CAMPBELL SECTION 5 4 JUNE 2 0 1 3
Furzer Street Precinct Update
Woden Valley Community Council
4 March 2015
CAMPBELL SECTION 5 4 JUNE 2 0 1 3
BACKGROUND
• Phillip Section 9 was identified on the ACT
Governments Indicative Land Release Program
• LDA first presented the Furzer Street project to the
WVCC in 2011.
• 1st EDP DA lodged and public consultation
undertaken May 2012.
• 2nd EDP lodged and public consultation
undertaken September 2013.
• Section 3 released and sold at auction (including
the requirement for replacement car parking)
• SKYPARK scheduled to open in April 2015.
CAMPBELL SECTION 5 4 JUNE 2 0 1 3
CONSTRUCTION PROGRAM
• LDA released a RFT for the civil and landscape works
• Canberra Contractors are the successful tenderer
• Construction commences March/April 2015
• Section 9 car park will be closed to the public shortly
after the structured car park on Section 3 is operational
• Stage 1 – Intersection Upgrades
• Stage 2 – Civil works associated with infrastructure
and realignment of Corinna Street
• Stage 3 – Landscape and park work
• Potential for some weekend and/or night work
CAMPBELL SECTION 5 4 JUNE 2 0 1 3
COMMUNITY ENGAGEMENT
• Presentations to Woden Valley Community Council
• Emails and letters to adjoining businesses/tenants and
adjoining lessees
• Emails and letters to interested parties – Pedal Power
• Letters on car windscreens in Section 9 car park
• Signage around Section 9
• Canberra Times Community Noticeboard
• EDD/LDA website