3. DATE FORMATING
Date shall be written as DD/MM/YY
format:
Where:
“DD” : Represents the Date.
“/” : Represents Separator.
“MM” : Represents the Month.
“YY” : Represents the Year.
4. DATE FORMATING
For Example: 01/12/18,
01 shall represent Date,
12 shall represent the Month and
18 shall represent the last two digits of the
current Calendar Year
6. TIME FORMATING
Time Entry shall be done in all Documents as
Twenty Four Hours Clock.
For Example: 1:40 PM shall be written as
13:40, 12:00 Midnight shall be written as
00:00 and 12:00 Noon shall be written as
12:00.
7. DOCUMENT ENTRIES
All Department, recording / signing the
documents / records shall use a ball point pen in
Blue ink.
IPQA in-process check shall be recorded with
ball point pen in Black ink.
Signing of all master documents shall be done
with ball point pen in blue ink.
Never use the symbol such as “–do-” for
repeated observations.
8. DOCUMENT ENTRIES
If any wrong entry made in documents:
For Example: If space available within the line then
01/12/18
01/12/2018 and shall put remark wrong entry rectified
with signature and date.
If space not available within the line then:
01/12/18
01/12/2018* and shall put where space is available *
wrong entry rectified with sort signature and date
9. DOCUMENT ENTRIES
Do not over write any data and do
not leave blank in process sheet,
batch manufacturing records,
logbooks and laboratory logbooks.
If, any page/column is not used,
draw line from left to right
diagonally and put remark as NA
(Not Applicable) with sign/date.
15. DOCUMENT ENTRIES
Corrective fluid (white ink) or erasable
pens should not be used to correct the
original information.
Master documents shall not be
stapled.
16. Verification of Data, Information, Calculations andTasks
Verification of data, information, calculations or
tasks performed by another person means the
verifier shall independently determine that the
data, information, calculations, or tasks are
accurate and correct. For example-when a
calculation is being verified, the verifier shall
repeat the calculation before signing off it.
When a performance of a task is being verified,
the verifier shall witness the task being
performed.
17. Verification of Data, Information, Calculations andTasks
When data is being verified, the verifier
shall witness the display or printout of
the instrument providing the data.
The entire format shall be filled by
concerned department officer/executive
and shall be verified by department head
or as written on the format.
18. Attachments, Printouts andCharts
Identify all printouts, charts attachments that
are used to support an analytical record or
process with the applicable batch number,
time, and date and operator initial.
Confirm that there is enough ink supply for all
print out and chart devices to make the
printout easily readable.
Print outs need to be continuous and if broken
there needs to be an explanation included.
19. Ratification
• Ratification shall be made in the master
document for errors identified during
final review or during operational use.
If there are any minor corrections like
typographical errors, then the concerned
department personnel shall raise the
‘Request for Document Ratification”
20. Ratification
• The request shall be justified by concern
HOD and shall be forwarded to QA
Head or designee for evaluation and
approval.
• The indicated ratification shall be made
in the soft copy after approval by QA
Head and shall be implemented on
upcoming revision of master document.