SlideShare a Scribd company logo
1 of 8
Download to read offline
Humboldt Bay Civil Works Project 
November 2015 
Program Manager:  
Pete Cou s 
HBPP Civil Works Cri cal Path 
2015 2016 2017 2018
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Refueling Bldg Phase 1  
CSM Wall Installa on 
Ini al Caission Dewatering 
Caisson Removal Phase 1 
Ac vated Drywell Region 
Caisson Removal 
Phase2 
Treme Removal & 
Caisson FSS 
Caisson Backfill 
Site Restora on 
Project Complete 
Cri cal Ac vity 
Baseline Ac vity 
 
 
Project Summary 
“The flexibility of the Cutter Soil Mix 
(CSM) approach allowed us a safe 
and effective means to successfully 
execute our plans to remove the 
caisson and demolish adjacent 
structures.” 
 
     ‐ John Gilbert, Project Manager 
Since July of 2013 CB&I has been engaged in the decommissioning, 
demoli on and final site closure of Pacific Gas and Electric’s (PG&E) 
Humboldt Bay Unit 3 Nuclear Power Plant (HBPP), an inac ve nu-
clear boiling water reactor located on the eastern shore of Hum-
boldt Bay in northwestern California.  
Significant challenges have been faced since mobiliza on of the 
CB&I Civil Works Team. These include HBPP’s original design and 
construc on and its close proximity to the bay and associated  dal 
interac ons which posed unique challenges to an effec ve decom-
missioning effort. 
On March of 2015 an Over Target Baseline (OTB) was approved 
which incorporated a solu on to the biggest challenge the project 
was facing—removal of the approximately 60’ diameter by 80’ 
deep caisson structure adjacent to the Pacific Ocean that posed sig-
nificant safety and groundwater control challenges. The solu on— 
using Cu er Soil Mix (CSM) technology and a one-of-kind, custom-
built CSM piece of equipment to install one of the largest and deep-
est CSM deep shoring and water-cutoff systems ever employed.  
   
Project Summary 
Safety 
Safety 
SAFETY  IS ALWAYS THE #1 PRIORITY 
Commenced on July 23rd, 2013 the Humboldt Bay Civil Works De-
commissioning Team has maintained a Zero Recordable Safety Rec-
ord. With over 670,000 hours worked since incep on and over 1000 
safe work days the project con nues to make Safety the #1 priority.  
 
 
 
 
 
CB&I maintains a Zero Incident Philosophy and u lizes the I CARE 
process to Observe At Risk Behaviors and Condi ons to prevent inci-
dents from occurring.  
The HBPP Project con nues to be singled out among all projects 
within PG&E for their outstanding safety achievements. 
Among the 2015 Achievements CB&I was awarded the most pres g-
ious safety award in the country, the Na onal Safety Council’s Green 
Cross for Safety medal. The HBPP Team was also awarded PG&E’s 
highest safety award, The Shermer L. Sibley Safety and Health 
Award. 
Zero Recordables 
Zero Medical Treatments 
Zero Lost Time Incidents 
“The footprint is small. Large construction equipment, 
concurrent demo operations, and first of a kind demo 
applications makes it imperative the project continually 
makes Safety the # 1 priority.” 
     ‐ Pete Coutts, CB&I Civil Works Program Manager 
Apr 10—Low Level Waste Storage Building 
Removal 
Apr 28—SAS Bldg Demo Completed  
May 11—Pre Trench North Yard Substruc-
tures Demo Complete 
Jun 8 — Completed 50% of Discharge Canal  
Jun 11—Drain Spent Fuel Pool Completed 
Jul 22 Discharge Canal—PG&E/NRC Final 
FSS Complete  
Aug 4—Liquid Radwaste Bldg Demoli on  
Sept 23—PGE License Amendment Request 
for RFB Open Air Demo  
Oct 6—RRB for Open Air Demo Approval  
Oct 9—Install Sec on 1 CSM Cut Off Wall 
Complete 
Oct 15—Remove Main Plant Exhaust Fan—
Above Grade, Underground and Backfill  
Nov 3—Temporary Backfill  of Spent Fuel 
Pool  
2015 Accomplishments 
Execu on Accomplishments 
2015 was a successful year for HBPP. All major milestones were 
achieved and include: 
Execu on 
 Comple on of Reactor Pressure Vessel Segmenta on and 
Removal 
 Demoli on of Liquid Radwaste Bldg to Grade 
 Started Cu er Soil Mix Wall Construc on 
 HBPP #3 Refueling Building systems and components re-
moval achieved Open Air Demoli on Status 
 Implementa on of Earned Value Management System  
 Completed 50% of Discharge Canal Remedia on 
 Reduc on of RCA to support RFB Open Air Demoli on 
 
Adding to these accomplishments, the project has managed over 
135 million pounds of material including contaminated waste, re-
use material, and backfill. To date the project has shipped over 
1,000 containers of contaminated waste without viola on. 
Jan 25 —Install Sec on 2 of CSM Cutoff 
Wall 
Feb 15 — Demo Low Level Waste Bldg 
Mar 16 — Refueling Bldg Demo Complete 
Mar 16  —Demo Concrete Stack Slab to 
ELev +12 
Mar 31— Turbine Bldg Demo and Ancillary 
Infrastructure Projects  
Apr 11—Demo High Level Storage Vault 
Apr 12 — Turbine Bldg Phase 2 Complete 
Apr 21 —CSM Outer Cutoff Wall Complete 
May 9 —Oily Water Separator Area Backfill  
May 19 —Demo Solid Rad Waste Bldg 
Complete  
Jun 21  —Install CSM shoring System Sec-
on 3 
 Jul 14 —CSM Wall Installa on Complete 
Sep 23—Start Caisson Removal 
Dec 20 —Intake Canal Complete 
2016 Forecasted Accomplishments 
Looking Forward 
2016 and beyond will be challenging and exci ng for HBPP.  The 
Cu er Soil Mix Deep Shoring Structure and Water Cut Off System 
(CSM) is expected to be complete by July 2016.  When finished, the 
CSM Shoring structure will be 110 feet in diameter and approxi-
mately 90 feet deep in-situ, surrounding the caisson structure with 
the outside ring (water cut off wall ) extending to a depth of 174-
feet effec vely cu ng off groundwater flow.  In order to reach a 
depth of 174-feet, a one of a kind specialty CSM drill rig was con-
structed in Germany by Bauer Equipment and shipped to the HBPP 
site.  Prior to excava on, the interior of the CSM Structure will be 
dewatered then CB&I will excavate the caisson structure from with-
in u lizing conven onal excava on methods.  The complete exca-
va on process is expected to complete in January of 2018. 
   
Execu on 
“The deep aquifers are a significant site challenge. Identi‐
fying early that the site geology was conducive to the use 
of CSM technology allowed us to consider the CSM ap‐
proach for both excavation support and the control of 
subsurface water.” 
                   ‐ Alan Brown PE, CSM Project Engineer 
Forecast Spend 
Performance 
The HBPP Civil Works Team has implemented an Earned Value 
Management System to objec vely and succinctly iden fy project 
execu on vs baseline. Performance is measured at Level IV of the 
WBS enabling the  project to maximize visibility of performance at 
the work package level. The project  underwent a bo oms-up ac v-
ity based es mate providing a high accuracy Es mate at Complete. 
The project is currently forecasted to complete 9 months ahead of 
the Contract Comple on date.  
Performance 
Progress Chart 
$13 
$24 
$15 
$9 
$12 
$7 $8 $7 $6 $6 
$7 
$10 
$0
$5
$10
$15
$20
$25
4Q2015
1Q2016
2Q2016
3Q2016
4Q2016
1Q2017
2Q2017
3Q2017
4Q2017
1Q2018
2Q2018
3Q2018
Millions
EAC  $205.8M 
% Complete  46% 
Forecast 
Complete 
Sept 10th, 
2018 
Project Stats 
Engineering  61% 
Construc on  40% 
Waste  45% 
  
Jan‐
15 
Feb‐
15 
Mar‐
15 
Apr‐
15 
May‐
15 
Jun‐
15 
Jul‐
15 
Aug‐
15 
Sep‐
15 
Oct‐
15 
CPI  1.01  1.00  1.00  1.00  0.98  0.99  0.98  0.97  0.99  0.98 
SPI  1.00  1.00  1.01  1.02  1.01  1.01  0.99  0.97  1.00  0.99 
Historical Cumula ve Performance Indices 
“The EVM system put in place on this project has provided the 
Team the tools necessary to effectively manage cost, schedule, 
change and risk. Since implementation of EVM the project has 
seen a major improvement in managerial control equating to sig‐
nificant cost avoidance and schedule savings.”  
    ‐ Shane Richardson, Project Controls Manager 
Humboldt Bay Civil Works Project 
1000 King Salmon 
Eureka, CA 95503 
www.CBI.com 
CB&ITM
  a world of Solu onsTM
 

More Related Content

What's hot

GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
Recycling and Resource Management Division
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Crosstown TO
 
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
Jason Brabec, PE, CFM
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Recycling and Resource Management Division
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.
FelixGao
 
Rick Guenther Jr Resume
Rick Guenther Jr ResumeRick Guenther Jr Resume
Rick Guenther Jr Resume
Rick Guenther
 
Hengistbury Head Phase II Development
Hengistbury Head Phase II Development Hengistbury Head Phase II Development
Hengistbury Head Phase II Development
Joshua Brunsdon
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Crosstown TO
 

What's hot (20)

Stevens_CV_2016
Stevens_CV_2016Stevens_CV_2016
Stevens_CV_2016
 
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
 
Denault_resume_2015b
Denault_resume_2015bDenault_resume_2015b
Denault_resume_2015b
 
A Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River DiversionA Tunnel Under Geylang River, The Story of Geylang River Diversion
A Tunnel Under Geylang River, The Story of Geylang River Diversion
 
Pierce County Upper Nisqually Protection & Stabilization Project
Pierce County Upper Nisqually Protection & Stabilization ProjectPierce County Upper Nisqually Protection & Stabilization Project
Pierce County Upper Nisqually Protection & Stabilization Project
 
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
 
Gude landfill remediation 161019
Gude landfill remediation 161019Gude landfill remediation 161019
Gude landfill remediation 161019
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
James River Project Update for the James River Partnership XVII
James River Project Update for the James River Partnership XVIIJames River Project Update for the James River Partnership XVII
James River Project Update for the James River Partnership XVII
 
Gude Landfill Remediation update
Gude Landfill Remediation updateGude Landfill Remediation update
Gude Landfill Remediation update
 
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)2016 FMA-presentation-Collaborateve FRR Projects (REV8)
2016 FMA-presentation-Collaborateve FRR Projects (REV8)
 
Kaigah Hydropower Project
Kaigah Hydropower ProjectKaigah Hydropower Project
Kaigah Hydropower Project
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspects
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.
 
Rick Guenther Jr Resume
Rick Guenther Jr ResumeRick Guenther Jr Resume
Rick Guenther Jr Resume
 
Hengistbury Head Phase II Development
Hengistbury Head Phase II Development Hengistbury Head Phase II Development
Hengistbury Head Phase II Development
 
20140414_FISH_FinalPresentation
20140414_FISH_FinalPresentation20140414_FISH_FinalPresentation
20140414_FISH_FinalPresentation
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
 

Viewers also liked

Coursera_CloudNetworking
Coursera_CloudNetworkingCoursera_CloudNetworking
Coursera_CloudNetworking
Santanu Ganguly
 
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital ProgramsCertificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
Maribel de la Vega
 
Diploma in Supply Chain Management
Diploma in Supply Chain ManagementDiploma in Supply Chain Management
Diploma in Supply Chain Management
Chanika Dias
 

Viewers also liked (11)

Iman kepada kitab kitab allah
Iman kepada kitab kitab allahIman kepada kitab kitab allah
Iman kepada kitab kitab allah
 
Coursera_CloudNetworking
Coursera_CloudNetworkingCoursera_CloudNetworking
Coursera_CloudNetworking
 
Sholat sunnah
Sholat sunnahSholat sunnah
Sholat sunnah
 
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital ProgramsCertificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
Certificado MITProfessionalX IOTx _ MIT Professional Education Digital Programs
 
Diploma in Supply Chain Management
Diploma in Supply Chain ManagementDiploma in Supply Chain Management
Diploma in Supply Chain Management
 
Ch 6 managing customer profitability
Ch 6 managing customer profitabilityCh 6 managing customer profitability
Ch 6 managing customer profitability
 
موهبة
موهبةموهبة
موهبة
 
SIEM - Activating Defense through Response by Ankur Vats
SIEM - Activating Defense through Response by Ankur VatsSIEM - Activating Defense through Response by Ankur Vats
SIEM - Activating Defense through Response by Ankur Vats
 
English Speaking Club: 2/17 Clarifying Opinions
English Speaking Club: 2/17 Clarifying OpinionsEnglish Speaking Club: 2/17 Clarifying Opinions
English Speaking Club: 2/17 Clarifying Opinions
 
Fjord Trends 2016 (German)
Fjord Trends 2016 (German)Fjord Trends 2016 (German)
Fjord Trends 2016 (German)
 
Handbook of formulae and constants
Handbook of formulae and constantsHandbook of formulae and constants
Handbook of formulae and constants
 

Similar to The rise of the Nuclear Decontamination and Decommissioning industry

Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project Director
Fabien Deschamps
 
Oxley Creek Publication
Oxley Creek PublicationOxley Creek Publication
Oxley Creek Publication
Olivia Newman
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015
Dave Hoover
 
CV_WeifnegLi_2016
CV_WeifnegLi_2016CV_WeifnegLi_2016
CV_WeifnegLi_2016
Weifeng Li
 
K5 4 Wells Portal Success Story
K5 4 Wells Portal Success StoryK5 4 Wells Portal Success Story
K5 4 Wells Portal Success Story
Daljit Brar
 
AGC Corporate Fact Sheet 151026
AGC Corporate Fact Sheet 151026AGC Corporate Fact Sheet 151026
AGC Corporate Fact Sheet 151026
Ann-Marie Pamplin
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx complete
Tj Dickey
 

Similar to The rise of the Nuclear Decontamination and Decommissioning industry (20)

Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project Director
 
Highbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW ApplicationHighbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW Application
 
Oxley Creek Publication
Oxley Creek PublicationOxley Creek Publication
Oxley Creek Publication
 
Winter 2012 Newsletter
Winter 2012 NewsletterWinter 2012 Newsletter
Winter 2012 Newsletter
 
Bull Neck Run at Spring Hill Recreation Center Stream Restoration
Bull Neck Run at Spring Hill Recreation Center Stream RestorationBull Neck Run at Spring Hill Recreation Center Stream Restoration
Bull Neck Run at Spring Hill Recreation Center Stream Restoration
 
Final Design Report
Final Design ReportFinal Design Report
Final Design Report
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015
 
Item #12 ppt Judson Nature Trail Building
Item #12   ppt Judson Nature Trail BuildingItem #12   ppt Judson Nature Trail Building
Item #12 ppt Judson Nature Trail Building
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Merrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation ProjectMerrywood Force Main Rehabilitation Project
Merrywood Force Main Rehabilitation Project
 
CV_WeifnegLi_2016
CV_WeifnegLi_2016CV_WeifnegLi_2016
CV_WeifnegLi_2016
 
K5 4 Wells Portal Success Story
K5 4 Wells Portal Success StoryK5 4 Wells Portal Success Story
K5 4 Wells Portal Success Story
 
AGC Corporate Fact Sheet 151026
AGC Corporate Fact Sheet 151026AGC Corporate Fact Sheet 151026
AGC Corporate Fact Sheet 151026
 
TJ Dickey Resume.docx complete
TJ Dickey Resume.docx completeTJ Dickey Resume.docx complete
TJ Dickey Resume.docx complete
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project Completion
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

The rise of the Nuclear Decontamination and Decommissioning industry