SlideShare a Scribd company logo
1 of 23
COMPARATIVE ASSESSMENT OF VARIOUS
EVACUATION STRATEGIES FOR HIGH–RISE BUILDINGS
Presented by
ARVINTH KUMAR S (120001010)
SATISH V (120001087)
VADDI VIKRAMA NARASIMHA (120001106)
Project Guide
G.I GUNARANI
Assistant Professor III
School of Civil Engineering
SASTRA Deemed to be University
SECOND REVIEW MEETING6/6/2020 1
SCHOOL OF CIVIL ENGINEERING
SECOND REVIEW MEETING
OBJECTIVES
6/6/2020 2
 To identify various strategies for evacuation of High Rise building and to
model these in people evacuation software- Pathfinder
 Assess the performance of each based on the Total Evacuation Time
 Analyse the benefits of each strategy
 Suggest appropriate improvements to the architectural plan pertaining to
the sufficiency of evacuation
SECOND REVIEW MEETING
METHODOLOGY- MODEL CREATION
6/6/2020 3
Fig depicting
evacuation strategy
using staircase only
Fig depicting
evacuation strategy
using staircase and lift
SECOND REVIEW MEETING
METHODOLOGY- MODEL CREATION
6/6/2020 4
Fig depicting
evacuation strategy
using staircase and
phased evacuation
Fig depicting
evacuation strategy
using staircase, lift and
phased evacuation
SECOND REVIEW MEETING
METHODOLOGY
Total Evacuation
6/6/2020 5
Building
on fire
Alert
Others
Keep
Family
Close
Group Evacuation
Sketch of Selected Evacuation Mode in Building
Family Teamwork Mode
SECOND REVIEW MEETING
METHODOLOGY
Phased Evacuation
6/6/2020 6
SECOND REVIEW MEETING
EVACUATION SCHEDULE
6/6/2020 7
Chart depicting scheduling algorithm based on the zone priorities
Red Zone: Critical and First Preference
Green Zone: Second Preference
Blue Zone: Third Preference
SECOND REVIEW MEETING
BASELINE SIMULATION
6/6/2020 8
Chart depicting algorithm for finding out the
base delay
SECOND REVIEW MEETING
DELAY FROM SIMULATION
6/6/2020 9
Chart depicting delay finding algorithm based on the zone
priorities
Red Zone: Critical and First Preference
Green Zone: Second Preference
Blue Zone: Third Preference
SECOND REVIEW MEETING
WORKS DONE
6/6/2020 10
8 8
7 7
6 6
5 5
4 4
3 3
2 2
1 1
FIRST FLOOR
8 1
7 2
6 3
5 4
4 5
3 6
2 7
1 8
EIGHTH FLOOR
Chart depicting evacuation schedule for three floors of
the building under study
SECOND REVIEW MEETING
WORKS DONE
6/6/2020 11
8 90
7 80
6 70
5 50
4 40
3 20
2 10
1 0
FIRST FLOOR
8 0
7 50
6 110
5 170
4 40
3 20
2 10
1 0
EIGHTHFLOOR
Chart depicting delay chart for extreme floors of
the building under study
SECOND REVIEW MEETING
WORKS DONE
6/6/2020 12
Chart depicting delay chart for fourth floor of the
building under study
8 50
7 40
6 20
5 10
4 0
3 70
2 10
1 0
FOURTH FLOOR
SECOND REVIEW MEETING
RESULT
6/6/2020 13
1 2 3 4 5 6 7 8
1 0 10 20 40 50 70 80 90
2 0 0 10 20 40 50 70 80
3 0 60 0 10 20 50 60 80
4 0 10 70 0 10 20 40 50
5 0 10 20 40 0 10 30 40
6 0 10 20 120 100 0 10 20
7 0 10 20 150 110 70 0 10
8 0 10 20 40 170 110 50 0
Overall evacuation chart using staircase and phased evacuation
for the building under study
SECOND REVIEW MEETING
RESULT
6/6/2020 14
Overall evacuation chart using staircase, lift and phased evacuation
for the building under study
1 2 3 4 5 6 7 8
1 0 10 20 40 50 0 10 L
2 0 0 10 20 40 50 0 L
3 0 70 0 10 20 60 0 L
4 0 10 60 0 10 20 30 L
5 0 10 20 70 0 10 20 L
6 0 10 20 90 70 0 0 L
7 0 10 20 100 80 40 0 L
8 0 10 20 40 100 L 0 0
SECOND REVIEW MEETING
RESULT
6/6/2020 15
Evacuation times obtained using Total Evacuation
Without Lift(s) With Lift(s)
212 217
SECOND REVIEW MEETING
RESULT
6/6/2020 16
Comparison of Phased evacuation times for various floors with Total Evacuation
SECOND REVIEW MEETING
DISCUSSION
1. Although the evacuation components may be provided as per local building
design code, their performance in high rise building evacuation scenario
can only be judged by simulation. Hence, the building should also be
designed keeping in mind evacuation.
2. Phased evacuation and evacuation by lift are effective methods but the
evacuation components are to be designed keeping these in mind.
3. Evacuation by lift increases the total evacuation time.
4. Phased evacuation delay chart depends on number of occupants. If the
building use case may change leading to it’s increase, the simulations have
to be rerun.
6/6/2020 17
SECOND REVIEW MEETING
References
1. Marina Gravit, Ivan Dmitriev and Kirill Kuzenkov,Phased Evacuation algorithm for
high–rise buildings,EECE,2018, MATEC Web of Conferences 245, 11012
2. Ronchi, Enrico & Nilsson, Daniel. (2013). Assessment of Total Evacuation Systems
for Tall Buildings.
3. Hao Chu, Jia Yu, Jiahong Wen , Min Yi and Yun Chen, Emergency Evacuation
Simulation and Management Optimization in Urban Residential Communities,
Sustainability, MDPI, 2019,11,10-12 .
4. Nair R.R, High Rise Building Emergency Evacuation, Industrial Safety Review,2019
5. Mansor, Hazrina & sahol hamid, Yazmin & Suliman, Nurul & Ahmad, Nursafarina &
Hamzah, Noorfaizah. (2019). Evacuation egress in high rise building: Review of the
current design evacuation solution. MATEC Web of Conferences. 258. 03012.
10.1051/matecconf/201925803012.
6. Kinateder, Max & Omori, Hidemi & Kuligowski, Erica. (2014). The Use of Elevators
for Evacuation in Fire Emergencies in International Buildings.
10.6028/NIST.TN.1825.
6/6/2020 18
SECOND REVIEW MEETING6/6/2020 19
6/6/2020 20
SECOND REVIEW MEETING
Problem Statement
Consider a high rise residential building G+8 located in an urban
area. Assuming an emergency occurring in any floor of the
building which requires the people to be evacuated with
requirements being that congestion is to be avoided in the
stairwell and to ensure evacuee comfort.
Choose a suitable evacuation algorithm and analyze using
appropriate software to design an evacuation plan for the
building.
6/6/2020 21
SECOND REVIEW MEETING
Literature Review
Paper Details Findings
International
Scientific Conference
on Energy,
Environmental and
Construction
Engineering,2018
A new phased evacuation algorithm for high-rise buildings and structures
Fire Protection
Research
Foundation,2013
This report focuses on the use of egress models to assess the optimal
strategy in the case of total
evacuation in high-rise buildings
MDPI, 2019 Various Pathfinder input data and its suitability over its alternates.
6/6/2020 22
SECOND REVIEW MEETING
Literature Review
Paper Details Findings
Industrial Safety
reviews, 2013
High Rise Building Emergency Evacuation strategies
MATEC Web of
Conferences, 2019
Review of the current design evacuation solutions
NIST Technical Note
1825
The Use of Elevators for Evacuation in Fire Emergencies in International
Buildings
6/6/2020 23

More Related Content

Similar to Second Review PPT

ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...
ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...
ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...Bala Balaji
 
IRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET Journal
 
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGPLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGIRJET Journal
 
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...IRJET Journal
 
Implementation of BIM for high rise buildings in Chennai
Implementation of BIM for high rise buildings in ChennaiImplementation of BIM for high rise buildings in Chennai
Implementation of BIM for high rise buildings in ChennaiSAURAV JHA
 
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdfPLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdfBaharAnjum
 
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesRussell Archibald
 
Analysis of Data Center to quantify the performance in terms of Thermal distr...
Analysis of Data Center to quantify the performance in terms of Thermal distr...Analysis of Data Center to quantify the performance in terms of Thermal distr...
Analysis of Data Center to quantify the performance in terms of Thermal distr...AM Publications
 
CAD_176_2020_1229-1240.pdf
CAD_176_2020_1229-1240.pdfCAD_176_2020_1229-1240.pdf
CAD_176_2020_1229-1240.pdfSukantaDAS82
 
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...IRJET Journal
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
Using BIM for the assessment of the seismic performance of educational buildings
Using BIM for the assessment of the seismic performance of educational buildingsUsing BIM for the assessment of the seismic performance of educational buildings
Using BIM for the assessment of the seismic performance of educational buildingsFelipe Muñoz La Rivera
 
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...IRJET Journal
 
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libre
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libreDevelopment_of_Computer_Aided_Critical_Lift_Planning_Software-libre
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libreSrikanth Chadalavada
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTIRJET Journal
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structuresSenthilnathan Kalidas
 
IRJET - Surveying using Drones and Providing Results by using Photogrammm...
IRJET -  	  Surveying using Drones and Providing Results by using Photogrammm...IRJET -  	  Surveying using Drones and Providing Results by using Photogrammm...
IRJET - Surveying using Drones and Providing Results by using Photogrammm...IRJET Journal
 
Seismic Analysis of I Shaped and Plus Shaped Building with and without damper
Seismic Analysis of I Shaped and Plus Shaped Building with and without damperSeismic Analysis of I Shaped and Plus Shaped Building with and without damper
Seismic Analysis of I Shaped and Plus Shaped Building with and without damperIRJET Journal
 
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...Marco Lisi
 

Similar to Second Review PPT (20)

ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...
ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...
ANALYSIS AND DESIGN OF MULTI STOREY (G+5) COMMERCIAL BUILDING BY STAAD PRO AN...
 
IRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro Project
 
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGPLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
 
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...
COMPARE THE EFFECT OF FLOATING COLUMN UNDER EARTHQUAKE EXCIATATION IN G+15 L ...
 
Implementation of BIM for high rise buildings in Chennai
Implementation of BIM for high rise buildings in ChennaiImplementation of BIM for high rise buildings in Chennai
Implementation of BIM for high rise buildings in Chennai
 
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdfPLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
PLANNING AND ANALYSIS OF COMMERCIAL BUILDING PROJECT REPORT.pdf
 
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
 
Analysis of Data Center to quantify the performance in terms of Thermal distr...
Analysis of Data Center to quantify the performance in terms of Thermal distr...Analysis of Data Center to quantify the performance in terms of Thermal distr...
Analysis of Data Center to quantify the performance in terms of Thermal distr...
 
CAD_176_2020_1229-1240.pdf
CAD_176_2020_1229-1240.pdfCAD_176_2020_1229-1240.pdf
CAD_176_2020_1229-1240.pdf
 
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...
IRJET- A Comparative Analysis and Design of G + 5 Multistoried Building using...
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
Using BIM for the assessment of the seismic performance of educational buildings
Using BIM for the assessment of the seismic performance of educational buildingsUsing BIM for the assessment of the seismic performance of educational buildings
Using BIM for the assessment of the seismic performance of educational buildings
 
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...
IRJET- Comparative Study of High Rise Building Subjected to Seismic and Wind ...
 
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libre
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libreDevelopment_of_Computer_Aided_Critical_Lift_Planning_Software-libre
Development_of_Computer_Aided_Critical_Lift_Planning_Software-libre
 
Whole Report (2)
Whole Report (2)Whole Report (2)
Whole Report (2)
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structures
 
IRJET - Surveying using Drones and Providing Results by using Photogrammm...
IRJET -  	  Surveying using Drones and Providing Results by using Photogrammm...IRJET -  	  Surveying using Drones and Providing Results by using Photogrammm...
IRJET - Surveying using Drones and Providing Results by using Photogrammm...
 
Seismic Analysis of I Shaped and Plus Shaped Building with and without damper
Seismic Analysis of I Shaped and Plus Shaped Building with and without damperSeismic Analysis of I Shaped and Plus Shaped Building with and without damper
Seismic Analysis of I Shaped and Plus Shaped Building with and without damper
 
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
A Through-life, Integrated and Concurrent Engineering Methodology for the Res...
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 

Second Review PPT

  • 1. COMPARATIVE ASSESSMENT OF VARIOUS EVACUATION STRATEGIES FOR HIGH–RISE BUILDINGS Presented by ARVINTH KUMAR S (120001010) SATISH V (120001087) VADDI VIKRAMA NARASIMHA (120001106) Project Guide G.I GUNARANI Assistant Professor III School of Civil Engineering SASTRA Deemed to be University SECOND REVIEW MEETING6/6/2020 1 SCHOOL OF CIVIL ENGINEERING
  • 2. SECOND REVIEW MEETING OBJECTIVES 6/6/2020 2  To identify various strategies for evacuation of High Rise building and to model these in people evacuation software- Pathfinder  Assess the performance of each based on the Total Evacuation Time  Analyse the benefits of each strategy  Suggest appropriate improvements to the architectural plan pertaining to the sufficiency of evacuation
  • 3. SECOND REVIEW MEETING METHODOLOGY- MODEL CREATION 6/6/2020 3 Fig depicting evacuation strategy using staircase only Fig depicting evacuation strategy using staircase and lift
  • 4. SECOND REVIEW MEETING METHODOLOGY- MODEL CREATION 6/6/2020 4 Fig depicting evacuation strategy using staircase and phased evacuation Fig depicting evacuation strategy using staircase, lift and phased evacuation
  • 5. SECOND REVIEW MEETING METHODOLOGY Total Evacuation 6/6/2020 5 Building on fire Alert Others Keep Family Close Group Evacuation Sketch of Selected Evacuation Mode in Building Family Teamwork Mode
  • 7. SECOND REVIEW MEETING EVACUATION SCHEDULE 6/6/2020 7 Chart depicting scheduling algorithm based on the zone priorities Red Zone: Critical and First Preference Green Zone: Second Preference Blue Zone: Third Preference
  • 8. SECOND REVIEW MEETING BASELINE SIMULATION 6/6/2020 8 Chart depicting algorithm for finding out the base delay
  • 9. SECOND REVIEW MEETING DELAY FROM SIMULATION 6/6/2020 9 Chart depicting delay finding algorithm based on the zone priorities Red Zone: Critical and First Preference Green Zone: Second Preference Blue Zone: Third Preference
  • 10. SECOND REVIEW MEETING WORKS DONE 6/6/2020 10 8 8 7 7 6 6 5 5 4 4 3 3 2 2 1 1 FIRST FLOOR 8 1 7 2 6 3 5 4 4 5 3 6 2 7 1 8 EIGHTH FLOOR Chart depicting evacuation schedule for three floors of the building under study
  • 11. SECOND REVIEW MEETING WORKS DONE 6/6/2020 11 8 90 7 80 6 70 5 50 4 40 3 20 2 10 1 0 FIRST FLOOR 8 0 7 50 6 110 5 170 4 40 3 20 2 10 1 0 EIGHTHFLOOR Chart depicting delay chart for extreme floors of the building under study
  • 12. SECOND REVIEW MEETING WORKS DONE 6/6/2020 12 Chart depicting delay chart for fourth floor of the building under study 8 50 7 40 6 20 5 10 4 0 3 70 2 10 1 0 FOURTH FLOOR
  • 13. SECOND REVIEW MEETING RESULT 6/6/2020 13 1 2 3 4 5 6 7 8 1 0 10 20 40 50 70 80 90 2 0 0 10 20 40 50 70 80 3 0 60 0 10 20 50 60 80 4 0 10 70 0 10 20 40 50 5 0 10 20 40 0 10 30 40 6 0 10 20 120 100 0 10 20 7 0 10 20 150 110 70 0 10 8 0 10 20 40 170 110 50 0 Overall evacuation chart using staircase and phased evacuation for the building under study
  • 14. SECOND REVIEW MEETING RESULT 6/6/2020 14 Overall evacuation chart using staircase, lift and phased evacuation for the building under study 1 2 3 4 5 6 7 8 1 0 10 20 40 50 0 10 L 2 0 0 10 20 40 50 0 L 3 0 70 0 10 20 60 0 L 4 0 10 60 0 10 20 30 L 5 0 10 20 70 0 10 20 L 6 0 10 20 90 70 0 0 L 7 0 10 20 100 80 40 0 L 8 0 10 20 40 100 L 0 0
  • 15. SECOND REVIEW MEETING RESULT 6/6/2020 15 Evacuation times obtained using Total Evacuation Without Lift(s) With Lift(s) 212 217
  • 16. SECOND REVIEW MEETING RESULT 6/6/2020 16 Comparison of Phased evacuation times for various floors with Total Evacuation
  • 17. SECOND REVIEW MEETING DISCUSSION 1. Although the evacuation components may be provided as per local building design code, their performance in high rise building evacuation scenario can only be judged by simulation. Hence, the building should also be designed keeping in mind evacuation. 2. Phased evacuation and evacuation by lift are effective methods but the evacuation components are to be designed keeping these in mind. 3. Evacuation by lift increases the total evacuation time. 4. Phased evacuation delay chart depends on number of occupants. If the building use case may change leading to it’s increase, the simulations have to be rerun. 6/6/2020 17
  • 18. SECOND REVIEW MEETING References 1. Marina Gravit, Ivan Dmitriev and Kirill Kuzenkov,Phased Evacuation algorithm for high–rise buildings,EECE,2018, MATEC Web of Conferences 245, 11012 2. Ronchi, Enrico & Nilsson, Daniel. (2013). Assessment of Total Evacuation Systems for Tall Buildings. 3. Hao Chu, Jia Yu, Jiahong Wen , Min Yi and Yun Chen, Emergency Evacuation Simulation and Management Optimization in Urban Residential Communities, Sustainability, MDPI, 2019,11,10-12 . 4. Nair R.R, High Rise Building Emergency Evacuation, Industrial Safety Review,2019 5. Mansor, Hazrina & sahol hamid, Yazmin & Suliman, Nurul & Ahmad, Nursafarina & Hamzah, Noorfaizah. (2019). Evacuation egress in high rise building: Review of the current design evacuation solution. MATEC Web of Conferences. 258. 03012. 10.1051/matecconf/201925803012. 6. Kinateder, Max & Omori, Hidemi & Kuligowski, Erica. (2014). The Use of Elevators for Evacuation in Fire Emergencies in International Buildings. 10.6028/NIST.TN.1825. 6/6/2020 18
  • 21. SECOND REVIEW MEETING Problem Statement Consider a high rise residential building G+8 located in an urban area. Assuming an emergency occurring in any floor of the building which requires the people to be evacuated with requirements being that congestion is to be avoided in the stairwell and to ensure evacuee comfort. Choose a suitable evacuation algorithm and analyze using appropriate software to design an evacuation plan for the building. 6/6/2020 21
  • 22. SECOND REVIEW MEETING Literature Review Paper Details Findings International Scientific Conference on Energy, Environmental and Construction Engineering,2018 A new phased evacuation algorithm for high-rise buildings and structures Fire Protection Research Foundation,2013 This report focuses on the use of egress models to assess the optimal strategy in the case of total evacuation in high-rise buildings MDPI, 2019 Various Pathfinder input data and its suitability over its alternates. 6/6/2020 22
  • 23. SECOND REVIEW MEETING Literature Review Paper Details Findings Industrial Safety reviews, 2013 High Rise Building Emergency Evacuation strategies MATEC Web of Conferences, 2019 Review of the current design evacuation solutions NIST Technical Note 1825 The Use of Elevators for Evacuation in Fire Emergencies in International Buildings 6/6/2020 23