SlideShare a Scribd company logo
1 of 12
Main Headquarters: 120 Water Street, Suite 350, North Andover, MA 01845 With offices in: NY, ME, TX, CA, OR www.ers-inc.com
PRE-INSTALLATION EVALUATION OF
INDUSTRIAL PROJECTS
Jonathan B. Maxwell and Betsy Ricker, ERS
Carley Murray, NYSERDA*
*Any opinions expressed, explicitly or implicitly, are
those of the authors and do not necessarily represent
those of the New York State Energy Research and
Development Authority
IEPEC Chicago August 2013
Pre-Installation Evaluation of
Industrial Projects
Jonathan B. Maxwell and Betsy Ricker, ERS
Carley Murray, NYSERDA*
*Any opinions expressed, explicitly or implicitly, are those of the authors and do not necessarily represent those of the New York State Energy Research
and Development Authority
OBJECTIVES
Primary
 Discuss methods, advantages, and
disadvantages of very early impact
evaluator involvement in a large industrial
process program
Also share
 Procedure
 Case studies of pre-retrofit activity
WHAT IS PRE-INSTALLATION IMPACT
EVALUATION?
 Core activity: Project engineering review before savings
claims are finalized
 Pre-installation savings calculation review
 Baseline characterization
 Pre-installation metering
 Also/possibly:
 Early free ridership assessment
 Early post-retrofit review & metering
 Training PA and their technical advisors
WHY DO IT?
 Benefits for evaluators
 Evaluator inspection in pre-retrofit state
 Input regarding administrator M&V plan
• Opportunity for independent direct M&V
 Baseline perspective at time of decision-
making
 Evaluator-administrator convergence/training
 Bottom Line:
 Increased engineering rigor
 less variability, greater confidence in results
WHY DO IT?
 Benefits for program administrators
 Evaluator-administrator convergence/training
 Adjustment to savings estimates prior to incentive
calculation
 Increased depth of engagement with facilitators
 Less disturbance to customers
 Bottom line:
 Better realization rates
 Fewer surprises
WHY NOT DO IT?
 Added cost for evaluators and administrators
 Planning
 $2k to $10k per project evaluator cost; less but some admin
• Modest ex post savings later
 Sunk evaluation costs on projects that don’t matriculate
 Monthly meetings
 Risks added calendar time to processing
 Short notice rush analysis required
 Baseline can require research. Admin waits?
 Added bureaucracy before closing the deal
HOW IT WORKS
ID candidate projects
Evaluator review
Evaluator & administrator meet on
analysis, baseline, and proposed pre-
installation metering.
Pre-install site
visit. Possible
metering
Existing
facility
New facility
Evaluation review
memo
Evaluator &
administrator
meet
Post-install site
visit
Tracking
HOW IT WORKS – SCREENING
 Establish screening criteria in advance
Example:
 All over 5 GWh/yr or 10,000 MMBtu/yr
 All over intermediate size range and process,
complex baseline, capacity expansion,
controls, etc
 Sample others in intermediate range
 Evaluator or administrator can ID projects
HOW IT WORKS - VARIATIONS
 Are early evaluator findings advisory or
definitive to program?
 Is free ridership assessed? Is result
shared? Is it considered when setting
incentives?
 Formality of communication
 Who does the M&V?
CASE STUDIES
 Paper includes four case studies
Good
 Working together on M&V approach
 Evaluator influencing administrator on
baseline characterization, and vice versa
Bad
 Lost sunk costs
 No consensus on baseline
 Timing challenges
SUMMARY PRE-INSTALLATION IMPACT
EVALUATION
 Advantages:
 Better evaluation engineering & statistical quality
 Better realization rates
 Fewer bad surprises at end of evaluation
 Costs:
 More labor
 Calendar concerns

More Related Content

What's hot

Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...
Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...
Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...Ben Linders
 
Structural Weld Overlay CPNPP
Structural Weld Overlay CPNPPStructural Weld Overlay CPNPP
Structural Weld Overlay CPNPPleansavant
 
William Whitcomb Resume
William Whitcomb ResumeWilliam Whitcomb Resume
William Whitcomb ResumeBill Whitcomb
 
Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.huangg
 
shaunDSmithResume_NR
shaunDSmithResume_NRshaunDSmithResume_NR
shaunDSmithResume_NRShaun Smith
 
Office Lean
Office LeanOffice Lean
Office Leanflevko
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 

What's hot (10)

Summer '16
Summer '16Summer '16
Summer '16
 
Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...
Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...
Controlling Project Performance by Using a Defect Model - SEPG NA 2008 - Ben ...
 
Structural Weld Overlay CPNPP
Structural Weld Overlay CPNPPStructural Weld Overlay CPNPP
Structural Weld Overlay CPNPP
 
William Whitcomb Resume
William Whitcomb ResumeWilliam Whitcomb Resume
William Whitcomb Resume
 
Technical Audit
Technical  AuditTechnical  Audit
Technical Audit
 
Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.Project Management Analysis on Project Manager at Lydall Inc.
Project Management Analysis on Project Manager at Lydall Inc.
 
Resume_Num1
Resume_Num1Resume_Num1
Resume_Num1
 
shaunDSmithResume_NR
shaunDSmithResume_NRshaunDSmithResume_NR
shaunDSmithResume_NR
 
Office Lean
Office LeanOffice Lean
Office Lean
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 

Viewers also liked

St. James Church - Energy Audit Report
St. James Church - Energy Audit ReportSt. James Church - Energy Audit Report
St. James Church - Energy Audit ReportMichael Clarke
 
Webinar - The Energy Report - A fully sustainable and renewable global energy...
Webinar - The Energy Report - A fully sustainable and renewable global energy...Webinar - The Energy Report - A fully sustainable and renewable global energy...
Webinar - The Energy Report - A fully sustainable and renewable global energy...Leonardo ENERGY
 
ME_63-_ENERGY_AUDIT_OF_APH
ME_63-_ENERGY_AUDIT_OF_APHME_63-_ENERGY_AUDIT_OF_APH
ME_63-_ENERGY_AUDIT_OF_APHDipesh Badgujar
 
Total energy conservation and energy management solutions for intensive energ...
Total energy conservation and energy management solutions for intensive energ...Total energy conservation and energy management solutions for intensive energ...
Total energy conservation and energy management solutions for intensive energ...ZAINI ABDUL WAHAB
 
Aemas overview pierre -launching v1 aemas launching vn-eng
Aemas overview   pierre -launching v1 aemas launching vn-engAemas overview   pierre -launching v1 aemas launching vn-eng
Aemas overview pierre -launching v1 aemas launching vn-engippvietnam
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteriaZAINI ABDUL WAHAB
 
Energy saving audit project( mgtc)
Energy saving audit project( mgtc)Energy saving audit project( mgtc)
Energy saving audit project( mgtc)moffaz
 
Building Systems - Mock Company Presentation
Building Systems - Mock Company PresentationBuilding Systems - Mock Company Presentation
Building Systems - Mock Company PresentationMichael Clarke
 
Energy audit an energy certification
Energy audit an energy certificationEnergy audit an energy certification
Energy audit an energy certificationLuca Vecchiato
 
Energy management and energy audit in rupandehi
Energy management and energy audit in rupandehiEnergy management and energy audit in rupandehi
Energy management and energy audit in rupandehiMohammad Abul Hasan Khan
 
Energy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in MalaysiaEnergy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in MalaysiaZAINI ABDUL WAHAB
 
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...Steve Lojuntin
 
Energy Efficiency for Malaysia-the way forward
Energy Efficiency for Malaysia-the way forwardEnergy Efficiency for Malaysia-the way forward
Energy Efficiency for Malaysia-the way forwardZAINI ABDUL WAHAB
 
Energy audit report presentation
Energy audit report presentationEnergy audit report presentation
Energy audit report presentationKyambadde Francisco
 

Viewers also liked (18)

St. James Church - Energy Audit Report
St. James Church - Energy Audit ReportSt. James Church - Energy Audit Report
St. James Church - Energy Audit Report
 
Webinar - The Energy Report - A fully sustainable and renewable global energy...
Webinar - The Energy Report - A fully sustainable and renewable global energy...Webinar - The Energy Report - A fully sustainable and renewable global energy...
Webinar - The Energy Report - A fully sustainable and renewable global energy...
 
Resume 082016
Resume 082016Resume 082016
Resume 082016
 
ME_63-_ENERGY_AUDIT_OF_APH
ME_63-_ENERGY_AUDIT_OF_APHME_63-_ENERGY_AUDIT_OF_APH
ME_63-_ENERGY_AUDIT_OF_APH
 
Total energy conservation and energy management solutions for intensive energ...
Total energy conservation and energy management solutions for intensive energ...Total energy conservation and energy management solutions for intensive energ...
Total energy conservation and energy management solutions for intensive energ...
 
Aemas pierre cazelles
Aemas    pierre cazellesAemas    pierre cazelles
Aemas pierre cazelles
 
Aemas overview pierre -launching v1 aemas launching vn-eng
Aemas overview   pierre -launching v1 aemas launching vn-engAemas overview   pierre -launching v1 aemas launching vn-eng
Aemas overview pierre -launching v1 aemas launching vn-eng
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteria
 
Energy saving audit project( mgtc)
Energy saving audit project( mgtc)Energy saving audit project( mgtc)
Energy saving audit project( mgtc)
 
Building Systems - Mock Company Presentation
Building Systems - Mock Company PresentationBuilding Systems - Mock Company Presentation
Building Systems - Mock Company Presentation
 
Energy audit an energy certification
Energy audit an energy certificationEnergy audit an energy certification
Energy audit an energy certification
 
Energy management and energy audit in rupandehi
Energy management and energy audit in rupandehiEnergy management and energy audit in rupandehi
Energy management and energy audit in rupandehi
 
Energy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in MalaysiaEnergy efficiency implementation program for state level in Malaysia
Energy efficiency implementation program for state level in Malaysia
 
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...
Proposal to BSEEP to adopt GreenPASS Operation (CIS 20 - CIDB) as Energy Effi...
 
Energy Efficiency for Malaysia-the way forward
Energy Efficiency for Malaysia-the way forwardEnergy Efficiency for Malaysia-the way forward
Energy Efficiency for Malaysia-the way forward
 
Energy audit report presentation
Energy audit report presentationEnergy audit report presentation
Energy audit report presentation
 
Registered Energy Manager Slide: Energy Audit
Registered Energy Manager Slide: Energy AuditRegistered Energy Manager Slide: Energy Audit
Registered Energy Manager Slide: Energy Audit
 
Energy Audit Report
Energy Audit ReportEnergy Audit Report
Energy Audit Report
 

Similar to Pre-Install Evaluation Industrial Projects

Preretrofitevaluationpresentation
PreretrofitevaluationpresentationPreretrofitevaluationpresentation
PreretrofitevaluationpresentationZondits
 
Pre installation evaluation 2013-08-12
Pre installation evaluation 2013-08-12Pre installation evaluation 2013-08-12
Pre installation evaluation 2013-08-12Zondits
 
Abhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek Banerjee
 
Abhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek Banerjee
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
Agile in a highly regulated organization
Agile in a highly regulated organizationAgile in a highly regulated organization
Agile in a highly regulated organizationTami Flowers
 
The project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project successThe project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project successMark Troncone MBA, PMP, CBAP, ITILv3, CSM
 
auditing Fram . from the start to Reporting .pdf
auditing Fram . from the start to Reporting .pdfauditing Fram . from the start to Reporting .pdf
auditing Fram . from the start to Reporting .pdfnguyenanvuong2007
 
Estimator Metrics STC 2009
Estimator Metrics STC 2009Estimator Metrics STC 2009
Estimator Metrics STC 2009Amit Bhardwaj
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012 Skript
 
Value of software testing
Value of software testingValue of software testing
Value of software testingQualitest
 
Van Atta.Judy.Resume
Van Atta.Judy.ResumeVan Atta.Judy.Resume
Van Atta.Judy.ResumeJudy Van Atta
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptGeorgeKabongah2
 
Anna_Nguyen_resume_05052015
Anna_Nguyen_resume_05052015Anna_Nguyen_resume_05052015
Anna_Nguyen_resume_05052015Anna Nguyen
 
Develop a Defect Prevention Strategy—or Else!
Develop a Defect Prevention Strategy—or Else!Develop a Defect Prevention Strategy—or Else!
Develop a Defect Prevention Strategy—or Else!TechWell
 

Similar to Pre-Install Evaluation Industrial Projects (20)

Preretrofitevaluationpresentation
PreretrofitevaluationpresentationPreretrofitevaluationpresentation
Preretrofitevaluationpresentation
 
Pre installation evaluation 2013-08-12
Pre installation evaluation 2013-08-12Pre installation evaluation 2013-08-12
Pre installation evaluation 2013-08-12
 
Abhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _Testing
 
Abhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _TestingAbhishek_Banerjee_Functional _Testing
Abhishek_Banerjee_Functional _Testing
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
Agile in a highly regulated organization
Agile in a highly regulated organizationAgile in a highly regulated organization
Agile in a highly regulated organization
 
The project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project successThe project manager and business analyst partnership - ensuring project success
The project manager and business analyst partnership - ensuring project success
 
Test Lead_Venkat Kallagunta
Test Lead_Venkat KallaguntaTest Lead_Venkat Kallagunta
Test Lead_Venkat Kallagunta
 
auditing Fram . from the start to Reporting .pdf
auditing Fram . from the start to Reporting .pdfauditing Fram . from the start to Reporting .pdf
auditing Fram . from the start to Reporting .pdf
 
Estimator Metrics STC 2009
Estimator Metrics STC 2009Estimator Metrics STC 2009
Estimator Metrics STC 2009
 
Quality unit 2012
Quality unit 2012 Quality unit 2012
Quality unit 2012
 
VENKAT KALLAGUNTA_RESUME
VENKAT KALLAGUNTA_RESUMEVENKAT KALLAGUNTA_RESUME
VENKAT KALLAGUNTA_RESUME
 
Value of software testing
Value of software testingValue of software testing
Value of software testing
 
Van Atta.Judy.Resume
Van Atta.Judy.ResumeVan Atta.Judy.Resume
Van Atta.Judy.Resume
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
 
Making your peer reviews happen af Peter Voldby Petersen, Callis
Making your peer reviews happen af Peter Voldby Petersen, CallisMaking your peer reviews happen af Peter Voldby Petersen, Callis
Making your peer reviews happen af Peter Voldby Petersen, Callis
 
Business Analyst interview Questions
Business Analyst interview QuestionsBusiness Analyst interview Questions
Business Analyst interview Questions
 
Anna_Nguyen_resume_05052015
Anna_Nguyen_resume_05052015Anna_Nguyen_resume_05052015
Anna_Nguyen_resume_05052015
 
Develop a Defect Prevention Strategy—or Else!
Develop a Defect Prevention Strategy—or Else!Develop a Defect Prevention Strategy—or Else!
Develop a Defect Prevention Strategy—or Else!
 
Project auditing
Project auditingProject auditing
Project auditing
 

More from Zondits

Fitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits OutsFitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits OutsZondits
 
Tenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceTenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceZondits
 
Charging Up End Users for Energy Storage: Who to Target?
Charging Up End Users for Energy Storage: Who to Target?Charging Up End Users for Energy Storage: Who to Target?
Charging Up End Users for Energy Storage: Who to Target?Zondits
 
Pay For Performance Incentives Using Performance-Based Rebates
Pay For Performance Incentives Using Performance-Based RebatesPay For Performance Incentives Using Performance-Based Rebates
Pay For Performance Incentives Using Performance-Based RebatesZondits
 
Packaged CHP Programs and Non-Wires Solutions
Packaged CHP Programs and Non-Wires SolutionsPackaged CHP Programs and Non-Wires Solutions
Packaged CHP Programs and Non-Wires SolutionsZondits
 
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0Zondits
 
What's Hot? Combined Heat and Power (CHP)
What's Hot? Combined Heat and Power (CHP)What's Hot? Combined Heat and Power (CHP)
What's Hot? Combined Heat and Power (CHP)Zondits
 
Commercial Building Codes: Finding the Path to Improved Compliance
Commercial Building Codes: Finding the Path to Improved ComplianceCommercial Building Codes: Finding the Path to Improved Compliance
Commercial Building Codes: Finding the Path to Improved ComplianceZondits
 
Facility Scale Battery Storage
Facility Scale Battery StorageFacility Scale Battery Storage
Facility Scale Battery StorageZondits
 
ERS at PSEG LI October 2015
ERS at PSEG LI October 2015ERS at PSEG LI October 2015
ERS at PSEG LI October 2015Zondits
 
Maintaining and Growing Efficiency Efforts in the Changing C&I Landscape
Maintaining and Growing Efficiency Efforts in the Changing C&I LandscapeMaintaining and Growing Efficiency Efforts in the Changing C&I Landscape
Maintaining and Growing Efficiency Efforts in the Changing C&I LandscapeZondits
 
Are we there yet
Are we there yetAre we there yet
Are we there yetZondits
 
Integrating processimpactevals
Integrating processimpactevalsIntegrating processimpactevals
Integrating processimpactevalsZondits
 
Facility scaleenergystorage
Facility scaleenergystorageFacility scaleenergystorage
Facility scaleenergystorageZondits
 
Optimization of industrial refrigeration plants
Optimization of industrial refrigeration plantsOptimization of industrial refrigeration plants
Optimization of industrial refrigeration plantsZondits
 
The benefits of advanced thermostats
The benefits of advanced thermostatsThe benefits of advanced thermostats
The benefits of advanced thermostatsZondits
 
Subsidizing the installation of demand enabling technologies
Subsidizing the installation of demand enabling technologiesSubsidizing the installation of demand enabling technologies
Subsidizing the installation of demand enabling technologiesZondits
 
Integrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesIntegrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesZondits
 
Innovative compressed air case studies
Innovative compressed air case studiesInnovative compressed air case studies
Innovative compressed air case studiesZondits
 
Industrial approaches addressing new energy code
Industrial approaches addressing new energy codeIndustrial approaches addressing new energy code
Industrial approaches addressing new energy codeZondits
 

More from Zondits (20)

Fitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits OutsFitting Energy Efficiency Into Commercial Tenant Fits Outs
Fitting Energy Efficiency Into Commercial Tenant Fits Outs
 
Tenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial SpaceTenant Focus: Winning Efficiency Projects in the Commercial Space
Tenant Focus: Winning Efficiency Projects in the Commercial Space
 
Charging Up End Users for Energy Storage: Who to Target?
Charging Up End Users for Energy Storage: Who to Target?Charging Up End Users for Energy Storage: Who to Target?
Charging Up End Users for Energy Storage: Who to Target?
 
Pay For Performance Incentives Using Performance-Based Rebates
Pay For Performance Incentives Using Performance-Based RebatesPay For Performance Incentives Using Performance-Based Rebates
Pay For Performance Incentives Using Performance-Based Rebates
 
Packaged CHP Programs and Non-Wires Solutions
Packaged CHP Programs and Non-Wires SolutionsPackaged CHP Programs and Non-Wires Solutions
Packaged CHP Programs and Non-Wires Solutions
 
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0
Using Data Analytics to Bridge the Gap between M&V 1.0 and 2.0
 
What's Hot? Combined Heat and Power (CHP)
What's Hot? Combined Heat and Power (CHP)What's Hot? Combined Heat and Power (CHP)
What's Hot? Combined Heat and Power (CHP)
 
Commercial Building Codes: Finding the Path to Improved Compliance
Commercial Building Codes: Finding the Path to Improved ComplianceCommercial Building Codes: Finding the Path to Improved Compliance
Commercial Building Codes: Finding the Path to Improved Compliance
 
Facility Scale Battery Storage
Facility Scale Battery StorageFacility Scale Battery Storage
Facility Scale Battery Storage
 
ERS at PSEG LI October 2015
ERS at PSEG LI October 2015ERS at PSEG LI October 2015
ERS at PSEG LI October 2015
 
Maintaining and Growing Efficiency Efforts in the Changing C&I Landscape
Maintaining and Growing Efficiency Efforts in the Changing C&I LandscapeMaintaining and Growing Efficiency Efforts in the Changing C&I Landscape
Maintaining and Growing Efficiency Efforts in the Changing C&I Landscape
 
Are we there yet
Are we there yetAre we there yet
Are we there yet
 
Integrating processimpactevals
Integrating processimpactevalsIntegrating processimpactevals
Integrating processimpactevals
 
Facility scaleenergystorage
Facility scaleenergystorageFacility scaleenergystorage
Facility scaleenergystorage
 
Optimization of industrial refrigeration plants
Optimization of industrial refrigeration plantsOptimization of industrial refrigeration plants
Optimization of industrial refrigeration plants
 
The benefits of advanced thermostats
The benefits of advanced thermostatsThe benefits of advanced thermostats
The benefits of advanced thermostats
 
Subsidizing the installation of demand enabling technologies
Subsidizing the installation of demand enabling technologiesSubsidizing the installation of demand enabling technologies
Subsidizing the installation of demand enabling technologies
 
Integrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesIntegrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processes
 
Innovative compressed air case studies
Innovative compressed air case studiesInnovative compressed air case studies
Innovative compressed air case studies
 
Industrial approaches addressing new energy code
Industrial approaches addressing new energy codeIndustrial approaches addressing new energy code
Industrial approaches addressing new energy code
 

Recently uploaded

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 

Pre-Install Evaluation Industrial Projects

  • 1. Main Headquarters: 120 Water Street, Suite 350, North Andover, MA 01845 With offices in: NY, ME, TX, CA, OR www.ers-inc.com PRE-INSTALLATION EVALUATION OF INDUSTRIAL PROJECTS Jonathan B. Maxwell and Betsy Ricker, ERS Carley Murray, NYSERDA* *Any opinions expressed, explicitly or implicitly, are those of the authors and do not necessarily represent those of the New York State Energy Research and Development Authority
  • 2. IEPEC Chicago August 2013 Pre-Installation Evaluation of Industrial Projects Jonathan B. Maxwell and Betsy Ricker, ERS Carley Murray, NYSERDA* *Any opinions expressed, explicitly or implicitly, are those of the authors and do not necessarily represent those of the New York State Energy Research and Development Authority
  • 3. OBJECTIVES Primary  Discuss methods, advantages, and disadvantages of very early impact evaluator involvement in a large industrial process program Also share  Procedure  Case studies of pre-retrofit activity
  • 4. WHAT IS PRE-INSTALLATION IMPACT EVALUATION?  Core activity: Project engineering review before savings claims are finalized  Pre-installation savings calculation review  Baseline characterization  Pre-installation metering  Also/possibly:  Early free ridership assessment  Early post-retrofit review & metering  Training PA and their technical advisors
  • 5. WHY DO IT?  Benefits for evaluators  Evaluator inspection in pre-retrofit state  Input regarding administrator M&V plan • Opportunity for independent direct M&V  Baseline perspective at time of decision- making  Evaluator-administrator convergence/training  Bottom Line:  Increased engineering rigor  less variability, greater confidence in results
  • 6. WHY DO IT?  Benefits for program administrators  Evaluator-administrator convergence/training  Adjustment to savings estimates prior to incentive calculation  Increased depth of engagement with facilitators  Less disturbance to customers  Bottom line:  Better realization rates  Fewer surprises
  • 7. WHY NOT DO IT?  Added cost for evaluators and administrators  Planning  $2k to $10k per project evaluator cost; less but some admin • Modest ex post savings later  Sunk evaluation costs on projects that don’t matriculate  Monthly meetings  Risks added calendar time to processing  Short notice rush analysis required  Baseline can require research. Admin waits?  Added bureaucracy before closing the deal
  • 8. HOW IT WORKS ID candidate projects Evaluator review Evaluator & administrator meet on analysis, baseline, and proposed pre- installation metering. Pre-install site visit. Possible metering Existing facility New facility Evaluation review memo Evaluator & administrator meet Post-install site visit Tracking
  • 9. HOW IT WORKS – SCREENING  Establish screening criteria in advance Example:  All over 5 GWh/yr or 10,000 MMBtu/yr  All over intermediate size range and process, complex baseline, capacity expansion, controls, etc  Sample others in intermediate range  Evaluator or administrator can ID projects
  • 10. HOW IT WORKS - VARIATIONS  Are early evaluator findings advisory or definitive to program?  Is free ridership assessed? Is result shared? Is it considered when setting incentives?  Formality of communication  Who does the M&V?
  • 11. CASE STUDIES  Paper includes four case studies Good  Working together on M&V approach  Evaluator influencing administrator on baseline characterization, and vice versa Bad  Lost sunk costs  No consensus on baseline  Timing challenges
  • 12. SUMMARY PRE-INSTALLATION IMPACT EVALUATION  Advantages:  Better evaluation engineering & statistical quality  Better realization rates  Fewer bad surprises at end of evaluation  Costs:  More labor  Calendar concerns

Editor's Notes

  1. Early timely free ridership assessment (not NYSERDA scope) “Greater confidence” in both engineering (believe in site analysis) and statistical (lower variability and better relative precision) contexts.
  2. “Better” means “bigger” for PAs, or at least “closer to 1.0.”
  3. $6k NYSERDA impact evaluator & 40-hr budget. Running high so far. Horror stories (ref CPUC Lockheed panel)
  4. For NYSERDA the administrator IDs. Know at least one other jurisdiction where the evaluator has the responsibility
  5. NYSERDA: Advisory, no, no, no, moderately formal, administrator for the most part CPUC: Definitive, yes, yes, no, formal, administrator for the most part OPA: Unknown, yes, yes, yes, unknown, evaluator
  6. Ex 1: Condensing economizer in ethanol plant. Lost 90% of savings due to noncompletion of boiler. Lost sunk cost & early ID on lost method—billing analysis no longer viable Ex 2: Chemical distillation. Admin convincing evaluators that added M&V was not worthwhile Ex 3: Beverage bottling: Evaluators not made aware of project until virtually the installation date (administrators had short notice as well) Ex 4: Data center: Baseline characterization