SlideShare a Scribd company logo
1 of 61
MAB1053
Bridge Engineering
Introduction
Prof. Dr. Azlan Abdul Rahman
Faculty of Civil Engineering, UTM,
Course Objectives




Upon completion of the course, participants will be able to:
Identify types, structural forms & design process of common
concrete bridges.
Perform basic calculations of bridge live loading based on
BS5400, BD37/01 & JKR Specification.
Use LUSAS finite element program for basic analysis of
concrete bridge deck.
Perform calculations for the basic design of prestressed
concrete bridge beam, bridge abutment and pier.
CONTENT WEEK/DATE LECTURER CONTENT WEEK/DATE LECTURER
• INTRODUCTION 4.0 METHODS FOR
BRIDGEDECK
ANALYSIS
- Introduction to Bridge Deck
Analysis
- Orthotropic Plate Theory
- Grillage Analysis
- Finite Element Analysis
- LUSASSoftware
- Worked Example
- Introduction to Bridges W1 (12/7/07) Ir. Dr. Wahid
- Choice of Bridge Decks W2 (19/7/07) Prof. Azlan
W8 (30/8/07) Dr. Redzuan
W9 (6/9/07) Dr. Redzuan
W10 (13/9/07)
W11 (20/9/07)
1st Ramadhan
Dr. Redzuan
W12(27/9/07) Dr. Redzuan
2.0 BRIDGE 5.0 PRESTRESSED
CONCRETE BRIDGE
- Fundamentals ofPrestressed
Concrete
- Design of Post-Tensioned
Concrete Beam
- Composite Prestressed
Concrete
SUB-STRUCTURE
- Bridge Abutments & Piers
- Bridge Bearings & Joints
W3 (26/7/07)
W4 (2/8/07)
Prof. Azlan
Prof. Azlan
W13 (4/10/07) Ir. Dr. Wahid
- General Bridge Loading W5 (9/8/07) Prof. Azlan W14(11/10/07) Ir. Dr. Wahid
W15(18/10/07) Ir. Dr. Wahid
3.0 BRIDGE LOADING
- General Bridge Loading
- Live Loads to BS5400 &
W6 (16/8/07) Prof. Azlan
BD37/01 & JKR Live W7 (23/8/07) Sem. Break
Loads
- Examples
Lecture Time Table
Introduction to Bridges
MAB1053
Bridge Engineering
What is a bridge?
 A bridge is a structure that spans a divide
such as:
• A stream/river/ravine/valley
• Railroad track/roadway/waterway
 The traffic that uses a bridge
may include:
• Pedestrian or cycle traffic
• Vehicular or rail traffic
• Water/gas pipes
• A combination of all the above
Function of A Bridge
 A bridge has to carry a service (which
may be highway or railway traffic, a
footpath, public utilities, etc.) over an
obstacle (which may be another road or
railway, a river, a valley, etc.) and to
transfer the loads from the service to the
foundations at ground level.
Classification of Bridges






According to functions : aqueduct, viaduct, highway,
pedestrian etc.
According to materials of construction : reinforced concrete,
prestressed concrete, steel, composite, timber etc.
According to form of superstructure : slab, beam, truss, arch,
suspension, cable-stayed etc.
According to interspan relation : simple, continuous,
cantilever.
According to the position of the bridge floor relative to the
superstructure : deck, through, half-through etc.
According to method of construction : pin-connected, riveted,
welded etc.
Classification of Bridges





According to road level relative to highest flood
level : high-level, submersible etc.
According to method of clearance for navigation :
movable-bascule, movable-swing, transporter
According to span : short, medium, long, right,
skew, curved.
According to degree of redundancy : determinate,
indeterminate
According to type of service and duration of use :
permanent, temporary bridge, military
General Span Types
Materials for Construction
A Typical Single Span Bridge
Basic Components of a Bridge
Bridges which Carry Loads
Mainly in Flexure
 By far the majority of bridges are of this type.
The loads are transferred to the bearings and
piers and hence to the ground by slabs or
beams acting in flexure, i.e. the bridges obtain
their load-carrying resistance from the ability of
the slabs and beams to resist bending moments
and shear forces.
 Only for the very shortest spans is it possible to
adopt a slab without any form of beam. This
type of bridge will thus be referred to generally
as a girder bridge.
Typical Beam/Girder Bridge
Bridges which Carry their
Loads Mainly as Axial
Forces


This type can be further subdivided into those bridges in
which the primary axial forces are compressive (arches)
and those in which these forces are tensile (suspension
bridges and cable-stayed bridges). Such forces normally
have to be resisted by members carrying forces of the
opposite sense.
It must not be thought that flexure is immaterial in such
structures. Certainly, in most suspension bridges, flexure
of the stiffening girder is not a primary loading in that
overstress is unlikely to cause overall failure; however, in
cable stayed bridges (particularly if the stays are widely
spaced) flexure of the girder is a primary loading.
Bridges which Carry their
Loads Mainly as Axial
Forces
Bridges which Carry their
Loads Mainly as Axial
Forces
Basic Types of Bridges
 Girder/Beam Bridge
 Truss Bridge
 Rigid Frame Bridge
 Arch Bridge
 Cable Stayed Bridge
 Suspension Bridge
Girder/Beam Bridge
• The most common and basic type
• Typical spans : 10m to 200m
Truss Bridge
• Truss is a simple skeletal structure.
• Typical span lengths are 40m to 500m.
Forces in a Truss Bridge
In design theory, the individual members of a simple truss are
only subject to tension and compression and not bending
forces. For most part, all the beams in a truss bridge are
straight.
Arch Bridges





Arches used a curved
structure which provides a high
resistance to bending forces.
Both ends are fixed in the
horizontal direction (no
horizontal movement allowed
in the bearings).
Arches can only be used
where ground is solid and
stable.
Hingeless arch is very stiff and
suffers less deflection.
Two-hinged arch uses hinged
bearings which allow rotation
and most commonly used for
steel arches and very
economical design.
Hinge-less Arch
Two hinged Arch
Arch Bridges


The three-hinged arch
adds an additional hinge at
the top and suffers very
little movement in either
foundation, but
experiences more
deflection. Rarely used.
The tied arch allows
construction even if the
ground is not solid enough
to deal with horizontal
forces.
Three-hinged Arch
Tied Arch
Forces in an Arch


Arches are well
suited to the use of
stone because they
are subject to
compression.
Many ancient and
well-known examples
of stone arches still
stand to this today.
Cable Stayed


A typical cable-stayed bridge is a continuous deck with
one or more towers erected above piers in the middle of
the span.
Cables stretch down diagonally from the towers and
support the deck. Typical spans 110m to 480m.
Cable Stay Towers
Cable stayed bridges may be classified by the
number of spans, number and type of towers, deck
type, number and arrangement of cables.
Cable Stay Arrangements
Cable Stayed Bridges
Suspension Bridge



A typical suspension bridge is a continuous deck with one or
more towers erected above piers in the middle of span. The
deck maybe of truss or box girder.
Cables pass over the saddle which allows free sliding.
At both ends large anchors are placed to hold the ends of the
cables.
Forces in Suspension Bridge
Site Information






Survey - existing ground level and site details.
Soil investigation - at least one bore-hole for each support
position to determine safe bearing pressure, aggressive
conditions and predict settlement.
Mining - details of old working and future seams.
River Board – navigation requirements, maximum flood
levels and scour problems around foundations.
Railways – frequency of trains, available track possession,
minimum headroom, position of supports and piling
techniques.
Statutory Undertakers – diversion of existing services,
provision for future services in the deck.
Site Information





Planning Authorities – normally concerned with aesthetic
appeal and the effect on local amenities.
Road Geometry – details of horizontal and vertical alignment
together with the road cross-section.
Design Standards – design live loading, visibility distances,
headroom standards and horizontal clearances.
Time – the time for design and the phasing of construction in
relation to other work.
Atmospheric Conditions – an aggressive environment may
involve high maintenance costs for steel construction and
special precautions in the detailed specification.
Conceptual Choice
Considerations
Initial conceptual choice should take account of:
 clearance requirements and the avoidance of
impact damage
 type & magnitude of loading
 topography and geology of the site
 possible erection methods
 local skills and materials
 future inspection and maintenance
 aesthetic and environmental aspects
Factors Affecting Conceptual
Choice
 The functional considerations that have greatest
influence on conceptual choice are:
 The clearance requirements (both vertically and
horizontally) and avoidance of impact
 The type and magnitude of the loading to be
carried
 The topography and geology of the site
Clearance Requirements



All bridges must be designed to ensure, as far as is
possible, that they are not struck by vehicles, vessels or
trains which may pass below them. This requirement is
normally met by specifying minimum clearances.
It must be remembered that designed values must take
into account deflections due to any loading that may occur
on the bridge structure.
Clearance requirements may thus determine the span of a
bridge and also have a significant bearing on the
construction depth. Whilst the requirements will not
normally determine precisely the type of bridge, it may well
eliminate some possibilities.
Clearance Requirements

 Typically, for example, a bridge over a major
highway would be expected to have a minimum
vertical clearance of about 5,3 metres; even this
may not protect it from accidental impact
In addition, pier positions must be such that the
likelihood of impact from errant vehicles is
minimised, both to protect the pier and the
vehicle itself. This requirement is usually
achieved by setting the pier back a reasonable
distance from the edge of the carriageway.
Clearance Requirements


Navigation authorities specify clearances over rivers,
to allow not only for the mast height and width of
vessels below the bridge, but also for particular
requirements for piers in the waterway (or on a flood
plain) to avoid excessive flow velocity and scour of
river banks.
In considering vertical clearance, a designer must bear
in mind the problems of attaining them. The approach
gradient for a highway bridge should not normally
exceed about 4% and a railway bridge much less. This
is of great importance when comparing fixed with
moving bridges.
Loading

 The type and magnitude of loading has a
significant bearing on the form of bridge.
Highway loading by its nature is impossible to
determine exactly, either in disposition or in
magnitude.
A highway bridge requires a deck on which the
traffic can run and (unless the span is so short
that a simple slab is adequate to span between
abutments) the deck must be strong enough to
distribute the loading to the main girders.
Loading
 Every country has its own specification for the magnitude of
loading on highway and railway bridges. For highway bridges
most national codes have in common a uniform loading together
with a line load (or series of point loads) to represent isolated
heavy axles. In many codes, the uniform load is of decreasing
intensity as the length of bridge increases, to allow for the
reduced probability of a concentration of heavy lorries.
 Furthermore, there are rules for multiple lane loadings,
frequently assuming that not more than two lanes are fully
loaded at any one time, again based on a probabilistic approach.
Many authorities also specify checks for a single very heavy
abnormal vehicle. In many codes, the effect of impact (dynamic
magnification) of highway loads is implicitly taken into account
by the static load specification.
Loading

 Additionally, forces arising from braking or
acceleration of vehicles, centrifugal effects on
curved bridges, temperature effects and wind
have to be taken into account where relevant.
Whilst the details of applied loads are
appropriate to the detailed design, rather than
the conceptual design of a bridge, certain
aspects enter into the concept. For example,
where heavy abnormal vehicles are specified,
the bridge will require good transverse load
distribution.
Topography & Geology of Bridge
Site



The overall topography of the site will probably determine the line of
the road or railway. Not infrequently this may mean that bridges will
have to cross other roads, railways or rivers at a substantial angle,
resulting in skew spans. Generally, the bridge site is fixed by the
geometry of the obstacle and local terrain.
The road may be on a curve; whilst it is possible to curve a bridge to
follow this, it is frequently expensive and structurally inefficient,
usually dictating the use of torsionally stiff girders even for short
spans. If the curve is slight, it may be preferable to construct the
bridge as a series of straight spans.
Poor foundation conditions will favour fewer foundations and hence
longer spans. A balance has to be found between the cost of
foundations and superstructure to minimise the total cost.
Other Factors
Method of Erection
 It has long been appreciated that a designer must consider
at the design stage the method by which a bridge will be
erected. Indeed it is not infrequently the case that such
consideration should be made even at the time of
conceptual choice, since it can happen that the
superficially most attractive design is impossible to erect in
a particular location.
 For example, a design that relies on being erected in large
pieces (such as a major box girder), may be ruled out
because of the impossibility of transporting such pieces to
a remote site with inadequate access roads.
Other Factors
Local Constructional Skills and Materials
 A bridge should be suited to local technology. It is not sensible
to specify a sophisticated design if all the material and labour
has to be imported.
Future Inspection and Maintenance
 Lack of attention to future maintenance both at the conceptual
design and the detailed design stages would results in many
bridges, otherwise satisfactory, have deteriorated because of
difficulty in inspection and maintenance. It is particularly
important that in locations where access is difficult (either
physically or because it would cause disruption of services)
details which deteriorate should be avoided as far as possible.
This will be considered further in various respects, for example
whether a bridge should be a series of simple spans or should
be continuous.
Other Factors
Aesthetic and Environmental Aspects


 The appearance of bridges has in recent years become a
matter of considerable importance. Frequently, a scheme takes
a road or railway through an area of great natural beauty and it
is important that any structures are in keeping with these
surroundings and do not adversely affect them.
For example, it is commonly accepted that a bridge is more
aesthetically pleasing with an odd number of spans than an
even number. In addition, a degree of deepening at piers can
add to the attraction.
The 3-span structures are more attractive than the two span
ones. Hence, unless there are other contra-indications, the
conceptual choice should probably tend towards a 3-span
solution.
Estimated Bridge Costs
Detailed Design Considerations






The design development needs to make the
correct choices for:
deck structure
layout i.e. spans and structural arrangements
continuous or simple construction
proportions, i.e. span/depth ratios
reducing fabrication labour to a minimum
design for ease of construction
Basic Components of a Bridge
The two basic parts are:


 Substructure - includes the piers, the abutments and the
foundations.
Superstructure - consists of the deck structure itself,
which support the direct loads due to traffic and all the
other permanent and variable leads to which the structure
is subjected.
The connection between the substructure and the
superstructure is usually made through bearings. However,
rigid connections between the piers (and sometimes the
abutments) may be adopted, particularly in frame bridges
with tall (flexible) piers.
Substructure : Piers
Piers are of two basic types:
 Column piers - Concrete column piers may have a solid
cross-section, or a box section may be the shape chosen for
the cross-section for structural and aesthetic reasons.
 Wall piers - generally less economical and less pleasing
from an aesthetic point of view. They are very often adopted
in cases where particular conditions exist, e.g. piers in rivers
with significant hydrodynamic actions or in bridges with tall
piers where box sections are adopted.
Basic Types of Bridge Piers
Substructure : Abutments
 The abutments establish the connection between
the bridge superstructure and the embankments.
They are designed to support the loads due to the
superstructure which are transmitted through the
bearings and to the pressures of the soil
contained by the abutment.
 The abutments must include expansion joints, to
accommodate the displacements of the deck, i.e.
the longitudinal shortening and expansion
movements of the deck due to temperature.
Basic Types of Abutments
Two basic types of abutments may be considered:



Wall (counterfort) abutments and Open abutments.
Counterfort wall abutments are adopted only when the
topographic conditions and the shapes of the backfill are
such that an open abutment cannot be used. They are
generally adopted when the required height of the front wall
is above 5.0 to 8.0m. If the depth is below this order of
magnitude, counterfort walls may not be necessary and a
simple wall cantilevering from the foundation may be
adopted.
The connection between the abutments and the backfill may
include an approach slab which ensures a smooth surface of
the pavement even after settlement of the adjacent backfill.
Basic Types of Bridge
Abutments – Wall & Counterfort
Wall Abutment Counterfort
Types of Wall Abutments
Basic Types of Bridge
Abutments – Open Type
Superstructure – Structural
Systems



 The longitudinal system of a bridge may be one of
the following types: beam, frame, arch, cable
stayed or suspension.
There are three main types of bridge transverse
systems, slab, beam-slab or box girder.
Bridge superstructures may use the beam and
plate girder, truss girder or box girder structural
systems.
Deck systems use a reinforced concrete slab, with
or without cross-girders, or a partially prestressed
concrete slab, or an orthotropic steel plate.
Bridge Longitudinal Structural
Systems
Bridge Deck

 The principal function of a bridge deck is to
provide support to local vertical loads (from
highway traffic, railway or pedestrians) and
transmit these loads to the primary
superstructure of the bridge.
As a result of its function, the deck will be
continuous along the bridge span and (apart
from some railway bridges) continuous across
the span. As a result of this continuity, it will act
as a plate (isotropic or orthotropic depending on
construction) to support local patch loads.
Design Case Study
MAB1053
Bridge Engineering
Bridge Layout Plan
Longitudinal & Transverse Sections
Deck and Piers

More Related Content

What's hot

Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Mohamed Yassin
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaKhyati Saggu
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridgeAKASH SHAH
 
Investigation for bridge construction
Investigation for bridge constructionInvestigation for bridge construction
Investigation for bridge constructionMadujith Sagara
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeMarian Joyce Macadine
 
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introductionM.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introductionvaignan
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
Bridge
BridgeBridge
Bridgeillpa
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREbabji syed
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaSuhas Khedkar
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repairKartikSuryawanshi2
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.Mohammad Furqan
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel StructureGaurang Kakadiya
 
Influence line diagram for model arch bridge
Influence line diagram for model arch bridgeInfluence line diagram for model arch bridge
Influence line diagram for model arch bridgekunalsahu9883
 

What's hot (20)

Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
 
Investigation for bridge construction
Investigation for bridge constructionInvestigation for bridge construction
Investigation for bridge construction
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridge
 
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introductionM.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Bridge
BridgeBridge
Bridge
 
Bridge construction atlas
Bridge construction atlasBridge construction atlas
Bridge construction atlas
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDURE
 
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore SaxenaComposite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
Influence line diagram for model arch bridge
Influence line diagram for model arch bridgeInfluence line diagram for model arch bridge
Influence line diagram for model arch bridge
 

Similar to Introductiontobridges07 08-090507223401-phpapp02-converted

introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfabhinavbharat9
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGEAELC
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,bMani Das
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringPooja Lonare
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...SalmanRabbani5
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areasSwapnali Kunjir
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolMicotol
 
Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space FramesAaqib Iqbal
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptxSpidra1
 
Transport enggineering
Transport enggineeringTransport enggineering
Transport enggineeringAparna Sharma
 
CHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engCHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engabdi beder
 

Similar to Introductiontobridges07 08-090507223401-phpapp02-converted (20)

introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdf
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
Suspension bridge
Suspension bridge Suspension bridge
Suspension bridge
 
bridges overview.pptx
bridges overview.pptxbridges overview.pptx
bridges overview.pptx
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areas
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
 
Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space Frames
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
 
Transport enggineering
Transport enggineeringTransport enggineering
Transport enggineering
 
Bridge intr.ppt
Bridge intr.pptBridge intr.ppt
Bridge intr.ppt
 
CHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engCHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design eng
 
Bridge Engg1.ppt
Bridge Engg1.pptBridge Engg1.ppt
Bridge Engg1.ppt
 

Recently uploaded

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 

Recently uploaded (20)

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 

Introductiontobridges07 08-090507223401-phpapp02-converted

  • 1. MAB1053 Bridge Engineering Introduction Prof. Dr. Azlan Abdul Rahman Faculty of Civil Engineering, UTM,
  • 2. Course Objectives     Upon completion of the course, participants will be able to: Identify types, structural forms & design process of common concrete bridges. Perform basic calculations of bridge live loading based on BS5400, BD37/01 & JKR Specification. Use LUSAS finite element program for basic analysis of concrete bridge deck. Perform calculations for the basic design of prestressed concrete bridge beam, bridge abutment and pier.
  • 3. CONTENT WEEK/DATE LECTURER CONTENT WEEK/DATE LECTURER • INTRODUCTION 4.0 METHODS FOR BRIDGEDECK ANALYSIS - Introduction to Bridge Deck Analysis - Orthotropic Plate Theory - Grillage Analysis - Finite Element Analysis - LUSASSoftware - Worked Example - Introduction to Bridges W1 (12/7/07) Ir. Dr. Wahid - Choice of Bridge Decks W2 (19/7/07) Prof. Azlan W8 (30/8/07) Dr. Redzuan W9 (6/9/07) Dr. Redzuan W10 (13/9/07) W11 (20/9/07) 1st Ramadhan Dr. Redzuan W12(27/9/07) Dr. Redzuan 2.0 BRIDGE 5.0 PRESTRESSED CONCRETE BRIDGE - Fundamentals ofPrestressed Concrete - Design of Post-Tensioned Concrete Beam - Composite Prestressed Concrete SUB-STRUCTURE - Bridge Abutments & Piers - Bridge Bearings & Joints W3 (26/7/07) W4 (2/8/07) Prof. Azlan Prof. Azlan W13 (4/10/07) Ir. Dr. Wahid - General Bridge Loading W5 (9/8/07) Prof. Azlan W14(11/10/07) Ir. Dr. Wahid W15(18/10/07) Ir. Dr. Wahid 3.0 BRIDGE LOADING - General Bridge Loading - Live Loads to BS5400 & W6 (16/8/07) Prof. Azlan BD37/01 & JKR Live W7 (23/8/07) Sem. Break Loads - Examples Lecture Time Table
  • 5. What is a bridge?  A bridge is a structure that spans a divide such as: • A stream/river/ravine/valley • Railroad track/roadway/waterway  The traffic that uses a bridge may include: • Pedestrian or cycle traffic • Vehicular or rail traffic • Water/gas pipes • A combination of all the above
  • 6. Function of A Bridge  A bridge has to carry a service (which may be highway or railway traffic, a footpath, public utilities, etc.) over an obstacle (which may be another road or railway, a river, a valley, etc.) and to transfer the loads from the service to the foundations at ground level.
  • 7. Classification of Bridges       According to functions : aqueduct, viaduct, highway, pedestrian etc. According to materials of construction : reinforced concrete, prestressed concrete, steel, composite, timber etc. According to form of superstructure : slab, beam, truss, arch, suspension, cable-stayed etc. According to interspan relation : simple, continuous, cantilever. According to the position of the bridge floor relative to the superstructure : deck, through, half-through etc. According to method of construction : pin-connected, riveted, welded etc.
  • 8. Classification of Bridges      According to road level relative to highest flood level : high-level, submersible etc. According to method of clearance for navigation : movable-bascule, movable-swing, transporter According to span : short, medium, long, right, skew, curved. According to degree of redundancy : determinate, indeterminate According to type of service and duration of use : permanent, temporary bridge, military
  • 11. A Typical Single Span Bridge
  • 13. Bridges which Carry Loads Mainly in Flexure  By far the majority of bridges are of this type. The loads are transferred to the bearings and piers and hence to the ground by slabs or beams acting in flexure, i.e. the bridges obtain their load-carrying resistance from the ability of the slabs and beams to resist bending moments and shear forces.  Only for the very shortest spans is it possible to adopt a slab without any form of beam. This type of bridge will thus be referred to generally as a girder bridge.
  • 15. Bridges which Carry their Loads Mainly as Axial Forces   This type can be further subdivided into those bridges in which the primary axial forces are compressive (arches) and those in which these forces are tensile (suspension bridges and cable-stayed bridges). Such forces normally have to be resisted by members carrying forces of the opposite sense. It must not be thought that flexure is immaterial in such structures. Certainly, in most suspension bridges, flexure of the stiffening girder is not a primary loading in that overstress is unlikely to cause overall failure; however, in cable stayed bridges (particularly if the stays are widely spaced) flexure of the girder is a primary loading.
  • 16. Bridges which Carry their Loads Mainly as Axial Forces
  • 17. Bridges which Carry their Loads Mainly as Axial Forces
  • 18. Basic Types of Bridges  Girder/Beam Bridge  Truss Bridge  Rigid Frame Bridge  Arch Bridge  Cable Stayed Bridge  Suspension Bridge
  • 19. Girder/Beam Bridge • The most common and basic type • Typical spans : 10m to 200m
  • 20. Truss Bridge • Truss is a simple skeletal structure. • Typical span lengths are 40m to 500m.
  • 21. Forces in a Truss Bridge In design theory, the individual members of a simple truss are only subject to tension and compression and not bending forces. For most part, all the beams in a truss bridge are straight.
  • 22. Arch Bridges      Arches used a curved structure which provides a high resistance to bending forces. Both ends are fixed in the horizontal direction (no horizontal movement allowed in the bearings). Arches can only be used where ground is solid and stable. Hingeless arch is very stiff and suffers less deflection. Two-hinged arch uses hinged bearings which allow rotation and most commonly used for steel arches and very economical design. Hinge-less Arch Two hinged Arch
  • 23. Arch Bridges   The three-hinged arch adds an additional hinge at the top and suffers very little movement in either foundation, but experiences more deflection. Rarely used. The tied arch allows construction even if the ground is not solid enough to deal with horizontal forces. Three-hinged Arch Tied Arch
  • 24. Forces in an Arch   Arches are well suited to the use of stone because they are subject to compression. Many ancient and well-known examples of stone arches still stand to this today.
  • 25. Cable Stayed   A typical cable-stayed bridge is a continuous deck with one or more towers erected above piers in the middle of the span. Cables stretch down diagonally from the towers and support the deck. Typical spans 110m to 480m.
  • 26. Cable Stay Towers Cable stayed bridges may be classified by the number of spans, number and type of towers, deck type, number and arrangement of cables.
  • 29. Suspension Bridge    A typical suspension bridge is a continuous deck with one or more towers erected above piers in the middle of span. The deck maybe of truss or box girder. Cables pass over the saddle which allows free sliding. At both ends large anchors are placed to hold the ends of the cables.
  • 31. Site Information       Survey - existing ground level and site details. Soil investigation - at least one bore-hole for each support position to determine safe bearing pressure, aggressive conditions and predict settlement. Mining - details of old working and future seams. River Board – navigation requirements, maximum flood levels and scour problems around foundations. Railways – frequency of trains, available track possession, minimum headroom, position of supports and piling techniques. Statutory Undertakers – diversion of existing services, provision for future services in the deck.
  • 32. Site Information      Planning Authorities – normally concerned with aesthetic appeal and the effect on local amenities. Road Geometry – details of horizontal and vertical alignment together with the road cross-section. Design Standards – design live loading, visibility distances, headroom standards and horizontal clearances. Time – the time for design and the phasing of construction in relation to other work. Atmospheric Conditions – an aggressive environment may involve high maintenance costs for steel construction and special precautions in the detailed specification.
  • 33. Conceptual Choice Considerations Initial conceptual choice should take account of:  clearance requirements and the avoidance of impact damage  type & magnitude of loading  topography and geology of the site  possible erection methods  local skills and materials  future inspection and maintenance  aesthetic and environmental aspects
  • 34. Factors Affecting Conceptual Choice  The functional considerations that have greatest influence on conceptual choice are:  The clearance requirements (both vertically and horizontally) and avoidance of impact  The type and magnitude of the loading to be carried  The topography and geology of the site
  • 35. Clearance Requirements    All bridges must be designed to ensure, as far as is possible, that they are not struck by vehicles, vessels or trains which may pass below them. This requirement is normally met by specifying minimum clearances. It must be remembered that designed values must take into account deflections due to any loading that may occur on the bridge structure. Clearance requirements may thus determine the span of a bridge and also have a significant bearing on the construction depth. Whilst the requirements will not normally determine precisely the type of bridge, it may well eliminate some possibilities.
  • 36. Clearance Requirements   Typically, for example, a bridge over a major highway would be expected to have a minimum vertical clearance of about 5,3 metres; even this may not protect it from accidental impact In addition, pier positions must be such that the likelihood of impact from errant vehicles is minimised, both to protect the pier and the vehicle itself. This requirement is usually achieved by setting the pier back a reasonable distance from the edge of the carriageway.
  • 37. Clearance Requirements   Navigation authorities specify clearances over rivers, to allow not only for the mast height and width of vessels below the bridge, but also for particular requirements for piers in the waterway (or on a flood plain) to avoid excessive flow velocity and scour of river banks. In considering vertical clearance, a designer must bear in mind the problems of attaining them. The approach gradient for a highway bridge should not normally exceed about 4% and a railway bridge much less. This is of great importance when comparing fixed with moving bridges.
  • 38. Loading   The type and magnitude of loading has a significant bearing on the form of bridge. Highway loading by its nature is impossible to determine exactly, either in disposition or in magnitude. A highway bridge requires a deck on which the traffic can run and (unless the span is so short that a simple slab is adequate to span between abutments) the deck must be strong enough to distribute the loading to the main girders.
  • 39. Loading  Every country has its own specification for the magnitude of loading on highway and railway bridges. For highway bridges most national codes have in common a uniform loading together with a line load (or series of point loads) to represent isolated heavy axles. In many codes, the uniform load is of decreasing intensity as the length of bridge increases, to allow for the reduced probability of a concentration of heavy lorries.  Furthermore, there are rules for multiple lane loadings, frequently assuming that not more than two lanes are fully loaded at any one time, again based on a probabilistic approach. Many authorities also specify checks for a single very heavy abnormal vehicle. In many codes, the effect of impact (dynamic magnification) of highway loads is implicitly taken into account by the static load specification.
  • 40. Loading   Additionally, forces arising from braking or acceleration of vehicles, centrifugal effects on curved bridges, temperature effects and wind have to be taken into account where relevant. Whilst the details of applied loads are appropriate to the detailed design, rather than the conceptual design of a bridge, certain aspects enter into the concept. For example, where heavy abnormal vehicles are specified, the bridge will require good transverse load distribution.
  • 41. Topography & Geology of Bridge Site    The overall topography of the site will probably determine the line of the road or railway. Not infrequently this may mean that bridges will have to cross other roads, railways or rivers at a substantial angle, resulting in skew spans. Generally, the bridge site is fixed by the geometry of the obstacle and local terrain. The road may be on a curve; whilst it is possible to curve a bridge to follow this, it is frequently expensive and structurally inefficient, usually dictating the use of torsionally stiff girders even for short spans. If the curve is slight, it may be preferable to construct the bridge as a series of straight spans. Poor foundation conditions will favour fewer foundations and hence longer spans. A balance has to be found between the cost of foundations and superstructure to minimise the total cost.
  • 42. Other Factors Method of Erection  It has long been appreciated that a designer must consider at the design stage the method by which a bridge will be erected. Indeed it is not infrequently the case that such consideration should be made even at the time of conceptual choice, since it can happen that the superficially most attractive design is impossible to erect in a particular location.  For example, a design that relies on being erected in large pieces (such as a major box girder), may be ruled out because of the impossibility of transporting such pieces to a remote site with inadequate access roads.
  • 43. Other Factors Local Constructional Skills and Materials  A bridge should be suited to local technology. It is not sensible to specify a sophisticated design if all the material and labour has to be imported. Future Inspection and Maintenance  Lack of attention to future maintenance both at the conceptual design and the detailed design stages would results in many bridges, otherwise satisfactory, have deteriorated because of difficulty in inspection and maintenance. It is particularly important that in locations where access is difficult (either physically or because it would cause disruption of services) details which deteriorate should be avoided as far as possible. This will be considered further in various respects, for example whether a bridge should be a series of simple spans or should be continuous.
  • 44. Other Factors Aesthetic and Environmental Aspects    The appearance of bridges has in recent years become a matter of considerable importance. Frequently, a scheme takes a road or railway through an area of great natural beauty and it is important that any structures are in keeping with these surroundings and do not adversely affect them. For example, it is commonly accepted that a bridge is more aesthetically pleasing with an odd number of spans than an even number. In addition, a degree of deepening at piers can add to the attraction. The 3-span structures are more attractive than the two span ones. Hence, unless there are other contra-indications, the conceptual choice should probably tend towards a 3-span solution.
  • 46. Detailed Design Considerations       The design development needs to make the correct choices for: deck structure layout i.e. spans and structural arrangements continuous or simple construction proportions, i.e. span/depth ratios reducing fabrication labour to a minimum design for ease of construction
  • 47. Basic Components of a Bridge The two basic parts are:    Substructure - includes the piers, the abutments and the foundations. Superstructure - consists of the deck structure itself, which support the direct loads due to traffic and all the other permanent and variable leads to which the structure is subjected. The connection between the substructure and the superstructure is usually made through bearings. However, rigid connections between the piers (and sometimes the abutments) may be adopted, particularly in frame bridges with tall (flexible) piers.
  • 48. Substructure : Piers Piers are of two basic types:  Column piers - Concrete column piers may have a solid cross-section, or a box section may be the shape chosen for the cross-section for structural and aesthetic reasons.  Wall piers - generally less economical and less pleasing from an aesthetic point of view. They are very often adopted in cases where particular conditions exist, e.g. piers in rivers with significant hydrodynamic actions or in bridges with tall piers where box sections are adopted.
  • 49. Basic Types of Bridge Piers
  • 50. Substructure : Abutments  The abutments establish the connection between the bridge superstructure and the embankments. They are designed to support the loads due to the superstructure which are transmitted through the bearings and to the pressures of the soil contained by the abutment.  The abutments must include expansion joints, to accommodate the displacements of the deck, i.e. the longitudinal shortening and expansion movements of the deck due to temperature.
  • 51. Basic Types of Abutments Two basic types of abutments may be considered:    Wall (counterfort) abutments and Open abutments. Counterfort wall abutments are adopted only when the topographic conditions and the shapes of the backfill are such that an open abutment cannot be used. They are generally adopted when the required height of the front wall is above 5.0 to 8.0m. If the depth is below this order of magnitude, counterfort walls may not be necessary and a simple wall cantilevering from the foundation may be adopted. The connection between the abutments and the backfill may include an approach slab which ensures a smooth surface of the pavement even after settlement of the adjacent backfill.
  • 52. Basic Types of Bridge Abutments – Wall & Counterfort Wall Abutment Counterfort
  • 53. Types of Wall Abutments
  • 54. Basic Types of Bridge Abutments – Open Type
  • 55. Superstructure – Structural Systems     The longitudinal system of a bridge may be one of the following types: beam, frame, arch, cable stayed or suspension. There are three main types of bridge transverse systems, slab, beam-slab or box girder. Bridge superstructures may use the beam and plate girder, truss girder or box girder structural systems. Deck systems use a reinforced concrete slab, with or without cross-girders, or a partially prestressed concrete slab, or an orthotropic steel plate.
  • 57. Bridge Deck   The principal function of a bridge deck is to provide support to local vertical loads (from highway traffic, railway or pedestrians) and transmit these loads to the primary superstructure of the bridge. As a result of its function, the deck will be continuous along the bridge span and (apart from some railway bridges) continuous across the span. As a result of this continuity, it will act as a plate (isotropic or orthotropic depending on construction) to support local patch loads.