SlideShare a Scribd company logo
1 of 10
Woden/Weston Creek
Community Hub
May 2015
Background
In the 2012-13 Budget $0.550 million was appropriated to investigate options for a
Community Hub in the Woden/Weston Creek area to accommodate a community
centre, a childcare centre and a seniors centre.
The Community Services Directorate (CSD) commissioned Stewart Architecture to
undertake an investigation and document site options for this Community Hub.
Stakeholders and Purpose
The key stakeholders are:
• Woden Community Service (WCS),
• Lollipop Childcare Centre (Lollipop),
• Weston Creek Community Association and
• Woden Seniors Club (Woden Seniors).
A new Community Hub will provide more appropriate accommodation for a community
and seniors centre, collocating the operations of WCS (which operates multiple sites)
and Woden Seniors.
The Report
The Study focussed on a model where the uses were contained in one building as
this would provide the opportunity to maximise the usage of shared space and reduce
overall space requirements.
After receiving the draft Study WCS indicated their preference for the child care
centre to be located separately to their operations. It is considered that relocation of
the child care centre is not as high a priority and this matter could be addressed
separately.
The Study recommended a community hub be located in the Woden town centre and
that additional site feasibility and design work be undertaken in order to select a
preferred site and design option.
The findings presented require more in-depth design work and consultation to ensure
optimal outcomes for government, the community and the community groups that
operate within the region.
The Sites identified by the Consultants
Section 80 option, Site 9
This option would see a community hub form
part of a larger community precinct development
and would require a territory plan variation.
The preliminary cost estimate for development
of a community hub on this site was
approximately $25 million.
This option ruled out
The Sites identified by the Consultants
Section 12, Site 1 (the existing site)
A number of issues were noted, namely that the
site, if progressed, would frustrate and
compromise development opportunities of
nearby sites and create overshadowing.
The preliminary cost estimate for development
of a community hub on this site is approximately
$22 million.
This option ruled out
The Sites identified by the Consultants
Section 9, Site 2
The option of locating the community hub as a
tenant in a larger commercial development
This option was not recommended.
The Study advised that the arrangement would
have significant drawbacks in delivering a
positive community asset with the level of
autonomy expected of a community facility.
The preliminary cost estimate for development
of a community hub on this site is approximately
$15 million.
Additional Sites – Callam Offices
Is largely vacant now that the ACT Government Office in
Gungahlin is completed
provides ample car parking and is potentially suitable for the
purposes required of a community hub.
A number of studies already undertaken including:
• Future Use Studies by GHD (in 2004)
• ...and Townsend Associates (in 2010);
• a 2014 Jones Lang LaSalle proposal for the site be used as a
community facility; and
• a 2014 community needs assessment completed by Buckley
Vann for the ACT Planning Strategy Woden Master Plan (for
the Environment and Planning Directorate) that drew attention
to Callam Offices as a possible site for a community hub.
•The studies referenced above highlight the shortcomings in the
suitability of Callam Offices as office accommodation.
Additional Sites – Cosmopolitan Building
The Cosmopolitan Building is a recently refurbished office building
targeting 4.5 star NABERS rating.
The building has new carpet, air conditioning and services. The building
has 7,361sqm of floor space, is split over five levels and has a
basement car park with 40 bays.
Re-use of this building as a community hub would have the advantage
of achieving a good outcome for the regeneration of the Woden town
centre and create a sense of belonging and community within the town
centre, an outcome that the Study identified as crucial to the ongoing
viability of a community hub.
Although the property is not listed on the market, it is understood that
the owners are willing to sell.
The Next Steps
The Chief Minister has indicated his preference for the remaining budget funds be used
on design and feasibility on:
• Callam Offices
• Cosmopolitan Building.
ED to commence negotiations with consultants with a view to having the work completed
by the end of 2015

More Related Content

What's hot

20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
Samat Jain
 

What's hot (20)

NJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets CotterNJ Future Forum 2012 Complete Streets Cotter
NJ Future Forum 2012 Complete Streets Cotter
 
20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award20120201 061327 multi-use_trail_bid_award
20120201 061327 multi-use_trail_bid_award
 
LTC, Jack R. Widmeyer Transportation Research Conference, Going to San Bernar...
LTC, Jack R. Widmeyer Transportation Research Conference, Going to San Bernar...LTC, Jack R. Widmeyer Transportation Research Conference, Going to San Bernar...
LTC, Jack R. Widmeyer Transportation Research Conference, Going to San Bernar...
 
Mount Dennis Mobility Hub Study
Mount Dennis Mobility Hub StudyMount Dennis Mobility Hub Study
Mount Dennis Mobility Hub Study
 
Six Points Reconfiguration - Community Update June, 2013
Six Points Reconfiguration - Community Update June, 2013Six Points Reconfiguration - Community Update June, 2013
Six Points Reconfiguration - Community Update June, 2013
 
Transit-Oriented Communities for South of Fraser
Transit-Oriented Communities for South of FraserTransit-Oriented Communities for South of Fraser
Transit-Oriented Communities for South of Fraser
 
City Partnerships Challenge - Melbourne Metro 2 brief
City Partnerships Challenge - Melbourne Metro 2 briefCity Partnerships Challenge - Melbourne Metro 2 brief
City Partnerships Challenge - Melbourne Metro 2 brief
 
Bike Rack Requirements
Bike Rack RequirementsBike Rack Requirements
Bike Rack Requirements
 
Fresh Energy's 2013 Power Breakfast | Jason Willett: Case Study
Fresh Energy's 2013 Power Breakfast | Jason Willett: Case StudyFresh Energy's 2013 Power Breakfast | Jason Willett: Case Study
Fresh Energy's 2013 Power Breakfast | Jason Willett: Case Study
 
Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2Advancing Sustainability in Discretionary Review 2
Advancing Sustainability in Discretionary Review 2
 
Transformative Climate Communities Program by Sophie Young
Transformative Climate Communities Program by Sophie YoungTransformative Climate Communities Program by Sophie Young
Transformative Climate Communities Program by Sophie Young
 
Delivering the Rehabilitation of the F.G. Gardiner Expressway
Delivering the Rehabilitation of the F.G. Gardiner ExpresswayDelivering the Rehabilitation of the F.G. Gardiner Expressway
Delivering the Rehabilitation of the F.G. Gardiner Expressway
 
TOD and Parking: Matching the Requirements to the Neighborhood by Meea Kang
TOD and Parking: Matching the Requirements to the Neighborhood by Meea KangTOD and Parking: Matching the Requirements to the Neighborhood by Meea Kang
TOD and Parking: Matching the Requirements to the Neighborhood by Meea Kang
 
TOD Wheeler Station
TOD Wheeler StationTOD Wheeler Station
TOD Wheeler Station
 
Woden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTEDWoden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTED
 
ConnectPB Crowdbrite Summary
ConnectPB Crowdbrite Summary ConnectPB Crowdbrite Summary
ConnectPB Crowdbrite Summary
 
Brisbane Innovation Series Apr10 Cate Collins
Brisbane Innovation Series  Apr10 Cate CollinsBrisbane Innovation Series  Apr10 Cate Collins
Brisbane Innovation Series Apr10 Cate Collins
 
Denver9/27_Art Rodgers
Denver9/27_Art RodgersDenver9/27_Art Rodgers
Denver9/27_Art Rodgers
 
Cts tradeshow remarks
Cts tradeshow remarksCts tradeshow remarks
Cts tradeshow remarks
 
Leveraging the Honolulu Rail Transit Project for Economic Growth and Building...
Leveraging the Honolulu Rail Transit Project for Economic Growth and Building...Leveraging the Honolulu Rail Transit Project for Economic Growth and Building...
Leveraging the Honolulu Rail Transit Project for Economic Growth and Building...
 

Similar to Woden/Weston Community centre Report

2023 Critical Issues Series: Economic Development Forum
2023 Critical Issues Series: Economic Development Forum2023 Critical Issues Series: Economic Development Forum
2023 Critical Issues Series: Economic Development Forum
The Chamber For a Greater Chapel Hill-Carrboro
 
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPDCommunity Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Design South East
 
Presentation to the Community on CBE Progress - August 2010
Presentation to the Community on CBE Progress - August 2010Presentation to the Community on CBE Progress - August 2010
Presentation to the Community on CBE Progress - August 2010
yscommunityresources
 
12.13.13 real property law institute
12.13.13 real property law institute12.13.13 real property law institute
12.13.13 real property law institute
The Port
 
C2C intro presentation
C2C intro presentationC2C intro presentation
C2C intro presentation
Philip Locke
 
Rockingham 2020
Rockingham 2020Rockingham 2020
Rockingham 2020
James May
 

Similar to Woden/Weston Community centre Report (20)

The Anatomy of Competition in Economic Development
The Anatomy of Competition in Economic DevelopmentThe Anatomy of Competition in Economic Development
The Anatomy of Competition in Economic Development
 
Strategic Estate Planning - case studies
Strategic Estate Planning - case studiesStrategic Estate Planning - case studies
Strategic Estate Planning - case studies
 
2023 Critical Issues Series: Economic Development Forum
2023 Critical Issues Series: Economic Development Forum2023 Critical Issues Series: Economic Development Forum
2023 Critical Issues Series: Economic Development Forum
 
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPDCommunity Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
 
LBAF_PHASE2_ALL_BOARDS (2).pdf
LBAF_PHASE2_ALL_BOARDS (2).pdfLBAF_PHASE2_ALL_BOARDS (2).pdf
LBAF_PHASE2_ALL_BOARDS (2).pdf
 
Presentation to the Community on CBE Progress - August 2010
Presentation to the Community on CBE Progress - August 2010Presentation to the Community on CBE Progress - August 2010
Presentation to the Community on CBE Progress - August 2010
 
Activity Centers Strategy - Council draft mins report 20-07-15
Activity Centers Strategy - Council draft mins report 20-07-15Activity Centers Strategy - Council draft mins report 20-07-15
Activity Centers Strategy - Council draft mins report 20-07-15
 
Mammoth Lakes Downtown Revitalization Action Plan 2.0
Mammoth Lakes Downtown Revitalization Action Plan 2.0Mammoth Lakes Downtown Revitalization Action Plan 2.0
Mammoth Lakes Downtown Revitalization Action Plan 2.0
 
URBAN DESIGN COMPENDIUM 1
URBAN DESIGN COMPENDIUM 1URBAN DESIGN COMPENDIUM 1
URBAN DESIGN COMPENDIUM 1
 
12.13.13 real property law institute
12.13.13 real property law institute12.13.13 real property law institute
12.13.13 real property law institute
 
C2C intro presentation
C2C intro presentationC2C intro presentation
C2C intro presentation
 
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreMammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
 
OCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization ProgramOCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization Program
 
Benefits Highlight Report
Benefits Highlight ReportBenefits Highlight Report
Benefits Highlight Report
 
Mammoth Lakes Downtown Revitalization Plan by Darin Dinsmore
Mammoth Lakes Downtown Revitalization Plan by Darin DinsmoreMammoth Lakes Downtown Revitalization Plan by Darin Dinsmore
Mammoth Lakes Downtown Revitalization Plan by Darin Dinsmore
 
Atlas Presentation: Birmingham
Atlas Presentation: BirminghamAtlas Presentation: Birmingham
Atlas Presentation: Birmingham
 
UCPCOG 2019 Comprehensive Economic Development Strategy
UCPCOG 2019 Comprehensive Economic Development StrategyUCPCOG 2019 Comprehensive Economic Development Strategy
UCPCOG 2019 Comprehensive Economic Development Strategy
 
WS3 Project Realities
WS3 Project Realities WS3 Project Realities
WS3 Project Realities
 
Rockingham 2020
Rockingham 2020Rockingham 2020
Rockingham 2020
 
Mack cali Investor presentation
Mack cali Investor presentation Mack cali Investor presentation
Mack cali Investor presentation
 

More from Woden Valley Community Council Inc

More from Woden Valley Community Council Inc (18)

David collett presentation wvcc 5 april 2017
David collett presentation   wvcc 5 april 2017David collett presentation   wvcc 5 april 2017
David collett presentation wvcc 5 april 2017
 
Gary rake presentation dv344 woden and dv345 mawson
Gary rake presentation dv344 woden and dv345 mawsonGary rake presentation dv344 woden and dv345 mawson
Gary rake presentation dv344 woden and dv345 mawson
 
Borrowdale house Carpark presentation
Borrowdale house Carpark presentationBorrowdale house Carpark presentation
Borrowdale house Carpark presentation
 
Hindmarsh Drive Traffic Signals
Hindmarsh Drive Traffic SignalsHindmarsh Drive Traffic Signals
Hindmarsh Drive Traffic Signals
 
John James Village project Garran - Presentation to WVCC March 1 2016
John James Village project Garran - Presentation to WVCC March 1 2016John James Village project Garran - Presentation to WVCC March 1 2016
John James Village project Garran - Presentation to WVCC March 1 2016
 
John James Village Presentation to WVCC March 1 2016
John James Village Presentation to WVCC March 1 2016John James Village Presentation to WVCC March 1 2016
John James Village Presentation to WVCC March 1 2016
 
ACT climate change adaptation strategy presentation to WVCC
ACT climate change adaptation strategy presentation to WVCC ACT climate change adaptation strategy presentation to WVCC
ACT climate change adaptation strategy presentation to WVCC
 
WVCC budget Breakdown
WVCC budget BreakdownWVCC budget Breakdown
WVCC budget Breakdown
 
EPD Curtin master plan consultation
EPD Curtin master plan consultationEPD Curtin master plan consultation
EPD Curtin master plan consultation
 
Act basin priority project
Act basin priority projectAct basin priority project
Act basin priority project
 
20150204 woden and mawson - wvcc
20150204   woden and mawson - wvcc20150204   woden and mawson - wvcc
20150204 woden and mawson - wvcc
 
WVCC march 2015 presntation
WVCC march 2015 presntationWVCC march 2015 presntation
WVCC march 2015 presntation
 
Parties at the shops
Parties at the shopsParties at the shops
Parties at the shops
 
141203 presentation woden valley community council
141203   presentation woden valley community council141203   presentation woden valley community council
141203 presentation woden valley community council
 
Mr Fluffy Act buyback scheme
Mr Fluffy Act buyback schemeMr Fluffy Act buyback scheme
Mr Fluffy Act buyback scheme
 
Presentation strathgordon court - woden valley community council 3 septembe...
Presentation   strathgordon court - woden valley community council 3 septembe...Presentation   strathgordon court - woden valley community council 3 septembe...
Presentation strathgordon court - woden valley community council 3 septembe...
 
Zhenfa Solar - Woden community council presentation
Zhenfa Solar - Woden community council presentationZhenfa Solar - Woden community council presentation
Zhenfa Solar - Woden community council presentation
 
Capital Metro presentation WVCC meeting July 2014
Capital Metro presentation WVCC meeting July 2014Capital Metro presentation WVCC meeting July 2014
Capital Metro presentation WVCC meeting July 2014
 

Recently uploaded

No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
Sheetaleventcompany
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
raffaeleoman
 

Recently uploaded (20)

Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Air breathing and respiratory adaptations in diver animals
Air breathing and respiratory adaptations in diver animalsAir breathing and respiratory adaptations in diver animals
Air breathing and respiratory adaptations in diver animals
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar Training
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptx
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
 

Woden/Weston Community centre Report

  • 2. Background In the 2012-13 Budget $0.550 million was appropriated to investigate options for a Community Hub in the Woden/Weston Creek area to accommodate a community centre, a childcare centre and a seniors centre. The Community Services Directorate (CSD) commissioned Stewart Architecture to undertake an investigation and document site options for this Community Hub.
  • 3. Stakeholders and Purpose The key stakeholders are: • Woden Community Service (WCS), • Lollipop Childcare Centre (Lollipop), • Weston Creek Community Association and • Woden Seniors Club (Woden Seniors). A new Community Hub will provide more appropriate accommodation for a community and seniors centre, collocating the operations of WCS (which operates multiple sites) and Woden Seniors.
  • 4. The Report The Study focussed on a model where the uses were contained in one building as this would provide the opportunity to maximise the usage of shared space and reduce overall space requirements. After receiving the draft Study WCS indicated their preference for the child care centre to be located separately to their operations. It is considered that relocation of the child care centre is not as high a priority and this matter could be addressed separately. The Study recommended a community hub be located in the Woden town centre and that additional site feasibility and design work be undertaken in order to select a preferred site and design option. The findings presented require more in-depth design work and consultation to ensure optimal outcomes for government, the community and the community groups that operate within the region.
  • 5. The Sites identified by the Consultants Section 80 option, Site 9 This option would see a community hub form part of a larger community precinct development and would require a territory plan variation. The preliminary cost estimate for development of a community hub on this site was approximately $25 million. This option ruled out
  • 6. The Sites identified by the Consultants Section 12, Site 1 (the existing site) A number of issues were noted, namely that the site, if progressed, would frustrate and compromise development opportunities of nearby sites and create overshadowing. The preliminary cost estimate for development of a community hub on this site is approximately $22 million. This option ruled out
  • 7. The Sites identified by the Consultants Section 9, Site 2 The option of locating the community hub as a tenant in a larger commercial development This option was not recommended. The Study advised that the arrangement would have significant drawbacks in delivering a positive community asset with the level of autonomy expected of a community facility. The preliminary cost estimate for development of a community hub on this site is approximately $15 million.
  • 8. Additional Sites – Callam Offices Is largely vacant now that the ACT Government Office in Gungahlin is completed provides ample car parking and is potentially suitable for the purposes required of a community hub. A number of studies already undertaken including: • Future Use Studies by GHD (in 2004) • ...and Townsend Associates (in 2010); • a 2014 Jones Lang LaSalle proposal for the site be used as a community facility; and • a 2014 community needs assessment completed by Buckley Vann for the ACT Planning Strategy Woden Master Plan (for the Environment and Planning Directorate) that drew attention to Callam Offices as a possible site for a community hub. •The studies referenced above highlight the shortcomings in the suitability of Callam Offices as office accommodation.
  • 9. Additional Sites – Cosmopolitan Building The Cosmopolitan Building is a recently refurbished office building targeting 4.5 star NABERS rating. The building has new carpet, air conditioning and services. The building has 7,361sqm of floor space, is split over five levels and has a basement car park with 40 bays. Re-use of this building as a community hub would have the advantage of achieving a good outcome for the regeneration of the Woden town centre and create a sense of belonging and community within the town centre, an outcome that the Study identified as crucial to the ongoing viability of a community hub. Although the property is not listed on the market, it is understood that the owners are willing to sell.
  • 10. The Next Steps The Chief Minister has indicated his preference for the remaining budget funds be used on design and feasibility on: • Callam Offices • Cosmopolitan Building. ED to commence negotiations with consultants with a view to having the work completed by the end of 2015