This document provides a breakdown of construction costs for a benchmark project consisting of 2 tower blocks, a 6-storey parking structure, and 1-storey of amenities on a 119,210 sqm site. It allocates costs among basement, podium, and tower structures. The total estimated construction cost is RM130.9 million, with the basement accounting for RM15 million (11.45%), podium RM17.9 million (13.71%), and tower RM98 million (74.85%). Mechanical and electrical systems represent the largest cost component for the basement (27.04%) and podium (22.18%), while structural works are largest for the tower (49.36%).