BAE SYSTEMS
Process Audit Report
21-Jun-2022
Audit Observations on 17-Nov-2021
1. Risk assessment – For all RFQ & Contracted projects, which covers all the aspects of the project
2. Capacity Analysis – Capacity assessment which includes current and future projects.
3. QA Manpower
4. Q2Q Workload Plan
5. Oursys ERP Implementation – (BOM creation, Process Layouts, Machining sequences)
6. Things Went Right / Things Gone Wrong – Lessons learned from Previous projects
7. KPI for all departments / Review on quarterly basis
8. For HSE/OSHAS – ISO 14001/45001 – Consultant status
9. Contract Requirements Flow down
10. International Standards Requirements
11. OEE & Daily Morning Meetings
12. Additional Lifting Equipment’s added.
• Summary of Audit Observations:
1. Number of Non-Conformances identified count 8
2. Number of Action Points count 23
3. Number of Action NC / Points Implemented count 24
4. Balance to be implemented count 7
5. Out of balance 7, 3 Points are ERP Implementation
6. 2 Points are HSE / OSHAS Implementation
7. 2 Points are Quality manager & Purchase Manager recruitment.
BAE Audit Score @ Aug-2021
Self Audit Score @ Jan-2022
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
1.1 Supplier to give details of quality
approvals held (i.e. ISO 9001,
AQAP etc.). Does the scope of
certification approval (ISO, AQAP
etc.) cover the requirements of
the product or service being
purchased?
Risk and Capability assessment
has not performed at RFQ
stage
Risk and Capacity assessment to
be performed for all projects at RFQ
stage
Closed
PMO not established to avoid
delays in delivery of POs
Dedicated PMO to be established-
Aerospace domain experience to be
hired
Sep 2022 HR Open
Risk Assessment Risk Planning
Evidences for closure
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
1.2 Is there a clear Quality focus
(Quality Manager) for the
business and is the position
identified on an organisational
chart?
Inadequate team strength in QA
dept.
Adequate team members filled in
QA dept. to perform QC, QA and
SQA activities.
QA Manager also appointed
Closed
Ref. # Process Findings / Observations Counter Measures ECD ACD Owner Status
1.3 Supplier to demonstrate the
process of how purchase orders
raised on sub-contractors to flow
down customer requirements +
are regular audits conducted with
the sub contractors?
Evidence not found for
Procurement SOP- Bought out
parts, Raw material, Machined
Parts, Special Process
The followings will be enhanced,
Annexure for PO Terms and
Conditions
Supplier Questionnaire
Supplier Registration
Supplier Evaluation and Approval
Supplier Performance Rating
Closed
Approved supplier list is not
updated with supplier details for
BAE projects, like Dollinger,
Gallagher, Fluitek, etc.
Needs to be updated Approved
Suppliers List
Closed
Supplier
Questionaire
Supplier
Registration
Supplier
Evaluation
Supplier Rating List of approved
Suppliers
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
1.5 Supplier to demonstrate how
purchased / sub-contract items
are verified as meeting
requirements prior to use
(First Article Inspection -FAI)
1) Corrective actions to be
taken for recovery in the
delivery timelines for existing
projects.
2)Preventive actions to avoid
such delays in future projects
3)Q2Q to submit detailed report
on "Lessons learned" during
implementation of the current
projects
TGR/TGW format available and
made sample for Header Tank
projects, it was reviewed and
approved.(Refer to next slide for
evidence)
Closed
Further the same will be deployed
for all projects, and we will submit to
BAE team for review.
Closed
1.7 Supplier has robust processes
adopted to ensure the
implementation and verification of
cause and corrective actions?
SQE Appointed for all outside
process & items inspection /
verification
Closed
For AHS Racks root cause analysis
to be done for delay, and
Welding process improvement plan
to be shared with BAE.
Closed
Welding
Improvements
Improvements:
• We make TGR, TGW for existing projects and in future this will be incorporated with BAE-SCM sheet for weekly review.
• For the KPI- Each departments will be evaluated based on KPI – Performance data on quarterly basis.
Quality Focus
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
2.1,
2.3,
2.5,
2.7
Has the supplier identified in the
organisation structure a senior
manager responsible for EHS?
No authorized personnel found
for EHS lead
Obtained EHS lead closed
ISO 14001 & 45001 certification
not found
ISO 14001 & 45001 certification
readiness on progress
Consultant fixed
Dec 2022
3.4 International Traffic in Arms
Regulations (ITAR) - Does the
supplier have a process in place
to manage export /Import
Compliance including but not
limited to the International Traffic
in Arms Regulations?
Evidences not found for the
followings,
a) Procedure related to export
control document handling
b) No training records for new &
existing employees
c) Internal audit related to
Export control compliances
SOP, Training, Internal Audit plan
needs to be implemented
Sep 2022
3.5 Ethics - Does the supplier have a
code of conduct with ethical
principles and standards
regarding the prevention of
bribery and corruption i.e.
prohibition of corrupt practices,
policy on facilitation payments,
political donations and gifts and
hospitality including sanctions for
non-compliance?
Ethics and code of conduct not
found
Training to be provided for existing
employees
Henceforth new employee will
obtain the training in day one itself
Closed
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
3.7 Sustainable Development (SD) -
Does the supplier understand
the concept of sustainability
relating to the maintenance and
enhancement of environmental,
social and economic resources,
in order to meet the need of
current and future generations?
SOP not found for sustainable
development of EHS
Consultant fixed for preparing
documents and policies for
ISO14001, 45001
Dec 2022 QA Open
Training will be provided to all
employees
Dec 2022 QA Open
3.8 Business Continuity
Management (BCM) - Does the
supplier have business continuity
contingency, or major incident
recovery plans in place to
ensure contracted BAE Systems
deliveries are maintained?
Succession plans not found to
ensure Business Continuity
Succession plan to be made for all
critical functions
Sep 2022 PPC/PMO Open
Not found Business continuity
plan
Business Continuity plan to be
made for critical functions and
equipment’s
Sep 2022 PPC/PMO Open
3.9 Lean Manufacturing - Does the
supplier adopt lean
manufacturing, such as process
mapping, 5S workplace
organisation, 7 wastes, root
cause analysis etc ?
TPM in the organization to
ensure equipment run-time to
meet the production
requirements.
Training to be provided to all the
employees and training records to
be maintained
Closed
4.9 Does the supplier measure of
production line efficiency and
manage capacity planning?
OEE is not being monitored 1) OEE monitored and reported to
management on monthly basis
and displayed in Production
area
2) - OEE for May 2022- need to
add next slide.
Closed
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
4.10 Does the supplier have
production issue boards (4M),
how regular are meetings
attended around the boards and
what are the outputs?
1) No monitoring of action items
evident & list of attendees. No
objective evidence for review
happening with top leadership.
1)No monitoring of action items
evident & list of attendees.
No objective evidence for review
happening with top leadership.
closed
4.1 Does the supplier hold a
company organisation chart?
1) Project Management as
function not included in Org.
chart. No dedicated Project
Manager.
2) Organization Structure to be
strengthened as multiple
positions are vacant.
1)Project Management as function
to be included in Org. chart.
Dedicated Project Manager to be
deputed.
2Project Manager will be appointed
soon- Interview process on going
Closed
1)Organization Structure to be
strengthened as multiple positions
are vacant.
2)Hiring process Plan Made. HR
closely working on it to fill all open
positions
4.4,6.1
2,6.2
Does the supplier have a
documented contract review
process, including risk mitigation
plans identified and in place prior
to contract award?
No ERP or SAP system being
followed.
1) Oursys ERP- Implementation
process is in progress.
2)All team members working for the
documents input to the ERP. From
Aug’2022 ERP will go live.
Closed
1)All machine details, instruments
details will be uploaded in ERP,
which will trigger us periodic
maintenance, calibration based on
the frequency what we set during
creation of data.
WIP
Production
• Daily Morning Meeting Sheet:
• Manpower Allocation & Open Positions
DEPARTMENT No. of Employees To be added D. O. Joinng
Production 21 1 Offer released
Manufacturing Engg. 6 0
Quality Control 5 2 9th May 2022 & Yet to finalize
Finishing & Deburring 4 0
Welding 3 0
PPC 2 1 To be recruit
Tool Room 2 0
Accounts 1 0
Assembly 1 1
Finished Goods & Logistics 2 0
Human Resources 1 1 Before 15th April 2022
Director - Operations 1 0
PMO 0 1 Interview done, yet to confirm the Joining date
Purchase 0 2 15th April 2022 &Yet to finalize
Grand Total 49 8
Before: After:
• No ERP • Oursys ERP finalized – To be start from Mid of Mar’ 2022.
ERP
Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status
4.6 Does the supplier have a documented
contract review process, including risk
mitigation plans identified and in place
prior to contract award?
1)Checklist being followed is generic &
doesn't include critical aspects viz.
Hardware parts procurement, Special
process etc. Contract review happening
at RFQ stage not after contract release.
1)Checklist to be reviewed to include all
critical aspects viz. Hardware parts
procurement, Special process etc.
2) Mechanism to be developed for Contract
review after contract release.
closed
2) Risk register to be strengthened viz.
RM delay issue should be identified as
risk for on-time delivery
1)Now we made new format to cover all the
aspects for Risks and contract review for all
RFQ packages and received Projects we
analysed the risk and Mitigation actions
taken.
4.7 Does the supplier have access to any
databases to get copies of both national
and international standards to support
the manufacturing processes?
1) Q2Q is not having any subscription.
No Master list of national &
international standards evident.
2)No mechanism demonstrated to
ensure latest standards being followed.
Directly procured or download various
standards on the respective websites.
Closed
4.12 How does the supplier flow down critical
- contractual requirements fed down to
the internal production line
(manufacturing instruction - route card)
to ensure compliance during
manufacturing processing?
No evidence demonstrated for
Hydrostatic testing requirements not
flowed down to production line for
Header tank.
1)Current product MO and setup sheets to
be revisited to ensure that all the critical and
contractual requirements- Currently it is
done by making process flow chart and
Manufacturing build book.
closed
4.13 Are all sub-contractors approved,
effectively managed and audited on a
regular basis by the supplier, also has the
supplier a control plan in place to flow
down critical - contractual requirements
to his external sub contractors to ensure
compliance during the sub contracted
manufacturing processing?
Mechanism to strengthen to flow down
customer requirements to sub-
contractors.
1)Currently, Contract requirements are being
shared to special process suppliers by
Annexure to PO, which covers SP Matrix,
Masking drawing.
2)From May’2022 all PO requirements will
be captured and flow down thru ERP.
3)For raw material, drawing requirements
and standard requirements to be send to RM
suppliers with PO.
Closed
Standards Database
• Procedure for Standards:
Improvements:
• Current Router format revised to cover complete process flow to include PO & Special requirements. .
• For Special Process Suppliers along with PO’s we are issuing Special Process matrix and Masking drawings.
Contract Requirements Flow down
Ref. # Process Findings / Observations Counter Measures ECD ACD
Gap
(In days) Owner Status
5.10 Has the supplier facility sufficient lifting
and handing capability (overhead crane
or forklift truck(s))?
1)Some large parts were placed on
foam sheets and wooden pallets on
floors. Trolleys to be designed for
handling parts during APQP stage.
1)Contract study report will capture Material
Handling requirements.
2)Format revised to capture and cover all
requirements during RFQ stage itself.
closed
Lifting Equipment's
Thank you

More Related Content

Similar to Corrective Action_.pptx

1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
SCOTT SITTNER
 
Parts Engineering Grade Standard.pptx
Parts Engineering Grade Standard.pptxParts Engineering Grade Standard.pptx
Parts Engineering Grade Standard.pptx
riski164923
 
2015 - RT & AWAY Intro Pack
2015 - RT & AWAY Intro Pack2015 - RT & AWAY Intro Pack
2015 - RT & AWAY Intro Pack
Matt Rendoth
 
NS Automotive QSP
NS Automotive QSPNS Automotive QSP
NS Automotive QSP
Nisarg Shah
 
Reducing timeincreasingvalue0503
Reducing timeincreasingvalue0503Reducing timeincreasingvalue0503
Reducing timeincreasingvalue0503
Omnex Inc.
 
ICD 10 Timeline
ICD 10 TimelineICD 10 Timeline
ICD 10 Timeline
Kforce
 
Iso ts-implementation-webinar5-17-05
Iso ts-implementation-webinar5-17-05Iso ts-implementation-webinar5-17-05
Iso ts-implementation-webinar5-17-05
Omnex Inc.
 

Similar to Corrective Action_.pptx (20)

1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
 
Parts Engineering Grade Standard.pptx
Parts Engineering Grade Standard.pptxParts Engineering Grade Standard.pptx
Parts Engineering Grade Standard.pptx
 
Engineering quality assurance manual
Engineering quality assurance manualEngineering quality assurance manual
Engineering quality assurance manual
 
2015 - RT & AWAY Intro Pack
2015 - RT & AWAY Intro Pack2015 - RT & AWAY Intro Pack
2015 - RT & AWAY Intro Pack
 
Maheswaran Resume
Maheswaran ResumeMaheswaran Resume
Maheswaran Resume
 
NS Automotive QSP
NS Automotive QSPNS Automotive QSP
NS Automotive QSP
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptx
 
Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
CMMI.ppt
CMMI.pptCMMI.ppt
CMMI.ppt
 
Reducing timeincreasingvalue0503
Reducing timeincreasingvalue0503Reducing timeincreasingvalue0503
Reducing timeincreasingvalue0503
 
Vinoth.s qa qc-ims (qms&ehs)
Vinoth.s   qa qc-ims (qms&ehs)Vinoth.s   qa qc-ims (qms&ehs)
Vinoth.s qa qc-ims (qms&ehs)
 
ICD 10 Timeline
ICD 10 TimelineICD 10 Timeline
ICD 10 Timeline
 
Iso ts-implementation-webinar5-17-05
Iso ts-implementation-webinar5-17-05Iso ts-implementation-webinar5-17-05
Iso ts-implementation-webinar5-17-05
 
Cal Tech Presentation 2015
Cal Tech Presentation 2015Cal Tech Presentation 2015
Cal Tech Presentation 2015
 
001 a strategy for productivity
001 a strategy for productivity001 a strategy for productivity
001 a strategy for productivity
 
001 a strategy for productivity
001 a strategy for productivity001 a strategy for productivity
001 a strategy for productivity
 
001 a strategy for productivity
001 a strategy for productivity001 a strategy for productivity
001 a strategy for productivity
 
Awareness session on iatf 16949 2016 standard
Awareness session on iatf 16949 2016 standardAwareness session on iatf 16949 2016 standard
Awareness session on iatf 16949 2016 standard
 
Resume_Balachandru
Resume_BalachandruResume_Balachandru
Resume_Balachandru
 
Sample ISO 13485 Quality Manual & Procedures Package
Sample ISO 13485 Quality Manual & Procedures Package Sample ISO 13485 Quality Manual & Procedures Package
Sample ISO 13485 Quality Manual & Procedures Package
 

More from VasudevanGovindaraj1 (10)

Employee Training Presentation AS9100.pptx
Employee Training Presentation AS9100.pptxEmployee Training Presentation AS9100.pptx
Employee Training Presentation AS9100.pptx
 
6S Training Overview.pptx
6S Training Overview.pptx6S Training Overview.pptx
6S Training Overview.pptx
 
AS9103_2001.pdf
AS9103_2001.pdfAS9103_2001.pdf
AS9103_2001.pdf
 
Trail part #9 Response.pptx
Trail part #9 Response.pptxTrail part #9 Response.pptx
Trail part #9 Response.pptx
 
AS9102B Overview.pptx
AS9102B Overview.pptxAS9102B Overview.pptx
AS9102B Overview.pptx
 
QMS Awareness.pptx
QMS Awareness.pptxQMS Awareness.pptx
QMS Awareness.pptx
 
Business Continuity Plan.pptx
Business Continuity Plan.pptxBusiness Continuity Plan.pptx
Business Continuity Plan.pptx
 
Exercises.pptx
Exercises.pptxExercises.pptx
Exercises.pptx
 
Project Management.pdf
Project Management.pdfProject Management.pdf
Project Management.pdf
 
6S Introduction.pdf
6S Introduction.pdf6S Introduction.pdf
6S Introduction.pdf
 

Recently uploaded

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 

Corrective Action_.pptx

  • 1. BAE SYSTEMS Process Audit Report 21-Jun-2022
  • 2. Audit Observations on 17-Nov-2021 1. Risk assessment – For all RFQ & Contracted projects, which covers all the aspects of the project 2. Capacity Analysis – Capacity assessment which includes current and future projects. 3. QA Manpower 4. Q2Q Workload Plan 5. Oursys ERP Implementation – (BOM creation, Process Layouts, Machining sequences) 6. Things Went Right / Things Gone Wrong – Lessons learned from Previous projects 7. KPI for all departments / Review on quarterly basis 8. For HSE/OSHAS – ISO 14001/45001 – Consultant status 9. Contract Requirements Flow down 10. International Standards Requirements 11. OEE & Daily Morning Meetings 12. Additional Lifting Equipment’s added.
  • 3. • Summary of Audit Observations: 1. Number of Non-Conformances identified count 8 2. Number of Action Points count 23 3. Number of Action NC / Points Implemented count 24 4. Balance to be implemented count 7 5. Out of balance 7, 3 Points are ERP Implementation 6. 2 Points are HSE / OSHAS Implementation 7. 2 Points are Quality manager & Purchase Manager recruitment.
  • 4. BAE Audit Score @ Aug-2021
  • 5. Self Audit Score @ Jan-2022
  • 6. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 1.1 Supplier to give details of quality approvals held (i.e. ISO 9001, AQAP etc.). Does the scope of certification approval (ISO, AQAP etc.) cover the requirements of the product or service being purchased? Risk and Capability assessment has not performed at RFQ stage Risk and Capacity assessment to be performed for all projects at RFQ stage Closed PMO not established to avoid delays in delivery of POs Dedicated PMO to be established- Aerospace domain experience to be hired Sep 2022 HR Open Risk Assessment Risk Planning Evidences for closure
  • 7. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 1.2 Is there a clear Quality focus (Quality Manager) for the business and is the position identified on an organisational chart? Inadequate team strength in QA dept. Adequate team members filled in QA dept. to perform QC, QA and SQA activities. QA Manager also appointed Closed Ref. # Process Findings / Observations Counter Measures ECD ACD Owner Status 1.3 Supplier to demonstrate the process of how purchase orders raised on sub-contractors to flow down customer requirements + are regular audits conducted with the sub contractors? Evidence not found for Procurement SOP- Bought out parts, Raw material, Machined Parts, Special Process The followings will be enhanced, Annexure for PO Terms and Conditions Supplier Questionnaire Supplier Registration Supplier Evaluation and Approval Supplier Performance Rating Closed Approved supplier list is not updated with supplier details for BAE projects, like Dollinger, Gallagher, Fluitek, etc. Needs to be updated Approved Suppliers List Closed Supplier Questionaire Supplier Registration Supplier Evaluation Supplier Rating List of approved Suppliers
  • 8. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 1.5 Supplier to demonstrate how purchased / sub-contract items are verified as meeting requirements prior to use (First Article Inspection -FAI) 1) Corrective actions to be taken for recovery in the delivery timelines for existing projects. 2)Preventive actions to avoid such delays in future projects 3)Q2Q to submit detailed report on "Lessons learned" during implementation of the current projects TGR/TGW format available and made sample for Header Tank projects, it was reviewed and approved.(Refer to next slide for evidence) Closed Further the same will be deployed for all projects, and we will submit to BAE team for review. Closed 1.7 Supplier has robust processes adopted to ensure the implementation and verification of cause and corrective actions? SQE Appointed for all outside process & items inspection / verification Closed For AHS Racks root cause analysis to be done for delay, and Welding process improvement plan to be shared with BAE. Closed Welding Improvements
  • 9. Improvements: • We make TGR, TGW for existing projects and in future this will be incorporated with BAE-SCM sheet for weekly review. • For the KPI- Each departments will be evaluated based on KPI – Performance data on quarterly basis. Quality Focus
  • 10. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 2.1, 2.3, 2.5, 2.7 Has the supplier identified in the organisation structure a senior manager responsible for EHS? No authorized personnel found for EHS lead Obtained EHS lead closed ISO 14001 & 45001 certification not found ISO 14001 & 45001 certification readiness on progress Consultant fixed Dec 2022 3.4 International Traffic in Arms Regulations (ITAR) - Does the supplier have a process in place to manage export /Import Compliance including but not limited to the International Traffic in Arms Regulations? Evidences not found for the followings, a) Procedure related to export control document handling b) No training records for new & existing employees c) Internal audit related to Export control compliances SOP, Training, Internal Audit plan needs to be implemented Sep 2022 3.5 Ethics - Does the supplier have a code of conduct with ethical principles and standards regarding the prevention of bribery and corruption i.e. prohibition of corrupt practices, policy on facilitation payments, political donations and gifts and hospitality including sanctions for non-compliance? Ethics and code of conduct not found Training to be provided for existing employees Henceforth new employee will obtain the training in day one itself Closed
  • 11. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 3.7 Sustainable Development (SD) - Does the supplier understand the concept of sustainability relating to the maintenance and enhancement of environmental, social and economic resources, in order to meet the need of current and future generations? SOP not found for sustainable development of EHS Consultant fixed for preparing documents and policies for ISO14001, 45001 Dec 2022 QA Open Training will be provided to all employees Dec 2022 QA Open 3.8 Business Continuity Management (BCM) - Does the supplier have business continuity contingency, or major incident recovery plans in place to ensure contracted BAE Systems deliveries are maintained? Succession plans not found to ensure Business Continuity Succession plan to be made for all critical functions Sep 2022 PPC/PMO Open Not found Business continuity plan Business Continuity plan to be made for critical functions and equipment’s Sep 2022 PPC/PMO Open 3.9 Lean Manufacturing - Does the supplier adopt lean manufacturing, such as process mapping, 5S workplace organisation, 7 wastes, root cause analysis etc ? TPM in the organization to ensure equipment run-time to meet the production requirements. Training to be provided to all the employees and training records to be maintained Closed 4.9 Does the supplier measure of production line efficiency and manage capacity planning? OEE is not being monitored 1) OEE monitored and reported to management on monthly basis and displayed in Production area 2) - OEE for May 2022- need to add next slide. Closed
  • 12.
  • 13. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 4.10 Does the supplier have production issue boards (4M), how regular are meetings attended around the boards and what are the outputs? 1) No monitoring of action items evident & list of attendees. No objective evidence for review happening with top leadership. 1)No monitoring of action items evident & list of attendees. No objective evidence for review happening with top leadership. closed 4.1 Does the supplier hold a company organisation chart? 1) Project Management as function not included in Org. chart. No dedicated Project Manager. 2) Organization Structure to be strengthened as multiple positions are vacant. 1)Project Management as function to be included in Org. chart. Dedicated Project Manager to be deputed. 2Project Manager will be appointed soon- Interview process on going Closed 1)Organization Structure to be strengthened as multiple positions are vacant. 2)Hiring process Plan Made. HR closely working on it to fill all open positions 4.4,6.1 2,6.2 Does the supplier have a documented contract review process, including risk mitigation plans identified and in place prior to contract award? No ERP or SAP system being followed. 1) Oursys ERP- Implementation process is in progress. 2)All team members working for the documents input to the ERP. From Aug’2022 ERP will go live. Closed 1)All machine details, instruments details will be uploaded in ERP, which will trigger us periodic maintenance, calibration based on the frequency what we set during creation of data. WIP
  • 14.
  • 16. • Manpower Allocation & Open Positions DEPARTMENT No. of Employees To be added D. O. Joinng Production 21 1 Offer released Manufacturing Engg. 6 0 Quality Control 5 2 9th May 2022 & Yet to finalize Finishing & Deburring 4 0 Welding 3 0 PPC 2 1 To be recruit Tool Room 2 0 Accounts 1 0 Assembly 1 1 Finished Goods & Logistics 2 0 Human Resources 1 1 Before 15th April 2022 Director - Operations 1 0 PMO 0 1 Interview done, yet to confirm the Joining date Purchase 0 2 15th April 2022 &Yet to finalize Grand Total 49 8
  • 17. Before: After: • No ERP • Oursys ERP finalized – To be start from Mid of Mar’ 2022. ERP
  • 18. Ref. # Process Findings / Observations Counter Measures ECD ACD Resp. Status 4.6 Does the supplier have a documented contract review process, including risk mitigation plans identified and in place prior to contract award? 1)Checklist being followed is generic & doesn't include critical aspects viz. Hardware parts procurement, Special process etc. Contract review happening at RFQ stage not after contract release. 1)Checklist to be reviewed to include all critical aspects viz. Hardware parts procurement, Special process etc. 2) Mechanism to be developed for Contract review after contract release. closed 2) Risk register to be strengthened viz. RM delay issue should be identified as risk for on-time delivery 1)Now we made new format to cover all the aspects for Risks and contract review for all RFQ packages and received Projects we analysed the risk and Mitigation actions taken. 4.7 Does the supplier have access to any databases to get copies of both national and international standards to support the manufacturing processes? 1) Q2Q is not having any subscription. No Master list of national & international standards evident. 2)No mechanism demonstrated to ensure latest standards being followed. Directly procured or download various standards on the respective websites. Closed 4.12 How does the supplier flow down critical - contractual requirements fed down to the internal production line (manufacturing instruction - route card) to ensure compliance during manufacturing processing? No evidence demonstrated for Hydrostatic testing requirements not flowed down to production line for Header tank. 1)Current product MO and setup sheets to be revisited to ensure that all the critical and contractual requirements- Currently it is done by making process flow chart and Manufacturing build book. closed 4.13 Are all sub-contractors approved, effectively managed and audited on a regular basis by the supplier, also has the supplier a control plan in place to flow down critical - contractual requirements to his external sub contractors to ensure compliance during the sub contracted manufacturing processing? Mechanism to strengthen to flow down customer requirements to sub- contractors. 1)Currently, Contract requirements are being shared to special process suppliers by Annexure to PO, which covers SP Matrix, Masking drawing. 2)From May’2022 all PO requirements will be captured and flow down thru ERP. 3)For raw material, drawing requirements and standard requirements to be send to RM suppliers with PO. Closed
  • 20. Improvements: • Current Router format revised to cover complete process flow to include PO & Special requirements. . • For Special Process Suppliers along with PO’s we are issuing Special Process matrix and Masking drawings. Contract Requirements Flow down
  • 21. Ref. # Process Findings / Observations Counter Measures ECD ACD Gap (In days) Owner Status 5.10 Has the supplier facility sufficient lifting and handing capability (overhead crane or forklift truck(s))? 1)Some large parts were placed on foam sheets and wooden pallets on floors. Trolleys to be designed for handling parts during APQP stage. 1)Contract study report will capture Material Handling requirements. 2)Format revised to capture and cover all requirements during RFQ stage itself. closed