SlideShare a Scribd company logo
1 of 15
PROJECT : FLYOVER
LOCATION :
NATIONAL HIGHWAY NH3
MANGLIYA,INDORE
CLIENT : NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI)
CONTRACTOR : INDORE DEWAS TOLLWAYS LTD.
SUB CONTRACTOR : GAYATRI PROJECTS PVT. LTD.
TEAM LEADER : Mr. AJAY PANDEY
PROJECT MANAGER : Mr.H.K.KATARE
AIM OF THE PROJECT
Following Is The Objective Of The Project:
SIX LANING OF INDORE-DEWAS SECTION OF NH-3 FROM 577.550 KM TO 610.000KM AND 0.000KM
TO 12.600KM
APPROX. LENGTH :45.05KM
LENGTH OF FLYOVER(APPROX.): 1KM
In the state of MADHYA PRADESH under NHDP phase V to be executed as BOT(toll) project on Design, Build,
Finance, Operate and Transfer “DBFOT” Pattern
FOUNDATION : PILE FOUNDATION
PROCESS FOR PREPARING PILE SHAFT :
 EXCAVATION OF PILE SHAFT.
 VERTICALITY OF THE CASING SHOULD BE MAINTAINED.
 WATER WILL BE PUMPED INTO THE CASING DURING THE EXCAVATION AND A CONSTANT WATER HEAD
WILL BE MAINTAINED SO AS TO PREVENT ENTRY OF ANY INGRESS MATERIAL FROM BOTTOM OF THE
CASING.
 THE EXCAVATION MUST BE DONE TILLA HARD STRATUM IS OBTAINED.
 REINFORCEMENT FOR THE CIRCULAR PIER AS PER DRAWING IS ERECTED
 CONCRETING IS DONE BY EMPLOYING SHUTTERING TO THE EXCAVATED PILE SHAFT USING RMC (READY
MIX CONCRETE).
SPAN OR DECK
It is the superstructure which bears the traffic load. It is a flat surface supported by
girders or beams and finished by coats of asphalt and concrete.
Deck slab is a concrete slab supported over precast, post tensioned concrete
girders.
Antiskid bituminous mastic coat 25mm thick can be provided as wearing coat.
Precast: The component is fabricated(i.e., concrete is cast) in a plant or factory.
Post-tensioning: When tensioning of strands or tendons is done after the concrete
is poured, it is called post-tensioning
GIRDERS
GIRDER
BEAM
GIRDER
BEAM
FLOOR
BEAM
STRINGER
BEAM STRINGER
BEAM
Girder is that part of superstructure that supports the
deck and transfers the load from deck to the abutment
or piers.
Longer spans, large traffic loads and wider spacing
between girders result in more depth of girders.
 Post tensioned simply supported prestressed concrete
(PC) I-girder bridges are widely used bridge system
for short to medium span (20m to 50m) highway
bridges due to its moderate self weight, structural
efficiency, ease of fabrication, low maintenance etc.
 In order to compete with steel bridge systems, the
design of PC I-girder Bridge system must lead to the
most economical use of materials.
PIERS :
 Wherever possible slender piers should be used so that there is sufficient flexibility to allow
temperature, shrinkage and creep effects to be transmitted to the abutments without the need
for bearings at the piers, or intermediate joints in the deck.
 Loads transmitted by bridge deck onto the piers:
 Vertical loads from self weight of deck
 Vertical loads from live loading conditions
 Horizontal loads from temperature, creep movements etc and wind
 Rotations due to deflection of the bridge deck.
A pier cap is a precast concrete structure which rests on a bridge pier and transfers the
concentrated loads from the bridge deck to the bridge piers.
PIER CAP :
PIER
PIER CAP
BEARING :
A bridge bearing is an element of superstructure which provides an interface between the superstructure and substructure. This
interface is vital because superstructure undergoes dimensional changes and deformations due to various factors which are listed as
follows:
 Thermal expansion/contraction
 Elastic deformation under live load
 Seismic forces
 Creep and shrinkage of concrete
 Settlement of supports
 Longitudinal forces - tractive/ breaking
 Wind loads.
If the movement between the superstructure and substructure are not allowed to take place freely, large amount of forces may
develop in the girder or the substructure. If the ability to move is not built into the bridge (span), it will push the supports until it
achieves the freedom required and in the process causing damage to the supports.
It is, therefore, necessary to permit relative movement between the girders and the substructure. Since the bearing is introduced
between superstructure and substructure for accommodating the various permitted movements, it has to transfer the entire load
from superstructure to the substructure of bridge.
CROSS SECTIONAL ELEMENTS:
 LANE WIDTH:
In general, safety increases with wider lanes up to a width of about 3.7 m. The lane width as per IRC: 73-1980 is 3.5 m for design speed of 100 kmph.
 SHOULDER:
Shoulders provide recovery area for errant vehicles; a refuge for stopped or disabled vehicles; and access for emergency and maintenance vehicles. Shoulders
can also provide an opportunity to improve sight distance through large cut sections. As per NHAI Guide lines 1.5m paved shoulder and 1.0m gravel
shoulder is proposed.
 MEDIANS:
Medians on divided highways serve a variety of important purposes related to safety, traffic operations, access control and aesthetics, including physical
separation of opposing traffic flows; storage area for right-turning vehicles; provision of pedestrian refuge space. As per NHAI Guidelines 4.5m raised
median width in Rural as well as Urban section is proposed.
 PAVEMENT CAMBER:
As per IRC: 73-1980 design standards recommend Consultants propose a camber of 2.5% for the main carriageway as well as the paved shoulders, and 3.5%
for unpaved (gravel) shoulders.
 SUPERELEVATION:
Super elevation is provided for all the horizontal curves with radius less than 2000 m in order to counteract the effect of centrifugal force. As per IRC : 38 -
1988, super elevation to fully counteract the centrifugal force for 75% of the design speed of 100 kmph neglecting the lateral friction developed is adopted in
design.The maximum super elevation is limited to 7% as per codal requirement.
ABUTMENT
An Abutment is a substructure at the end of span on which the superstructure ,.i.e,
deck of the slab rests.
Functions of abutment wall :
To transfer load from the superstructure to the
foundation.
To resist or transfer self weight, lateral loads such
as earth pressure and wind loads.
To support one end of approach slab.
In case of multispan bridge, the end span is supported by abutment and the
intermediate span is supported by piers.
PANEL FACED REINFORCED EARTH RETAINING
WALL
Reinforced soil/earth is the composite of frictional soil and
tension resistant material such as plastic, synthetic and fibre
reinforced materials which restrict tensile strain which might
develop under gravity and boundary forces.
Geogrids are often used for reinforcing the soil. They are
poly vinyl chloride(pvc) coated. They resist settlement of soil
due to imposed load as the withstand these loads by virtue of
their elastic property.
These panels are interlocked with each other and are erected
as per their shapes so that they rest one over another on a
bearing pad and a key is used to maintain the position of the
erected panel,however,after some time the key is removed
and verticality of the wall is maintained.
METHOD OF CONSTRUCTION:
LEVELLING PAD
Levelling pad is prepared by compactors and rollers to place the
panels.The thickness of levelling pad is as per requirements.
 PLACE THE PANELS ON BEARING PAD
The panels are placed on the bearing pads so as to bear shocks due to
applied loads by virtue of their elastic property.
ERECT AND VERTICALLY ALIGN THE
PANELS
The panels are vertically aligned and placed one over another so that they
are interlocked and their alignment is maintained.
BRACINGS ARE PLACED TO MAINTAIN THE
POSITION OF THE PANELS
The bracings are temporarily placed and horizontal joints are provided.
BACKFILLING AND COMPACTION
The backfilling is done by laying the excavated soil along with coarse aggregate,murram and churi and compaction is
done by rollers and surface vibrators.
LAYING OF GEOGRIDS
 Geogrids are laid in transverse direction connected to a plastic pipe at one end which is stuck to the panel.These
are fixed to the compacted soil so that they do not move.
 Geogrids are synthetic material used to reinforce soil.It is made by using polymer materials such as
polyethene,polyster or polypropylene.Soil pulls apart under tension but geogrids are much stronger in tension hence
transfer load to a wider area.Moreover,due to their elastic property,they reduce settlement of soil. Soil on one side
of geogrid interlocks with soil on other side on compaction.
BACKFILLING AND COMPACTION
ERECTION OF PANELS UPTO REQUIRED
HEIGHT BY SEBSEQUENT LAYING OF
GEOGRIDS AND BACKFILL AND
COMPACTING THE FILL
CRASH BARRIER:
Crash barriers keep vehicles within their roadway and prevent vehicles from
colliding with dangerous obstacles such as boulders, buildings, walls or large
storm drains.
Crash barriers are installed within medians of divided
highways to prevent errant vehicles from entering the
opposing carriageway of traffic and help to reduce
head-on collisions.
While barriers are normally designed to minimize injury
to vehicle occupants, injuries do occur in collisions with
traffic barriers. They should only be installed where a
collision with the barrier is likely to be less severe than a collision with the
hazard behind it. Where possible, it is preferable to remove, relocate or modify a
hazard, rather than shield it with a barrier.
THANK YOU FOR YOUR PATIENCE
• PROJECT REPORT BY :
SACHIN DEWANI (4th YEAR,CIVIL ENGG.)
SIKKIM MANIPAL INSTITUTE OF TECHNOLOGY, SIKKIM
FOR: DEPARTMENT OF CIVIL ENGG.,
SIKKIM MANIPAL INSTITUTE OF TECHNOLOGY, SIKKIM

More Related Content

What's hot

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elementssubbu lakshmi
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONTEJPRAKASH KUMAWAT
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its typesprathiekraj1
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge constructionKundan Sanap
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC BridgePRASUNMANI
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Chandan Singh
 

What's hot (20)

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Bridge report
Bridge reportBridge report
Bridge report
 
flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
Box culverts
Box culvertsBox culverts
Box culverts
 
ppt
pptppt
ppt
 
Segmental bridge
Segmental bridgeSegmental bridge
Segmental bridge
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTIONHIGH FLOOD LEVEL BRIDGE CONSTRUCTION
HIGH FLOOD LEVEL BRIDGE CONSTRUCTION
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its types
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 
Training report - RCC Bridge
Training report - RCC BridgeTraining report - RCC Bridge
Training report - RCC Bridge
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 

Similar to PROJECT

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Construction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewConstruction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewSourav Goswami
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...IRJET Journal
 
journal publishing, how to publish research paper, Call For research paper, i...
journal publishing, how to publish research paper, Call For research paper, i...journal publishing, how to publish research paper, Call For research paper, i...
journal publishing, how to publish research paper, Call For research paper, i...IJERD Editor
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESIRJET Journal
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfOmarAbdi39
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesRaghvendraBajpai3
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technologyGedalaJairam
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavementAminat Aliu
 
Pile Foundation Associated to Metro Rail Hyderabad
Pile Foundation Associated to Metro Rail HyderabadPile Foundation Associated to Metro Rail Hyderabad
Pile Foundation Associated to Metro Rail Hyderabadpaperpublications3
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 

Similar to PROJECT (20)

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Construction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewConstruction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An Overview
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
 
journal publishing, how to publish research paper, Call For research paper, i...
journal publishing, how to publish research paper, Call For research paper, i...journal publishing, how to publish research paper, Call For research paper, i...
journal publishing, how to publish research paper, Call For research paper, i...
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdf
 
M1303078488
M1303078488M1303078488
M1303078488
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic Wastes
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavement
 
Pile Foundation Associated to Metro Rail Hyderabad
Pile Foundation Associated to Metro Rail HyderabadPile Foundation Associated to Metro Rail Hyderabad
Pile Foundation Associated to Metro Rail Hyderabad
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 

PROJECT

  • 1. PROJECT : FLYOVER LOCATION : NATIONAL HIGHWAY NH3 MANGLIYA,INDORE
  • 2. CLIENT : NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) CONTRACTOR : INDORE DEWAS TOLLWAYS LTD. SUB CONTRACTOR : GAYATRI PROJECTS PVT. LTD. TEAM LEADER : Mr. AJAY PANDEY PROJECT MANAGER : Mr.H.K.KATARE
  • 3. AIM OF THE PROJECT Following Is The Objective Of The Project: SIX LANING OF INDORE-DEWAS SECTION OF NH-3 FROM 577.550 KM TO 610.000KM AND 0.000KM TO 12.600KM APPROX. LENGTH :45.05KM LENGTH OF FLYOVER(APPROX.): 1KM In the state of MADHYA PRADESH under NHDP phase V to be executed as BOT(toll) project on Design, Build, Finance, Operate and Transfer “DBFOT” Pattern
  • 4. FOUNDATION : PILE FOUNDATION PROCESS FOR PREPARING PILE SHAFT :  EXCAVATION OF PILE SHAFT.  VERTICALITY OF THE CASING SHOULD BE MAINTAINED.  WATER WILL BE PUMPED INTO THE CASING DURING THE EXCAVATION AND A CONSTANT WATER HEAD WILL BE MAINTAINED SO AS TO PREVENT ENTRY OF ANY INGRESS MATERIAL FROM BOTTOM OF THE CASING.  THE EXCAVATION MUST BE DONE TILLA HARD STRATUM IS OBTAINED.  REINFORCEMENT FOR THE CIRCULAR PIER AS PER DRAWING IS ERECTED  CONCRETING IS DONE BY EMPLOYING SHUTTERING TO THE EXCAVATED PILE SHAFT USING RMC (READY MIX CONCRETE).
  • 5. SPAN OR DECK It is the superstructure which bears the traffic load. It is a flat surface supported by girders or beams and finished by coats of asphalt and concrete. Deck slab is a concrete slab supported over precast, post tensioned concrete girders. Antiskid bituminous mastic coat 25mm thick can be provided as wearing coat. Precast: The component is fabricated(i.e., concrete is cast) in a plant or factory. Post-tensioning: When tensioning of strands or tendons is done after the concrete is poured, it is called post-tensioning
  • 6. GIRDERS GIRDER BEAM GIRDER BEAM FLOOR BEAM STRINGER BEAM STRINGER BEAM Girder is that part of superstructure that supports the deck and transfers the load from deck to the abutment or piers. Longer spans, large traffic loads and wider spacing between girders result in more depth of girders.  Post tensioned simply supported prestressed concrete (PC) I-girder bridges are widely used bridge system for short to medium span (20m to 50m) highway bridges due to its moderate self weight, structural efficiency, ease of fabrication, low maintenance etc.  In order to compete with steel bridge systems, the design of PC I-girder Bridge system must lead to the most economical use of materials.
  • 7. PIERS :  Wherever possible slender piers should be used so that there is sufficient flexibility to allow temperature, shrinkage and creep effects to be transmitted to the abutments without the need for bearings at the piers, or intermediate joints in the deck.  Loads transmitted by bridge deck onto the piers:  Vertical loads from self weight of deck  Vertical loads from live loading conditions  Horizontal loads from temperature, creep movements etc and wind  Rotations due to deflection of the bridge deck. A pier cap is a precast concrete structure which rests on a bridge pier and transfers the concentrated loads from the bridge deck to the bridge piers. PIER CAP : PIER PIER CAP
  • 8. BEARING : A bridge bearing is an element of superstructure which provides an interface between the superstructure and substructure. This interface is vital because superstructure undergoes dimensional changes and deformations due to various factors which are listed as follows:  Thermal expansion/contraction  Elastic deformation under live load  Seismic forces  Creep and shrinkage of concrete  Settlement of supports  Longitudinal forces - tractive/ breaking  Wind loads. If the movement between the superstructure and substructure are not allowed to take place freely, large amount of forces may develop in the girder or the substructure. If the ability to move is not built into the bridge (span), it will push the supports until it achieves the freedom required and in the process causing damage to the supports. It is, therefore, necessary to permit relative movement between the girders and the substructure. Since the bearing is introduced between superstructure and substructure for accommodating the various permitted movements, it has to transfer the entire load from superstructure to the substructure of bridge.
  • 9. CROSS SECTIONAL ELEMENTS:  LANE WIDTH: In general, safety increases with wider lanes up to a width of about 3.7 m. The lane width as per IRC: 73-1980 is 3.5 m for design speed of 100 kmph.  SHOULDER: Shoulders provide recovery area for errant vehicles; a refuge for stopped or disabled vehicles; and access for emergency and maintenance vehicles. Shoulders can also provide an opportunity to improve sight distance through large cut sections. As per NHAI Guide lines 1.5m paved shoulder and 1.0m gravel shoulder is proposed.  MEDIANS: Medians on divided highways serve a variety of important purposes related to safety, traffic operations, access control and aesthetics, including physical separation of opposing traffic flows; storage area for right-turning vehicles; provision of pedestrian refuge space. As per NHAI Guidelines 4.5m raised median width in Rural as well as Urban section is proposed.  PAVEMENT CAMBER: As per IRC: 73-1980 design standards recommend Consultants propose a camber of 2.5% for the main carriageway as well as the paved shoulders, and 3.5% for unpaved (gravel) shoulders.  SUPERELEVATION: Super elevation is provided for all the horizontal curves with radius less than 2000 m in order to counteract the effect of centrifugal force. As per IRC : 38 - 1988, super elevation to fully counteract the centrifugal force for 75% of the design speed of 100 kmph neglecting the lateral friction developed is adopted in design.The maximum super elevation is limited to 7% as per codal requirement.
  • 10. ABUTMENT An Abutment is a substructure at the end of span on which the superstructure ,.i.e, deck of the slab rests. Functions of abutment wall : To transfer load from the superstructure to the foundation. To resist or transfer self weight, lateral loads such as earth pressure and wind loads. To support one end of approach slab. In case of multispan bridge, the end span is supported by abutment and the intermediate span is supported by piers.
  • 11. PANEL FACED REINFORCED EARTH RETAINING WALL Reinforced soil/earth is the composite of frictional soil and tension resistant material such as plastic, synthetic and fibre reinforced materials which restrict tensile strain which might develop under gravity and boundary forces. Geogrids are often used for reinforcing the soil. They are poly vinyl chloride(pvc) coated. They resist settlement of soil due to imposed load as the withstand these loads by virtue of their elastic property. These panels are interlocked with each other and are erected as per their shapes so that they rest one over another on a bearing pad and a key is used to maintain the position of the erected panel,however,after some time the key is removed and verticality of the wall is maintained.
  • 12. METHOD OF CONSTRUCTION: LEVELLING PAD Levelling pad is prepared by compactors and rollers to place the panels.The thickness of levelling pad is as per requirements.  PLACE THE PANELS ON BEARING PAD The panels are placed on the bearing pads so as to bear shocks due to applied loads by virtue of their elastic property. ERECT AND VERTICALLY ALIGN THE PANELS The panels are vertically aligned and placed one over another so that they are interlocked and their alignment is maintained. BRACINGS ARE PLACED TO MAINTAIN THE POSITION OF THE PANELS The bracings are temporarily placed and horizontal joints are provided.
  • 13. BACKFILLING AND COMPACTION The backfilling is done by laying the excavated soil along with coarse aggregate,murram and churi and compaction is done by rollers and surface vibrators. LAYING OF GEOGRIDS  Geogrids are laid in transverse direction connected to a plastic pipe at one end which is stuck to the panel.These are fixed to the compacted soil so that they do not move.  Geogrids are synthetic material used to reinforce soil.It is made by using polymer materials such as polyethene,polyster or polypropylene.Soil pulls apart under tension but geogrids are much stronger in tension hence transfer load to a wider area.Moreover,due to their elastic property,they reduce settlement of soil. Soil on one side of geogrid interlocks with soil on other side on compaction. BACKFILLING AND COMPACTION ERECTION OF PANELS UPTO REQUIRED HEIGHT BY SEBSEQUENT LAYING OF GEOGRIDS AND BACKFILL AND COMPACTING THE FILL
  • 14. CRASH BARRIER: Crash barriers keep vehicles within their roadway and prevent vehicles from colliding with dangerous obstacles such as boulders, buildings, walls or large storm drains. Crash barriers are installed within medians of divided highways to prevent errant vehicles from entering the opposing carriageway of traffic and help to reduce head-on collisions. While barriers are normally designed to minimize injury to vehicle occupants, injuries do occur in collisions with traffic barriers. They should only be installed where a collision with the barrier is likely to be less severe than a collision with the hazard behind it. Where possible, it is preferable to remove, relocate or modify a hazard, rather than shield it with a barrier.
  • 15. THANK YOU FOR YOUR PATIENCE • PROJECT REPORT BY : SACHIN DEWANI (4th YEAR,CIVIL ENGG.) SIKKIM MANIPAL INSTITUTE OF TECHNOLOGY, SIKKIM FOR: DEPARTMENT OF CIVIL ENGG., SIKKIM MANIPAL INSTITUTE OF TECHNOLOGY, SIKKIM