SlideShare a Scribd company logo
1 of 8
Download to read offline
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
1. EQUALUZATION TANK:
The project started with septic tank cleaning. It is 60 m3
tank in which industrial waste/ effluent of entire plant
would accumulate. The tank has rectangular base area of
40 ft2 approximately. Submersible pumps were used to
remove water and subsequently, sweepers put out all
the sludge manually and disposed it into drain. All safety
measures were adopted during the entire cleaning
process. Compressed air line was provided so as to avoid
short of breath problem. The man holes were kept open throughout in order to avoid
accumulation of toxic gases inside the tank. Once the cleaning process was completed, floor
was leveled using concrete. It was strengthened using SBR binder. The floor was allowed to
cure and dry.
Then concrete blocks for the aeration header were plastered to the surface. They were installed
in such a way that the aeration header lies along the centre of the tank. As there are three
portions in the tank, core cutting was done to allow passage of header from one compartment
to another. The header (3’’) was then installed, 100 mm from the underground level, supported
by blocks. They were further clamped with u bolts and were then coated with concrete. All
remaining pebbles were removed from the tank after installation.
Diffusers serve the medium for the aeration. They are
coarse bubble diffusers, which provide efficient mixing
followed by growth of micro-organisms, which are actually
responsible to carry out the process, i.e. decreasing COD &
BOD. Diffusers are attached to the aeration header. Silicone
is used to provide water proofing.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
Two submersible pumps are also placed, that will
transfer the water to the bio reactor, delivering pressure
of about 1.5 bar. 2’’ line is connected to the pump
outlet, evolving from a cut out provided for this purpose.
These lines connect to a header from which a common
emerges, connecting the septic tank and the reactor.
Double union ball valves are provided followed by NRV
to prevent back flow. Line (1/2’’) for pressure gauge is
also provided. A frame is fabricated for the cut out,
coated with red oxide to prevent corrosion. Checkered
plates have been fabricated. Ropes are provided to
facilitate easy removal of pumps when required. A drain
line is provided to with draw water outside the factory.
This is provided for safety measures, i.e. avoiding entry
of dead organisms into the reactor. Supports are
fabricated as required.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
2. SUPPORTS FABRICATION AND INSTALLTION:
Three types of E supports were designed and fabricated
for the piping spool and cable trays. They were coated
with red oxide and painted royal blue color. The spool
and cable trays were then run on the supports.
3. CONSTRUCTION OF PIT:
It started with excavation of pit having approx.
dimensions of 5*5*5 ft. during excavation seepage water
starts accumulating. Therefore, padlo was used to cater this problem. After then pit was given
physical structure using wooden planks. Iron reinforced concrete was used for its construction.
It was then left for some days to cure and dry. The floor was later on plastered.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
An enclosure of material SS 316, was fabricated
for the bar screen. Bar screen having dimensions
of about 1600*900 mm, will be placed at an
angle of 45ᴼ. This bar screen is responsible to
retain all the solid material present in the
effluent. Rawl bolts and concrete support the
enclosure. Later on ceiling for the pit is laid using
reinforced concrete.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
A cavity is provided for manhole frame and
checkered plate. Finally bitumen diluted in
turpentine oil is coated on the outside wall to
prevent entry of seepage water into the pit.
4. BLOWER INSTALLATION:
Blower is palced on the foundation pad. The line (3’’)
originating from the septic tank is connected with
the 1.5’’ line, attached to the blower, through a
reducing bush. A bellow is provided on the dsicharge
side to prevent breakage of nozzle.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
5. BIOPLUG/MEMPAC PIPING & AUXILIARIES:
Bioreactor is responsible for the entire waste water treatment. Its
capacity is 35m3 and material of construction is mild steel. Epoxy lining
is done on the interior side to prevent corrosion. It acquires the feed
through the septic tank’s submersible pumps. The line merges to
header. The header itself consist of two lines, to carry the liquor to the
membrane tank. These two lines are attached to the submersible
pumps placed in the bioplug. These pumps have 68 ip (ingress
protection) value. A recycle line is attached to the
header, for recirculation purpose. Butterfly valves are
used in the line, connected to the header. A mini screen
is placed at the feed inlet to prevent entry of foreign
solid material.
Air is introduced into the reactor by means of aeration
header to which diffusers are attached. These diffusers
evenly distribute air, through a blower, present in the
membrane container. Pipeline used for air is galvanized iron. An air
breather/filter is attcahed a the suction of blower to prevent entry of
dust/ debris present in the environment.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
this blower supplies air to reactor as well as to the
membrane tank as required, i.e. air can be used as
cleaning agent for membrane. This process is referred as
membrane scouring.
The water is filtered through UF membrane. These
membranes are composed of PVDF (poly vinyl difluoride).
The filtering phenomemon is done by creating a negative
pressure by means of permeate pump. As a result of
which, sludge is reatined in the membrane tank, where as
water is transferred to the permeate tank. Back pulse tank
is also filled side by side as the water flows through
permeate pump. A recycle line is provided to feed sludge
back to the reactor, once the membrane tank over flows.
Through this line, a tee is provided to fill the sludge to
the sludge tank. This is done by means of gravity.
Supports have been fabricated to run pipe spools and
cable trays. Butterfly valves are used in the drain
connection. Drain lines have not been completed as they
are to be concealed as required by client. Trench will be
dug by client. Screw pumps for the transfer of sludge
from the sludge tank to the filter press have been
placed. Their suction header have been fabricated.
MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15
Polymer dosing tank has been placed. Its
foundation platform has been fabricated. It is
responsible to agglomerate the sludge, inorder to
facilitate sedimentation phenomenon. Frame for
air conditioner, to be placed in container, has
been fabricated.
MISSING FITTINGS IN THE SHIPMENT:
 Incomplete set of bolts/studs.
 Part of saddle clamp missing.
 gaskets unavialability.
 Mating flanges missing
 Fittings for polymer dosing tank missing.
 Solenoid valve wiring tempered.
 Hypo dosing system fitting tempered.
 Antique type of filter press.
 Cast iron butterfly valve missing.
 Contardiction in given isometric drawing and
actual fitting.

More Related Content

What's hot

Sanitation and plumbing
Sanitation and plumbing Sanitation and plumbing
Sanitation and plumbing Hansa katare
 
Laying and Testing of sewer
Laying and Testing of sewerLaying and Testing of sewer
Laying and Testing of sewersathyan s
 
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGWATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGKaran Patel
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of waterGokul Saud
 
Sewer appurtenances
Sewer appurtenances Sewer appurtenances
Sewer appurtenances SitalParajuli
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYRIDDHESH VARIK
 
04 plumbing fixtures II
04 plumbing fixtures   II04 plumbing fixtures   II
04 plumbing fixtures IIHena Dutt
 
03 plumbing fixtures
03 plumbing fixtures03 plumbing fixtures
03 plumbing fixturesHena Dutt
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and applianceHarsha Singh
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyManish Pandey
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a BuildingAroh Thombre
 
Drainage system
Drainage systemDrainage system
Drainage systemNikhil Jp
 
Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 finaliampichu
 

What's hot (20)

Plumbing
PlumbingPlumbing
Plumbing
 
Refuse Chute
Refuse ChuteRefuse Chute
Refuse Chute
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenances
 
Sanitary and water supply
Sanitary and water supplySanitary and water supply
Sanitary and water supply
 
Sanitation and plumbing
Sanitation and plumbing Sanitation and plumbing
Sanitation and plumbing
 
House plumbing
House plumbingHouse plumbing
House plumbing
 
Laying and Testing of sewer
Laying and Testing of sewerLaying and Testing of sewer
Laying and Testing of sewer
 
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGWATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
 
PIPE SYSTEMS1
PIPE SYSTEMS1PIPE SYSTEMS1
PIPE SYSTEMS1
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
 
Sewer appurtenances
Sewer appurtenances Sewer appurtenances
Sewer appurtenances
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
 
Plumbing presentation
Plumbing presentationPlumbing presentation
Plumbing presentation
 
04 plumbing fixtures II
04 plumbing fixtures   II04 plumbing fixtures   II
04 plumbing fixtures II
 
03 plumbing fixtures
03 plumbing fixtures03 plumbing fixtures
03 plumbing fixtures
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliance
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 final
 

Similar to DPR TILL 15-06-15

Sanotary installation
Sanotary installationSanotary installation
Sanotary installationRajiva Gupta
 
International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)ijceronline
 
Rainwater harvesting
Rainwater harvesting Rainwater harvesting
Rainwater harvesting vidooshak
 
Unit ii introduction to water supply scheme
Unit  ii introduction to water supply schemeUnit  ii introduction to water supply scheme
Unit ii introduction to water supply schemeMadhukarJadhav8
 
Rooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRevadhBalraj
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdfAihamAltayeh1
 
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationAttleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationThomasSexton8
 
7145044 rain-water-harvesting
7145044 rain-water-harvesting7145044 rain-water-harvesting
7145044 rain-water-harvestingGerrie Rousseau
 
Selection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainageSelection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainageJessy Mariaraj
 
Sanitary fitting.pptx
Sanitary fitting.pptxSanitary fitting.pptx
Sanitary fitting.pptxyasirkhan470
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2ctlachu
 
construction of drain and seers
construction of drain and seersconstruction of drain and seers
construction of drain and seersjeetusinghkumar
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxPRACHI DESSAI
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDr. M. Kumaresan Hort.
 
Water supply system (distribution system and house water plumbing)
Water supply system (distribution system and house water plumbing)Water supply system (distribution system and house water plumbing)
Water supply system (distribution system and house water plumbing)Basant Lekhak
 

Similar to DPR TILL 15-06-15 (20)

DPR TILL 02-06-15
DPR TILL 02-06-15DPR TILL 02-06-15
DPR TILL 02-06-15
 
Sanotary installation
Sanotary installationSanotary installation
Sanotary installation
 
International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)
 
Rainwater harvesting
Rainwater harvesting Rainwater harvesting
Rainwater harvesting
 
Unit ii introduction to water supply scheme
Unit  ii introduction to water supply schemeUnit  ii introduction to water supply scheme
Unit ii introduction to water supply scheme
 
Rooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource managementRooftop Rainwater Harvesting -Natural resource management
Rooftop Rainwater Harvesting -Natural resource management
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
 
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station RehabilitationAttleboro Luther's Reservoir Dam & Pump Station Rehabilitation
Attleboro Luther's Reservoir Dam & Pump Station Rehabilitation
 
7145044 rain-water-harvesting
7145044 rain-water-harvesting7145044 rain-water-harvesting
7145044 rain-water-harvesting
 
Selection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainageSelection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainage
 
Sewer Appurtances
Sewer AppurtancesSewer Appurtances
Sewer Appurtances
 
HOUSE DRAINAGE
 HOUSE DRAINAGE HOUSE DRAINAGE
HOUSE DRAINAGE
 
Sanitary fitting.pptx
Sanitary fitting.pptxSanitary fitting.pptx
Sanitary fitting.pptx
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2
 
16
1616
16
 
construction of drain and seers
construction of drain and seersconstruction of drain and seers
construction of drain and seers
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptx
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
 
Water supply system (distribution system and house water plumbing)
Water supply system (distribution system and house water plumbing)Water supply system (distribution system and house water plumbing)
Water supply system (distribution system and house water plumbing)
 

DPR TILL 15-06-15

  • 1. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 1. EQUALUZATION TANK: The project started with septic tank cleaning. It is 60 m3 tank in which industrial waste/ effluent of entire plant would accumulate. The tank has rectangular base area of 40 ft2 approximately. Submersible pumps were used to remove water and subsequently, sweepers put out all the sludge manually and disposed it into drain. All safety measures were adopted during the entire cleaning process. Compressed air line was provided so as to avoid short of breath problem. The man holes were kept open throughout in order to avoid accumulation of toxic gases inside the tank. Once the cleaning process was completed, floor was leveled using concrete. It was strengthened using SBR binder. The floor was allowed to cure and dry. Then concrete blocks for the aeration header were plastered to the surface. They were installed in such a way that the aeration header lies along the centre of the tank. As there are three portions in the tank, core cutting was done to allow passage of header from one compartment to another. The header (3’’) was then installed, 100 mm from the underground level, supported by blocks. They were further clamped with u bolts and were then coated with concrete. All remaining pebbles were removed from the tank after installation. Diffusers serve the medium for the aeration. They are coarse bubble diffusers, which provide efficient mixing followed by growth of micro-organisms, which are actually responsible to carry out the process, i.e. decreasing COD & BOD. Diffusers are attached to the aeration header. Silicone is used to provide water proofing.
  • 2. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 Two submersible pumps are also placed, that will transfer the water to the bio reactor, delivering pressure of about 1.5 bar. 2’’ line is connected to the pump outlet, evolving from a cut out provided for this purpose. These lines connect to a header from which a common emerges, connecting the septic tank and the reactor. Double union ball valves are provided followed by NRV to prevent back flow. Line (1/2’’) for pressure gauge is also provided. A frame is fabricated for the cut out, coated with red oxide to prevent corrosion. Checkered plates have been fabricated. Ropes are provided to facilitate easy removal of pumps when required. A drain line is provided to with draw water outside the factory. This is provided for safety measures, i.e. avoiding entry of dead organisms into the reactor. Supports are fabricated as required.
  • 3. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 2. SUPPORTS FABRICATION AND INSTALLTION: Three types of E supports were designed and fabricated for the piping spool and cable trays. They were coated with red oxide and painted royal blue color. The spool and cable trays were then run on the supports. 3. CONSTRUCTION OF PIT: It started with excavation of pit having approx. dimensions of 5*5*5 ft. during excavation seepage water starts accumulating. Therefore, padlo was used to cater this problem. After then pit was given physical structure using wooden planks. Iron reinforced concrete was used for its construction. It was then left for some days to cure and dry. The floor was later on plastered.
  • 4. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 An enclosure of material SS 316, was fabricated for the bar screen. Bar screen having dimensions of about 1600*900 mm, will be placed at an angle of 45ᴼ. This bar screen is responsible to retain all the solid material present in the effluent. Rawl bolts and concrete support the enclosure. Later on ceiling for the pit is laid using reinforced concrete.
  • 5. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 A cavity is provided for manhole frame and checkered plate. Finally bitumen diluted in turpentine oil is coated on the outside wall to prevent entry of seepage water into the pit. 4. BLOWER INSTALLATION: Blower is palced on the foundation pad. The line (3’’) originating from the septic tank is connected with the 1.5’’ line, attached to the blower, through a reducing bush. A bellow is provided on the dsicharge side to prevent breakage of nozzle.
  • 6. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 5. BIOPLUG/MEMPAC PIPING & AUXILIARIES: Bioreactor is responsible for the entire waste water treatment. Its capacity is 35m3 and material of construction is mild steel. Epoxy lining is done on the interior side to prevent corrosion. It acquires the feed through the septic tank’s submersible pumps. The line merges to header. The header itself consist of two lines, to carry the liquor to the membrane tank. These two lines are attached to the submersible pumps placed in the bioplug. These pumps have 68 ip (ingress protection) value. A recycle line is attached to the header, for recirculation purpose. Butterfly valves are used in the line, connected to the header. A mini screen is placed at the feed inlet to prevent entry of foreign solid material. Air is introduced into the reactor by means of aeration header to which diffusers are attached. These diffusers evenly distribute air, through a blower, present in the membrane container. Pipeline used for air is galvanized iron. An air breather/filter is attcahed a the suction of blower to prevent entry of dust/ debris present in the environment.
  • 7. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 this blower supplies air to reactor as well as to the membrane tank as required, i.e. air can be used as cleaning agent for membrane. This process is referred as membrane scouring. The water is filtered through UF membrane. These membranes are composed of PVDF (poly vinyl difluoride). The filtering phenomemon is done by creating a negative pressure by means of permeate pump. As a result of which, sludge is reatined in the membrane tank, where as water is transferred to the permeate tank. Back pulse tank is also filled side by side as the water flows through permeate pump. A recycle line is provided to feed sludge back to the reactor, once the membrane tank over flows. Through this line, a tee is provided to fill the sludge to the sludge tank. This is done by means of gravity. Supports have been fabricated to run pipe spools and cable trays. Butterfly valves are used in the drain connection. Drain lines have not been completed as they are to be concealed as required by client. Trench will be dug by client. Screw pumps for the transfer of sludge from the sludge tank to the filter press have been placed. Their suction header have been fabricated.
  • 8. MONTHLY PROGRESS REPORT FOR RB PROJECT TILL 15/06/15 Polymer dosing tank has been placed. Its foundation platform has been fabricated. It is responsible to agglomerate the sludge, inorder to facilitate sedimentation phenomenon. Frame for air conditioner, to be placed in container, has been fabricated. MISSING FITTINGS IN THE SHIPMENT:  Incomplete set of bolts/studs.  Part of saddle clamp missing.  gaskets unavialability.  Mating flanges missing  Fittings for polymer dosing tank missing.  Solenoid valve wiring tempered.  Hypo dosing system fitting tempered.  Antique type of filter press.  Cast iron butterfly valve missing.  Contardiction in given isometric drawing and actual fitting.