SlideShare a Scribd company logo
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents132.1Develop Charter/ScopeProject
Manager22.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager22.4Develop
Communication PlanProject Manager23Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits105.1Obtain Electrical
PermitsSparks Electrical PM106Plumbing Permits106.1Obtain
Plumbing PermitsWaterworks Plumbing PM107Building
Permits107.1Obtain Building PermitsEast Side Framing &
Drywall PM108Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM38.2Framing-BuildEast Side Framing &
Drywall158.3Framing-InspectCity & County58.4Framing-
Project Sign-offProject Manager19Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM311.2Drywall-InstallEast Side Framing
& Drywall1511.3Drywall-InspectCity & County511.4Drywall-
Project Sign-offProject Manager112Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents142.1Develop Charter/ScopeProject
Manager32.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager32.4Develop
Communication PlanProject Manager13Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits145.1Obtain Electrical
PermitsSparks Electrical PM146Plumbing Permits86.1Obtain
Plumbing PermitsWaterworks Plumbing PM87Building
Permits87.1Obtain Building PermitsEast Side Framing &
Drywall PM88Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM48.2Framing-BuildEast Side Framing &
Drywall108.3Framing-InspectCity & County78.4Framing-
Project Sign-offProject Manager39Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM411.2Drywall-InstallEast Side Framing
& Drywall1011.3Drywall-InspectCity & County611.4Drywall-
Project Sign-offProject Manager412Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
Sheet1Work Breakdown StructureProject Name:District 4
Warehouse MoveProject Manager:Date:Work Breakdown
Structure Purpose and LimitationsThe purpose of this worksheet
is to:Identify the work to be doneIdentify the types of resources
required for the workDevelop estimates for each work
elementThis worksheet does not address:When the work will be
completedUse the following table to define the major
deliverables and associated task detail for each deliverable. Use
the example (in red) for help in determining how to break up the
work and identify the Work ID numbers. Expand the table as
needed.Work Package
TaskTasksResource(s) RequiredEstimated Duration
(in days)
TasksEstimated Duration
(in days)
Work PackageID1Project Kick-off41.1Book location for
meetingProject Manager11.2Invite stakeholdersProject
Manager11.3Prepare presentationProject Manager11.4Conduct
the meetingProject Manager and Attendees12Project
Documents142.1Develop Charter/ScopeProject
Manager32.2Develop WBSProject Manager and
Workers72.3Develop Project PlanProject Manager32.4Develop
Communication PlanProject Manager13Status
Reports/Meetings33.1Develop Status ReportProject
Manager13.2Set schedule for team meetingsProject
Manager13.4Set schedule for stakeholder meetingsProject
Manager14Initial Planning Meetings with Vendors54.1Meet
with Framing/DrywallProject Manager and East Side Framing
PM14.2Meet with ElectricalProject Manager and Sparks
Electrical PM14.3Meet with PlumbingProject Manager and
Waterworks Plumbing PM14.4Meet with Finish WorkProject
Manager and Woodcraft Carpentry PM14.5Meet with Student
WorkersProject Manager and Student Workers
Manger15Electrical Permits145.1Obtain Electrical
PermitsSparks Electrical PM146Plumbing Permits86.1Obtain
Plumbing PermitsWaterworks Plumbing PM87Building
Permits87.1Obtain Building PermitsEast Side Framing &
Drywall PM88Framing248.1Framing-Order SuppliesEast Side
Framing & Drywall PM48.2Framing-BuildEast Side Framing &
Drywall108.3Framing-InspectCity & County78.4Framing-
Project Sign-offProject Manager39Electrical199.1Electrical-
Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks
Electrical109.3Electrical-InspectCity & County59.4Electrical-
Project Sign-offProject Manager110Plumbing1910.1Plumbing-
Order SuppliesWaterworks Plumbing PM310.2Plumbing-
InstallWaterworks Plumbing1010.3Plumbing-InspectCity &
County510.4Plumbing-Project Sign-offProject
Manager111Drywall2411.1Drywall-Order SuppliesEast Side
Framing & Drywall PM411.2Drywall-InstallEast Side Framing
& Drywall1011.3Drywall-InspectCity & County611.4Drywall-
Project Sign-offProject Manager412Finish Work2412.1Finish-
Order SuppliesWoodcraft Carpentry PM312.2Finish-
InstallWoodcraft Carpentry1512.3Finish-InspectCity &
County512.4Finish-Project Sign-offProject
Manager113Workbenches2013.1Workbenches-Order
SuppliesStudent Workers Manager213.2Workbenches-
BuildStudent Workers1513.3Workbenches-Quality
inspectionProject Manager213.4Workbenches-Project Sign-
offProject Manager114Equipment Packing514.1Pack production
equipmentCity Equipment Movers PM214.2Pack non-production
equipmentCity Equipment Movers214.3Project Sign-offProject
Manager115Move715.1Move production equipmentExpress
Moving Company PM315.2Move non-production
equipmentExpress Moving Company315.3Project Sign-
offProject Manager116Procurement Closure516.1Review
contract workProject Manager316.2Release contractorsProject
Manager116.3Pay contractorsProject Manager117Project
Closure717.1Final reportProject Manager317.2Archive
documentationProject Manager317.3Lessons LearnedProject
Manager1
Sheet2
Sheet3
Running Head: DISTRICT4WAREHOUSEMOVE
1
DISTRICT4WAREHOUSEMOVE
6
District4WarehouseMove
Cannon_F_M3_A2
August 24th,2018
Please see my comments below to see the items that need to be
addressed in the write-up (report).
District4WarehouseMove
(a) Project plan with precedence relationship is given below:
ID
Task
Estimated Duration
Pred1ecessor
1
Start of the project
4
2
Documents of the project
8
1
3
Status Meetings/Reports
2
2
4
Initial Meetings Planning
4
3
5
Permits of Electricity
11
4
6
Permits of Plumbing
11
4
7
Permits of Buildings
15
5
8
Framing
55
5
9
Electrical
11
6
10
Plumbing
11
7
11
Drywall
2
8
12
Work Finnish
30
9,10,11,12
13
Workbenches
19
12
14
Packing Equipment
16
13
15
Move
2
14
16
Closure Procurement
2
15
17
Closure Project
9
16
(b) Project network diagram (Activity on Node) diagram is
following
(c) Alternative paths and Critical path are as listed below
For the whole project to be completed, it will take up to 122
days.
References (What is it you are referencing when there is no
write-up?)
Mind Tool, Inc. (2013) Project Management Phases and
Processes. Retrieved October 26, 2013 from
Piscopo, M. (2013) Performance Report. Retrieved October 26,
2013 from
http://www.projectmanagementdocs.com/project-
documents/performance-report.html
Project Closure (n.d.) Retrieved October 26, 2013 from
https://wiki.state.ma.us/confluence/download/attachments/6989
4234/Closure+Training.pdf
Comments:
The project plan was not correctly developed and the
appropriate work breakdown structure (WBS) was not properly
completed.
The predecessor column was not correctly completed and set
included additional aspects that set it apart from the ordinary.
Critical paths activities were not correctly identified with
additional insights.
The risks that would impact the project schedule were not
correctly identified with appropriate information/action to
mitigate those risks.
The paper was not adequately organized with a good
introduction and conclusion. There was no writing to assess
spelling/grammar error. APA elements were not appropriately
addressed.
Running head: DEFINING PROJECT SCOPE
1
Defining Project Scope
6
Defining Project Scope
Cannon_F_M1_A3
August 9th,2018
Defining Project Scope
Introduction
A project scope contains information about a project. The kind
of information in his case is the details of what can be included
in the project or what can be excluded from it. (Neville, T. Et
al). A project scope in my own terms can be regarded to as a
blue print of a project. Trillo Apparel Current (TAC) is an
operational company that as four divisions. The company has its
headquarters in Albuquerque, New Mexico and it is estimated to
have around 3000 employees as its human resources. The
company has intentions of expanding its facilities and moves its
facility to a selected location that has sufficient room that can
accommodate the companyโ€™s production and the shipping
department. In this paper we are going to define the scope of
this new project or initiative that the company has decided to
work on. We are going to look at the projectโ€™s objective, its
deliverables, milestones, technical requirements, and the review
with the customer.
Project Objective
The intent, outcomes and the effects of the project to its target
group can be defined to as the project objective. In this case,
the intent of the project is to create sufficient room for the
company that can accommodate its production and shipping
departments. The anticipated outcomes of this project will be
deployment of two operations within then companyโ€™s operations
in one location. The anticipated effect of this project is that it
may cause disruptions to the production activities within the
company. The company has to renovate its warehouse so that it
can accommodate the East districtโ€™s operational needs.
Deliverables
The inspections and authorizing of this project can take up to
three weeks all this being reliant to the projectโ€™s inspectorโ€™s
flexibility. Contacts have already been granted and the Pack,
move and unpack production equipment, and Move non-
production equipment and materials will take up to 5days.
Framing, drywall, finish work and Build work benches for
production floor are set to take place in 15days, and the
electrical and the plumping woks can take up to 10days. The
project is expected to be completed within 4 months.
Milestones
The milestones that do accompany this project is that the
company expects the actual move of the materials that can
accommodate the companyโ€™s needs has to be done within 5 days
and in this case the renovation of the warehouse has to take
over two weeks.
Technical requirements
The technical requirements of this project require carpenters,
masons, electricians and the necessary manpower and
supervision to take place.
Limits and exclusion
The renovation of the ware house is scheduled to take place in
two weeksโ€™ time and the movement of equipment into the
warehouse has to take place within 5 days so that it can offer
minimum disruption to the companyโ€™s production activities.
This means that the movement of the equipment has to be done
away with or postponed until the renovation has completely
been done. In this case, the companyโ€™s productivity will be
affected.
Reviews with the customer
The customer being the company wants this done within a scope
of 5 days. In this case, it is quite impossible because the walls
have to dry and the complete renovation of the warehouse has to
be done so that it can be ready. The customer has to adjust its
productivity to provide room for the completion of the project.
Reference (not APA formatted)
Neville, T. Et al. Defining the Scope of a Project. Name of the
Source. City:State.
You need to provide the names of the authors in the body of the
paper; then, you can abbreviate in the reference page
Comments:
The project scope document was well prepared and the expected
outcomes were clear with the specifications of deliverables,
milestones, technical requirements, limits and exclusions, and
reviews with customers.
The complete scope of the project was adequately prepared with
the different areas affected by the project and responsibilities of
the client and the project team.
All sections of the scope checklist were included: project
objectives, deliverables, milestones, technical requirements,
limits and exclusions, and reviews with customers.
The paper was well written with correct grammar and spelling.
APA style was attempted and appropriately followed.
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx

More Related Content

Similar to Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx

dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
SunilHotkar2
ย 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
TecnicoItca
ย 
Part 3Aยท After creating the resource pool, copy the screen image.docx
Part 3Aยท After creating the resource pool, copy the screen image.docxPart 3Aยท After creating the resource pool, copy the screen image.docx
Part 3Aยท After creating the resource pool, copy the screen image.docx
herbertwilson5999
ย 
Techno functional dcoument template v1.0
Techno functional dcoument template v1.0Techno functional dcoument template v1.0
Techno functional dcoument template v1.0
Avinash Kadam
ย 
Daycare construction project
Daycare construction projectDaycare construction project
Daycare construction project
YOUBEJOSEPH
ย 
Project Output Powerpoint Presentation Slides
Project Output Powerpoint Presentation SlidesProject Output Powerpoint Presentation Slides
Project Output Powerpoint Presentation Slides
SlideTeam
ย 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
evonnehoggarth79783
ย 
Project resource plan for manager
Project resource plan for managerProject resource plan for manager
Project resource plan for manager
hangngoainhapcomvn
ย 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
mary772
ย 
Chapter 4
Chapter 4Chapter 4
Chapter 4
uncleRhyme
ย 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
Aditya Pandey
ย 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
ssuserc0e4e0
ย 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
jessiehampson
ย 
Ch05
Ch05Ch05
Ch05
chris1217
ย 
Project Result PowerPoint Presentation Slides
Project Result PowerPoint Presentation Slides Project Result PowerPoint Presentation Slides
Project Result PowerPoint Presentation Slides
SlideTeam
ย 
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docxProject EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
briancrawford30935
ย 
Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides
SlideTeam
ย 
Version #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docxVersion #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docx
jessiehampson
ย 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
Ronald Oroya
ย 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
Kushal Patel
ย 

Similar to Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx (20)

dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
ย 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
ย 
Part 3Aยท After creating the resource pool, copy the screen image.docx
Part 3Aยท After creating the resource pool, copy the screen image.docxPart 3Aยท After creating the resource pool, copy the screen image.docx
Part 3Aยท After creating the resource pool, copy the screen image.docx
ย 
Techno functional dcoument template v1.0
Techno functional dcoument template v1.0Techno functional dcoument template v1.0
Techno functional dcoument template v1.0
ย 
Daycare construction project
Daycare construction projectDaycare construction project
Daycare construction project
ย 
Project Output Powerpoint Presentation Slides
Project Output Powerpoint Presentation SlidesProject Output Powerpoint Presentation Slides
Project Output Powerpoint Presentation Slides
ย 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
ย 
Project resource plan for manager
Project resource plan for managerProject resource plan for manager
Project resource plan for manager
ย 
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docxCMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
CMGT 410 Week 1 Project Plan DraftA project plan is a docume.docx
ย 
Chapter 4
Chapter 4Chapter 4
Chapter 4
ย 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
ย 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
ย 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
ย 
Ch05
Ch05Ch05
Ch05
ย 
Project Result PowerPoint Presentation Slides
Project Result PowerPoint Presentation Slides Project Result PowerPoint Presentation Slides
Project Result PowerPoint Presentation Slides
ย 
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docxProject EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
Project EvaluationSD2 - countFuncLOC projectProject Team[DATE]Dev.docx
ย 
Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides Project Gain PowerPoint Presentation Slides
Project Gain PowerPoint Presentation Slides
ย 
Version #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docxVersion #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docx
ย 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
ย 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
ย 

More from bjohn46

Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docxSheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
bjohn46
ย 
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docxSheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
bjohn46
ย 
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docxSheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
bjohn46
ย 
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docxSheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
bjohn46
ย 
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docxSheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
bjohn46
ย 
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docxSheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
bjohn46
ย 
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docxSheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
bjohn46
ย 
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docxSheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
bjohn46
ย 
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docxSheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
bjohn46
ย 
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docxSheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
bjohn46
ย 
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docxSheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
bjohn46
ย 
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docxSheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
bjohn46
ย 
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docxSheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
bjohn46
ย 
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docxSheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
bjohn46
ย 
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docxSheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
bjohn46
ย 
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docxSheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
bjohn46
ย 
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docxSheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
bjohn46
ย 
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docxSheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
bjohn46
ย 
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docxSheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
bjohn46
ย 
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docxSheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
bjohn46
ย 

More from bjohn46 (20)

Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docxSheet1Rate your skills using the following scaleChapter 1 You Ma.docx
Sheet1Rate your skills using the following scaleChapter 1 You Ma.docx
ย 
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docxSheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
Sheet1Quarterย Sales PersonRegionQuarterly Sales31-MarSmithEast$750.docx
ย 
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docxSheet1project codeproject nameEmployeesQB280001Account Management .docx
Sheet1project codeproject nameEmployeesQB280001Account Management .docx
ย 
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docxSheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
Sheet1Quantity (miles of pipeline)Total CostTotal Fixed CostTotal .docx
ย 
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docxSheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
Sheet1Pro Forma Income StatementYear 1Year 2Year 3Year 4Year 5Visi.docx
ย 
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docxSheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 8 Assignment20Is the Lean .docx
ย 
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docxSheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
Sheet1Presentation by Tony StudentSlide NumberSlide TitleSlide Tex.docx
ย 
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docxSheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
Sheet1Pretax IncomeYang, Ziyun make sure to add back income t.docx
ย 
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docxSheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
Sheet1PMGT 576 Assignment Rubric โ€“ Unit 7 Assignment20Are all of t.docx
ย 
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docxSheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
Sheet1Plan APlan BPro Forma Income Statement AccountsEBIT700100013.docx
ย 
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docxSheet1Phase of Business Financal Management needsDebt FinancingEq.docx
Sheet1Phase of Business Financal Management needsDebt FinancingEq.docx
ย 
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docxSheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
Sheet1PeriodEngine Failures(a) 4-period moving average(b) weighted.docx
ย 
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docxSheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
Sheet1Participant#Verbal Label Condition (Smashed or Hit)Age Condi.docx
ย 
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docxSheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
Sheet1No.Strengths (3)Weaknesses (2)Recommendations (2)Evidence (u.docx
ย 
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docxSheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
ย 
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docxSheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
Sheet1ManhattanBrooklynQueensThe BronxStaten IslandEducationMarita.docx
ย 
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docxSheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
Sheet1Learning Solultions NameVersion NumberMediumTypeLessonSc.docx
ย 
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docxSheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
Sheet1LMH10090H80M70L605040302010NumberRisk NameFull Risk CostRisk.docx
ย 
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docxSheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
Sheet1Item Price# of ItemsTotal PriceCups$1.896$11.34Plates$1.506$.docx
ย 
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docxSheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
Sheet1In_OutAustralian_CityInternational_CityAirlineRoutePort_Coun.docx
ย 

Recently uploaded

Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
ย 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
ย 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
nitinpv4ai
ย 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
MysoreMuleSoftMeetup
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
ย 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
MJDuyan
ย 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
David Douglas School District
ย 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
RidwanHassanYusuf
ย 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
ย 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
ย 
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
ย 
CIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdfCIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdf
blueshagoo1
ย 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
nitinpv4ai
ย 
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
Nguyen Thanh Tu Collection
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
Mohammad Al-Dhahabi
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
ย 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
deepaannamalai16
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
Celine George
ย 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
ย 

Recently uploaded (20)

Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
ย 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
ย 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
ย 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
ย 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
ย 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
ย 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
ย 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
ย 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
ย 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
ย 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
ย 
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Prรฉsentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
ย 
CIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdfCIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdf
ย 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
ย 
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
Bร€I TแบฌP Bแป” TRแปข TIแบพNG ANH LแปšP 9 Cแบข Nฤ‚M - GLOBAL SUCCESS - Nฤ‚M HแปŒC 2024-2025 - ...
ย 
skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)skeleton System.pdf (skeleton system wow)
skeleton System.pdf (skeleton system wow)
ย 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
ย 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
ย 
How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17How to Predict Vendor Bill Product in Odoo 17
How to Predict Vendor Bill Product in Odoo 17
ย 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
ย 

Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx

  • 1. Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers Manger15Electrical Permits105.1Obtain Electrical
  • 2. PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing & Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject Manager1
  • 3. Sheet2 Sheet3 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers
  • 4. Manger15Electrical Permits105.1Obtain Electrical PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing & Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject
  • 5. Manager1 Sheet2 Sheet3 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents132.1Develop Charter/ScopeProject Manager22.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager22.4Develop Communication PlanProject Manager23Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student
  • 6. WorkersProject Manager and Student Workers Manger15Electrical Permits105.1Obtain Electrical PermitsSparks Electrical PM106Plumbing Permits106.1Obtain Plumbing PermitsWaterworks Plumbing PM107Building Permits107.1Obtain Building PermitsEast Side Framing & Drywall PM108Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM38.2Framing-BuildEast Side Framing & Drywall158.3Framing-InspectCity & County58.4Framing- Project Sign-offProject Manager19Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM311.2Drywall-InstallEast Side Framing & Drywall1511.3Drywall-InspectCity & County511.4Drywall- Project Sign-offProject Manager112Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive
  • 7. documentationProject Manager317.3Lessons LearnedProject Manager1 Sheet2 Sheet3 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents142.1Develop Charter/ScopeProject Manager32.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager32.4Develop Communication PlanProject Manager13Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and Waterworks Plumbing PM14.4Meet with Finish WorkProject
  • 8. Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers Manger15Electrical Permits145.1Obtain Electrical PermitsSparks Electrical PM146Plumbing Permits86.1Obtain Plumbing PermitsWaterworks Plumbing PM87Building Permits87.1Obtain Building PermitsEast Side Framing & Drywall PM88Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM48.2Framing-BuildEast Side Framing & Drywall108.3Framing-InspectCity & County78.4Framing- Project Sign-offProject Manager39Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM411.2Drywall-InstallEast Side Framing & Drywall1011.3Drywall-InspectCity & County611.4Drywall- Project Sign-offProject Manager412Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject Manager116.3Pay contractorsProject Manager117Project
  • 9. Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject Manager1 Sheet2 Sheet3 Sheet1Work Breakdown StructureProject Name:District 4 Warehouse MoveProject Manager:Date:Work Breakdown Structure Purpose and LimitationsThe purpose of this worksheet is to:Identify the work to be doneIdentify the types of resources required for the workDevelop estimates for each work elementThis worksheet does not address:When the work will be completedUse the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.Work Package TaskTasksResource(s) RequiredEstimated Duration (in days) TasksEstimated Duration (in days) Work PackageID1Project Kick-off41.1Book location for meetingProject Manager11.2Invite stakeholdersProject Manager11.3Prepare presentationProject Manager11.4Conduct the meetingProject Manager and Attendees12Project Documents142.1Develop Charter/ScopeProject Manager32.2Develop WBSProject Manager and Workers72.3Develop Project PlanProject Manager32.4Develop Communication PlanProject Manager13Status Reports/Meetings33.1Develop Status ReportProject Manager13.2Set schedule for team meetingsProject Manager13.4Set schedule for stakeholder meetingsProject Manager14Initial Planning Meetings with Vendors54.1Meet with Framing/DrywallProject Manager and East Side Framing PM14.2Meet with ElectricalProject Manager and Sparks Electrical PM14.3Meet with PlumbingProject Manager and
  • 10. Waterworks Plumbing PM14.4Meet with Finish WorkProject Manager and Woodcraft Carpentry PM14.5Meet with Student WorkersProject Manager and Student Workers Manger15Electrical Permits145.1Obtain Electrical PermitsSparks Electrical PM146Plumbing Permits86.1Obtain Plumbing PermitsWaterworks Plumbing PM87Building Permits87.1Obtain Building PermitsEast Side Framing & Drywall PM88Framing248.1Framing-Order SuppliesEast Side Framing & Drywall PM48.2Framing-BuildEast Side Framing & Drywall108.3Framing-InspectCity & County78.4Framing- Project Sign-offProject Manager39Electrical199.1Electrical- Order SuppliesSparks Electrical PM39.2Electrical-InstallSparks Electrical109.3Electrical-InspectCity & County59.4Electrical- Project Sign-offProject Manager110Plumbing1910.1Plumbing- Order SuppliesWaterworks Plumbing PM310.2Plumbing- InstallWaterworks Plumbing1010.3Plumbing-InspectCity & County510.4Plumbing-Project Sign-offProject Manager111Drywall2411.1Drywall-Order SuppliesEast Side Framing & Drywall PM411.2Drywall-InstallEast Side Framing & Drywall1011.3Drywall-InspectCity & County611.4Drywall- Project Sign-offProject Manager412Finish Work2412.1Finish- Order SuppliesWoodcraft Carpentry PM312.2Finish- InstallWoodcraft Carpentry1512.3Finish-InspectCity & County512.4Finish-Project Sign-offProject Manager113Workbenches2013.1Workbenches-Order SuppliesStudent Workers Manager213.2Workbenches- BuildStudent Workers1513.3Workbenches-Quality inspectionProject Manager213.4Workbenches-Project Sign- offProject Manager114Equipment Packing514.1Pack production equipmentCity Equipment Movers PM214.2Pack non-production equipmentCity Equipment Movers214.3Project Sign-offProject Manager115Move715.1Move production equipmentExpress Moving Company PM315.2Move non-production equipmentExpress Moving Company315.3Project Sign- offProject Manager116Procurement Closure516.1Review contract workProject Manager316.2Release contractorsProject
  • 11. Manager116.3Pay contractorsProject Manager117Project Closure717.1Final reportProject Manager317.2Archive documentationProject Manager317.3Lessons LearnedProject Manager1 Sheet2 Sheet3 Running Head: DISTRICT4WAREHOUSEMOVE 1 DISTRICT4WAREHOUSEMOVE 6 District4WarehouseMove Cannon_F_M3_A2 August 24th,2018 Please see my comments below to see the items that need to be addressed in the write-up (report). District4WarehouseMove (a) Project plan with precedence relationship is given below: ID Task Estimated Duration Pred1ecessor 1 Start of the project 4 2
  • 12. Documents of the project 8 1 3 Status Meetings/Reports 2 2 4 Initial Meetings Planning 4 3 5 Permits of Electricity 11 4 6 Permits of Plumbing 11 4 7 Permits of Buildings 15 5 8 Framing 55 5 9 Electrical 11 6 10 Plumbing 11 7 11
  • 13. Drywall 2 8 12 Work Finnish 30 9,10,11,12 13 Workbenches 19 12 14 Packing Equipment 16 13 15 Move 2 14 16 Closure Procurement 2 15 17 Closure Project 9 16 (b) Project network diagram (Activity on Node) diagram is following (c) Alternative paths and Critical path are as listed below For the whole project to be completed, it will take up to 122 days.
  • 14. References (What is it you are referencing when there is no write-up?) Mind Tool, Inc. (2013) Project Management Phases and Processes. Retrieved October 26, 2013 from Piscopo, M. (2013) Performance Report. Retrieved October 26, 2013 from http://www.projectmanagementdocs.com/project- documents/performance-report.html Project Closure (n.d.) Retrieved October 26, 2013 from https://wiki.state.ma.us/confluence/download/attachments/6989 4234/Closure+Training.pdf Comments: The project plan was not correctly developed and the appropriate work breakdown structure (WBS) was not properly completed. The predecessor column was not correctly completed and set included additional aspects that set it apart from the ordinary. Critical paths activities were not correctly identified with additional insights. The risks that would impact the project schedule were not correctly identified with appropriate information/action to mitigate those risks. The paper was not adequately organized with a good introduction and conclusion. There was no writing to assess spelling/grammar error. APA elements were not appropriately addressed. Running head: DEFINING PROJECT SCOPE
  • 15. 1 Defining Project Scope 6 Defining Project Scope Cannon_F_M1_A3 August 9th,2018 Defining Project Scope Introduction A project scope contains information about a project. The kind of information in his case is the details of what can be included in the project or what can be excluded from it. (Neville, T. Et al). A project scope in my own terms can be regarded to as a blue print of a project. Trillo Apparel Current (TAC) is an operational company that as four divisions. The company has its headquarters in Albuquerque, New Mexico and it is estimated to have around 3000 employees as its human resources. The company has intentions of expanding its facilities and moves its facility to a selected location that has sufficient room that can accommodate the companyโ€™s production and the shipping department. In this paper we are going to define the scope of this new project or initiative that the company has decided to work on. We are going to look at the projectโ€™s objective, its deliverables, milestones, technical requirements, and the review with the customer. Project Objective The intent, outcomes and the effects of the project to its target group can be defined to as the project objective. In this case, the intent of the project is to create sufficient room for the company that can accommodate its production and shipping departments. The anticipated outcomes of this project will be
  • 16. deployment of two operations within then companyโ€™s operations in one location. The anticipated effect of this project is that it may cause disruptions to the production activities within the company. The company has to renovate its warehouse so that it can accommodate the East districtโ€™s operational needs. Deliverables The inspections and authorizing of this project can take up to three weeks all this being reliant to the projectโ€™s inspectorโ€™s flexibility. Contacts have already been granted and the Pack, move and unpack production equipment, and Move non- production equipment and materials will take up to 5days. Framing, drywall, finish work and Build work benches for production floor are set to take place in 15days, and the electrical and the plumping woks can take up to 10days. The project is expected to be completed within 4 months. Milestones The milestones that do accompany this project is that the company expects the actual move of the materials that can accommodate the companyโ€™s needs has to be done within 5 days and in this case the renovation of the warehouse has to take over two weeks. Technical requirements The technical requirements of this project require carpenters, masons, electricians and the necessary manpower and supervision to take place. Limits and exclusion The renovation of the ware house is scheduled to take place in two weeksโ€™ time and the movement of equipment into the warehouse has to take place within 5 days so that it can offer minimum disruption to the companyโ€™s production activities. This means that the movement of the equipment has to be done
  • 17. away with or postponed until the renovation has completely been done. In this case, the companyโ€™s productivity will be affected. Reviews with the customer The customer being the company wants this done within a scope of 5 days. In this case, it is quite impossible because the walls have to dry and the complete renovation of the warehouse has to be done so that it can be ready. The customer has to adjust its productivity to provide room for the completion of the project. Reference (not APA formatted) Neville, T. Et al. Defining the Scope of a Project. Name of the Source. City:State. You need to provide the names of the authors in the body of the paper; then, you can abbreviate in the reference page Comments: The project scope document was well prepared and the expected outcomes were clear with the specifications of deliverables, milestones, technical requirements, limits and exclusions, and reviews with customers. The complete scope of the project was adequately prepared with the different areas affected by the project and responsibilities of the client and the project team. All sections of the scope checklist were included: project objectives, deliverables, milestones, technical requirements, limits and exclusions, and reviews with customers. The paper was well written with correct grammar and spelling. APA style was attempted and appropriately followed.