BEMIDJI GUARANTEED ENERGY
SAVINGS PROGRAM (GESP)
Mayor Rita C. Albrecht
GESP
GUARANTEED
ENERGY
SAVING
PROGRAM
What is GESP?
• Guaranteed Energy Saving Project leverages
energy and operational savings to finance
building retrofits and renewal projects
• Written guarantee from contractor for
savings to pay annual financing
• If savings not met, contractor will reimburse
the shortfall
How did we get started?
Received a
cold call from
Honeywell
• 9 Buildings were
evaluated
The Sanford Center
Public Library--1980s vintage
Public Works Building
Waste Water Treatment--2 buildings
Ice Arena--Oldest structure
City Hall built in 1970s
How did we get started?
• Also included fire hall and law enforcement
center
• Honeywell determined potential projects and
estimated energy savings
• Presented the information to city council
How did we get started?
• Staff contacted other government entities
who had gone through the process
• Staff contacted the Dept. of Commerce for
information about GESP
• Council decided to use the GESP process
• City advertised a request for proposals
• Chose Honeywell as contractor for the
project
Project Scope
• $2.5 million in
approved projects
• 9 different City
owned buildings
Project examples
• Interior building
lighting
improvements -
$231K
• Building envelope
sealing –
windows/doors
caulking
Project examples
• Energy system
control
improvements
• Mechanical (HVAC)
system
upgrades/replaceme
nts - $550K
Project examples
• Exterior street
lighting upgrades to
LED - $1.2 million
Estimated Savings
• Annual Energy Savings generated $99,000
• Annual operations and Maintenance savings
$21,000
• One time utility rebates $122,000
Streetlight retrofit
• 1,014 Streetlight LED change-
out
• Engineer’s estimate $906,000
• Bids came in at $583,000
• Project will be completed April-
September 2015
Streetlight retrofit
• Estimated utility savings of
$70,000/year
• Significant annual cost
savings on maintenance
and repair (20 year bulb
life)
• Payback of approximately
7-8 years
Challenges
Challenges of GESP
• Initial project with City our size and for
Honeywell
• Time delays to get to construction phase to
follow GESP process
• Some glitches in project financing – required
financing over 20 years vs. 15 years
• Not all projects were selected due to long
payback periods
Benefits
• Streamlined process
for selection and
implementation of
program
• Competitive bidding
among prequalified
energy companies
• Minimized work load
on City staff; no
energy experts on
staff
• Accelerated timeline to
implement projects
• Majority of projects
paid for with energy
savings over period of
time
• All bidding and
contracting is
completed by
Honeywell
Benefits
Project recap
• $2.5 million in approved projects
• 9 different City owned buildings
• Annual energy savings generated
$99,000
• Annual operations and maintenance savings
$21,000
• One time utility rebates
$122,000
Rita C. Albrecht, Bemidji Mayor

Bemidji Guaranteed Energy Savings Program

  • 1.
    BEMIDJI GUARANTEED ENERGY SAVINGSPROGRAM (GESP) Mayor Rita C. Albrecht
  • 2.
  • 4.
    What is GESP? •Guaranteed Energy Saving Project leverages energy and operational savings to finance building retrofits and renewal projects • Written guarantee from contractor for savings to pay annual financing • If savings not met, contractor will reimburse the shortfall
  • 5.
    How did weget started? Received a cold call from Honeywell
  • 6.
    • 9 Buildingswere evaluated
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
    How did weget started? • Also included fire hall and law enforcement center • Honeywell determined potential projects and estimated energy savings • Presented the information to city council
  • 14.
    How did weget started? • Staff contacted other government entities who had gone through the process • Staff contacted the Dept. of Commerce for information about GESP • Council decided to use the GESP process • City advertised a request for proposals • Chose Honeywell as contractor for the project
  • 15.
    Project Scope • $2.5million in approved projects • 9 different City owned buildings
  • 16.
    Project examples • Interiorbuilding lighting improvements - $231K • Building envelope sealing – windows/doors caulking
  • 17.
    Project examples • Energysystem control improvements • Mechanical (HVAC) system upgrades/replaceme nts - $550K
  • 18.
    Project examples • Exteriorstreet lighting upgrades to LED - $1.2 million
  • 19.
    Estimated Savings • AnnualEnergy Savings generated $99,000 • Annual operations and Maintenance savings $21,000 • One time utility rebates $122,000
  • 20.
    Streetlight retrofit • 1,014Streetlight LED change- out • Engineer’s estimate $906,000 • Bids came in at $583,000 • Project will be completed April- September 2015
  • 21.
    Streetlight retrofit • Estimatedutility savings of $70,000/year • Significant annual cost savings on maintenance and repair (20 year bulb life) • Payback of approximately 7-8 years
  • 22.
  • 23.
    Challenges of GESP •Initial project with City our size and for Honeywell • Time delays to get to construction phase to follow GESP process • Some glitches in project financing – required financing over 20 years vs. 15 years • Not all projects were selected due to long payback periods
  • 24.
    Benefits • Streamlined process forselection and implementation of program • Competitive bidding among prequalified energy companies • Minimized work load on City staff; no energy experts on staff
  • 25.
    • Accelerated timelineto implement projects • Majority of projects paid for with energy savings over period of time • All bidding and contracting is completed by Honeywell Benefits
  • 26.
    Project recap • $2.5million in approved projects • 9 different City owned buildings • Annual energy savings generated $99,000 • Annual operations and maintenance savings $21,000 • One time utility rebates $122,000
  • 27.
    Rita C. Albrecht,Bemidji Mayor