5. Station capital value : 1.000.000.000
Capital Cost of Civil Works : 200.000.000
Total Cost of Remedial Works: 165.000.000
Cost of Civil Remedial Works : 30.000.000
Remedial works duration : 2 years
Civil Works substantial completion : 18 months
WHAT HAS BEEN ACHIEVED
6. Multi Contract Approach
Number of Contracts : Around 430
Number of Civil Works Contracts : Around 30
WHAT HAS BEEN ACHIEVED
7. Key Decision 1 : Engineering team made up of
Engineers that have worked on power station
Key Decision 2 : Use contractors that have
worked on EAC stations before
Key Decision 3 : Identify priority Buildings and
follow staged approach to remedy damage
Key Decision 4 : Size contracts to manageable
quantum awarding directly to multiple
specialized contractors
Strategy
8. Key Decision 5 : Order long lead materials directly
and make these available to contractors -cladding
Key Decision 6 : Innovative solutions to weather
seal buildings fast
Key Decision 7 : Innovative solutions for speed as
well as improved performance
Key Decision 8 : Rectify to extent possible damaged
steel to reduce delays in steel delivery
Strategy
14. Lesson 1: Imperative for organizations to
develop and preserve their know-how
Lesson 2: Contract strategies need to be
formulated depending on project needs. Multi
contract approach prooves valuable to achieve
results
Lesson 3 : A solution to a complex problem is
made up of small simple steps.
Lessons learned