1 | P a g e
SAQIB IMRAN 0341-7549889 1
Assala mu alykum My Name is saqib imran and I am the
student of b.tech (civil) in sarhad univeristy of
science and technology peshawer.
I have written this notes by different websites and
some by self and prepare it for the student and also
for engineer who work on field to get some knowledge
from it.
I hope you all students may like it.
Remember me in your pray, allah bless me and all of
you friends.
If u have any confusion in this notes contact me on my
gmail id: Saqibimran43@gmail.com
or text me on 0341-7549889.
Saqib imran.
2 | P a g e
SAQIB IMRAN 0341-7549889 2
HIGHWAY
TYPES OF FAILURES IN FLEXIBLE PAVEMENTS
The different types of failures in flexible pavements are described below:
1. Subgrade failure.
2. Base failure or base course failure.
3. Surface failure or wearing course failure.
1. SUBGRADE FAILURE:
Excessive deformation in subgrade soil of a flexible failure is called subgrade failure.
This is one of the main causes of failure of flexible pavements. This type of failure
causes undulations (ups and downs) and corrugations in the pavement surface.
Causes Of Subgrade Failure:
1. Inadequate stability.
2. Inadequate road drainage.
3. Excessive stress application.
2. BASE COURSE FAILURE:
Excessive deformation in the base or foundation course of a flexible pavement is known
as base course failure.
This type of failure causes potholes, waves, and corrugations in the pavement surface.
Causes Of Base Course Failure:
1. Insufficient strength.
2. Loss of binding action.
3. Crushing of base course material.
4. Lack of lateral confinement of the granular base course.
5. Insufficient wearing course.
6. Inadequate quality control.
7. Inadequate road drainage.
3 | P a g e
SAQIB IMRAN 0341-7549889 3
3. SURFACE FAILURE:
Excessive deformation in the wearing course of a flexible pavement is called surface
failure or wearing course failure.
This type of failure causes ruts, potholes, cracks etc in the pavement structure.
Causes Of Surface Failure:
1. lack of proper mix design
2. Use of the inferior type of binder.
3. Inadequate quality control.
4. Volatization and oxidation of binder.
RESULTS OF FLEXIBLE FAILURE:
1. RUTS:
The longitudinal depressions or cuts in flexible pavement is known as ruts. These are
usually formed ion earth or W.B.M roads of one lane width due to repetitive traffic wheel
loads on the same location, particularly under wheeled traffic.
4 | P a g e
SAQIB IMRAN 0341-7549889 4
2. POT HOLES:
The isolated depressions, more or less circular in shape formed in flexible pavements
are called pot holes or patches. These are usually formed in all types of flexible
pavements due to disintegration of road metal or lack of binding surface course with the
underlying base.
3. FROST HEAVING:
A localized heaving up of pavement portion is known as frost heaving.
The water which may find access to pavement structure freezes in cold climates. The
expansion accompanying this frost action causes upheaval which in turn may crack the
pavement surface.
5 | P a g e
SAQIB IMRAN 0341-7549889 5
4. SHEAR FAILURE CRACKING:
The formation of a fracture or cracking due to upheaval of pavement portion followed by
a depression called shear failure cracking. This type of failure occurs due to localized
weakness in the pavement.
5. LONGITUDINAL CRACKING:
The formation of cracks in the longitudinal direction of a road pavement is called
longitudinal cracking.
This failure is caused due to frost action, different volume changes in subgrade,
settlement of filling material or due to sliding of side slopes.
6 | P a g e
SAQIB IMRAN 0341-7549889 6
6. MAP CRACKING:
The development of irregular cracks, usually formed on bituminous surfacing is called
map cracking.
This type of flexible road failure is due to excessive wear of the road surface or due to
localized weakness in the underlying base course.
7 | P a g e
SAQIB IMRAN 0341-7549889 7
CEMENT CONCRETE ROADS – ADVANTAGES AND DISADVANTAGES
Cement Concrete Road
CEMENT CONCRETE ROADS:
The roads having their wearing surface consisting of cement concrete (plane or
reinforced) are known as cement concrete roads or concrete roads.
These roads are types of rigid pavements and remain in serviceable condition under all
weather conditions. Thus concrete roads are also considered as all weather roads. Due
to their excellent riding surface, pleasing appearance and long life under most severe
traffic conditions, cement concrete roads are much preferred.
Cement concrete roads are superior to most other types of roads including bituminous
roads. These roads are very popular as high cost pavements in developed countries like
America, Russia, Japan etc.
ADVANTAGES OF CEMENT CONCRETE ROADS:
1. Concrete roads have long life than any other roads.
2. These roads are durable and are practically unaffected by weathering agencies.
3. They provide an excellent riding surface under all weather conditions.
4. They provide an impervious, dustless and sanitary surface.
8 | P a g e
SAQIB IMRAN 0341-7549889 8
5. They do not develop corrugations.
6 Can be laid on any subgrade.
7. Can be easily reinforced when they are to resist high stresses due to heavy wheel
loads of the traffic.
8. Concrete roads are non slipery and offer less tractive resistance.
9. They provide good visibility for traffic during night hours.
10. Maintenance cost is low.
DISADVANTAGES OF CEMENT CONCRETE ROADS:
1. The initial cost of concrete roads is high.
2. They are liable to crack and warp due to temperature variations.
3. Become noisy under iron-tyred traffic.
4. Skilled supervision and labour are required for construction.
5. less resilient than bituminous or W.B.M roads.
6. Require long time for curing and thus cannot be opened to traffic earlier.
7. It is very difficult to locate and repair sewers and water mains lying under the
pavement in their case.
COMPONENTS OF ROAD PAVEMENT STRUCTURE
COMPONENTS OF ROAD PAVEMENT STRUCTURE:
Following are the different components of road structure:
1. Subgrade
2. Sub-base
3. Base course
4. Surface course or wearing course
All these components belong to a typical flexible pavement, whereas rigid pavement
usually consists of subgrade, subbase and a concrete slab.
9 | P a g e
SAQIB IMRAN 0341-7549889 9
1. SUBGRADE:
The finished and compacted surface of earthwork on which a road pavement rests is
called subgrade or formation.
The subgrade of a road may be provided on an embankment, in cutting or existing
ground level depending upon the topography and the finalized formation level. It
consists of well compacted natural soil brought to the required camber and gradient.
The thickness and type of pavement structure depend upon the supporting power of the
subgrade because the entire load of the pavement, including the load of traffic
transmitted through the pavement, is ultimately taken up by the subgrade.
2. SUB-BASE:
A layer of granular material provided in between the subgrade and the base course in a
road pavement is known as sub-base.
It is provided as an additional layer when subgrade is of poor quality. It consists of a
layer comparatively cheaper material like burnt clinker, natural gravel or slag.
3. BASE COURSE:
A layer of boulders or bricks provided over the subbase or immediately over the
subgrade in the absence of sub-base in a road pavement is called base course or soling
or foundation course.
This course is considered as the most important and major component of road structure
because this course is to bear the impact of traffic transferred through the wearing
course. It consists of a stable material like boulders, gravel, one or two layers of well-
burnt bricks etc. In case of rocky subgrade, this course is not provided.
4. SURFACE COURSE OR WEARING COURSE:
The topmost layer of the road pavement directly exposed to traffic is called is called
wearing course or surfacing.
10 | P a g e
SAQIB IMRAN 0341-7549889 10
It may consist of one or more number of layers in case of flexible pavements. A good
wearing course should be impervious and weather resisting. it should be able to resist
abrasive action of the traffic.
SUPERELEVATION OF ROAD – ADVANTAGES AND DESIGN OF SUPER
ELEVATION
SUPERELEVATION OF ROAD:
The inward transverse inclination provided to the cross-section of the carriageway at
horizontally curved portion of a road is called superelevation, cant or banking.
Superelevation is provided to counteract the effect of centrifugal force and to minimize
the tendency of the vehicle to overturn or skid by raising the outer edge of pavement
with respect to the inner edge, providing a transverse slope throughout the length of the
horizontal curve.
It is expressed as the ratio of elevation of the outer edge above the inner edge to the
horizontal width of carriageway or as the tangent of the angle of slope of the road
surface. It is generally denoted by ‘e’ or S.E.
OBJECTS OF PROVIDING SUPERELEVATION:
1. To counteract the effect of centrifugal force acting on the moving vehicle to pull out
the same outward on a horizontal curve.
2. To help a fast moving vehicle to negotiate a curved path without overturning and
skidding.
11 | P a g e
SAQIB IMRAN 0341-7549889 11
3. To ensure safety to the fast moving traffic.
4. To prevent damaging effect on the road surface due to improper distribution of load.
ADVANTAGES OF SUPERELEVATION:
1. It allows running of vehicle at high speed on a curved path as on a straight path
without any danger of overturning and thus results into increased volume of traffic.
2. It provides more or less even distribution of load on wheels and hence uniform stress
is offered on the foundation which results into less wear on wheel tyres and springs as
well as economy in maintenance cost of the road.
3. It also helps to keep the vehicles to their proper side on the pavement and thus
prevents collision of vehicles moving in opposite directions on a curved portion of the
road.
4. It provides drainage of the whole width of road towards the inner side. Thus, there is
no necessity of providing side drain on the outer side of the road.
DESIGN OF SUPERELEVATION:
To design superelevation for mixed type of traffic is a complex problem. The Indian
Roads Congress has recommended to provide superelevation to counteract the
centrifugal force fully due to 75% of the design speed and limiting the maximum
superelevation to 1 in 15 or 7%.
Following are the steps adopted to design the superelevation of a road:
Step 1:
Calculate the superelevation for 75% of design speed neglecting the friction i.e f = 0
V = 75%(V) = 0.75 V
We know that, e+f = V²/127R
e + 0 = (0.75 V)²/127R
Step 2:
If the calculated value ‘e’ is less than 7% or 0.07, then provide the obtained value. If it
exceeds 0.07 then provide the limiting value of superelevation emax = 0.07 and proceed to
the next step.
12 | P a g e
SAQIB IMRAN 0341-7549889 12
Step 3:
Check the coefficient of friction developed for the maximum value of e = 0.07 at the full
value of design speed,
If the value of ‘f’ thus calculated is less than 0.15, the superelevation of 0.07 is safe for
the design speed. If not, calculate the restricted speed as given in step 4.
Step 4:
If the calculated value of ‘f’ exceeds 0.15, then the speed of the vehicles is restricted to
the value Vr m/sec or Vr km/hr as calculated after allowing the limiting values of e and f
in the following equation:
13 | P a g e
SAQIB IMRAN 0341-7549889 13
In case of an important highway, it is always desirable to design the road without speed
restriction at curves. Hence, the curve should be realigned, if possible with a longer
radius of curvature so that the design speed can be maintained without any restriction.
DIFFERENCE BETWEEN FLEXIBLE PAVEMENTS AND RIGID PAVEMENTS
FLEXIBLE PAVEMENTS:
The pavements having low or negligible flexural strength and are flexible in their
structural action under the loads are known as flexible pavements.
RIGID PAVEMENTS:
Rigid pavements are those which contain great amount of flexural strength or flexural
rigidity.
In rigid pavements, the stresses are not transferred from grain to grain to the lower
layers as in the ease of flexible pavement layers.
DIFFERENCE BETWEEN FLEXIBLE PAVEMENTS
AND RIGID PAVEMENTS:
POINT OF
DIFFERENCE
FLEXIBLE
PAVEMENTS
RIGID
PAVEMENTS
Initial cost Their initial cost is low. Their initial cost is high.
Life span They have short life
span.
They have long life span.
Thickness Their thickness is more. Their thickness is less.
Joints Joints are not required. Joints are essentially
required.
Subgrade A reasonably good
subgrade is required.
A good subgrade is not
necessary.
Durability They are less durable They are more durable.
Temperature effect Stresses are not induced
in these pavements due
Heavy stresses are
induced in these
14 | P a g e
SAQIB IMRAN 0341-7549889 14
to temperature
variations.
pavements due to
temperature variations.
Repair work Easy repair work. Difficult to repair.
Skill and supervision Moderate skill and less
supervision are required.
More skill and
supervision is required.
Feasibility of providing
underground works
It is easy to lay, locate or
repair underground
pipes below these
pavements.
It is very difficult to
provide or repair
underground pipes
below these pavements.
Openings to traffic after
construction
Can be opened to traffic
shortly after
construction.
Require curing after
construction and thus
cause delay in opening to
traffic.
Resiliency More resilient to traffic
load.
Less resilient to traffic
load.
Corrugations They develop
corrugations.
No corrugations are
developed in these
pavements.
Behavior with subgrade
settlement.
They adjust according to
any deformation of
subgrade without
rupture.
They do not adjust
according to any
deformation of subgrade
without rupture.
Tractive resistance They have more tractive
resistance.
They have less tractive
resistance.
Traffic suitability Suitable for all types of
traffic.
Noisy under iron
wheeled traffic.
Night visibility Blacktop pavements
provide poor visibility at
night.
They offer good visibility
at night.
Glaring effect They do not usually
cause glare due to
reflected sunlight.
They often cause glare
due to reflected sunlight.
Feasibility of stage
development
Stage development is
feasible.
Stage development is not
feasible.
15 | P a g e
SAQIB IMRAN 0341-7549889 15
Effect Of loading They adjust themselves
to normal loading by
undergoing elastic
deformation.
They tend to act as a
beam or cantilever and
resist deformation.
Maintenance cost Maintenance cost is
high.
Maintenance cost is low.
WHAT IS BITUMEN AND ITS USES
WHAT IS BITUMEN AND ITS USES:
Bitumen is the binding material present in asphalt. Sometimes it is also known as
mineral tar. Bitumen is produced by partial distillation of crude petroleum.
it is chemically a hydrocarbon and insoluble in water. But it totally dissolves in alkalies,
alkaline carbonates, benzol, chloroform, bisulphide, naptha, coal tar, petroleum spirit
and oil of turpentine.
It is obtained from 87% carbon, 11% hydrogen and 2% oxygen (By weight). The
bitumen is produced in solid or semi-solid state and black or brown in color.
FORMS OF BITUMEN:
The general forms of bitumen are as following
16 | P a g e
SAQIB IMRAN 0341-7549889 16
1. BITUMEN EMULSION:
It is a liquid compound which contains a large amount of bitumen in aqueous medium. It
is suspended by some appropriate stabilizing agents in the aqueous medium.
2 CUT-BACK BITUMEN:
This form of bitumen is produced by fluxing asphaltic bitumen in presence of some
liquid distillates of petroleum or coal tar. Cut-back bitumen can be used as bitumen
paint in cold.
3 BLOWN BITUMEN:
It is a special form of bitumen produced by passing air under pressure at a higher
temperature. This type of bitumen can be used as heat insulating material, roofing and
damp-proofing felts, producing asphalt pipe and joint fillers etc.
4 PLASTIC BITUMEN:
It comprises of bitumen thinner and appropriate inert filler (40%-45%). Plastic bitumen
can be used for filling cracks in masonry structures, stopping leakages etc.
5 STRAIGHT RUN BITUMEN:
This type of bitumen is obtained by distillation of the bitumen to a definite viscosity or
penetration without further treatment:
APPLICATION OF BITUMEN:
 Road Construction.
 Hydraulics & erosion control Catchment areas, basins.
 Dam groutings,
 Dam linings,
 Embankment protection
 Dam linings,
 Embankment protection
 Ditch linings, Reservoir linings
 Reservoir linings
 Jetties, Dyke protection
 Dyke protection
 Swimming pools
 Waste ponds
 Water barriers
 Mattresses for levee & bank protection
 Membrane linings,
 Waterproofing
 Revetments
17 | P a g e
SAQIB IMRAN 0341-7549889 17
 Sand dune stabilization,
 Drainage gutters,
 Backed felts
FIELD DENSITY TEST OF SOIL BY SAND CONE METHOD
FIELD DENSITY TEST ( SAND CONE METHOD):
The sand cone method is one of the most common methods that are used for field
density test in highway construction. The dry density test is carried out in the field to
check the compaction of the layers.
Compaction is very useful for preparing the sub-base grade and other layers of
pavement. Compaction is done in the construction of embankment for increasing the
stability as well as for decreasing the settlement.
In field compaction, the compacting moisture content should be controlled first and the
adequacy of rolling should be controlled by checking the achieved dry density and
comparing with the maximum dry density.
Base layer – 98%
Sub base layer – 98%
Type 1 layer – 95 %
ABC layer – 100%
PROCEDURE OF TEST:
1. First, take the weight of the empty sand cone and then fill it with dry sand and then
weight again.
18 | P a g e
SAQIB IMRAN 0341-7549889 18
2. Collect the excavated soil from the hole and measure the weight.
3. After weighting, collect the specimen of soil to determine the water content in it.
4. Now place the sand cone on the test hole with the help of the base plate and allow
the sand to run by opening the control valve.
5. When the sand stops running, close the valve and weight the cone with the existing
sand. Finally, calculate the dry density of the soil by given below formula. If the test fails,
compact and perform the test again.
CALCULATION:
The volume of the hole = Mass of sand in hole/Density of used sand.
Wet density = Mass of wet excavated soil/Volume of hole
Dry density = Wet density × 100%/ Moisture content of soil + 100
Degree of compaction = Dry density × 100%/Maximun dry density.
TYPES OF ROAD CAMBER- ADVANTAGES AND METHODS OF
PROVIDING CAMBER
WHAT IS CAMBER?
Camber is the slope provided to the road surface in the transverse direction to drain off
the rainwater from the road surface. It is also known as cross slope of road.
WHY CAMBER IS PROVIDED IN ROAD?
1. To protect the road by preventing the entry of surface water into the subgrade soil
through pavement.
2. To prevent the entry of water into the bituminous pavement layers.
19 | P a g e
SAQIB IMRAN 0341-7549889 19
3. To remove the rainwater from the pavement surface as quickly as possible and to
allow the pavement to get dry soon after the rain.
TYPES OF CAMBER:
1. COMPOSITE CAMBER:
It consists of two straight slopes from the edges with a parabolic or circular crown in the
center of camber. This type of camber can be easily constructed and maintained.
2. SLOPED OR STRAIGHT CAMBER:
It consists of two straight slopes from the edges joining at the center of the carriageway.
This type of camber is very simple and can be easily constructed and maintained.
3. PARABOLIC OR BARREL CAMBER:
It consists of a continuous curve either elliptical or parabolic. It provides a flat road
surface at the middle and steeper towards the edges. On account of steeper edges, this
type of camber provides better drainage property. This camber is therefore preferred by
fast moving vehicles and suggested for urban roads.
20 | P a g e
SAQIB IMRAN 0341-7549889 20
This type of camber is difficult to construct and maintain. The barrel camber has more
steeper edges which are inconvenient to use. Moreover, the steeper edges are errored
quickly and hence additional kerbs are to be provided.
ADVANTAGES OF CAMBER:
1. Camber provides quick drainage of rainwater and thus saves the foundation course
of the road structure from weakening by percolation of rainwater to it through the road
surface.
2. This prevents rainwater to accumulate in local shrinkages or depressions and forming
water pool on the road surface, which are disagreeable to the public as well as to the
road structure.
METHOD OF PROVIDING CAMBER:
Usually, camber is provided on the straight roads by raising the center of the
carriageway with respect to the edges, forming a crown or highest point on the center
line.
At horizontal curves with superelevation, the surface drainage is effected by raising the
outer edge of pavement with respect to the inner edge while providing the desired
superelevation. the rate of camber or cross slope is usually designed by 1 in ‘n’ which
means the transverse slope is in ratio 1 vertical to “n” horizontal. Camber is also
expressed in percentage. If the camber is x %, the cross slope is x in 100.
21 | P a g e
SAQIB IMRAN 0341-7549889 21
RECOMMENDED VALUES OF CAMBER FOR
DIFFERENT TYPES OF ROAD SURFACES BY
IRC:
TYPES OF CURVES ON HILL ROADS
TYPES OF CURVES ON HILL ROADS:
The types of curves provided on hill roads are as following:
1 Hair-pin curves,
2 salient curves,
3 Re-entrant curves.
1. HAIR-PIN CURVES:
‘The curve in a hill road which changes its direction through an angle of 180 or so, down
the hill on the same side is known as hair-pin curve.
22 | P a g e
SAQIB IMRAN 0341-7549889 22
This curve is so called because it conforms to the shape of a hair-pin. The bend so
formed at the hair-pin curve in a hill road is known as pin bend. This type of curve
should be located on hill side having the minimum slope and maximum stability. It must
also be safe from the view point of land slides and ground water. Hair-pin bends
with long arms and farther spacing are always preferred. They reduce construction
problems and expensive protective works. Hair-pin curves or bends of serpentine nature
are difficult to negotiate and should, therefore,e be avoided as far as possible.
2. SALIENT CURVES:
The curves having their convexity on the outer edges of a hill road are called salient
curves.
The center of curvature of a salient curve lies toward the hill side. This type of curve
occurs in the road length constructed on the ridge of a hill. The bend so formed at the
salient curve in hill road is known as corner bend.
23 | P a g e
SAQIB IMRAN 0341-7549889 23
Salient curves are very dangerous for fast-moving traffic. At such a curve or at corner
bend, the portion of projecting hill side is usually cut down to improve the visibility. The
outer edge of the road at such a curve is essentially provided with a parapet wall for
protection of the vehicles from falling down the hill slope.
3. RE-ENTRANT CURVES:
The curves having their convexity on the inner edge of a hill road are called re-entrant
curve.
The center of curvature of a re-entrant curve lies away from the hill side. This type of
curve occurs in the road length constructed in the valley of a hill.
24 | P a g e
SAQIB IMRAN 0341-7549889 24
These curves are less dangerous as they provided adequate visibility to the fast-moving
traffic. At such curves, the parapet wall is provided only for safety of fast-moving traffic.

More Related Content

What's hot

Pavement design
Pavement designPavement design
Pavement designhusna004
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaKhyati Saggu
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridgeAKASH SHAH
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
PPT On High level bridge
PPT On High level bridgePPT On High level bridge
PPT On High level bridgeLOKESH
 
Introductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertedIntroductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertednaveen kumar
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD hitendra pendam
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its typesprathiekraj1
 
Hill road construction
Hill road constructionHill road construction
Hill road constructionGeet KH
 
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVILGIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVILAM Publications
 
SSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres SanchezSSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres SanchezEva Lantsoght
 
Construction of roads presentations
Construction of roads presentationsConstruction of roads presentations
Construction of roads presentationsIjaz Hassan Khan
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenanceDharmesh Vadher
 

What's hot (20)

Pavement design
Pavement designPavement design
Pavement design
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
 
flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
Bridge construction atlas
Bridge construction atlasBridge construction atlas
Bridge construction atlas
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
PPT On High level bridge
PPT On High level bridgePPT On High level bridge
PPT On High level bridge
 
Introductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertedIntroductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-converted
 
Bridge report
Bridge reportBridge report
Bridge report
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its types
 
Hill road construction
Hill road constructionHill road construction
Hill road construction
 
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVILGIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
 
ppt
pptppt
ppt
 
Ch4 cross section elements
Ch4 cross section elementsCh4 cross section elements
Ch4 cross section elements
 
SSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres SanchezSSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres Sanchez
 
Construction of roads presentations
Construction of roads presentationsConstruction of roads presentations
Construction of roads presentations
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
 

Similar to Highway pdf

Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESMalay Talaviya
 
Rigid pavement in Magallanes Interchange
Rigid pavement in Magallanes InterchangeRigid pavement in Magallanes Interchange
Rigid pavement in Magallanes Interchangeharoldtaylor1113
 
Seminar Presentation "Pavements failures and their maintenance"
Seminar Presentation "Pavements failures and their maintenance"Seminar Presentation "Pavements failures and their maintenance"
Seminar Presentation "Pavements failures and their maintenance"ctakshaykumar1
 
highway maintenance and evaluation
highway maintenance and evaluation highway maintenance and evaluation
highway maintenance and evaluation Senthamizhan M
 
Highway Failure & their Maintenance Final Project.pptx
Highway Failure & their Maintenance Final Project.pptxHighway Failure & their Maintenance Final Project.pptx
Highway Failure & their Maintenance Final Project.pptxjohnjohn497573
 
Pavement and Types of pavement
Pavement and Types of pavementPavement and Types of pavement
Pavement and Types of pavementSaleemAbbasLound
 
highway microproject renew (CE3I).pptx
highway microproject renew (CE3I).pptxhighway microproject renew (CE3I).pptx
highway microproject renew (CE3I).pptxR68DineshWaghmare
 
Visual assessment of pavement condition
Visual assessment of pavement conditionVisual assessment of pavement condition
Visual assessment of pavement conditionSulav Sigdel
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 
pavement engineering 17-10-20 (2) (2).pptx
pavement engineering 17-10-20 (2) (2).pptxpavement engineering 17-10-20 (2) (2).pptx
pavement engineering 17-10-20 (2) (2).pptxlogeshwari jambunathan
 
Pavement Analysis and Design.pptx
Pavement Analysis and Design.pptxPavement Analysis and Design.pptx
Pavement Analysis and Design.pptxEmaan Sharma
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Transportation Pavement.pptx
Transportation Pavement.pptxTransportation Pavement.pptx
Transportation Pavement.pptxWajehUlHassan
 
Highway failure and their maintenance
Highway failure and their maintenanceHighway failure and their maintenance
Highway failure and their maintenanceMantoshRajput
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance pptBeing Deepak
 

Similar to Highway pdf (20)

Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
Rigid pavement in Magallanes Interchange
Rigid pavement in Magallanes InterchangeRigid pavement in Magallanes Interchange
Rigid pavement in Magallanes Interchange
 
Pavement failures
Pavement failuresPavement failures
Pavement failures
 
Seminar Presentation "Pavements failures and their maintenance"
Seminar Presentation "Pavements failures and their maintenance"Seminar Presentation "Pavements failures and their maintenance"
Seminar Presentation "Pavements failures and their maintenance"
 
highway maintenance and evaluation
highway maintenance and evaluation highway maintenance and evaluation
highway maintenance and evaluation
 
Highway Failure & their Maintenance Final Project.pptx
Highway Failure & their Maintenance Final Project.pptxHighway Failure & their Maintenance Final Project.pptx
Highway Failure & their Maintenance Final Project.pptx
 
Pavement and Types of pavement
Pavement and Types of pavementPavement and Types of pavement
Pavement and Types of pavement
 
highway microproject renew (CE3I).pptx
highway microproject renew (CE3I).pptxhighway microproject renew (CE3I).pptx
highway microproject renew (CE3I).pptx
 
Visual assessment of pavement condition
Visual assessment of pavement conditionVisual assessment of pavement condition
Visual assessment of pavement condition
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
pavement engineering 17-10-20 (2) (2).pptx
pavement engineering 17-10-20 (2) (2).pptxpavement engineering 17-10-20 (2) (2).pptx
pavement engineering 17-10-20 (2) (2).pptx
 
Types of pavement
Types of pavementTypes of pavement
Types of pavement
 
Pavement Analysis and Design.pptx
Pavement Analysis and Design.pptxPavement Analysis and Design.pptx
Pavement Analysis and Design.pptx
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Transportation Pavement.pptx
Transportation Pavement.pptxTransportation Pavement.pptx
Transportation Pavement.pptx
 
Pavement Deterioration
Pavement DeteriorationPavement Deterioration
Pavement Deterioration
 
Highway failure and their maintenance
Highway failure and their maintenanceHighway failure and their maintenance
Highway failure and their maintenance
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
Road
RoadRoad
Road
 

More from Saqib Imran

Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notesSaqib Imran
 
Misaali mard مثالی مرد
Misaali mard مثالی مردMisaali mard مثالی مرد
Misaali mard مثالی مردSaqib Imran
 
Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Saqib Imran
 
Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Saqib Imran
 
Khatm e nabuwat 4
Khatm e nabuwat 4Khatm e nabuwat 4
Khatm e nabuwat 4Saqib Imran
 
Khatm e nabuwat 3
Khatm e nabuwat 3Khatm e nabuwat 3
Khatm e nabuwat 3Saqib Imran
 
Khatm e nabuwat 2
Khatm e nabuwat 2Khatm e nabuwat 2
Khatm e nabuwat 2Saqib Imran
 
Khatm e nabuwat 1
Khatm e nabuwat 1Khatm e nabuwat 1
Khatm e nabuwat 1Saqib Imran
 
Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Saqib Imran
 
Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Saqib Imran
 
Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Saqib Imran
 
Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Saqib Imran
 
Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Saqib Imran
 
Khatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesKhatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesSaqib Imran
 
40 hadees in urdu
40 hadees in urdu40 hadees in urdu
40 hadees in urduSaqib Imran
 
40 hadees in urdu & english
40 hadees in urdu & english40 hadees in urdu & english
40 hadees in urdu & englishSaqib Imran
 
Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notesSaqib Imran
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Saqib Imran
 
Foundations and pavements ce367
Foundations and pavements   ce367Foundations and pavements   ce367
Foundations and pavements ce367Saqib Imran
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Saqib Imran
 

More from Saqib Imran (20)

Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notes
 
Misaali mard مثالی مرد
Misaali mard مثالی مردMisaali mard مثالی مرد
Misaali mard مثالی مرد
 
Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2Khatm e nubuwwat lesson no 2
Khatm e nubuwwat lesson no 2
 
Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1Khatm e nubuwwat lesson no 1
Khatm e nubuwwat lesson no 1
 
Khatm e nabuwat 4
Khatm e nabuwat 4Khatm e nabuwat 4
Khatm e nabuwat 4
 
Khatm e nabuwat 3
Khatm e nabuwat 3Khatm e nabuwat 3
Khatm e nabuwat 3
 
Khatm e nabuwat 2
Khatm e nabuwat 2Khatm e nabuwat 2
Khatm e nabuwat 2
 
Khatm e nabuwat 1
Khatm e nabuwat 1Khatm e nabuwat 1
Khatm e nabuwat 1
 
Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7Khatm e nubuwwat lesson no 7
Khatm e nubuwwat lesson no 7
 
Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6Khatm e nubuwwat lesson no 6
Khatm e nubuwwat lesson no 6
 
Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5Khatm e nubuwwat lesson no 5
Khatm e nubuwwat lesson no 5
 
Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4Khatm e nubuwwat lesson no 4
Khatm e nubuwwat lesson no 4
 
Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3Khatm e nubuwwat lesson no 3
Khatm e nubuwwat lesson no 3
 
Khatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadeesKhatm e nubuwwat 40 hadees
Khatm e nubuwwat 40 hadees
 
40 hadees in urdu
40 hadees in urdu40 hadees in urdu
40 hadees in urdu
 
40 hadees in urdu & english
40 hadees in urdu & english40 hadees in urdu & english
40 hadees in urdu & english
 
Engineering basic notes
Engineering basic notesEngineering basic notes
Engineering basic notes
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462
 
Foundations and pavements ce367
Foundations and pavements   ce367Foundations and pavements   ce367
Foundations and pavements ce367
 
Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Highway pdf

  • 1. 1 | P a g e SAQIB IMRAN 0341-7549889 1 Assala mu alykum My Name is saqib imran and I am the student of b.tech (civil) in sarhad univeristy of science and technology peshawer. I have written this notes by different websites and some by self and prepare it for the student and also for engineer who work on field to get some knowledge from it. I hope you all students may like it. Remember me in your pray, allah bless me and all of you friends. If u have any confusion in this notes contact me on my gmail id: Saqibimran43@gmail.com or text me on 0341-7549889. Saqib imran.
  • 2. 2 | P a g e SAQIB IMRAN 0341-7549889 2 HIGHWAY TYPES OF FAILURES IN FLEXIBLE PAVEMENTS The different types of failures in flexible pavements are described below: 1. Subgrade failure. 2. Base failure or base course failure. 3. Surface failure or wearing course failure. 1. SUBGRADE FAILURE: Excessive deformation in subgrade soil of a flexible failure is called subgrade failure. This is one of the main causes of failure of flexible pavements. This type of failure causes undulations (ups and downs) and corrugations in the pavement surface. Causes Of Subgrade Failure: 1. Inadequate stability. 2. Inadequate road drainage. 3. Excessive stress application. 2. BASE COURSE FAILURE: Excessive deformation in the base or foundation course of a flexible pavement is known as base course failure. This type of failure causes potholes, waves, and corrugations in the pavement surface. Causes Of Base Course Failure: 1. Insufficient strength. 2. Loss of binding action. 3. Crushing of base course material. 4. Lack of lateral confinement of the granular base course. 5. Insufficient wearing course. 6. Inadequate quality control. 7. Inadequate road drainage.
  • 3. 3 | P a g e SAQIB IMRAN 0341-7549889 3 3. SURFACE FAILURE: Excessive deformation in the wearing course of a flexible pavement is called surface failure or wearing course failure. This type of failure causes ruts, potholes, cracks etc in the pavement structure. Causes Of Surface Failure: 1. lack of proper mix design 2. Use of the inferior type of binder. 3. Inadequate quality control. 4. Volatization and oxidation of binder. RESULTS OF FLEXIBLE FAILURE: 1. RUTS: The longitudinal depressions or cuts in flexible pavement is known as ruts. These are usually formed ion earth or W.B.M roads of one lane width due to repetitive traffic wheel loads on the same location, particularly under wheeled traffic.
  • 4. 4 | P a g e SAQIB IMRAN 0341-7549889 4 2. POT HOLES: The isolated depressions, more or less circular in shape formed in flexible pavements are called pot holes or patches. These are usually formed in all types of flexible pavements due to disintegration of road metal or lack of binding surface course with the underlying base. 3. FROST HEAVING: A localized heaving up of pavement portion is known as frost heaving. The water which may find access to pavement structure freezes in cold climates. The expansion accompanying this frost action causes upheaval which in turn may crack the pavement surface.
  • 5. 5 | P a g e SAQIB IMRAN 0341-7549889 5 4. SHEAR FAILURE CRACKING: The formation of a fracture or cracking due to upheaval of pavement portion followed by a depression called shear failure cracking. This type of failure occurs due to localized weakness in the pavement. 5. LONGITUDINAL CRACKING: The formation of cracks in the longitudinal direction of a road pavement is called longitudinal cracking. This failure is caused due to frost action, different volume changes in subgrade, settlement of filling material or due to sliding of side slopes.
  • 6. 6 | P a g e SAQIB IMRAN 0341-7549889 6 6. MAP CRACKING: The development of irregular cracks, usually formed on bituminous surfacing is called map cracking. This type of flexible road failure is due to excessive wear of the road surface or due to localized weakness in the underlying base course.
  • 7. 7 | P a g e SAQIB IMRAN 0341-7549889 7 CEMENT CONCRETE ROADS – ADVANTAGES AND DISADVANTAGES Cement Concrete Road CEMENT CONCRETE ROADS: The roads having their wearing surface consisting of cement concrete (plane or reinforced) are known as cement concrete roads or concrete roads. These roads are types of rigid pavements and remain in serviceable condition under all weather conditions. Thus concrete roads are also considered as all weather roads. Due to their excellent riding surface, pleasing appearance and long life under most severe traffic conditions, cement concrete roads are much preferred. Cement concrete roads are superior to most other types of roads including bituminous roads. These roads are very popular as high cost pavements in developed countries like America, Russia, Japan etc. ADVANTAGES OF CEMENT CONCRETE ROADS: 1. Concrete roads have long life than any other roads. 2. These roads are durable and are practically unaffected by weathering agencies. 3. They provide an excellent riding surface under all weather conditions. 4. They provide an impervious, dustless and sanitary surface.
  • 8. 8 | P a g e SAQIB IMRAN 0341-7549889 8 5. They do not develop corrugations. 6 Can be laid on any subgrade. 7. Can be easily reinforced when they are to resist high stresses due to heavy wheel loads of the traffic. 8. Concrete roads are non slipery and offer less tractive resistance. 9. They provide good visibility for traffic during night hours. 10. Maintenance cost is low. DISADVANTAGES OF CEMENT CONCRETE ROADS: 1. The initial cost of concrete roads is high. 2. They are liable to crack and warp due to temperature variations. 3. Become noisy under iron-tyred traffic. 4. Skilled supervision and labour are required for construction. 5. less resilient than bituminous or W.B.M roads. 6. Require long time for curing and thus cannot be opened to traffic earlier. 7. It is very difficult to locate and repair sewers and water mains lying under the pavement in their case. COMPONENTS OF ROAD PAVEMENT STRUCTURE COMPONENTS OF ROAD PAVEMENT STRUCTURE: Following are the different components of road structure: 1. Subgrade 2. Sub-base 3. Base course 4. Surface course or wearing course All these components belong to a typical flexible pavement, whereas rigid pavement usually consists of subgrade, subbase and a concrete slab.
  • 9. 9 | P a g e SAQIB IMRAN 0341-7549889 9 1. SUBGRADE: The finished and compacted surface of earthwork on which a road pavement rests is called subgrade or formation. The subgrade of a road may be provided on an embankment, in cutting or existing ground level depending upon the topography and the finalized formation level. It consists of well compacted natural soil brought to the required camber and gradient. The thickness and type of pavement structure depend upon the supporting power of the subgrade because the entire load of the pavement, including the load of traffic transmitted through the pavement, is ultimately taken up by the subgrade. 2. SUB-BASE: A layer of granular material provided in between the subgrade and the base course in a road pavement is known as sub-base. It is provided as an additional layer when subgrade is of poor quality. It consists of a layer comparatively cheaper material like burnt clinker, natural gravel or slag. 3. BASE COURSE: A layer of boulders or bricks provided over the subbase or immediately over the subgrade in the absence of sub-base in a road pavement is called base course or soling or foundation course. This course is considered as the most important and major component of road structure because this course is to bear the impact of traffic transferred through the wearing course. It consists of a stable material like boulders, gravel, one or two layers of well- burnt bricks etc. In case of rocky subgrade, this course is not provided. 4. SURFACE COURSE OR WEARING COURSE: The topmost layer of the road pavement directly exposed to traffic is called is called wearing course or surfacing.
  • 10. 10 | P a g e SAQIB IMRAN 0341-7549889 10 It may consist of one or more number of layers in case of flexible pavements. A good wearing course should be impervious and weather resisting. it should be able to resist abrasive action of the traffic. SUPERELEVATION OF ROAD – ADVANTAGES AND DESIGN OF SUPER ELEVATION SUPERELEVATION OF ROAD: The inward transverse inclination provided to the cross-section of the carriageway at horizontally curved portion of a road is called superelevation, cant or banking. Superelevation is provided to counteract the effect of centrifugal force and to minimize the tendency of the vehicle to overturn or skid by raising the outer edge of pavement with respect to the inner edge, providing a transverse slope throughout the length of the horizontal curve. It is expressed as the ratio of elevation of the outer edge above the inner edge to the horizontal width of carriageway or as the tangent of the angle of slope of the road surface. It is generally denoted by ‘e’ or S.E. OBJECTS OF PROVIDING SUPERELEVATION: 1. To counteract the effect of centrifugal force acting on the moving vehicle to pull out the same outward on a horizontal curve. 2. To help a fast moving vehicle to negotiate a curved path without overturning and skidding.
  • 11. 11 | P a g e SAQIB IMRAN 0341-7549889 11 3. To ensure safety to the fast moving traffic. 4. To prevent damaging effect on the road surface due to improper distribution of load. ADVANTAGES OF SUPERELEVATION: 1. It allows running of vehicle at high speed on a curved path as on a straight path without any danger of overturning and thus results into increased volume of traffic. 2. It provides more or less even distribution of load on wheels and hence uniform stress is offered on the foundation which results into less wear on wheel tyres and springs as well as economy in maintenance cost of the road. 3. It also helps to keep the vehicles to their proper side on the pavement and thus prevents collision of vehicles moving in opposite directions on a curved portion of the road. 4. It provides drainage of the whole width of road towards the inner side. Thus, there is no necessity of providing side drain on the outer side of the road. DESIGN OF SUPERELEVATION: To design superelevation for mixed type of traffic is a complex problem. The Indian Roads Congress has recommended to provide superelevation to counteract the centrifugal force fully due to 75% of the design speed and limiting the maximum superelevation to 1 in 15 or 7%. Following are the steps adopted to design the superelevation of a road: Step 1: Calculate the superelevation for 75% of design speed neglecting the friction i.e f = 0 V = 75%(V) = 0.75 V We know that, e+f = V²/127R e + 0 = (0.75 V)²/127R Step 2: If the calculated value ‘e’ is less than 7% or 0.07, then provide the obtained value. If it exceeds 0.07 then provide the limiting value of superelevation emax = 0.07 and proceed to the next step.
  • 12. 12 | P a g e SAQIB IMRAN 0341-7549889 12 Step 3: Check the coefficient of friction developed for the maximum value of e = 0.07 at the full value of design speed, If the value of ‘f’ thus calculated is less than 0.15, the superelevation of 0.07 is safe for the design speed. If not, calculate the restricted speed as given in step 4. Step 4: If the calculated value of ‘f’ exceeds 0.15, then the speed of the vehicles is restricted to the value Vr m/sec or Vr km/hr as calculated after allowing the limiting values of e and f in the following equation:
  • 13. 13 | P a g e SAQIB IMRAN 0341-7549889 13 In case of an important highway, it is always desirable to design the road without speed restriction at curves. Hence, the curve should be realigned, if possible with a longer radius of curvature so that the design speed can be maintained without any restriction. DIFFERENCE BETWEEN FLEXIBLE PAVEMENTS AND RIGID PAVEMENTS FLEXIBLE PAVEMENTS: The pavements having low or negligible flexural strength and are flexible in their structural action under the loads are known as flexible pavements. RIGID PAVEMENTS: Rigid pavements are those which contain great amount of flexural strength or flexural rigidity. In rigid pavements, the stresses are not transferred from grain to grain to the lower layers as in the ease of flexible pavement layers. DIFFERENCE BETWEEN FLEXIBLE PAVEMENTS AND RIGID PAVEMENTS: POINT OF DIFFERENCE FLEXIBLE PAVEMENTS RIGID PAVEMENTS Initial cost Their initial cost is low. Their initial cost is high. Life span They have short life span. They have long life span. Thickness Their thickness is more. Their thickness is less. Joints Joints are not required. Joints are essentially required. Subgrade A reasonably good subgrade is required. A good subgrade is not necessary. Durability They are less durable They are more durable. Temperature effect Stresses are not induced in these pavements due Heavy stresses are induced in these
  • 14. 14 | P a g e SAQIB IMRAN 0341-7549889 14 to temperature variations. pavements due to temperature variations. Repair work Easy repair work. Difficult to repair. Skill and supervision Moderate skill and less supervision are required. More skill and supervision is required. Feasibility of providing underground works It is easy to lay, locate or repair underground pipes below these pavements. It is very difficult to provide or repair underground pipes below these pavements. Openings to traffic after construction Can be opened to traffic shortly after construction. Require curing after construction and thus cause delay in opening to traffic. Resiliency More resilient to traffic load. Less resilient to traffic load. Corrugations They develop corrugations. No corrugations are developed in these pavements. Behavior with subgrade settlement. They adjust according to any deformation of subgrade without rupture. They do not adjust according to any deformation of subgrade without rupture. Tractive resistance They have more tractive resistance. They have less tractive resistance. Traffic suitability Suitable for all types of traffic. Noisy under iron wheeled traffic. Night visibility Blacktop pavements provide poor visibility at night. They offer good visibility at night. Glaring effect They do not usually cause glare due to reflected sunlight. They often cause glare due to reflected sunlight. Feasibility of stage development Stage development is feasible. Stage development is not feasible.
  • 15. 15 | P a g e SAQIB IMRAN 0341-7549889 15 Effect Of loading They adjust themselves to normal loading by undergoing elastic deformation. They tend to act as a beam or cantilever and resist deformation. Maintenance cost Maintenance cost is high. Maintenance cost is low. WHAT IS BITUMEN AND ITS USES WHAT IS BITUMEN AND ITS USES: Bitumen is the binding material present in asphalt. Sometimes it is also known as mineral tar. Bitumen is produced by partial distillation of crude petroleum. it is chemically a hydrocarbon and insoluble in water. But it totally dissolves in alkalies, alkaline carbonates, benzol, chloroform, bisulphide, naptha, coal tar, petroleum spirit and oil of turpentine. It is obtained from 87% carbon, 11% hydrogen and 2% oxygen (By weight). The bitumen is produced in solid or semi-solid state and black or brown in color. FORMS OF BITUMEN: The general forms of bitumen are as following
  • 16. 16 | P a g e SAQIB IMRAN 0341-7549889 16 1. BITUMEN EMULSION: It is a liquid compound which contains a large amount of bitumen in aqueous medium. It is suspended by some appropriate stabilizing agents in the aqueous medium. 2 CUT-BACK BITUMEN: This form of bitumen is produced by fluxing asphaltic bitumen in presence of some liquid distillates of petroleum or coal tar. Cut-back bitumen can be used as bitumen paint in cold. 3 BLOWN BITUMEN: It is a special form of bitumen produced by passing air under pressure at a higher temperature. This type of bitumen can be used as heat insulating material, roofing and damp-proofing felts, producing asphalt pipe and joint fillers etc. 4 PLASTIC BITUMEN: It comprises of bitumen thinner and appropriate inert filler (40%-45%). Plastic bitumen can be used for filling cracks in masonry structures, stopping leakages etc. 5 STRAIGHT RUN BITUMEN: This type of bitumen is obtained by distillation of the bitumen to a definite viscosity or penetration without further treatment: APPLICATION OF BITUMEN:  Road Construction.  Hydraulics & erosion control Catchment areas, basins.  Dam groutings,  Dam linings,  Embankment protection  Dam linings,  Embankment protection  Ditch linings, Reservoir linings  Reservoir linings  Jetties, Dyke protection  Dyke protection  Swimming pools  Waste ponds  Water barriers  Mattresses for levee & bank protection  Membrane linings,  Waterproofing  Revetments
  • 17. 17 | P a g e SAQIB IMRAN 0341-7549889 17  Sand dune stabilization,  Drainage gutters,  Backed felts FIELD DENSITY TEST OF SOIL BY SAND CONE METHOD FIELD DENSITY TEST ( SAND CONE METHOD): The sand cone method is one of the most common methods that are used for field density test in highway construction. The dry density test is carried out in the field to check the compaction of the layers. Compaction is very useful for preparing the sub-base grade and other layers of pavement. Compaction is done in the construction of embankment for increasing the stability as well as for decreasing the settlement. In field compaction, the compacting moisture content should be controlled first and the adequacy of rolling should be controlled by checking the achieved dry density and comparing with the maximum dry density. Base layer – 98% Sub base layer – 98% Type 1 layer – 95 % ABC layer – 100% PROCEDURE OF TEST: 1. First, take the weight of the empty sand cone and then fill it with dry sand and then weight again.
  • 18. 18 | P a g e SAQIB IMRAN 0341-7549889 18 2. Collect the excavated soil from the hole and measure the weight. 3. After weighting, collect the specimen of soil to determine the water content in it. 4. Now place the sand cone on the test hole with the help of the base plate and allow the sand to run by opening the control valve. 5. When the sand stops running, close the valve and weight the cone with the existing sand. Finally, calculate the dry density of the soil by given below formula. If the test fails, compact and perform the test again. CALCULATION: The volume of the hole = Mass of sand in hole/Density of used sand. Wet density = Mass of wet excavated soil/Volume of hole Dry density = Wet density × 100%/ Moisture content of soil + 100 Degree of compaction = Dry density × 100%/Maximun dry density. TYPES OF ROAD CAMBER- ADVANTAGES AND METHODS OF PROVIDING CAMBER WHAT IS CAMBER? Camber is the slope provided to the road surface in the transverse direction to drain off the rainwater from the road surface. It is also known as cross slope of road. WHY CAMBER IS PROVIDED IN ROAD? 1. To protect the road by preventing the entry of surface water into the subgrade soil through pavement. 2. To prevent the entry of water into the bituminous pavement layers.
  • 19. 19 | P a g e SAQIB IMRAN 0341-7549889 19 3. To remove the rainwater from the pavement surface as quickly as possible and to allow the pavement to get dry soon after the rain. TYPES OF CAMBER: 1. COMPOSITE CAMBER: It consists of two straight slopes from the edges with a parabolic or circular crown in the center of camber. This type of camber can be easily constructed and maintained. 2. SLOPED OR STRAIGHT CAMBER: It consists of two straight slopes from the edges joining at the center of the carriageway. This type of camber is very simple and can be easily constructed and maintained. 3. PARABOLIC OR BARREL CAMBER: It consists of a continuous curve either elliptical or parabolic. It provides a flat road surface at the middle and steeper towards the edges. On account of steeper edges, this type of camber provides better drainage property. This camber is therefore preferred by fast moving vehicles and suggested for urban roads.
  • 20. 20 | P a g e SAQIB IMRAN 0341-7549889 20 This type of camber is difficult to construct and maintain. The barrel camber has more steeper edges which are inconvenient to use. Moreover, the steeper edges are errored quickly and hence additional kerbs are to be provided. ADVANTAGES OF CAMBER: 1. Camber provides quick drainage of rainwater and thus saves the foundation course of the road structure from weakening by percolation of rainwater to it through the road surface. 2. This prevents rainwater to accumulate in local shrinkages or depressions and forming water pool on the road surface, which are disagreeable to the public as well as to the road structure. METHOD OF PROVIDING CAMBER: Usually, camber is provided on the straight roads by raising the center of the carriageway with respect to the edges, forming a crown or highest point on the center line. At horizontal curves with superelevation, the surface drainage is effected by raising the outer edge of pavement with respect to the inner edge while providing the desired superelevation. the rate of camber or cross slope is usually designed by 1 in ‘n’ which means the transverse slope is in ratio 1 vertical to “n” horizontal. Camber is also expressed in percentage. If the camber is x %, the cross slope is x in 100.
  • 21. 21 | P a g e SAQIB IMRAN 0341-7549889 21 RECOMMENDED VALUES OF CAMBER FOR DIFFERENT TYPES OF ROAD SURFACES BY IRC: TYPES OF CURVES ON HILL ROADS TYPES OF CURVES ON HILL ROADS: The types of curves provided on hill roads are as following: 1 Hair-pin curves, 2 salient curves, 3 Re-entrant curves. 1. HAIR-PIN CURVES: ‘The curve in a hill road which changes its direction through an angle of 180 or so, down the hill on the same side is known as hair-pin curve.
  • 22. 22 | P a g e SAQIB IMRAN 0341-7549889 22 This curve is so called because it conforms to the shape of a hair-pin. The bend so formed at the hair-pin curve in a hill road is known as pin bend. This type of curve should be located on hill side having the minimum slope and maximum stability. It must also be safe from the view point of land slides and ground water. Hair-pin bends with long arms and farther spacing are always preferred. They reduce construction problems and expensive protective works. Hair-pin curves or bends of serpentine nature are difficult to negotiate and should, therefore,e be avoided as far as possible. 2. SALIENT CURVES: The curves having their convexity on the outer edges of a hill road are called salient curves. The center of curvature of a salient curve lies toward the hill side. This type of curve occurs in the road length constructed on the ridge of a hill. The bend so formed at the salient curve in hill road is known as corner bend.
  • 23. 23 | P a g e SAQIB IMRAN 0341-7549889 23 Salient curves are very dangerous for fast-moving traffic. At such a curve or at corner bend, the portion of projecting hill side is usually cut down to improve the visibility. The outer edge of the road at such a curve is essentially provided with a parapet wall for protection of the vehicles from falling down the hill slope. 3. RE-ENTRANT CURVES: The curves having their convexity on the inner edge of a hill road are called re-entrant curve. The center of curvature of a re-entrant curve lies away from the hill side. This type of curve occurs in the road length constructed in the valley of a hill.
  • 24. 24 | P a g e SAQIB IMRAN 0341-7549889 24 These curves are less dangerous as they provided adequate visibility to the fast-moving traffic. At such curves, the parapet wall is provided only for safety of fast-moving traffic.