV
s 5HVWULFWLRQV
s ,QLWLDO VWDWH
s )LQDO VWDWH
s 7DVN VHTXHQFHV
s 7LPH VFKHGXOH
s ,QIRUPDWLRQ UHTXLUHG
13. General description
3BK 17416 3001 RJZZA 02 9 / 72A L EC T L
1 General description
This chapter provides general information concerning the
operating principle and requirements of the procedure:
s Hardware description
s Prerequisites
s Restrictions
s Initial state
s Final state
s Task sequences
s Time schedule
s Information required
14. General description
10 / 72 3BK 17416 3001 RJZZA 02A L EC T L
1.1 Hardware description
1.1.1 Rack configuration
Figures 1 to 3, which show the layout of the equipment fitted in
each rack for each BSC configuration, are provided to assist the
visual check procedure.
The key used in the figures is as follows:
Table 1-1 Rack key
CE number at a CPRC unit = Network address
AB = OSI- CPRC
AC= SYS- CPRC
AA= BC- CPRC
number at a DTCC unit = Network address
number at a TCUC unit = Network address
NE number at an QA unit = Qmux address
SWCH number at a AS unit AS = Access Switch Number
number at a GS unit GS1/n = Group Switch Stage 1/Plane
+Switch Element Number
GS2/n = Group Switch Stage 2/Plane
+Switch Element Number
number at a BCLA unit SYS = System
Variant
RACK = Rack
Variant
M = Master S = Slave
15. Generaldescription
3BK174163001RJZZA0211/72ALECTL
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
top rack unit for the fuses
D
C
D
C
D
C
D
C
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
C
P
R
C
S
W
C
H
S
W
C
H
C
P
R
C
C
P
R
C
C
P
R
C
C
P
R
C
C
P
R
C
air baffle
S
W
C
H
S
W
C
H
D
C
GS2/1 ........................ GS2/1
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
SAU
01
SAU
03
SAU
02
SAU
04
SAU
06
SAU
07
SAU
08
SAU
05
0 1 2 3 4 5 6 7
GS2/2 ........................ GS2/2
0 1 2 3 4 5 6 7
GS2/3 ........................ GS2/3
0 1 2 3 4 5 6 7
3 7
AS
6
QA
7
QAAS
2 6
AS
4
QA
5
QA
030
031
032
033
034
035
036
037
020
021
022
023
024
025
026
027
GS2/0 ........................ GS2/0
0 1 2 3 4 5 6 7
GS1/0 ........................ GS1/0
0 1 2 3 4 5 6 7
2
QA
010
011
012
013
014
015
016
017
AS
1 5
AS SYS
M S M S
RACK
AS
1 5
AS
000
001
002
003
004
005
CB A01 ........................ CB A09
A01 B71 B72
CB B71 ........................ CB B78
fuse fuse fuse
A02
fuse
A05
fuse
B75
fuse
A06
fuse
A07
fuse
A09
fuse
B77
fuse
B78
fuse
B76
fuse
A08
fuse
N+1
N+1
ABIS16 BSCL06
ATER16
BGSA10SYSA16SYSB06
BGSA10
ATER16
ATER16
BGSA10 BGSA10 BGSA10
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
top rack unit for the fuses
D
C
D
C
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
C
P
R
C
S
W
C
H
S
W
C
H
C
P
R
C
C
P
R
C
C
P
R
C
C
P
R
C
C
P
R
C
air baffle
S
W
C
H
S
W
C
H
D
C
GS2/1 ........................ GS2/1
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
SAU
01
SAU
03
SAU
02
SAU
04
SAU
06
SAU
07
SAU
08
SAU
05
0 1 2 3 4 5 6 7
GS2/2 ........................ GS2/2
0 1 2 3 4 5 6 7
GS2/3 ........................ GS2/3
0 1 2 3 4 5 6 7
3 7
AS
6
QA
7
QAAS
2 6
AS
4
QA
5
QA
030
031
032
033
034
035
036
037
020
021
022
023
024
025
026
027
GS2/0 ........................ GS2/0
0 1 2 3 4 5 6 7
GS1/0 ........................ GS1/0
0 1 2 3 4 5 6 7
2
QA
010
011
012
013
014
015
016
017
AS
1 5
AS SYS
M S M S
RACK
AS
0 4
AS
000
001
002
003
004
005
CB A01 ........................ CB A09
A01 B71 B72
CB B71 ........................ CB B78
fuse fuse fuse
A05
fuse
B75
fuse
A06
fuse
A07
fuse
A09
fuse
B77
fuse
B78
fuse
B76
fuse
A08
fuse
N+1
ABIS16 BSCL06
ATER16
BGSA10SYSA16SYSB06
BGSA10
ATER16
ABIS16
ATER16
ABIS16
GBIS16
BGSA10 BGSA10 BGSA10
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
8
QA
100
101
102
103
104
105
106
107
AS
8 12
AS
A03
fuse
A04
fuse
N+1
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
10
QA
110
111
112
113
114
115
116
117
AS
9 13
AS
B74
fuse
B
I
U
A
S
W
C
H
S
W
C
H
14
QAAS
11 15
AS
D
C
D
C
B73
fuse
S
W
C
H
S
W
C
H
GS1/1
0 1
S
W
C
H
S
W
C
H
GS1/1
2 3
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
130
131
132
133
134
135
136
137
S
W
C
H
S
W
C
H
GS1/1
6 7
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
10 14
AS
12
QA
13
120
121
122
123
124
125
126
127
A02
fuse
S
W
C
H
S
W
C
H
GS1/1
4 5
QA
N+1
Half Rack Full Rack
DC/DC converter removed, starting from rack variant 3BK 06796 AAAC
Figure1-1RackLayoutRack1,Configuration1and2
16. Generaldescription
12/723BK174163001RJZZA02ALECTL
DC/DC converter removed, starting from rack variant 3BK 06796 AAAC
SAU
03
SAU
04
ABIS16
ATER16
ABIS16
GBIS16
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
8
QA
300
301
302
303
304
305
306
307
AS
24 28
AS
A03
fuse
A04
fuse
N+1
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
10
QA
310
311
312
313
314
315
316
317
AS
25 29
AS
B74
fuse
B
I
U
A
S
W
C
H
S
W
C
H
14
QAAS
27 31
AS
D
C
D
C
B73
fuse
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
330
331
332
333
334
335
336
337
S
W
C
H
S
W
C
H
GS1/3
6 7
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
26 30
AS
12
QA
13
320
321
322
323
324
325
326
327
A02
fuse
S
W
C
H
S
W
C
H
GS1/3
4 5
QA
N+1
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
top rack unit for the fuses
D
C
D
C
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
air baffle
S
W
C
H
S
W
C
H
D
C
GS2/5 ........................ GS2/5
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
SAU
01
SAU
02
SAU
06
SAU
07
SAU
08
SAU
05
0 1 2 3 4 5 6 7
GS2/6 ........................ GS2/6
0 1 2 3 4 5 6 7
GS2/7 ........................ GS2/7
0 1 2 3 4 5 6 7
19 23
AS
6
QA
7
QAAS
18 22
AS
4
QA
5
QA
230
231
232
233
234
235
236
237
220
221
222
223
224
225
226
227
GS2/4 ........................ GS2/4
0 1 2 3 4 5 6 7
GS1/2 ........................ GS1/2
0 1 2 3 4 5 6 7
2
QA
210
211
212
213
214
215
216
AS
17 21
AS
M S
RACK
AS
16 20
AS
CB A01 ........................ CB A09
A01 B71 B72
CB B71 ........................ CB B78
use use fuse
A05
fuse
B75
fuse
A06
use
A07
fuse
A09
fuse
B77
fuse
B78
fuse
B76
fuse
A08
fuse
N+1
ABIS16 BSCL06
ATER16
BGSA10SYSA16SYSB06
BGSA10
ATER16
BGSA10 BGSA10 BGSA10
B
I
U
A
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
0
QA
200
201
202
203
205
T
C
U
C
T
C
U
C
T
C
U
C
206
207
204
217
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
top rack unit for the fuses
D
C
D
C
D
C
D
C
01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
air baffle
S
W
C
H
S
W
C
H
D
C
GS2/5 ........................ GS2/5
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
SAU
01
SAU
03
SAU
02
SAU
04
SAU
06
SAU
07
SAU
08
SAU
05
0 1 2 3 4 5 6 7
GS2/6 ........................ GS2/6
0 1 2 3 4 5 6 7
GS2/7 ........................ GS2/7
0 1 2 3 4 5 6 7
19 23
AS
6
QA
7
QAAS
18 22
AS
4
QA
5
QA
230
231
232
233
234
235
236
237
220
221
222
223
224
225
226
227
GS2/4 ........................ GS2/4
0 1 2 3 4 5 6 7
GS1/2 ........................ GS1/2
0 1 2 3 4 5 6 7
2
QA
210
211
212
213
214
215
216
AS
17 21
AS
M S
RACK
AS
16 20
AS
CB A01 ........................ CB A09
A01 B71 B72
CB B71 ........................ CB B78
fuse fuse fuse
A02
fuse
A05
fuse
B75
fuse
A06
fuse
A07
fuse
A09
fuse
B77
fuse
B78
fuse
B76
fuse
A08
fuse
N+1
N+1
ABIS16 BSCL06
ATER16
BGSA10SYSA16SYSB06
BGSA10
ATER16
ATER16
BGSA10 BGSA10 BGSA10
B
I
U
A
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
0
QA
200
201
202
203
205
T
C
U
C
T
C
U
C
T
C
U
C
206
207
204
217
Half Rack Full Rack
S
W
C
H
S
W
C
H
GS1/3
0 1
S
W
C
H
S
W
C
H
GS1/3
2 3
S
W
C
H
S
W
C
H
GS1/3
2 3
S
W
C
H
S
W
C
H
GS1/3
0 1
Figure1-2RackLayoutRack2,Configuration3and4
17. General description
3BK 17416 3001 RJZZA 02 13 / 72A L EC T L
SAU
03
SAU
04
ABIS16
ATER16
ABIS16
GBIS16
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
8
QA
500
501
502
503
504
505
506
507
AS
4044
AS
A03
fuse
A04
fuse
N+1
B
I
U
A
T
C
U
C
D
C
D
C
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
10
QA
510
511
512
513
514
515
516
517
AS
4145
AS
B74
fuse
B
I
U
A
S
W
C
H
S
W
C
H
14
QAAS
4347
AS
D
C
D
C
B73
fuse
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
530
531
532
533
534
535
536
537
S
W
C
H
S
W
C
H
GS1/5
67
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
4247
AS
12
QA
13
520
521
522
523
524
525
526
527
A02
fuse
S
W
C
H
S
W
C
H
GS1/5
45
QA
N+1
0103050709111315171921232527293133353739414345474951535557596163
toprackunitforthefuses
D
C
D
C
0103050709111315171921232527293133353739414345474951535557596163
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
D
C
D
C
S
W
C
H
S
W
C
H
airbaffle
SAU
01
SAU
02
SAU
06
SAU
07
SAU
08
SAU
05
.
3539
AS
6
QA
7
QAAS
3438
AS
4
QA
5
QA
430
431
432
433
434
435
436
437
420
421
422
423
424
425
426
427
GS1/4........................GS1/4
01234567
2
QA
410
411
412
413
414
415
416
AS
3337
AS
MS
RACK
AS
3236
AS
CBA01........................CBA09CBB71........................CBB78
A05
fuse
B75
fuse
A06
fuse
A07
fuse
A09
fuse
B77
fuse
B76
fuse
A08
fuse
N+1
ABIS16BSCL06
ATER16
SYSA16SYSB06
BGSA10
ATER16
B
I
U
A
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
0
QA
400
401
402
403
405
T
C
U
C
T
C
U
C
T
C
U
C
406
407
404
417
0103050709111315171921232527293133353739414345474951535557596163
toprackunitforthefuses
D
C
D
C
0103050709111315171921232527293133353739414345474951535557596163
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
D
C
D
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
D
T
C
C
A
S
M
B
D
T
C
C
D
T
C
C
D
T
C
C
S
W
C
H
S
W
C
H
AS
D
C
D
C
B
I
U
A
T
C
U
C
B
C
L
A
B
C
L
A
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
D
C
D
C
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
S
W
C
H
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
D
C
D
C
T
S
C
A
D
C
D
C
S
W
C
H
S
W
C
H
airbaffle
SAU
01
SAU
03
SAU
02
SAU
04
SAU
06
SAU
07
SAU
08
SAU
05
3539
AS
6
QA
7
QAAS
3438
AS
4
QA
5
QA
430
431
432
433
434
435
436
437
420
421
422
423
424
425
426
427
GS1/4........................GS1/4
01234567
2
QA
410
411
412
413
414
415
416
AS
3337
AS
MS
RACK
AS
3236
AS
CBA01........................CBA09CBB71........................CBB78
A05
fuse
B75
fuse
A06
fuse
A07
fuse
A09
fuse
B77
fuse
B76
fuse
A08
fuse
N+1
ABIS16BSCL06
ATER16
SYSA16SYSB06
BGSA10
ATER16
B
I
U
A
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
T
C
U
C
0
QA
400
401
402
403
405
T
C
U
C
T
C
U
C
T
C
U
C
406
407
404
417
HalfRackFullRack
S
W
C
H
S
W
C
H
GS1/5
01
S
W
C
H
S
W
C
H
GS1/5
23
S
W
C
H
S
W
C
H
GS1/5
23
S
W
C
H
S
W
C
H
GS1/5
01
Figure 1-3 Rack Layout Rack 3, Configuration 5 and 6
18. General description
14 / 72 3BK 17416 3001 RJZZA 02A L EC T L
1.2 Prerequisites
➤ The site must comply with the “safety rules” (See “BSS Methods
Handbook ”).
➤ At least two Atermux PCM links must be available
1.3 Restrictions
➤ There are no restrictions in this document.
1.4 Initial state
➤ The BSC racks are installed and wired on the customer’s site.
➤ The power supply is connected and powered up, but the racks
are not powered up (all circuit breakers at the top of each
rack must be in the OFF position)
1.5 Final state
➤ The BSC is powered up and downloaded with the build
requested by the customer.
➤ The BSC is connected to TC and OMC-R, ready for physical
connection of the BTSs.
19. General description
3BK 17416 3001 RJZZA 02 15 / 72A L EC T L
1.6 Operating principle
B e fo r e le a v i n g fo r th e s ite
B e fo r e s t a r t in g
(o n a r r i v a l a t th e s i te )
H a r d w a r e c h e c k
C h e c k in g th e p o w e r s u p p ly
a n d p o w e r in g u p
In s ta l lin g th e B S C T e r m in a l
a n d X .2 5 b o a r d
In s ta l lin g th e B S C T e r m in a l
a n d X .2 5 b o a r d
In s ta l lin g th e B S S S W
f r o m f lo p p y d is k s
B u ild d e liv e r y ?
IO M E G A z i pF lo p p y d is k s
In s ta l lin g th e B S S S W
f r o m I O M E G A z ip d i s k
R e lo c a ti o n o f
s y s te m C P R C s
L o a d i n g a n d a c tiv a t in g
th e B S C s o ft w a r e
C h e c k in g b a tte r y b a c k u p
o f S - C P R C b o a r d s
C o r r e c t in g th e B S C
d a te a n d tim e
A l a r m c a b le s
a r e in s t a l le d ?
Y E SN O
T e s tin g th e e x te r n a l
a la r m s
B S C c o n fi g u r a t io n
m o r e th a n 2 ?
Y E SN O
B S C h a r d w a r e te s t
S e tti n g a n d c h e c k in g
B S C - O M C -R li n k
F in i s h in g c o m m is s i o n in g
C h e c k in g B S C - T C
li n k
20. General description
16 / 72 3BK 17416 3001 RJZZA 02A L EC T L
1.7 Time Schedule
Task time
(mn)
1
st
person
time
(mn)
2nd
person
Preliminary checks
Before leaving for the site 20 20
Before starting 20 20
Hardware check
(1)
10-60
(2)
10-60
(2)
Checking the Power Supply and
Powering Up
(1)
25 25
Installing the BSC Terminal and BSS SW
Installing the BSC Terminal software and
X.25 communication board
45
Installing the Craft Terminal 10
Installing the BSS software 10-20
(3)
Commissioning tests
Relocation of system-CPRCs 2
Loading and activating the BSC software 90
Checking battery backup of S-CPRC boards 30
Correcting the BSC date and time 2
Option: Testing the external alarms 10 10
Option: Hardware test 40
Checking BSC - TC link 20
Setting and checking the BSC - OMC-
R link
30
Finishing commissioning 20
6h24-7h24 1h25-2h15
(1)
tasks where two persons are mandatory for execution
(2)
depending on BSC configuration (1-6)
(3)
10 min from IOMEGA zip, 20 min from floppy disks
The times given are based on technical constraints, not taking
into account safety considerations.
21. General description
3BK 17416 3001 RJZZA 02 17 / 72A L EC T L
1.8 Information required
1. Site
• DDF map
2. Equipment configuration
• Rack configuration number (1 to 6)
• X.25 routing:
- extraction at BSC site
- extraction on TRCU modules via X.25 packet switch
- X.25 routed through MSC
• BSS topology
• BSS software version
3. Other
• Version of TSC firmware (B5 , B6 or higher)
• Status of A interface cables at the TC side (connected to
MSC or looped)
• Which A interface cables are connected at the MSC (if
applicable)
• External alarm cables (available or not)
23. Preliminary checks
3BK 17416 3001 RJZZA 02 19 / 72A L EC T L
2 Preliminary checks
This chapter describes the preparation of the operation in two steps:
s At back-office
s At arrival on site.
24. Preliminary checks
20 / 72 3BK 17416 3001 RJZZA 02A L EC T L
2.1 Before going to the site
Check prerequisitesCheck prerequisitesCheck prerequisitesCheck prerequisites
fulfilmentfulfilmentfulfilmentfulfilment
C
s See prerequisites in chapter 1
Check availability ofCheck availability ofCheck availability ofCheck availability of
Needed informationNeeded informationNeeded informationNeeded information
?
s See needed information in chapter 1
Check availability ofCheck availability ofCheck availability ofCheck availability of
documentationdocumentationdocumentationdocumentation
s 2 See documentation list in appendix
Check availability of toolsCheck availability of toolsCheck availability of toolsCheck availability of tools s 2 See tools kit list in appendix, refer to the
« Tools catalogue » for content checking
Check availability andCheck availability andCheck availability andCheck availability and
version of softwareversion of softwareversion of softwareversion of software
s 2 See software list in appendix, refer to the
corresponding documents for SW version
checking
2.2 Before you start (at arrival on site)
Check applicableCheck applicableCheck applicableCheck applicable
notifications andnotifications andnotifications andnotifications and
operation instructionsoperation instructionsoperation instructionsoperation instructions
4
s Refer to “Applicable notifications list” for
checking if notifications have to applied during
the operation (ITL)
s Refer to “Applicable operation instructions
list” for checking if operation instructions have to
applied during the operation (IO)
Check that the safetyCheck that the safetyCheck that the safetyCheck that the safety
instructions have beeninstructions have beeninstructions have beeninstructions have been
appliedappliedappliedapplied
s Refer to “Method Handbook” for checking that the
safety precautions have been taken, in accordance
with safety instructions
Read instructions to beRead instructions to beRead instructions to beRead instructions to be
applied in case ofapplied in case ofapplied in case ofapplied in case of
anomalyanomalyanomalyanomaly
s Refer to “Method Handbook” for instructions
Fulfil completion checkFulfil completion checkFulfil completion checkFulfil completion check
listlistlistlist
!
s Complete header field of the CCL
2 see Check Completion List
s The CCL is completed as each instruction is
carried out
Check the antistaticCheck the antistaticCheck the antistaticCheck the antistatic
wrist strapwrist strapwrist strapwrist strap
s Check the resistance of antistatic wrist strap is less
then 1 MΩ
s Connect the antistatic wrist strap to rack earth
25. Hardware check
3BK 17416 3001 RJZZA 02 21 / 72A L EC T L
3 Hardware check
This chapter describes how to check the BSC configuration and
HTS of the boards inside the BSC.
26. Hardware check
22 / 72 3BK 17416 3001 RJZZA 02A L EC T L
PurposePurposePurposePurpose
➤ To check that the BSC configuration corresponds to the
customer’s order.
➤ To verify that the hardware level of the boards inside BSC is as
requested by the customer, by taking the rack inventory.
ProcedureProcedureProcedureProcedure
See Information required
See Chapter 1 “Rack
Configuration”
A. Verify the presence and position of the boards according to
the requested configuration.
Refer to “CI 08 - Site
Equipment Inventory”
B. Perform the rack inventory.
ATTENTION
Check that there are no alarms of type “NOT IN CAL”,
when running Inventar for BTS. This ensures that the
boards inside the BSC meet the requirements of a specific
customer.
27. Checking the Power Supply and Powering Up
3BK 17416 3001 RJZZA 02 23 / 72A L EC T L
4 Checking the Power Supply and Powering Up
This chapter describes the tasks to perform to check the power
supply and power up the BSC.
28. Checking the Power Supply and Powering Up
24 / 72 3BK 17416 3001 RJZZA 02A L EC T L
PurposePurposePurposePurpose
➤ To check the rating of the fuses at the customer power panel.
➤ To check the polarity of power voltage and to power up the
BSC racks.
4.1 Check the rating of the fuses
ProcedureProcedureProcedureProcedure
A. On the customer power panel (cabinet), check for the
existence of two DC power supply distribution circuits. Each
distribution circuit is provided with a DC circuit breaker (fuse
holder).
B. On the site power panel, disconnect the two -48V power
supply lines (line A and B) at the rack fuse holders.
See SPP-27 C. Check that the fuse ratings are in accordance with the SPP
document.
4.2 Discharge the capacitors in the racks
ProcedureProcedureProcedureProcedure
A. At the customer power panel, make sure the two -48 V power
supply lines for BSC are disconnected.
B. Close (ON position) all the rack (and extension rack if
applicable) circuit breakers for 10 seconds.
C. Open (OFF position) all the rack circuit breakers.
29. Checking the Power Supply and Powering Up
3BK 17416 3001 RJZZA 02 25 / 72A L EC T L
4.3 Check the polarity of the power supply line,
Branch A
ProcedureProcedureProcedureProcedure
Action Results
A. At the BSC top rack filter units for each
rack (basic rack and extension racks if
applicable) remove the protection caps
from the power supply terminals.
B. Connect the -48 V power supply (branch
A) at the fuseholder.
Branch A is connected.
N O T IC E Branch A is associated with the fuseholder marked BAT A.
C. Using the multimeter, check the presence
of -48V DC between BAT A and BATRET
for all racks (basic and extensions).
Check that no voltage is present between
BAT B and BATRET for all racks.
-48V DC present between BAT A
and BATRET
No voltage is present between
BAT B and BATRET.
See Chapter 1 “Racks
configuration”
D. Switch all the rack circuit breakers to ON.
Note: Converters B72 and B78 are
removed starting from rack variant 3BK
06796 AAAC.
The DC/DC converters A01-A09
for all racks are powered up.
The DC/DC converters B71-B78
for all racks are not powered up.
E. Switch all the rack circuit breakers to OFF. No board in the racks is
powered up.
F. At the customer power panel, disconnect
the -48 V power supply (branch A) at the
fuseholder.
Branch A is disconnected.
30. Checking the Power Supply and Powering Up
26 / 72 3BK 17416 3001 RJZZA 02A L EC T L
4.4 Check the polarity of the power supply line,
Branch B
ProcedureProcedureProcedureProcedure
Action Results
see § 4.2 A. Discharge the capacitors in the rack. The capacitors are discharged.
B. At the BSC top rack filter units for each
rack (basic rack and extension racks if
applicable) remove the protection caps
from the power supply terminals.
C. Connect the -48 V power supply (branch
B) at the fuseholder.
Branch B is connected.
N O T IC E Branch B is associated with the fuseholder marked BAT B.
D. Using the multimeter, check the presence
of -48V DC between BAT B and BATRET
for all racks (basic and extension).
Check that no voltage is present between
BAT A and BATRET for all racks.
-48V DC present between BAT B
and BATRET
No voltage is present between
BAT A and BATRET.
See Chapter 1 “Racks
configuration”
E. Switch all the rack circuit breakers to ON.
Note: Converters B72 and B78 are
removed starting from rack variant 3BK
06796 AAAC.
The DC/DC converters B71-B78
for all racks are powered up.
The DC/DC converters A01-A09
for all racks are not powered up.
F. Switch all the rack circuit breakers to OFF. No board in the racks is
powered up.
G. At the customer power panel, disconnect
the -48 V power supply (branch B) at the
fuseholder.
Branch B is disconnected.
4.5 Power up the BSC racks
ProcedureProcedureProcedureProcedure
A. Switch ON the two power supply lines at the fuseholders.
B. Switch ON all the rack circuit breakers, powering up the racks.
Refer to “BSS Methods
Handbook”
C. All the boards take about 1 minute to run their self-tests.
31. Installing the BSC Terminal and BSS SW
3BK 17416 3001 RJZZA 02 27 / 72A L EC T L
5 Installing the BSC Terminal and BSS SW
This chapter describes installation procedures for the following
software:
s BSC Terminal and X.25 communication board
s Craft Terminal
s BSS software
32. Installing the BSC Terminal and BSS SW
28 / 72 3BK 17416 3001 RJZZA 02A L EC T L
5.1 Installing the BSC Terminal software and the
X.25 communication board
PurposePurposePurposePurpose
➤ To install:
• the X.25 communication board in Windows environment
• the BSC Terminal software in Windows environment
5.1.1 Install EICON C31 board
ProcedureProcedureProcedureProcedure
Refer to “BSS Methods
Handbook”
A. Install the EICON C31(for notebook) board in Windows
environment
5.1.2 Install Windows BSC Terminal
ProcedureProcedureProcedureProcedure
Refer to “BSS Methods
Handbook”
A. Install BSC Terminal software for Windows
5.2 Installing the Craft Terminal
PurposePurposePurposePurpose
➤ To install the LMT-CT Craft Terminal program on the PC
ProcedureProcedureProcedureProcedure
Refer to “BSS Methods
Handbook”
A. Install Craft Terminal for Windows
33. Installing the BSC Terminal and BSS SW
3BK 17416 3001 RJZZA 02 29 / 72A L EC T L
5.3 Installing the BSS software
PurposePurposePurposePurpose
➤ To install the BSS software on the PC and to print the
“CONTENTS.LST”
5.3.1 Case 1: Build is delivered on floppy disks
ProcedureProcedureProcedureProcedure
A. On the notebook create the following directory(ies):
C:BUILDBSSB7”Name of the customer build”
B. Copy all the build delivery compressed files (gzip) from floppy
disks to the new created directory (all files in same directory).
C. Copy gzip.exe from C:Program FilesAlcatelWINBSCB7 to
C:BUILDBSSB7”Name of customer build”
D. Open a command prompt window:
Start ðððð Programs ðððð Command Prompt
E. In the command prompt window enter the following
commands:
cd BUILDBSSB7”Name of customer build” CR
gzip -dvN *.gz CR
Note: *.gz means all the files in the current directory with the
extension gz.
All the gzip files are uncompressed.
F. Using a text editor (eg. Notepad) open the “CONTENTS.LST”
file.
Refer to “BSS software
list”
G. Check the BSC master file (i.e. bscmxtxx) version specified in
“CONTENTS.LST” against the requested customer version.
34. Installing the BSC Terminal and BSS SW
30 / 72 3BK 17416 3001 RJZZA 02A L EC T L
5.3.2 Case 2: Build is delivered on IOMEGA ZIP disk
NOTICE
In this case it is mandatory for the notebook to have an IOMEGA
ZIP drive installed.
ProcedureProcedureProcedureProcedure
A. On the notebook create the following directory or directories:
C:BUILDBSSB7”Name of customer build”
B. Copy all the build delivery files from the IOMEGA ZIP disk to
the new created directory.
C. Copy gzip.exe from C:Program FilesAlcatelWINBSCB7 to
C:BUILDBSSB7”Name of the customer build”
D. Open a command prompt window:
Start ðððð Programs ðððð Command Prompt
E. In the command prompt window enter the following
commands:
cd BUILDBSSB7”Name of the customer build” CR
gzip -dvN *.gz CR
Note: *.gz means all the files in the current directory with
extension gz.
All the gzip files are uncompressed.
F. Using a text editor (eg. Notepad) open the “CONTENTS.LST”
file.
Refer to “BSS software
list”
G. Check the BSC master file (i.e. bscmxtxx) version specified in
“CONTENTS.LST” against the requested customer version.
35. Commissioning tests
3BK 17416 3001 RJZZA 02 31 / 72A L EC T L
6 Commissioning tests
This chapter describes the following tasks:
s Relocation of system CPRCs
s Loading and activating the BSC software
s Checking battery backup of S-CPRC boards
s Correcting the BSC date and time
36. Commissioning tests
32 / 72 3BK 17416 3001 RJZZA 02A L EC T L
6.1 Relocation of system-CPRCs
PurposePurposePurposePurpose
➤ To move the S-CPRC PBAs from their transport positions to
their operational positions.
ProcedureProcedureProcedureProcedure
WARNING
Use the antistatic wrist strap when working in contact
with the BSC boards, otherwise permanent damage could
be caused to the boards.
Action Results
Refer to “BSS Methods
Handbook” for LEDs
meaning
A. Move the S-CPRC PBAs from their
transport positions to their operational
positions as follows:
-PBA in position 23 (transport) to
position 21 (operational).
-PBA in position 27 (transport) to
position 25 (operational).
System CPRCs are in operational
position.
The boards run their self-tests for
about 1 minute. When the bottom
LED is blinking they are requesting
to be loaded.
37. Commissioning tests
3BK 17416 3001 RJZZA 02 33 / 72A L EC T L
6.2 Loading and Activating the BSC software
PurposePurposePurposePurpose
➤ To prepare the X.25 link by downloading the minibuild
➤ To configure the first BIUA module of each rack with a generic
file
➤ Option: To upgrade the TSCA firmware from B5
➤ To load and activate the BSC software.
6.2.1 Prepare X.25 configuration link
ProcedureProcedureProcedureProcedure
Refer to “Tools
catalogue for field activity”
for cable reference
A. Connect the COM1 port of the BSC Terminal to the 9 pin
connector of the system CPRC 1 (SAU 08 position 21) using
the CPRC serial cable.
B. To run ‘BSC Terminal B7’, from the Taskbar, select:
Start ðððð Programs ðððð WinBSC ðððð B7 ðððð Windows
BSC Terminal B7
The following window appears:
B. Select serial connection and Logging in the ‘BSC
Communication Control’ window and click Connect.
C. In the ‘Windows BSC Terminal’ window select:
Utilities ðððð Minibuild Loading
The ‘Minibuild Loading’ window opens:
38. Commissioning tests
34 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Refer to “BSS Methods
Handbook” to monitor the
progress of the download
by observing the LEDs on
the CPRC PBA
D. Give the path of the minibuild directory in the “Directory Path”
field (as in the figure) field using the Browse button. Select
Available Files ‘bssmini.*’ and click Go!.
The files are automatically downloaded.
When the download is complete, a successful report
message appears.
N O T IC E
Check the lower right corner in ‘Windows BSC Terminal’
windows to monitor communication between PC and BSC
equipment (“the message has been sent to BSC...” and a
reply has been received).
E. Exit Windows BSC Terminal:
- click the shortcut exit button (top right corner in the
‘Windows BSC Terminal‘ window)
- click Yes to confirm the close connection message
below:
39. Commissioning tests
3BK 17416 3001 RJZZA 02 35 / 72A L EC T L
6.2.2 Configure the rack’s first BIUA with the generic file
ProcedureProcedureProcedureProcedure
A. Connect the LMT Terminal to the first BIUA PBA using LMT-CT
Terminal/MMI cable.
B. Run ‘Craft Terminal B7’:
Double click the LMT Terminal SW icon.
When the password window appears, click the OK button.
The Alcatel Main Menu appears:
C. In the Alcatel Main Menu Select: Session ðððð Connect
The Craft Terminal software establishes the connection with
the BIUA board:
D. In the “BIUSC” Menu select:
Options ê Data ê Download
and in the “Write Block” window click Browse.
40. Commissioning tests
36 / 72 3BK 17416 3001 RJZZA 02A L EC T L
See Chapter 1 “Rack
Configuration”
E. In the “Open” window select, using “Folders” field, the
transmission data file corresponding to the module rack
position:
ê LMT-CT ê Setting...
F. Click OK.
In the “Write Block” window click OK again, and wait for
the successful ‘Report’ message window below:
G. In the “BIUSC” Menu, disconnect the board link by selecting:
Session ê Disconnect
The “Alcatel” menu is activated.
Disconnect the RS232 cable from BIUA board.
H. Repeat the section Configure the rack’s first BIUA with
initial generic file, for the first BIUA module of each BSC
rack.
41. Commissioning tests
3BK 17416 3001 RJZZA 02 37 / 72A L EC T L
6.2.3 Check and upgrade the TSCA FW
ATTENTION
This upgrade MUST be performed if the TSCA FW does
not correspond to release B6 or B7!
PurposePurposePurposePurpose To upgrade the TSCA SW from B5 to B6 (even if the
commissioning of BSC is done in B7).
6.2.3.1 Check the FW version on the TSCA board
ProcedureProcedureProcedureProcedure
A. Connect the LMT Terminal to the first TSCA PBA using LMT-CT
Terminal/MMI cable.
B. Run Craft Terminal B7:
Double click the LMT Terminal SW icon.
When the password window appears, click the OK button.
The Alcatel Main Menu appears:
C. In the Alcatel Main Menu Select:
TSC ðððð Download Migration Software
D. If the connection is not established, the FW version is for
release B6 or higher and no FW upgrade is required.
E. If the Craft Terminal software establishes the connection with
the TSCA board an update of FW is required.
42. Commissioning tests
38 / 72 3BK 17416 3001 RJZZA 02A L EC T L
6.2.3.2 If applicable, upgrade TSCA firmware from B5 to B6
1. Installing the TSC B6 software on the PC
A. Create the directory TSC_FW on the PC.
see BSS Software List B. Copy the firmware delivery for release B6 (TSCSAQxx.0xx)
from the floppy disk into the TSC_FW directory.
C. Leave the diskettes of the installed software in the site
documentation.
2. Upgrading the TSCA board to FW level B6
A. The Craft Terminal software sets up the connection with the
TSCA board, following the action of the command already
given at LMT CT B7:
TSC ðððð Download Migration Software
B. The following messages appear:
“Waiting for Download Request from TSC...”
“Download of Both Code and Data Requested.
Proceed?”
Click OK .
C. The program asks for the TSC CODE file .
D. Select the file that you installed in the TSC_FW directory:
è C: TSC_FW / TSCSAQxx.0xx
Choose this file and click OK.
E. The following messages appears:
“TSC is currently erasing a page of memory.”
And then download starts.
F. “Download of Data Requested.Proceed?” appears.
Click OK .
G. Select the file with data from the LMT CT directory:
è.../LMT_CT/B7/Settings/g2/tsca/empty_db.tsc
Choose this file and click OK.
H. Wait for the TSC to download successfully. (After the TSCA
board has been downloaded wait approximately 10 minutes).
I. Manually reset the board.
J. After the TSCA board has been reset, the B6 firmware should
be active and will start sending a load request via TSL.
K. Apply the same procedure for each TSCA board.
43. Commissioning tests
3BK 17416 3001 RJZZA 02 39 / 72A L EC T L
6.2.4 Format Disk A
ProcedureProcedureProcedureProcedure
1. Set up the X.25 communication link
Refer to “Tools
catalogue for field activity”
for cable reference type.
A. Connect the X.25 number 0 port of the BSC Terminal to the
25 pin connector of system CPRC 1 (SAU 08 position 21)
using CPRC parallel cable.
B. Open a new session and select the X.25 link.
C. Select X.25 connection and Logging in the ‘BSC
Communication Control’ window and click Connect.
N O T IC E
If an “X25 Link” error message window appears verify the
link with the BSC equipment and repeat the last two steps
again.
2. Format Disk A
A. In the ‘Windows BSC Terminal‘ main menu select:
Commands ðððð Disk operations ðððð Format SSD
the ‘Format SSD’ window opens.
B. In the “Directory Path” field enter the full path to the BSS
directory using the Browse button (e.g.:
C:BUILDBSSBSSS7_1).
C. Select Disk A.
D. A list of files that can be used to format the SSD appears.
Select the BSS-masterfile xxxMxTxx . xxx and click Enter.
E. Click Go! to initiate SSD formatting.
When SSD formatting is complete, a report appears
showing the result of the formatting.
44. Commissioning tests
40 / 72 3BK 17416 3001 RJZZA 02A L EC T L
6.2.5 Load the BSS software onto disk A
ProcedureProcedureProcedureProcedure
A. In the ‘Windows BSC Terminal‘ main menu select:
Commands ðððð Disk operations ðððð File Transfer
from PC to BSC
The BSS File Directory window opens:
B. In the “Directory Path” field enter the full path to the BSS
directory using the Browse button (e.g.:
C:BUILDBSSBSSS7_1).
C. Select the BSS-masterfile xxxMxTxx . xxx and click Enter.
D. Specify the Destination Disk. Select Disk A.
E. In the ‘Files To Transfer’ window the files to be transferred are
displayed.
F. Click Go! to initiate the file transfer (Start Download).
G. Check reports.
45. Commissioning tests
3BK 17416 3001 RJZZA 02 41 / 72A L EC T L
6.2.6 Check the content of disk A
ProcedureProcedureProcedureProcedure
A. To generate and print out the content of disk A, from the
‘Windows BSC Terminal‘ main menu select:
Commands ðððð Disk operations ðððð Control SSD
B. Select the parameters as in the ‘Control SSD’ window below
and then click OK.
C. In the ‘Windows BSC Terminal’ window check the command
reports.
D. Compare the content of disk A, shown in the reports window,
with the CONTENTS.LST file.
6.2.7 System initialization
ProcedureProcedureProcedureProcedure
Action Results
A. In ‘Windows BSC Terminal‘ select the following
menu path:
Commands ðððð System Activation ðððð
System initialization
‘System Initialisation’
window opens.
46. Commissioning tests
42 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Refer to “BSS Methods
Handbook” describing the
various LED states for the
different boards.
B. Select the parameters as in the ‘System
Initialisation’ window above and then click
OK.
The loading procedure is indicated by the
LEDs on the board front panels.
All BSC boards, including
NE and TSCA, upload the
software stored in CPRC
board.
NOTICE
After the system initialization command the BSC Terminal loses the
X.25 connection with the BSC.
After about 5 minutes, reestablish the link by closing and
reopening BSC Terminal.
C. Wait about 20 min. for the successful report.
Verify that all CE's are equipped. If CE missing,
run Hardware Test to investigate.
BSC is successfully
initialized.
6.2.8 Set to OPR the SBLs of the declared BTSs
ProcedureProcedureProcedureProcedure
A. In ‘Windows BSC Terminal‘ select:
Commands ðððð Equipment Handling ðððð SBL
Disable
B. Select the parameters as in the ‘SBL Disable’ window below:
see Information
required
C. In the Unit number field enter the parameter number from
the corresponding BTSs.
D. Click OK and wait for the successful report.
47. Commissioning tests
3BK 17416 3001 RJZZA 02 43 / 72A L EC T L
6.2.9 Check board status
ProcedureProcedureProcedureProcedure
A. To generate and print out the states of the faulty SBLs, in
‘Windows BSC Terminal’ select:
Commands ðððð Equipment Handling ðððð SBL State
List
B. Select the parameters as in the ‘SBL State List’ window below
and then click OK.
C. In the ‘Windows BSC Terminal’ window check the reports to
verify that all the CPR, DTC, TCU, TSC and SWITCH SBLs of
the BSC are In Traffic. They should not appear in the State
List command report.
NOTICE
The State List command displays the states of all SBLs that are not
In Traffic.
In the ‘Windows BSC Terminal’ window use the mouse to double-
click on the compressed report message any time you want a “Full
Report View”.
6.2.10 Format disk B
ProcedureProcedureProcedureProcedure
See Appendix A. Disable Alarm Reports.
CAUTION
If the sequence of operations is blocked at any time,
apply WORKAROUND no.1 for restarting the BSC
Terminal.
48. Commissioning tests
44 / 72 3BK 17416 3001 RJZZA 02A L EC T L
B. In ‘Windows BSC Terminal’ select:
Commands ðððð Disk Operations ðððð Format Duplex
SSD
C. In ‘Format Duplex SSD’ enter the Source - Destination
parameter and click 0K.
D. Check the reports to see if the action was successful.
E. Wait for the final report “FILE TRANSFER RESULT”.
6.2.11 Copy the BSS software to disk B
ProcedureProcedureProcedureProcedure
A. In ‘Windows BSC Terminal’ select the following menu path:
Commands ðððð Disk Operations ðððð File
Transfer from BSC to BSC
B. Enter the Source and Destination disk parameters, select “All
Files” and click 0K.
C. In the ‘Windows BSC Terminal’ window check the reports
(check to see that the BOOTROOT file already exists on disk B).
49. Commissioning tests
3BK 17416 3001 RJZZA 02 45 / 72A L EC T L
6.2.12 Check the content of disk B
ProcedureProcedureProcedureProcedure
A. Repeat the instructions in section 6.2.6 for Disk B.
6.2.13 Activate disk B
ProcedureProcedureProcedureProcedure
A. In the ‘Windows BSC Terminal’ main menu select:
Commands ðððð Equipment Handling ðððð SBL
Initialise
B. Click 0K.
See Appendix C. Enable Alarm Reports.
D. Check the message reports.
50. Commissioning tests
46 / 72 3BK 17416 3001 RJZZA 02A L EC T L
6.3 Checking battery backup of S-CPRC boards
PurposePurposePurposePurpose
➤ To check that the content of the S-CPRC disks is not altered
(safeguarded by the internal battery backup) by a loss of BSC
power supply.
ProcedureProcedureProcedureProcedure
Action Results
A. At the customer power panel switch OFF the
breakers for the two BSC branches (A and B).
BSC is powered down.
B. At the customer power panel switch OFF the
breakers for the two BSC branches (A and B).
BSC is powered up and
starts initialization.
Refer to “BSS Methods
Handbook” for LED states
C. Wait for BSC initialisation to finish (follow the
different LED states).
Refer to the above
sections
D. Check the board status as described in the
above sections.
The respective SBLs are
“IT”.
Refer to the above
sections
E. Check the content of the S-CPRC disks (A and B)
against the “CONTENTS.LST” file.
The content of the S-CPRC
disks was not altered by
the loss of power supply.
51. Commissioning tests
3BK 17416 3001 RJZZA 02 47 / 72A L EC T L
6.4 Correcting the BSC date and time
ProcedureProcedureProcedureProcedure
A. In ‘Windows BSC Terminal’ select the following menu path:
Commands ðððð Date Time ðððð Modify Date Time
B. Select the parameters as in the example ‘Modify Date and
Time’ window below and then click OK.
52. Commissioning tests
48 / 72 3BK 17416 3001 RJZZA 02A L EC T L
6.5 Option: Testing the external alarms
PurposePurposePurposePurpose
➤ To verify the external alarms sent to the BSC Terminal.
ProcedureProcedureProcedureProcedure
Action Results
See Chapter 1
“Information required”
A. If the external alarms are not looped at the
DDF, the external alarms should be active
at the BSC Terminal. They will remain
active until they are either connected or
looped.
If they are looped at the DDF, the
procedure will entail checking that they are
correctly sent to the BSC Terminal by
opening them in turn.
See Chapter 1
“Information required”
B. If the external alarms cables are installed,
simulate the alarms, one by one, at the
DDF side, by inserting disconnect
terminals.
The corresponding alarms are
reported at the BSC Terminal.
(for example:
Alarm Class: 32-Environmental
Alarm type: 002-EXT-ALARM)
C. Remove the disconnect terminals, one by
one.
The corresponding alarms
disappear.
53. Option: Hardware Test
3BK 17416 3001 RJZZA 02 49 / 72A L EC T L
7 Option: Hardware Test
This chapter describes the following sequence of hardware tests
in “off-line” mode, applied for BSC configuration 3 or higher:
s Network test
s Broadcast test
s Clock test
54. Option: Hardware Test
50 / 72 3BK 17416 3001 RJZZA 02A L EC T L
7.1 BSC hardware test
ATTENTION This test applies only for BSC configuration 3 or higher!
PurposePurposePurposePurpose
➤ To perform the following sequence of hardware tests in “off-
line” mode:
• Network test to detect failures in the switching network
cabling.
• Broadcast test to detect failures in the broadcast bus
cabling and faulty PBAs.
• Clock test to detect failures in the clock distribution bus
cabling. It also detects faulty PBAs.
ProcedureProcedureProcedureProcedure
Action Results
1. Preparing the BSC for the test
A. The hardware test must be executed in
configuration 3 or higher, to check the
inter-rack cabling.
N O T IC E For a BSC in configuration 1 or 2 the Hardware Test is not
needed.
B. Before the BSC can be tested, it must
be in the idle state.
Software in all the Control Elements
(CE) is running in the idle mode.
2. Reboot the BSC in “off-line test” mode
A. From the ”Windows BSC Terminal”
window main menu, select:
Commands è Commissioning
Tests è BSC System Test
Init
The “BSC System Test Init” window
opens.
B. Select the parameters as in the “BSC
System Test Init” window below:
55. Option: Hardware Test
3BK 17416 3001 RJZZA 02 51 / 72A L EC T L
C. Click OK. A message indicating that the
command has been sent to the BSC
appears in the lower left corner of
the “Windows BSC Terminal”
window.
D. Wait about 20 min. for BSC to run in
the test mode.
(Wait about 5min, exit and reconnect
the BSC Terminal).
When the BSC is in test mode, both
top LEDs are blinking fast.
2. Network Test
A. In the ”Windows BSC Terminal” main
menu select:
Commands è Commissioning
Tests è Test Facilities for
G2 è Network Test
The “Network Test” window opens.
B. Select the parameters as in the
“Network Test” window below and click
OK.
56. Option: Hardware Test
52 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Refer to “BSS Methods
Handbook” for cable and
plug descriptions.
See Example of Inter Rack
Cabling in appendix
C. Wait for the report message and try to
fix the problem, if there is one.
- note down the given address.
If one or more BSC test reports are
not successful the report will provide
the identities of the network
addresses of the links on which the
most errors were detected.
- find the given address in the Inter
Rack Cable List and check the
corresponding cables for their
addresses on both racks.
(Use the mouse to double-click the
compressed report message any time
you want a “Full Report View”).
3. Broadcast Test
A. In the ”Windows BSC Terminal” main
menu select:
Commands è Commissioning
Tests è Test Facilities for
G2 è Broadcast Test
The “Broadcast Test” window opens
B. Select the parameters as in the
“Broadcast Test” window below and
click OK.
C. Wait for the successful report message.
4. Clock Test
A. In the ”Windows BSC Terminal” main
menu select:
Commands è Commissioning
Tests è Test Facilities for
G2 è Clock Test
The “Clock Test” window opens.
B. Select the parameters as in the “Clock
Test” window below and click OK.
57. Option: Hardware Test
3BK 17416 3001 RJZZA 02 53 / 72A L EC T L
C. Wait for the successful report message.
NOTICE
If any hardware test fails, try to identify the problem and fix it.
Repeat all the hardware tests if necessary. If the failure persists,
check the cabling between the racks (see BSS Methods Handbook)!
7.2 Reboot the BSC in OPERATIONAL mode
ProcedureProcedureProcedureProcedure
Action Results
A. From the ”Windows BSC Terminal”
window main menu, select:
Commands è Commissioning
Tests è BSC System Test
Init
“BSC System Test Init” windows
opens.
B. Select the parameters as in the “BSC
System Test Init” window below:
58. Option: Hardware Test
54 / 72 3BK 17416 3001 RJZZA 02A L EC T L
C. Click OK. A message indicating that the
command has been sent to the BSC
appears in the lower left corner of
the “Windows BSC Terminal”
window.
D. Wait about 15 min. for BSC to run in
operational mode.
(Exit and reconnect the BSC Terminal)
When the BSC is in operational
mode both bottom LEDs are
blinking fast.
See § 6.2.8 E. Check board status. CPR, DTC, TCU, TSC and SWITCH
SBLs are “IT”.
59. Option: Checking the BSC-TC link
3BK 17416 3001 RJZZA 02 55 / 72A L EC T L
8 Option: Checking the BSC-TC link
This chapter describes how to check the BSC - TC link.
60. Option: Checking the BSC-TC link
56 / 72 3BK 17416 3001 RJZZA 02A L EC T L
PurposePurposePurposePurpose
➤ To remove the loops at the DDF for AterMux PCMs on the BSC
side and check the alarm reported by ASMB boards.
➤ To check the state of A trunk SBLs.
ProcedureProcedureProcedureProcedure
CAUTION
Apply the following task only if the TC is installed and
connected at the DDF on the BSC site.
1. Remove the AterMux loops and check the alarms on
the ASMB boards
See Information
required
A. At the DDF on the BSC side remove the loops for the AterMux
PCMs that are connected to TC equipment.
B. Open the LMT Terminal application and connect the RS232
cable to the notebook (COM).
C. For each ASMB board that corresponds to the removed loop
at the DDF:
s connect the serial cable to the board
s Session ðððð Connect
s The message “SM2M connection established” appears
s Click OK.
s Choose:
Services ðððð Alarm Collection
See Information
required
D. Case 1: A interface cables are looped at TC site
Check that the message “No Alarms Detected” appears,
meaning that the TC link has no alarms.
See Information
required
E. Case 2: A interface cables are connected to MSC
Check that for the A tributaries connected to MSC there are no
alarms.
Also check there are no alarms for the “Highway and control
module”.
61. Option: Checking the BSC-TC link
3BK 17416 3001 RJZZA 02 57 / 72A L EC T L
2. Check the status of A trunk SBLs
A. At the BSC Terminal:
Commands ðððð Equipment Handling ðððð SBL Read
Status
B. èObject class: SBL
èUnit Type: BSC
èUnit Number: 1
èSBL Type: ATR
èNbr: A trunk number (corresponding to the number of
the A trunk connected to the MSC or looped at the TC)
èSbNbr: 255
C. Click OK.
D. Check that the ATR SBL is “in traffic” in the report window.
E. Repeat steps A-D for all the A trunks that are connected to the
MSC (corresponding to the AterMux PCMs connected to the
TC).
62. Option: Checking the BSC-TC link
58 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Page intentionally left blank
63. Option: Checking the BSC-TC link
This chapter describes how to check the BSC - TC link.
3BK 17416 3001 RJZZA 02 59 / 72A L EC T L
9 Setting and checking the BSC - OMC-R link
This chapter describes how to set up the BSC - OMC-R link.
64. Option: Checking the BSC-TC link
This chapter describes how to check the BSC - TC link.
60 / 72 3BK 17416 3001 RJZZA 02A L EC T L
PurposePurposePurposePurpose
➤ To set up the BSC - OMC-R link (only if the BSC is linked to
the OMC via the X.25 network)
➤ To test the connection.
ProcedureProcedureProcedureProcedure
1. Physical connection
ATTENTION
This step applies only if the BSC is linked to the OMC via
the X.25 network.
Action Results
BSC site A. Connect the modem to the 25-way
connector (reference 3BK 07784 GLAA)
on CPRC board C (subrack 8, slot 17).
On the modem LEDs 103 and
104 must be ON.
On the CPRC C board the top
LED must be OFF.
BSC site B. At BSC Terminal verify the alarms. The Unsolicited Alarm Report
should appear:
This message indicates that the
X.25 link has been
reestablished.
2. Test the communication
Action Results
OMC-R site A. Ask the operator to check at OMC-R that
the BSC - OMC-R link is operational.
The operator confirms the link is
operational.
BSC site B. Check the X.25 SBL status. The corresponding X.25 SBL is
“IT”.
OMC-R site C. Perform a Software Audit of BSS
equipment.
Software audit report message.
OMC-R site D. Check for communication Errors Reports
in the “BSS_xx Follow up” message
window.
No communication errors.
65. Finishing commissioning
3BK 17416 3001 RJZZA 02 61 / 72A L EC T L
10 Finishing commissioning
This chapter describes the tasks that have to be performed at
the end of commissioning.
66. Finishing commissioning
62 / 72 3BK 17416 3001 RJZZA 02A L EC T L
PurposePurposePurposePurpose
➤ To ensure that commissioning is totally complete, and a copy
of all reports from the commissioning of the BSC equipment
is left with the equipment on site.
ProcedureProcedureProcedureProcedure
A. Close the doors of the racks.
B. Leave the site tidy.
C. Close the site and hand the keys to the keyholder.
D. Return the completed forms and the inventory files relating to
the operation to base.
67. Abbreviations
3BK 17416 3001 RJZZA 02 63 / 72A L EC T L
Abbreviations
ASMC Ater submultiplexer C
Ater Interface between BSC and TC
BSS Base station subsystem
DDF Digital distribution frame
CCL Completion check list
GSM Global system for mobile communications
G2 Second generation
ITL-PRO Procedure technical and support information
NE Network Elements (i.e.: BIUA, ASMB ...)
PCM Pulse Code Modulation
SAU Subrack unit
SR Subrack
TC Transcoder
68. Abbreviations
64 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Page intentionally left blank
69. Appendix A List of Items Required
3BK 17416 3001 RJZZA 02 65 / 72A L EC T L
Appendix A List of Items Required
1 List of documents required
The following table is used to check, at base, the availability of the
necessary documents.
Document tittle Reference
Applicable notification list (ITL-PRO) release B7 3DF 00462 0015 UAZZA
Applicable operation instructions (IO) release B7 3DF 00300 0015 UAZZA
BSS site premises inspection, post handover 8BL 00704 0016 DRBRA
Site premises inspection form (CEL) 8BL 00704 0015 DRBRA
SPP-27, Specification for site preparation G2 BSC 8BL 00704 0018 DRBRA
Tools catalogue for field activity 3BK 20458 0001 RJZZA
Completion Check List (CCL) 3BK 17408 3001 QZZZA
BSS Methods Handbook release B7 3BK 17408 0002 PCZZA
Site Equipment Inventory CI 08 3BK 17257 0001 RJZZA
BSS software list Depending on the software version requested
by the customer
2 List of tools required
The following table is used to check, at base, the availability of the
necessary tools.
see « Tools catalogue » for checking the content
Kit name Reference Calibration
Basic kit OUT 001 No
Test cables and plugs (G2 BSC) OUT 013 No
Digital multimeter DES 001 No
Utility PC (BSC LMT) DES 002 No
Inventory kit N° 7 OUT 017 No
70. Appendix A List of Items Required
66 / 72 3BK 17416 3001 RJZZA 02A L EC T L
3 List of software required
The following table is used to check, at base, the availability and the
version of the necessary software.
refer to the corresponding document for checking the SW
version
Name Version checking
Operating system See Tools catalogue for field activity
BSC Terminal/BSCWATxxx BSS software list
LMT_CT/CTxxx.exe BSS software list
TSCSAQxx.0xx BSS software list
BSSBUILD BSS software list
EICON card driver for Windows NT BSS software list
71. Appendix B Example of Inter-Rack Cabling
3BK 17416 3001 RJZZA 02 67 / 72A L EC T L
Appendix B Example of Inter-Rack Cabling
1
2
3
rack B rack A
A = rack A
B = rack B
Figure 10-4 Connecting extension loom
A. Run the interconnection loom at the rear
of the racks (fig.1). Use the addresses
written on the end cable labels (fig.1).
B. Connect the cables to the rear of the
racks.
The addresses locate a locking latch (1
fig.2), and the connector must be
plugged just below it (2 fig.2).
C. Tie the cables to the racks.
Example (fig.2) : 03::36BA03
Subrack 03
Slot 36
Board connector BA
Locking latch address 03
1
2
01
04
07
10
13
16
19
22
25
28
31
01
03
07
10
13
16
19
22
25
28
31
AA
BA
Figure 10-5 Locking latch address
72. Appendix B Example of Inter-Rack Cabling
68 / 72 3BK 17416 3001 RJZZA 02A L EC T L
Page intentionally left blank
73. Appendix C Disabling/enabling alarm reports
3BK 17416 3001 RJZZA 02 69 / 72A L EC T L
Appendix C Disabling/enabling alarm reports
PurposePurposePurposePurpose
➤ To disable Alarm Reports during files transfers between PC
and BSC equipment. This measure is taken to avoid
unsuccessful files transfers.
➤ To enable Alarm Reports when file transfers are finished.
1 Disable Alarm Reports
ProcedureProcedureProcedureProcedure
A. From the ‘Windows BSC Terminal’ main menu:
Commands ðððð Alarm Handling ðððð Enable PC
Report
B. Select the parameters as in the window below and then click
OK.
C. In the ‘Windows BSC Terminal’ window check the report
message.
74. Appendix C Disabling/enabling alarm reports
70 / 72 3BK 17416 3001 RJZZA 02A L EC T L
2 Enable Alarm Reports
ProcedureProcedureProcedureProcedure
A. From the ‘Windows BSC Terminal’ main menu select:
Commands ðððð Alarm Handling ðððð Enable PC
Report
B. Select the parameters as in the window below and then click
OK.
C. In the ‘Windows BSC Terminal’ window check the report.
75. Appendix D Workarounds
3BK 17416 3001 RJZZA 02 71 / 72A L EC T L
Appendix D Workarounds
1 - Exit/Connect WinBSC Terminal
PurposePurposePurposePurpose
➤ To exit from the WinBSC Terminal interface any time the
sequence of operations is blocked.
ProcedureProcedureProcedureProcedure
A. To exit from Windows BSC Terminal:
- click the shortcut exit button (top corner corner in the
‘Windows BSC Terminal‘ window)
- click Yes to confirm the close connection message
below:
B. The following message window appears:
C. To close the connection choose Yes.
D. To run ‘BSC Terminal B7’, from the Taskbar, select:
Start ðððð Programs ðððð WinBSC ðððð B7 ðððð Windows
BSC Terminal B7
The following window appears:
76. Appendix D Workarounds
72 / 72 3BK 17416 3001 RJZZA 02A L EC T L
E. In the ‘BSC Communication Control’ window select:
X25 for “Link Selection” and the “Logging” option and click
Connect.
N O T IC E If an “X25 Link” error message window appears verify the
link with the BSC equipment and repeat the last two steps
again.