CHAPTER 4
Defining Scope, Quality, Responsibility, and Activity Sequence
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Teaching Strategies
The two vignettes reinforce consideration of the situation
through research and communication with the stakeholders.
The first vignette addresses the changing conditions for project
planning of worldwide construction projects due to weather
variability and increased extreme weather situations.
The second examines a change in process for commerce. The
desire was to increase credit card use; work with the
stakeholders revealed a hesitation and distrust of credit cards
due to potential fraud with an option for continued practices of
e-commerce using debit cards. (See Premium Deck for Slides.)
Sometimes planning seems to be a waste of time for a short
project. However, even very small projects need some degree of
planning.
Tell the students a story of a failed project. Have students
identify how having a clear project objective, a project scope
document, a project plan, a work breakdown structure, a
responsibility assignment matrix, and a network diagram could
have changed the outcome.
Have students create a work breakdown structure and network
diagram for a project they will have to complete during the
class semester. Have the students explain the relationship
between tasks that must be completed sequentially and those
that can be completed simultaneously.
The network diagram for the consumer market study is included
in the chapter materials. Have the students compare the
textbook diagram with the one created in Microsoft Project.
Have the students report on the similarities and the differences.
Optional Supplemental Activities
Recall that Chapter 1 offered an optional activity for student
groups to contribute several hours to a not-for-profit
organization. Have each group that participated in this activity
give a 10 minute presentation and submit a 2-3 page write-up
that discusses how that organization’s projects are planned,
performed, controlled, and terminated. In addition, require each
group to give at least 3 suggestions on ideas that could improve
the projects at that organization.
Have students seek a project management mentor and report on
their experiences related to developing the project scope and
identifying the work breakdown structure.
Have students present an article from the International Journal
of Project Management to the class. Have them post their
critical review of the article to the class website, blog, wiki, or
other class space to allow others to review and comment.
1
Chapter Concepts
Clearly defining the project objective
Preparing a project scope document
Understanding the importance of planning for quality
Creating a work breakdown structure
Assigning responsibility for work items
Defining specific activities
Creating a network diagram
Utilizing a project management methodology called the systems
development life cycle for information systems development
projects
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Chapter Concepts
This chapter discusses the project scope document, quality, how
to define what activities need to be done, who will be
responsible for them, and in what sequence they will be
performed. It describes techniques and tools used to pl an the
work items and activities that need to be performed in order to
accomplish the project objective successfully. The project scope
defines what work needs to be done and what deliverables need
to be produced. Then, specific activities are defined and
arranged in a sequence of dependent relationships to determine
how the work will be performed.
This chapter will help student to become familiar with:
Clearly defining the project objective
Preparing a project scope document
Understanding the importance of planning for quality
Creating a work breakdown structure
Assigning responsibility for work items
Defining specific activities
Creating a network diagram
Utilizing a project management methodology called the systems
development life cycle for information systems development
projects
2
Learning Outcomes
Establish a clear project objective
Prepare a project scope document
Discuss the importance and elements of a project quality plan
Develop a work breakdown structure
Prepare a responsibility assignment matrix
Describe how to define specific activities
Create a network diagram
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Learning Outcomes
After studying this chapter, students should be able to:
Establish a clear project objective
Prepare a project scope document
Discuss the importance and elements of a project quality plan
Develop a work breakdown structure
Prepare a responsibility assignment matrix
Describe how to define specific activities
Create a network diagram
3
Project Integration Management
Project Scope Management
Project Quality Management
Project Resource Management
Project Schedule Management
Project Management Knowledge Areas from PMBOK® Guide
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Project Management Knowledge Areas from PMBOK® Guide
Concepts in this chapter support the following Project
Management Knowledge Areas of the PMI Guide to the Project
Management Body of Knowledge (PMBOK® Guide):
Project Integration Management
Project Scope Management
Project Quality Management
Project Resource Management
Project Schedule Management
4
Establish Project Objective
Planning process is based on the project objective
Establishes what is to be accomplished
Often stated in the project charter or RFP
Is the tangible end product
Project objective includes
Expected benefits
Primary project end product or deliverable
Date required to be completed
Budget
Changes agreed upon by customer and contractor
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Establish Project Objective
The planning process is based on the project objective.
The project objective establishes what is to be accomplished.
Often the project objective is stated in the project charter or
RFP.
It is the tangible end product that the project team or contractor
must produce and deliver in order for the sponsor or customer to
achieve the expected benefits from implementing the project.
The project objective should include the following elements:
Expected benefits that will result from implementation of the
project and define success
Primary project end product or deliverable
Date by which the project is required to be completed
Budget within which the project must be completed
Situations can arise where the project objective needs to be
modified as the project proceeds because of extenuating
circumstances or new information. The project manager and the
customer must agree on all changes to the project objective.
Any such changes might affect the remaining work scope,
deliverables, completion date, and final cost.
5
Define Project Scope
Project Scope
Project Scope Document
Defines what needs done
Includes
Items contained in project charter, RFP, proposal
More detail
Establishes common understanding of scope with stakeholders
Usually contains
Customer requirements
Statement of Work
Deliverables
Acceptance Criteria
Work Breakdown Structure
Establishes baseline
Change control system to avoid scope creep
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Define Project Scope
The project scope defines what needs to be done.
A project scope document includes many of the items contained
in the project charter, RFP, or contractor’s proposal, but in
much greater detail. The document is valuable for establishing a
common understanding among project stakeholders regarding
the scope of the project.
The project scope document usually contains the following
sections:
Customer requirements define the functional or performance
specifications for the project’s end product and other project
deliverables.
It should also include or reference applicable technical
specifications, standards, and codes that must be used and met
regarding quality and performance of the project work and
deliverables.
Statement of Work (SOW) defines the major tasks that will need
to be performed to accomplish the work that needs to be done
and produce all the project deliverables.
Deliverables are the products or outputs that the project team or
contractor will produce and provide to the customer during and
at the completion of the performance of the project.
Acceptance criteria for all project deliverables must be
described in greater detail than what is stated in the project
charter or request for proposal
Work Breakdown Structure (WBS) is a hierarchical
decomposition of the project work scope into work packages
that produce the project deliverables.
The agreed-upon project scope document establishes the
baseline for any changes that may be made to the scope during
the performance of the project.
A change control system needs to be established to define how
changes will be documented, approved, and communicated. The
project team or contractor must avoid scope creep, which is
informally making changes to the project scope without
appropriate approval.
6
Plan for Quality
Complete work according to specifications and standards
Plan for assuring quality as project progresses
Include
References for specifications and standards
Written procedures for quality tools and techniques
Key aspects
Monitor as the project progresses
Do work right the first time rather than rework
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Plan for Quality
Planning for quality is a necessary, yet often forgotten or
dismissed, function on a project. It is essential to have a plan
for assuring the quality of project deliverables and results,
rather than waiting until the end of the project to check if the
sponsor/customer requirements and expectations on project
deliverables have been met.
It is important to plan for quality in performing the project.
This helps assure that the work is done according to
specifications and applicable standards and that deliverables
meet acceptance criteria.
A project quality plan includes or references:
Project specifications and standards
Industry or government standards (for design, testing, safety,
construction, etc.)
Codes that must be used and met during the performance of the
project work
Written procedures for using various quality tools and
techniques
The key to quality control is to:
Monitor the quality of the work early and regularly throughout
the performance of the project
Compare results with quality standards
Make any necessary corrective actions immediately, rather than
waiting until all the work is completed before checking or
inspecting for quality
To ensure that a project is done right the first time, a project
should focus on doing the work in accordance with quality
standards, and therefore preventing quality problems.
7
Create Work Breakdown Structure
Deliverable-oriented hierarchical decomposition
Organize project work and deliverables
Create logical groupings
Subdivide into more manageable components
Deliverable is output of work package
Resource requirements and durations can be assigned
Accountability can be assigned
Project manager can monitor and control
Graphic chart or indentured list
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Create Work Breakdown Structure
Once the project scope document has been agreed on and
prepared, the next step in the planning phase is to create a
detailed work breakdown structure (WBS)
This is a deliverable-oriented hierarchical decomposition of the
project work scope into work packages, or activity groupings,
that produce the project deliverables.
Creating a WBS is a structured approach for organizing all the
project work and deliverables into logical groupings. This helps
to subdivide the deliverables into more manageable components
called work items, to help ensure that all tasks required to
complete the project are identified and included in the baseline
project plan.
The WBS should be deconstructed to a level that identifies
individual work packages for each specific deliverable listed in
the project scope document.
Dividing a project into work packages and work items helps a
contractor increase the level of confidence that:
All the activities that need to be performed to produce the
deliverable can be defined
The types and quantities of resources can be determined
The associated activity durations and costs can be reasonably
estimated.
Work items should be broken down to the level at which a
single organization (marketing communications, materials
engineering, human resources, a subcontractor, etc.) or
individual can be assigned responsibility and accountability for
accomplishing the work package.
The WBS can be created using a graphic chart format or as a
list.
8
WBS with Breakdown to Different Levels
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in pa rt,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
WBS with Breakdown to Different Levels
This figure depicts the work breakdown structure in a graphic
chart format for a community festival project.
Note that not all of the branches in a WBS have to be broken
down to the same level.
9
WBS
Graphic Chart
Indentured List
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
WBS
The top figure depicts the WBS for the consumer market study
project example. This project is also the example used in the
Microsoft Project appendices.
Have students examine the relationship between this figure and
the entries in the Microsoft Project task list.
The bottom figure depicts an indentured list for the work
breakdown structure.
For each of the work packages, the deliverable is listed.
This format is helpful for large projects where a diagram would
become too large and unwieldy.
10
Assign Responsibility
Responsibility assignment matrix
Designate responsible individuals
P = Primary responsibility
S = Support responsibility
Associates responsibility
For each work item
For each individual
Only one primary per work item
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Assign Responsibility
A responsibility assignment matrix (RAM) defines who will be
responsible for the work. It is a tool used to designate the
individuals responsible for accomplishing the different work
items in the work breakdown structure (WBS).
This figure depicts the RAM for the WBS in Figure 4.1, the
community festival project.
The RAM often uses a P to designate primary responsibility and
an S to indicate support responsibility for a specific work item.
The RAM shows all the individuals associated with each work
item in the WBS, as well as all the work items associated with
each individual.
Only one individual should be designated as the lead, or
primary, person responsible for each work item.
11
Define Activities
Responsible resources define activities
Breakdown work packages to work items
Level needed to perform deliverable
May not be able to define all
Comprehensive activity list
Not always require expenditure of effort
Could be wait time
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Define Activities
Using the WBS, the individual or team responsible for each
work package must next define all the specific activities that
need to be performed to produce the end item, or deliverable.
Breaking down each work package into its component activities
reveals the level at which each activity must be performed to
produce the deliverable.
Some activities may not be easily definable.
When all the specific activities have been defined for all of the
work packages, they should be consolidated into a
comprehensive activity list.
Because of the allocation of resources, there may be wait time
between the end of one activity and the start of another one.
This figure shows the work breakdown structure for a consumer
market study project. It depicts the specific activities that need
to be performed for each work package.
Have the students compare this list to the entries for the tasks in
the Microsoft Project appendix.
12
Sequence Activities
Network diagram
Defines the sequence of activities and relationships
Tool for arranging order
Common techniques
PERT
CPM
PDM
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Sequence Activities
A network diagram defines the sequence of how the activities
will get done. It is a tool for arranging the specific activities in
the best sequence and defining their dependent relationships.
The three most common techniques of network diagramming are
program evaluation and review technique (PERT), the critical
path method (CPM), and the precedence diagramming method
(PDM).
In the past, there were distinguishable methodological
differences between PERT and CPM. Today, however, when
most people refer to a CPM diagram or PERT chart, they mean a
generic network diagram.
The top figure shows a complete network diagram for a
consumer market study project, with the person responsible for
each activity included on the diagram.
The bottom figure shows a network diagram for a web-based
reporting system project.
13
Network Principles
Activities
Represented by a box
Consume time
Described by verb
Relationships
Linked in serial sequence
Complete concurrently
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Network Principles
Each activity is represented by a box in the network diagram
and the description of the activity is written within the box, as
shown in this figure.
Activities consume time, and their description usually begins
with a verb (such as get, wash, and dry in this example).
Activities have a dependent relationship—that is, they are
linked in a logical sequence in a network diagram to show
which activities must be finished before others can start.
Certain activities have to be done in serial sequence.
Some activities may be done concurrently.
14
Loops
Illogical relationship among activities
Perpetually repeats itself
Not acceptable
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Loops
An illogical relationship among activities is known as a loop.
In preparing a network diagram, drawing activities in a loop is
not acceptable because it portrays a path of activities that
perpetually repeats itself.
15
Laddering
Set of repeating activities
Serial sequence
One work
Two wait
Can be performed at same time
Would need triple resources
Ladder activities
Allow for shortest possible time for completion
Best use of the three workers and experts
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Laddering
Some projects have a set of activities that are repeated several
times.
The top figure shows a series of activities that must be done in
serial sequence, which means that, for an activity with three
people, at any one time only one person is working while two
other people are waiting.
The middle figure shows a set of activities that can be
performed concurrently. However, it is often not practical to
perform the activities in this way because the organization
would need triple the experts– one for each room.
The bottom figure shows a technique known as laddering. This
approach allows the project to be completed in the shortest
possible time, while making the best use of available resources.
16
Create Network Diagram
Tips and Techniques
Logical sequence of activities
Show dependent relationships
Elaborate as project progresses
Use subnetworks for similar activity sequences and
relationships
Development of Diagram
Questions to answer
Finish before next start?
Done concurrently?
Cannot be started next?
Guidelines for detail level
Define each work package
Draw summary level network then add detail
Detail to responsibility or deliverable change
Duration less than project progress review
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Create Network Diagram
A network diagram is a drawing of the activities for a project,
displayed in boxes in their logical sequence and connected by
arrows to indicate dependent relationships. The network
diagram shows how the project should be performed from start
to completion.
Three questions need to be answered regarding each activity.
The network is based upon the answers:
Which activities must be finished immediately before this
activity can be started?
Which activities can be done concurrently with this activity?
Which activities cannot be started until immediately after this
activity is finished?
Guidelines for the level of detail in the network diagram are:
Based on the work breakdown structure for a project; specific
activities should be defined for each work package.
It may be preferable to draw a summary-level network first that
depicts a small number of higher level activities and then
expand to a more detailed network.
The level of detail may be determined by certain obvious
interface or transfer points such as a change in responsibility or
if there is a tangible output or product or deliverable as a result
of an activity.
Activities should not be longer in estimated duration than the
project progress review.
It is not unusual to progressively elaborate the network di agram
as the project progresses and more information becomes clear.
Sub-networks can be used to represent similar projects for
different customers. Certain portions of projects may include
the same types of activities in the same sequence and with the
same dependent relationships.
17
Planning
for Information Systems Development
Definition
Computer-based system
Accepts data as input
Processes the data
Produces useful information
Examples
Computerized order entry
E-commerce
Automatic teller machines
Billing, payroll, and inventory
Process
Plan, execute, and control
Systems Development Life Cycle
Problem definition
System analysis
System design
System development
System testing
System implementation
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Planning for Information Systems Development
The Microsoft Project example will continue through chapters 4
– 8. It highlights the concepts for each chapter in the example.
The Microsoft Project file for the example is available with the
instructor materials.
An information system (IS) is a computer-based system that
accepts data as input, processes the data, and produces useful
information for users.
Information systems include computerized order entry systems,
e-commerce systems, automatic teller machines, and billing,
payroll, and inventory systems.
The development of an IS is a challenging process that requires
extensive planning and control to ensure that the system meets
user requirements and is finished on time and within budget.
A project management planning tool, or methodology, called the
systems development life cycle (SDLC) is often used to help
plan, execute, and control IS development projects.
It consists of the following steps:
Problem definition -- Data are gathered and analyzed and
problems and opportunities are clearly defined.
System analysis -- The development team defines the scope of
the system to be developed, interviews potential users, studies
the existing system (which might be manual), and defines user
requirements.
System design -- Several alternative conceptual designs are
produced and evaluated. The best is selected for further design
and development.
System development -- The actual system is brought into
existence.
System testing – This step involves looking for logical errors,
database errors, errors of omission, security errors, and other
problems that might prevent the system from being successful.
System implementation -- The existing system is replaced with
the new, improved, system and users are trained.
18
An IS Example: Internet Applications Development for ABC
Office Designs
ABC Office Designs
Large number of sales representatives
Sell office furniture to major corporations
State assignments in four regions
Management monitor state and regional sales
Build Web-based IS system to track prices, inventory, and
competition
Project
Project manager identified
WBS follows SDLC
Responsibility assignment matrix completed
List of tasks compiled and predecessors identified
Network diagram created
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
An IS Example: Internet Applications Development for ABC
Office Designs
A corporation called ABC Office Designs has a large number of
sales representatives who sell office furniture to major
corporations. Each sales representative is assigned to a specific
state, and each state belongs to one of four regions in the
country.
To enable management to monitor the number and amount of
sales for each representative, for each state, and for each
region, ABC has decided to build a Web-based information
system that will track prices, inventory, and the competition.
The IS department within the corporation has assigned Beth
Smith to be the project manager of the Web-based reporting
system development project.
The following four slides depict figures related to this project.
First, we will see the major tasks that were identified for the
project.
Then we will look at the responsibility assignment matrix for
the project with the primary and secondary responsibilities for
each task assigned.
We will then look at a list of all tasks to be done, with the
immediate predecessor for each task listed to the right of the
task.
Finally, we will examine the network diagram created by Beth
and the project team that represents the interdependencies listed
in the immediate predecessor list.
19
IS Example: WBS follows SDLC
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
IS Example: WBS follows SDLC
This figure depicts the major tasks that were identified for the
project. The WBS follows the SDLC.
20
IS Example: Responsibility Assignment Matrix
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
IS Example: Responsibility Assignment Matrix
Here we see the responsibility assignment matrix for the
project, with the primary and secondary responsibilities for each
task assigned.
Make sure that students note that all the tasks in the WBS
appear in the responsibility assignment matrix.
21
IS Example: Task List and Predecessors
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
IS Example: Task List and Predecessors
This figure depicts a list of all tasks to be completed, with the
immediate predecessor for each task listed to the right of the
task.
Have the students examine the interdependencies of the tasks.
22
IS Example: Network Diagram
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
IS Example: Network Diagram
Here is the network diagram created by Beth and the project
team.
This figure represents the interdependencies listed in the
immediate predecessor list.
23
Project Management Information Systems
Wide variety of systems available
Plan and control projects in interactive mode
Plan and test different options
Create reports, diagrams, and charts
Interface with other software applications
Appendix A has additional information
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Project Management Information Systems
A wide variety of affordable project management information
systems are available for purchase.
These systems allow the project manager and the project team to
plan and control projects in a completely interactive mode.
Planning and testing different options for task durations,
dependencies, constraints, resources, schedules, and costs can
be completed in a project management information system.
Information systems help project managers to create reports,
change management, network diagrams, and Gantt charts.
Project management information systems also interface with
other software applications.
Appendix A contains information related to project management
information systems.
24
Critical Success Factors
Plan the work and then work the plan. It is important to develop
a plan before starting to perform the project. Taking the time to
develop a well-thought-out plan is critical to the successful
accomplishment of any project.
Participation builds commitment. By participating in the
planning of the work, individuals will become committed to
accomplishing it according to the plan.
The project must have a clear objective of what is to be
accomplished. The objective should be defined in terms of end
product or deliverable, schedule, and budget, and it must be
agreed upon by the customer and the project team that will
perform the project.
The project scope document is valuable for establishing a
common understanding and agreement among project
stakeholders regarding the scope of the project.
Having a quality plan at the outset of the project is extremely
beneficial because it will help prevent incurring additional costs
and schedule extensions due to rework caused by work and
deliverables that fail to meet quality requirements and customer
expectations.
The key to quality control is to monitor the quality of the work
early and regularly throughout the performance of the project,
rather than waiting until all the work is completed before
checking or inspecting for quality.
The network diagram is also is a communication tool for the
project team because it shows who is responsible for each
activity and how each person’s work fits into the overall
project.
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Critical Success Factors
Plan the work and then work the plan. It is important to develop
a plan before starting to perform the project. Taking the time to
develop a well-thought-out plan is critical to the successful
accomplishment of any project.
Participation builds commitment. By participating in the
planning of the work, individuals will become committed to
accomplishing it according to the plan.
The project must have a clear objective of what is to be
accomplished. The objective should be defined in terms of end
product or deliverable, schedule, and budget, and it must be
agreed upon by the customer and the project team that will
perform the project.
The project scope document is valuable for establishing a
common understanding and agreement among project
stakeholders regarding the scope of the project.
Having a quality plan at the outset of the project is extremely
beneficial because it will help prevent incurring additional costs
and schedule extensions due to rework caused by work and
deliverables that fail to meet quality requirements and customer
expectations.
The key to quality control is to monitor the quality of the work
early and regularly throughout the performance of the project,
rather than waiting until all the work is completed before
checking or inspecting for quality.
The network diagram is also is a communication tool for the
project team because it shows who is responsible for each
activity and how each person’s work fits into the overall
project.
25
Summary
The planning process is based on the project objective, which
establishes what is to be accomplished.
The project scope defines what needs to be done.
The project scope document usually contains the customer
requirements, statement of work, deliverables, acceptance
criteria, and a work breakdown structure.
The quality plan must include or reference the specifications,
industry or government standards, and codes that must be used
and met during the performance of the project work.
The work breakdown structure establishes the framework for
how the work will get done to produce the project deliverables.
A responsibility assignment matrix defines who will be
responsible for the work.
Activities define more specifically how the work will get done.
A network diagram defines the sequence of how and when the
activities will be performed.
Project planning is a critical activity in developing an
information system (IS).
A project management planning tool or methodology, called the
systems development life cycle (SDLC), is often used to help
plan, execute, and control IS development projects.
Numerous project management information systems are
available to help project managers plan, track, and control
projects in a completely interactive way.
© 2018 Cengage®. May not be scanned, copied or duplicated,
or posted to a publicly accessible website, in whole or in part,
except for use as permitted in a license distributed with a
certain product or service or otherwise on a password-protected
website or school-approved learning management system for
classroom use.
Summary
The planning process is based on the project objective, which
establishes what is to be accomplished.
The project scope defines what needs to be done.
The project scope document usually contains the customer
requirements, statement of work, deliverables, acceptance
criteria, and a work breakdown structure.
The quality plan must include or reference the specifications ,
industry or government standards, and codes that must be used
and met during the performance of the project work.
The work breakdown structure establishes the framework for
how the work will get done to produce the project deliverables.
A responsibility assignment matrix defines who will be
responsible for the work.
Activities define more specifically how the work will get done.
A network diagram defines the sequence of how and when the
activities will be performed.
Project planning is a critical activity in developing an
information system (IS).
A project management planning tool or methodology, called the
systems development life cycle (SDLC), is often used to help
plan, execute, and control IS development projects.
Numerous project management information systems are
available to help project managers plan, track, and control
projects in a completely interactive way.
26

More Related Content

Similar to CHAPTER 4Defining Scope, Quality, Responsibility, and Activity

025218911.pdf
025218911.pdf025218911.pdf
025218911.pdfEidTahir
 
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docxChapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docxbartholomeocoombs
 
Study guidespdf_p_mstudy_project management framework_framework
 Study guidespdf_p_mstudy_project management framework_framework Study guidespdf_p_mstudy_project management framework_framework
Study guidespdf_p_mstudy_project management framework_frameworkMohammad Ghouse
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docxwrite4
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docxwrite22
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docxwrite12
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
Section-1 250 words Subject Initiating the ProjectR.docx
Section-1 250 words  Subject Initiating the ProjectR.docxSection-1 250 words  Subject Initiating the ProjectR.docx
Section-1 250 words Subject Initiating the ProjectR.docxjeffreye3
 
University of the Cumberlands Project Management Worksheet.docx
University of the Cumberlands Project Management Worksheet.docxUniversity of the Cumberlands Project Management Worksheet.docx
University of the Cumberlands Project Management Worksheet.docxwrite5
 
Strayer cis 443 week 10 term paper
Strayer cis 443 week 10 term paperStrayer cis 443 week 10 term paper
Strayer cis 443 week 10 term papershyaminfo16
 
Stayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paperStayer cis 443 week 10 term paper
Stayer cis 443 week 10 term papershyaminfo105
 
Stayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paperStayer cis 443 week 10 term paper
Stayer cis 443 week 10 term papernikig6806
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docxgilbertkpeters11344
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_managementSociety of Women Engineers
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project CharterBogdan Gorka
 

Similar to CHAPTER 4Defining Scope, Quality, Responsibility, and Activity (20)

025218911.pdf
025218911.pdf025218911.pdf
025218911.pdf
 
Whitman_Ch10.pptx
Whitman_Ch10.pptxWhitman_Ch10.pptx
Whitman_Ch10.pptx
 
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docxChapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
Chapter FourDefining the Project© 2021 McGraw Hill. All ri.docx
 
Study guidespdf_p_mstudy_project management framework_framework
 Study guidespdf_p_mstudy_project management framework_framework Study guidespdf_p_mstudy_project management framework_framework
Study guidespdf_p_mstudy_project management framework_framework
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx
 
2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx2 page apa with scholarly journal reference and intext.docx
2 page apa with scholarly journal reference and intext.docx
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
Section-1 250 words Subject Initiating the ProjectR.docx
Section-1 250 words  Subject Initiating the ProjectR.docxSection-1 250 words  Subject Initiating the ProjectR.docx
Section-1 250 words Subject Initiating the ProjectR.docx
 
University of the Cumberlands Project Management Worksheet.docx
University of the Cumberlands Project Management Worksheet.docxUniversity of the Cumberlands Project Management Worksheet.docx
University of the Cumberlands Project Management Worksheet.docx
 
Strayer cis 443 week 10 term paper
Strayer cis 443 week 10 term paperStrayer cis 443 week 10 term paper
Strayer cis 443 week 10 term paper
 
Stayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paperStayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paper
 
Stayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paperStayer cis 443 week 10 term paper
Stayer cis 443 week 10 term paper
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
4 Project Goals, Scope, and CharterChaosDigital VisionGe.docx
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 

More from WilheminaRossi174

Senior Seminar in Business Administration BUS 499Coope.docx
Senior Seminar in Business Administration BUS 499Coope.docxSenior Seminar in Business Administration BUS 499Coope.docx
Senior Seminar in Business Administration BUS 499Coope.docxWilheminaRossi174
 
Select two countries that have been or currently are in confli.docx
Select two countries that have been or currently are in confli.docxSelect two countries that have been or currently are in confli.docx
Select two countries that have been or currently are in confli.docxWilheminaRossi174
 
Serial KillersFor this assignment you will review a serial kille.docx
Serial KillersFor this assignment you will review a serial kille.docxSerial KillersFor this assignment you will review a serial kille.docx
Serial KillersFor this assignment you will review a serial kille.docxWilheminaRossi174
 
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docx
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docxSESSION 1Michael Delarosa, Department ManagerWhat sugg.docx
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docxWilheminaRossi174
 
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docx
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docxSheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docx
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docxWilheminaRossi174
 
Selecting & Implementing Interventions – Assignment #4.docx
Selecting & Implementing Interventions – Assignment #4.docxSelecting & Implementing Interventions – Assignment #4.docx
Selecting & Implementing Interventions – Assignment #4.docxWilheminaRossi174
 
Seediscussions,stats,andauthorprofilesforthispublicati.docx
Seediscussions,stats,andauthorprofilesforthispublicati.docxSeediscussions,stats,andauthorprofilesforthispublicati.docx
Seediscussions,stats,andauthorprofilesforthispublicati.docxWilheminaRossi174
 
Shared Reading FrameworkFollow this framework when viewing the v.docx
Shared Reading FrameworkFollow this framework when viewing the v.docxShared Reading FrameworkFollow this framework when viewing the v.docx
Shared Reading FrameworkFollow this framework when viewing the v.docxWilheminaRossi174
 
Self-disclosureDepth of reflectionResponse demonstrates an in.docx
Self-disclosureDepth of reflectionResponse demonstrates an in.docxSelf-disclosureDepth of reflectionResponse demonstrates an in.docx
Self-disclosureDepth of reflectionResponse demonstrates an in.docxWilheminaRossi174
 
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docx
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docxSheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docx
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docxWilheminaRossi174
 
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docx
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docxSeemingly riding on the coattails of SARS-CoV-2, the alarming sp.docx
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docxWilheminaRossi174
 
See the attachment of 1 Article belowPlease answer all the que.docx
See the attachment of 1 Article belowPlease answer all the que.docxSee the attachment of 1 Article belowPlease answer all the que.docx
See the attachment of 1 Article belowPlease answer all the que.docxWilheminaRossi174
 
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docx
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docxSHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docx
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docxWilheminaRossi174
 
Select a healthcare legislature of interest. Discuss the historica.docx
Select a healthcare legislature of interest. Discuss the historica.docxSelect a healthcare legislature of interest. Discuss the historica.docx
Select a healthcare legislature of interest. Discuss the historica.docxWilheminaRossi174
 
See discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxSee discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxWilheminaRossi174
 
Segmented Assimilation Theory and theLife Model An Integrat.docx
Segmented Assimilation Theory and theLife Model An Integrat.docxSegmented Assimilation Theory and theLife Model An Integrat.docx
Segmented Assimilation Theory and theLife Model An Integrat.docxWilheminaRossi174
 
Select a local, state, or national public policy that is relev.docx
Select a local, state, or national public policy that is relev.docxSelect a local, state, or national public policy that is relev.docx
Select a local, state, or national public policy that is relev.docxWilheminaRossi174
 
School of Community and Environmental HealthMPH Program .docx
School of Community and Environmental HealthMPH Program .docxSchool of Community and Environmental HealthMPH Program .docx
School of Community and Environmental HealthMPH Program .docxWilheminaRossi174
 
School Effects on Psychological Outcomes During Adolescence.docx
School Effects on Psychological Outcomes During Adolescence.docxSchool Effects on Psychological Outcomes During Adolescence.docx
School Effects on Psychological Outcomes During Adolescence.docxWilheminaRossi174
 
Search the gene belonging to the accession id you selected in week 2.docx
Search the gene belonging to the accession id you selected in week 2.docxSearch the gene belonging to the accession id you selected in week 2.docx
Search the gene belonging to the accession id you selected in week 2.docxWilheminaRossi174
 

More from WilheminaRossi174 (20)

Senior Seminar in Business Administration BUS 499Coope.docx
Senior Seminar in Business Administration BUS 499Coope.docxSenior Seminar in Business Administration BUS 499Coope.docx
Senior Seminar in Business Administration BUS 499Coope.docx
 
Select two countries that have been or currently are in confli.docx
Select two countries that have been or currently are in confli.docxSelect two countries that have been or currently are in confli.docx
Select two countries that have been or currently are in confli.docx
 
Serial KillersFor this assignment you will review a serial kille.docx
Serial KillersFor this assignment you will review a serial kille.docxSerial KillersFor this assignment you will review a serial kille.docx
Serial KillersFor this assignment you will review a serial kille.docx
 
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docx
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docxSESSION 1Michael Delarosa, Department ManagerWhat sugg.docx
SESSION 1Michael Delarosa, Department ManagerWhat sugg.docx
 
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docx
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docxSheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docx
Sheet11a & 1b.RESDETAILRes NumCheck InCheck OutCust IDCustFNameCus.docx
 
Selecting & Implementing Interventions – Assignment #4.docx
Selecting & Implementing Interventions – Assignment #4.docxSelecting & Implementing Interventions – Assignment #4.docx
Selecting & Implementing Interventions – Assignment #4.docx
 
Seediscussions,stats,andauthorprofilesforthispublicati.docx
Seediscussions,stats,andauthorprofilesforthispublicati.docxSeediscussions,stats,andauthorprofilesforthispublicati.docx
Seediscussions,stats,andauthorprofilesforthispublicati.docx
 
Shared Reading FrameworkFollow this framework when viewing the v.docx
Shared Reading FrameworkFollow this framework when viewing the v.docxShared Reading FrameworkFollow this framework when viewing the v.docx
Shared Reading FrameworkFollow this framework when viewing the v.docx
 
Self-disclosureDepth of reflectionResponse demonstrates an in.docx
Self-disclosureDepth of reflectionResponse demonstrates an in.docxSelf-disclosureDepth of reflectionResponse demonstrates an in.docx
Self-disclosureDepth of reflectionResponse demonstrates an in.docx
 
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docx
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docxSheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docx
Sheet1Excel for Finance Majorsweek 1week 2week 3week 4week 5week 6.docx
 
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docx
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docxSeemingly riding on the coattails of SARS-CoV-2, the alarming sp.docx
Seemingly riding on the coattails of SARS-CoV-2, the alarming sp.docx
 
See the attachment of 1 Article belowPlease answer all the que.docx
See the attachment of 1 Article belowPlease answer all the que.docxSee the attachment of 1 Article belowPlease answer all the que.docx
See the attachment of 1 Article belowPlease answer all the que.docx
 
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docx
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docxSHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docx
SHAPING SCHOOL CULTURE BY LIVING THE VISION AND MISSIONNameI.docx
 
Select a healthcare legislature of interest. Discuss the historica.docx
Select a healthcare legislature of interest. Discuss the historica.docxSelect a healthcare legislature of interest. Discuss the historica.docx
Select a healthcare legislature of interest. Discuss the historica.docx
 
See discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docxSee discussions, stats, and author profiles for this publicati.docx
See discussions, stats, and author profiles for this publicati.docx
 
Segmented Assimilation Theory and theLife Model An Integrat.docx
Segmented Assimilation Theory and theLife Model An Integrat.docxSegmented Assimilation Theory and theLife Model An Integrat.docx
Segmented Assimilation Theory and theLife Model An Integrat.docx
 
Select a local, state, or national public policy that is relev.docx
Select a local, state, or national public policy that is relev.docxSelect a local, state, or national public policy that is relev.docx
Select a local, state, or national public policy that is relev.docx
 
School of Community and Environmental HealthMPH Program .docx
School of Community and Environmental HealthMPH Program .docxSchool of Community and Environmental HealthMPH Program .docx
School of Community and Environmental HealthMPH Program .docx
 
School Effects on Psychological Outcomes During Adolescence.docx
School Effects on Psychological Outcomes During Adolescence.docxSchool Effects on Psychological Outcomes During Adolescence.docx
School Effects on Psychological Outcomes During Adolescence.docx
 
Search the gene belonging to the accession id you selected in week 2.docx
Search the gene belonging to the accession id you selected in week 2.docxSearch the gene belonging to the accession id you selected in week 2.docx
Search the gene belonging to the accession id you selected in week 2.docx
 

Recently uploaded

_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 

Recently uploaded (20)

_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 

CHAPTER 4Defining Scope, Quality, Responsibility, and Activity

  • 1. CHAPTER 4 Defining Scope, Quality, Responsibility, and Activity Sequence © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Teaching Strategies The two vignettes reinforce consideration of the situation through research and communication with the stakeholders. The first vignette addresses the changing conditions for project planning of worldwide construction projects due to weather variability and increased extreme weather situations. The second examines a change in process for commerce. The desire was to increase credit card use; work with the stakeholders revealed a hesitation and distrust of credit cards due to potential fraud with an option for continued practices of e-commerce using debit cards. (See Premium Deck for Slides.) Sometimes planning seems to be a waste of time for a short project. However, even very small projects need some degree of planning. Tell the students a story of a failed project. Have students identify how having a clear project objective, a project scope document, a project plan, a work breakdown structure, a responsibility assignment matrix, and a network diagram could have changed the outcome. Have students create a work breakdown structure and network diagram for a project they will have to complete during the class semester. Have the students explain the relationship between tasks that must be completed sequentially and those
  • 2. that can be completed simultaneously. The network diagram for the consumer market study is included in the chapter materials. Have the students compare the textbook diagram with the one created in Microsoft Project. Have the students report on the similarities and the differences. Optional Supplemental Activities Recall that Chapter 1 offered an optional activity for student groups to contribute several hours to a not-for-profit organization. Have each group that participated in this activity give a 10 minute presentation and submit a 2-3 page write-up that discusses how that organization’s projects are planned, performed, controlled, and terminated. In addition, require each group to give at least 3 suggestions on ideas that could improve the projects at that organization. Have students seek a project management mentor and report on their experiences related to developing the project scope and identifying the work breakdown structure. Have students present an article from the International Journal of Project Management to the class. Have them post their critical review of the article to the class website, blog, wiki, or other class space to allow others to review and comment. 1 Chapter Concepts Clearly defining the project objective Preparing a project scope document Understanding the importance of planning for quality Creating a work breakdown structure Assigning responsibility for work items Defining specific activities Creating a network diagram Utilizing a project management methodology called the systems development life cycle for information systems development projects
  • 3. © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Chapter Concepts This chapter discusses the project scope document, quality, how to define what activities need to be done, who will be responsible for them, and in what sequence they will be performed. It describes techniques and tools used to pl an the work items and activities that need to be performed in order to accomplish the project objective successfully. The project scope defines what work needs to be done and what deliverables need to be produced. Then, specific activities are defined and arranged in a sequence of dependent relationships to determine how the work will be performed. This chapter will help student to become familiar with: Clearly defining the project objective Preparing a project scope document Understanding the importance of planning for quality Creating a work breakdown structure Assigning responsibility for work items Defining specific activities Creating a network diagram Utilizing a project management methodology called the systems development life cycle for information systems development projects 2 Learning Outcomes Establish a clear project objective Prepare a project scope document Discuss the importance and elements of a project quality plan
  • 4. Develop a work breakdown structure Prepare a responsibility assignment matrix Describe how to define specific activities Create a network diagram © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Learning Outcomes After studying this chapter, students should be able to: Establish a clear project objective Prepare a project scope document Discuss the importance and elements of a project quality plan Develop a work breakdown structure Prepare a responsibility assignment matrix Describe how to define specific activities Create a network diagram 3 Project Integration Management Project Scope Management Project Quality Management Project Resource Management Project Schedule Management Project Management Knowledge Areas from PMBOK® Guide © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for
  • 5. classroom use. Project Management Knowledge Areas from PMBOK® Guide Concepts in this chapter support the following Project Management Knowledge Areas of the PMI Guide to the Project Management Body of Knowledge (PMBOK® Guide): Project Integration Management Project Scope Management Project Quality Management Project Resource Management Project Schedule Management 4 Establish Project Objective Planning process is based on the project objective Establishes what is to be accomplished Often stated in the project charter or RFP Is the tangible end product Project objective includes Expected benefits Primary project end product or deliverable Date required to be completed Budget Changes agreed upon by customer and contractor © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Establish Project Objective The planning process is based on the project objective. The project objective establishes what is to be accomplished.
  • 6. Often the project objective is stated in the project charter or RFP. It is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project. The project objective should include the following elements: Expected benefits that will result from implementation of the project and define success Primary project end product or deliverable Date by which the project is required to be completed Budget within which the project must be completed Situations can arise where the project objective needs to be modified as the project proceeds because of extenuating circumstances or new information. The project manager and the customer must agree on all changes to the project objective. Any such changes might affect the remaining work scope, deliverables, completion date, and final cost. 5 Define Project Scope Project Scope Project Scope Document Defines what needs done Includes Items contained in project charter, RFP, proposal More detail Establishes common understanding of scope with stakeholders Usually contains Customer requirements Statement of Work Deliverables Acceptance Criteria Work Breakdown Structure Establishes baseline Change control system to avoid scope creep
  • 7. © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Define Project Scope The project scope defines what needs to be done. A project scope document includes many of the items contained in the project charter, RFP, or contractor’s proposal, but in much greater detail. The document is valuable for establishing a common understanding among project stakeholders regarding the scope of the project. The project scope document usually contains the following sections: Customer requirements define the functional or performance specifications for the project’s end product and other project deliverables. It should also include or reference applicable technical specifications, standards, and codes that must be used and met regarding quality and performance of the project work and deliverables. Statement of Work (SOW) defines the major tasks that will need to be performed to accomplish the work that needs to be done and produce all the project deliverables. Deliverables are the products or outputs that the project team or contractor will produce and provide to the customer during and at the completion of the performance of the project. Acceptance criteria for all project deliverables must be described in greater detail than what is stated in the project charter or request for proposal Work Breakdown Structure (WBS) is a hierarchical decomposition of the project work scope into work packages that produce the project deliverables.
  • 8. The agreed-upon project scope document establishes the baseline for any changes that may be made to the scope during the performance of the project. A change control system needs to be established to define how changes will be documented, approved, and communicated. The project team or contractor must avoid scope creep, which is informally making changes to the project scope without appropriate approval. 6 Plan for Quality Complete work according to specifications and standards Plan for assuring quality as project progresses Include References for specifications and standards Written procedures for quality tools and techniques Key aspects Monitor as the project progresses Do work right the first time rather than rework © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Plan for Quality Planning for quality is a necessary, yet often forgotten or dismissed, function on a project. It is essential to have a plan for assuring the quality of project deliverables and results, rather than waiting until the end of the project to check if the sponsor/customer requirements and expectations on project deliverables have been met. It is important to plan for quality in performing the project.
  • 9. This helps assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria. A project quality plan includes or references: Project specifications and standards Industry or government standards (for design, testing, safety, construction, etc.) Codes that must be used and met during the performance of the project work Written procedures for using various quality tools and techniques The key to quality control is to: Monitor the quality of the work early and regularly throughout the performance of the project Compare results with quality standards Make any necessary corrective actions immediately, rather than waiting until all the work is completed before checking or inspecting for quality To ensure that a project is done right the first time, a project should focus on doing the work in accordance with quality standards, and therefore preventing quality problems. 7 Create Work Breakdown Structure Deliverable-oriented hierarchical decomposition Organize project work and deliverables Create logical groupings Subdivide into more manageable components Deliverable is output of work package Resource requirements and durations can be assigned Accountability can be assigned Project manager can monitor and control Graphic chart or indentured list © 2018 Cengage®. May not be scanned, copied or duplicated,
  • 10. or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Create Work Breakdown Structure Once the project scope document has been agreed on and prepared, the next step in the planning phase is to create a detailed work breakdown structure (WBS) This is a deliverable-oriented hierarchical decomposition of the project work scope into work packages, or activity groupings, that produce the project deliverables. Creating a WBS is a structured approach for organizing all the project work and deliverables into logical groupings. This helps to subdivide the deliverables into more manageable components called work items, to help ensure that all tasks required to complete the project are identified and included in the baseline project plan. The WBS should be deconstructed to a level that identifies individual work packages for each specific deliverable listed in the project scope document. Dividing a project into work packages and work items helps a contractor increase the level of confidence that: All the activities that need to be performed to produce the deliverable can be defined The types and quantities of resources can be determined The associated activity durations and costs can be reasonably estimated. Work items should be broken down to the level at which a single organization (marketing communications, materials engineering, human resources, a subcontractor, etc.) or individual can be assigned responsibility and accountability for accomplishing the work package. The WBS can be created using a graphic chart format or as a list.
  • 11. 8 WBS with Breakdown to Different Levels © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in pa rt, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. WBS with Breakdown to Different Levels This figure depicts the work breakdown structure in a graphic chart format for a community festival project. Note that not all of the branches in a WBS have to be broken down to the same level. 9 WBS Graphic Chart Indentured List © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. WBS The top figure depicts the WBS for the consumer market study
  • 12. project example. This project is also the example used in the Microsoft Project appendices. Have students examine the relationship between this figure and the entries in the Microsoft Project task list. The bottom figure depicts an indentured list for the work breakdown structure. For each of the work packages, the deliverable is listed. This format is helpful for large projects where a diagram would become too large and unwieldy. 10 Assign Responsibility Responsibility assignment matrix Designate responsible individuals P = Primary responsibility S = Support responsibility Associates responsibility For each work item For each individual Only one primary per work item © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Assign Responsibility A responsibility assignment matrix (RAM) defines who will be responsible for the work. It is a tool used to designate the individuals responsible for accomplishing the different work items in the work breakdown structure (WBS).
  • 13. This figure depicts the RAM for the WBS in Figure 4.1, the community festival project. The RAM often uses a P to designate primary responsibility and an S to indicate support responsibility for a specific work item. The RAM shows all the individuals associated with each work item in the WBS, as well as all the work items associated with each individual. Only one individual should be designated as the lead, or primary, person responsible for each work item. 11 Define Activities Responsible resources define activities Breakdown work packages to work items Level needed to perform deliverable May not be able to define all Comprehensive activity list Not always require expenditure of effort Could be wait time © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Define Activities Using the WBS, the individual or team responsible for each work package must next define all the specific activities that need to be performed to produce the end item, or deliverable. Breaking down each work package into its component activities reveals the level at which each activity must be performed to produce the deliverable.
  • 14. Some activities may not be easily definable. When all the specific activities have been defined for all of the work packages, they should be consolidated into a comprehensive activity list. Because of the allocation of resources, there may be wait time between the end of one activity and the start of another one. This figure shows the work breakdown structure for a consumer market study project. It depicts the specific activities that need to be performed for each work package. Have the students compare this list to the entries for the tasks in the Microsoft Project appendix. 12 Sequence Activities Network diagram Defines the sequence of activities and relationships Tool for arranging order Common techniques PERT CPM PDM © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Sequence Activities A network diagram defines the sequence of how the activities will get done. It is a tool for arranging the specific activities in the best sequence and defining their dependent relationships.
  • 15. The three most common techniques of network diagramming are program evaluation and review technique (PERT), the critical path method (CPM), and the precedence diagramming method (PDM). In the past, there were distinguishable methodological differences between PERT and CPM. Today, however, when most people refer to a CPM diagram or PERT chart, they mean a generic network diagram. The top figure shows a complete network diagram for a consumer market study project, with the person responsible for each activity included on the diagram. The bottom figure shows a network diagram for a web-based reporting system project. 13 Network Principles Activities Represented by a box Consume time Described by verb Relationships Linked in serial sequence Complete concurrently © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Network Principles
  • 16. Each activity is represented by a box in the network diagram and the description of the activity is written within the box, as shown in this figure. Activities consume time, and their description usually begins with a verb (such as get, wash, and dry in this example). Activities have a dependent relationship—that is, they are linked in a logical sequence in a network diagram to show which activities must be finished before others can start. Certain activities have to be done in serial sequence. Some activities may be done concurrently. 14 Loops Illogical relationship among activities Perpetually repeats itself Not acceptable © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Loops An illogical relationship among activities is known as a loop. In preparing a network diagram, drawing activities in a loop is not acceptable because it portrays a path of activities that perpetually repeats itself. 15 Laddering Set of repeating activities Serial sequence
  • 17. One work Two wait Can be performed at same time Would need triple resources Ladder activities Allow for shortest possible time for completion Best use of the three workers and experts © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Laddering Some projects have a set of activities that are repeated several times. The top figure shows a series of activities that must be done in serial sequence, which means that, for an activity with three people, at any one time only one person is working while two other people are waiting. The middle figure shows a set of activities that can be performed concurrently. However, it is often not practical to perform the activities in this way because the organization would need triple the experts– one for each room. The bottom figure shows a technique known as laddering. This approach allows the project to be completed in the shortest possible time, while making the best use of available resources. 16 Create Network Diagram
  • 18. Tips and Techniques Logical sequence of activities Show dependent relationships Elaborate as project progresses Use subnetworks for similar activity sequences and relationships Development of Diagram Questions to answer Finish before next start? Done concurrently? Cannot be started next? Guidelines for detail level Define each work package Draw summary level network then add detail Detail to responsibility or deliverable change Duration less than project progress review © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Create Network Diagram A network diagram is a drawing of the activities for a project, displayed in boxes in their logical sequence and connected by arrows to indicate dependent relationships. The network diagram shows how the project should be performed from start to completion. Three questions need to be answered regarding each activity. The network is based upon the answers: Which activities must be finished immediately before this activity can be started? Which activities can be done concurrently with this activity?
  • 19. Which activities cannot be started until immediately after this activity is finished? Guidelines for the level of detail in the network diagram are: Based on the work breakdown structure for a project; specific activities should be defined for each work package. It may be preferable to draw a summary-level network first that depicts a small number of higher level activities and then expand to a more detailed network. The level of detail may be determined by certain obvious interface or transfer points such as a change in responsibility or if there is a tangible output or product or deliverable as a result of an activity. Activities should not be longer in estimated duration than the project progress review. It is not unusual to progressively elaborate the network di agram as the project progresses and more information becomes clear. Sub-networks can be used to represent similar projects for different customers. Certain portions of projects may include the same types of activities in the same sequence and with the same dependent relationships. 17 Planning for Information Systems Development Definition Computer-based system Accepts data as input Processes the data Produces useful information Examples Computerized order entry E-commerce Automatic teller machines Billing, payroll, and inventory Process Plan, execute, and control
  • 20. Systems Development Life Cycle Problem definition System analysis System design System development System testing System implementation © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Planning for Information Systems Development The Microsoft Project example will continue through chapters 4 – 8. It highlights the concepts for each chapter in the example. The Microsoft Project file for the example is available with the instructor materials. An information system (IS) is a computer-based system that accepts data as input, processes the data, and produces useful information for users. Information systems include computerized order entry systems, e-commerce systems, automatic teller machines, and billing, payroll, and inventory systems. The development of an IS is a challenging process that requires extensive planning and control to ensure that the system meets user requirements and is finished on time and within budget. A project management planning tool, or methodology, called the systems development life cycle (SDLC) is often used to help plan, execute, and control IS development projects. It consists of the following steps: Problem definition -- Data are gathered and analyzed and problems and opportunities are clearly defined.
  • 21. System analysis -- The development team defines the scope of the system to be developed, interviews potential users, studies the existing system (which might be manual), and defines user requirements. System design -- Several alternative conceptual designs are produced and evaluated. The best is selected for further design and development. System development -- The actual system is brought into existence. System testing – This step involves looking for logical errors, database errors, errors of omission, security errors, and other problems that might prevent the system from being successful. System implementation -- The existing system is replaced with the new, improved, system and users are trained. 18 An IS Example: Internet Applications Development for ABC Office Designs ABC Office Designs Large number of sales representatives Sell office furniture to major corporations State assignments in four regions Management monitor state and regional sales Build Web-based IS system to track prices, inventory, and competition Project Project manager identified WBS follows SDLC Responsibility assignment matrix completed List of tasks compiled and predecessors identified Network diagram created © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a
  • 22. certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. An IS Example: Internet Applications Development for ABC Office Designs A corporation called ABC Office Designs has a large number of sales representatives who sell office furniture to major corporations. Each sales representative is assigned to a specific state, and each state belongs to one of four regions in the country. To enable management to monitor the number and amount of sales for each representative, for each state, and for each region, ABC has decided to build a Web-based information system that will track prices, inventory, and the competition. The IS department within the corporation has assigned Beth Smith to be the project manager of the Web-based reporting system development project. The following four slides depict figures related to this project. First, we will see the major tasks that were identified for the project. Then we will look at the responsibility assignment matrix for the project with the primary and secondary responsibilities for each task assigned. We will then look at a list of all tasks to be done, with the immediate predecessor for each task listed to the right of the task. Finally, we will examine the network diagram created by Beth and the project team that represents the interdependencies listed in the immediate predecessor list. 19 IS Example: WBS follows SDLC
  • 23. © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. IS Example: WBS follows SDLC This figure depicts the major tasks that were identified for the project. The WBS follows the SDLC. 20 IS Example: Responsibility Assignment Matrix © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. IS Example: Responsibility Assignment Matrix Here we see the responsibility assignment matrix for the project, with the primary and secondary responsibilities for each task assigned. Make sure that students note that all the tasks in the WBS appear in the responsibility assignment matrix. 21 IS Example: Task List and Predecessors © 2018 Cengage®. May not be scanned, copied or duplicated,
  • 24. or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. IS Example: Task List and Predecessors This figure depicts a list of all tasks to be completed, with the immediate predecessor for each task listed to the right of the task. Have the students examine the interdependencies of the tasks. 22 IS Example: Network Diagram © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. IS Example: Network Diagram Here is the network diagram created by Beth and the project team. This figure represents the interdependencies listed in the immediate predecessor list. 23 Project Management Information Systems Wide variety of systems available Plan and control projects in interactive mode Plan and test different options Create reports, diagrams, and charts
  • 25. Interface with other software applications Appendix A has additional information © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Project Management Information Systems A wide variety of affordable project management information systems are available for purchase. These systems allow the project manager and the project team to plan and control projects in a completely interactive mode. Planning and testing different options for task durations, dependencies, constraints, resources, schedules, and costs can be completed in a project management information system. Information systems help project managers to create reports, change management, network diagrams, and Gantt charts. Project management information systems also interface with other software applications. Appendix A contains information related to project management information systems. 24 Critical Success Factors Plan the work and then work the plan. It is important to develop a plan before starting to perform the project. Taking the time to develop a well-thought-out plan is critical to the successful accomplishment of any project. Participation builds commitment. By participating in the planning of the work, individuals will become committed to accomplishing it according to the plan. The project must have a clear objective of what is to be
  • 26. accomplished. The objective should be defined in terms of end product or deliverable, schedule, and budget, and it must be agreed upon by the customer and the project team that will perform the project. The project scope document is valuable for establishing a common understanding and agreement among project stakeholders regarding the scope of the project. Having a quality plan at the outset of the project is extremely beneficial because it will help prevent incurring additional costs and schedule extensions due to rework caused by work and deliverables that fail to meet quality requirements and customer expectations. The key to quality control is to monitor the quality of the work early and regularly throughout the performance of the project, rather than waiting until all the work is completed before checking or inspecting for quality. The network diagram is also is a communication tool for the project team because it shows who is responsible for each activity and how each person’s work fits into the overall project. © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Critical Success Factors Plan the work and then work the plan. It is important to develop a plan before starting to perform the project. Taking the time to develop a well-thought-out plan is critical to the successful accomplishment of any project. Participation builds commitment. By participating in the planning of the work, individuals will become committed to
  • 27. accomplishing it according to the plan. The project must have a clear objective of what is to be accomplished. The objective should be defined in terms of end product or deliverable, schedule, and budget, and it must be agreed upon by the customer and the project team that will perform the project. The project scope document is valuable for establishing a common understanding and agreement among project stakeholders regarding the scope of the project. Having a quality plan at the outset of the project is extremely beneficial because it will help prevent incurring additional costs and schedule extensions due to rework caused by work and deliverables that fail to meet quality requirements and customer expectations. The key to quality control is to monitor the quality of the work early and regularly throughout the performance of the project, rather than waiting until all the work is completed before checking or inspecting for quality. The network diagram is also is a communication tool for the project team because it shows who is responsible for each activity and how each person’s work fits into the overall project. 25 Summary The planning process is based on the project objective, which establishes what is to be accomplished. The project scope defines what needs to be done. The project scope document usually contains the customer requirements, statement of work, deliverables, acceptance criteria, and a work breakdown structure. The quality plan must include or reference the specifications, industry or government standards, and codes that must be used and met during the performance of the project work. The work breakdown structure establishes the framework for how the work will get done to produce the project deliverables.
  • 28. A responsibility assignment matrix defines who will be responsible for the work. Activities define more specifically how the work will get done. A network diagram defines the sequence of how and when the activities will be performed. Project planning is a critical activity in developing an information system (IS). A project management planning tool or methodology, called the systems development life cycle (SDLC), is often used to help plan, execute, and control IS development projects. Numerous project management information systems are available to help project managers plan, track, and control projects in a completely interactive way. © 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as permitted in a license distributed with a certain product or service or otherwise on a password-protected website or school-approved learning management system for classroom use. Summary The planning process is based on the project objective, which establishes what is to be accomplished. The project scope defines what needs to be done. The project scope document usually contains the customer requirements, statement of work, deliverables, acceptance criteria, and a work breakdown structure. The quality plan must include or reference the specifications , industry or government standards, and codes that must be used and met during the performance of the project work. The work breakdown structure establishes the framework for how the work will get done to produce the project deliverables. A responsibility assignment matrix defines who will be responsible for the work.
  • 29. Activities define more specifically how the work will get done. A network diagram defines the sequence of how and when the activities will be performed. Project planning is a critical activity in developing an information system (IS). A project management planning tool or methodology, called the systems development life cycle (SDLC), is often used to help plan, execute, and control IS development projects. Numerous project management information systems are available to help project managers plan, track, and control projects in a completely interactive way. 26