3. ABOUT EMTSPL
• EMTSPL provides services in the field of electrical
engineering, main focus on diagnostic testing services
of Electrical Power equipments. Erection, Testing &
Commissioning of Electrical equipments.
• Our board of directors are Ex-OPTCL & Ex-NALCO.
• Electrical Engineers having long years of experience in
relevant field form the core of EMTSPL group.
• EMTSPL provide services in the state of Odisha &
neighboring states.
4. CREDENTIALS
• TPCODL Project:
Bhubaneswar Capital Region & Puri town all TOCODL 33/11 KV Sub-Stations Health audit & recommendation.
Total 50 Sub-stations in the year of 2020-21
• TPNODL Project:
Checking Healthiness of electrical equipments at TPNODL, Balasore in the year of 2021-22
(2000+ Transformers, 52 Power Transformers, 57 Metering Cubicle, 112 Metering Unit etc)
• TPSODL-SIEMENS Project:
Erection, Testing & Commissioning of new CRP & RTU Panels at 22 TPSODL PSS.
• IOCL Pumping station, Berhampur:
Complete testing & commissioning of electrical HT & LT systems
• IOCL Oil terminal Paradip:
Thermography scanning of HT & LT Panels in various control rooms.
• OPTCL Project:
220 KV/132 KV/33 KV new Sub-Station Testing & Commissioning
• OPTCL ODSSP 33/11 KV SS Project:
ODSSP 33/11 KV new substation Testing & Commissioning
• NALCO Project:
Lean Slurry project Electrical testing & commissioning
• MCL Project:
220/33 KV Substation Testing & Commissioning
& Many more ……….
6. PROPOSAL FOR KALINGA STADIUM
ELECTRICAL PANEL HEALTH AUDIT
Objective of Audit:
• To Prevent fire hazard & electrical short circuit
• To prevent electrical breakdown of panel
components
• Protection availability for fault & overload
conditions
• Adequacy of component rating to meet full load
requirement
• Alternate supply source availability in case of
critical load panels
8. Activities Findings
• Thermal Scanning of electrical panel
internal components by thermo-vision
camera
• Electrical Loading pattern measurement
of R,Y,B Phase of electrical panels
• Neutral Healthiness check by
measurement of neutral current
•Insulation resistance measurement of
main incoming cable
• Identification of hot spot & source
contributing to hot spot
• To ensure balance loading
• To ensure no current or very less
current flow in neutral.
• To ensure healthy IR value
9.
10.
11. Activities Findings
• Terminal looseness & internal component
cleanness
• Internal wiring check of panel component
• Proper sealing of Panel door
• Voltage measurement at panel incoming
• Source of heating
• Healthiness of panel wiring
• To prevent entry of dust inside the
panel
• To assess adequacy of voltage.
12. • To prevent unexpected breakdown
• Reliability of systems will be enhanced
13. OTHER CRITICAL OBSERVATIONS
• Electrical drawing availability for complete power
distribution system of Kalinga Staduim may be
ensured. SLD made available at the earliest.
• Recording of all types of installation details may be
done for future study & replacement plan.
• Periodic different maintenance plans need to be
implemented.