SlideShare a Scribd company logo
1 of 37
By:
SANTOSH KUMAR SINGH
ASSTT. MANAGER(TECH.)
JAL POWER CORPORATION LTD.
“AWARE OF THE PREPARATION OF DETAILED
PROJECT REPORTS FOR HYDRO ELECTRIC
SCHEMES, THEIR ACCEPTANCE AND
EXAMINATION FOR CONCURRANCE.”
Scheme aims at best ultimate development of the River
Designed based on optimum benefits, not conflict with irrigation point of
view.
Scheme takes into account the development of water resource change
over the period.
Location of all parts of scheme be optimum.
Scheme either included in N.E.P. or generation of Power at reasonable
tariff.
Prepared after essential site surveys and investigations are completed.
• Introduction
• Justification of project from
power supply angle
• Basin Development
• Inter-state//Inter-national
Aspects
• Survey & Investigation
• Hydrology
• Reservoir
• Power Potential & Installed
Capacity
• Design of Civil Structure
• E&M Design
• Transmission of Power &
Communication facilities
• Construction Programmes
(PERT & BAR e.t.c.)
• Project Organization
• Infrastructure facilities
• Environmental & Ecology
Aspects
• Cost Estimates
• Allocation of Cost
• Economic Evaluation
• Future Utilization of Buildings
• Reaccomodations
• Clearance
• INTRODUCTION
– Types of Projects.
– Location of the project area including Long. & Latit.
– Access facilities & communication systems.
– Climate Condition.
– Description of Topography, physiographic and geology.
– Historical background in respect of earlier 7 present proposal of the
project.
– Alternatives studies carried out for majors components and choice of
project parameters.
– Natural resources of state /Region.
– Socio-economic aspects.
– Land requirement for project construction- forest/village/ agriculture
lands and area of submergence.
– Population affected.
– Environmental aspects.
– Defense angle, if any.
– Cost & benefits of scheme.
• JUSTIFICATION OF PROJECT FROM POWER SUPPLY
ANGLE
– Demand considerations on all India/ regional basis.
– Resources for power development in the region/state.
– Available generating capacity in the state region from
different sources.
– Peak load and energy requirement in future in all
India/region/state up to the likely date of project completion.
– Likely addition to generating capacity in future in the all
India/region/state indicating power supply position with or
without the project under consideration and improvement I
the hydro-thermal mix.
• BASIN DEVELOPMENT
– The course of the river
– Power potential of the river basin and stages of the
development.
– Whether trans-basin diversion of waters involved.
– Fitment of the scheme in the overall basin
development.
– Fitment of the scheme in the power potential
assessment studies.
– Effect of future upstream/downstream developments
on the potential of proposed scheme.
• INTER-STATE / INTER-NATIONAL ASPECTS
– States/countries traversed by the river.
– Distribution of catchment in states/countries and yields from
the catchment of state/country concerned.
– Effect of the following on the project:
• a) Inter-state agreement on sharing of waters, sharing of
benefits and costs, acceptance of submergence in the
upstream state(s), if any.
• b) Inter-state adjudication, if any
• c) Interstate aspects of territory, property etc. coming under
submergence, oustees rehabilitation, compensation etc.
• d) Any other aspect of the project involving inter-state
problems
• e) Inter-national aspects, if any
• SURVEY & INVESTIGATION
– Topographical survey of various components of project.
– Archaeological surveys in the reservoir area.
– Mineral surveys in the catchment areas.
– Right of way surveys for the reservoirs.
– Communication surveys.
– Geology & geo-technical features.
– Seismicity.
– Foundation investigations of different
structures/components of the project indicating boreholes
details, soil/rock strata etc.
– Construction materials investigations
– Hydrological and meteorological investigations
• HYDROLOGY
– Hydrological inputs for the project planning
– Effect of project development on hydrologic
regime
– Hydrologic studies for water availability, design
flood, design flood levels, sedimentation etc.
– Catchment area, annual run-off, submergence, suitability of soil/rock, dead storage level
– Sedimentation data and studies
– Fixation of storage and reservoir levels, { maximum water level (MWL), full reservoir level
(FRL), minimum draw down level (MDDL) }, flood cushion etc.
– Life of reservoir in years with basis
– Capacities at MWL, FRL, MDDL, Dead Storage level etc. at project planning stage and after
25, 50, 75 and 100 years or more of operation
– Water tightness of the reservoir
– Annual losses (month-wise) (evaporation, seepage etc.)
– Flood absorption on regular/flash flood
– Effect on subsoil water tables in the adjoining areas upstream and downstream of the dam
– Seismic characteristics and effects due to construction of dam
– Reservoir rim stability
– Area of submergence
– Land acquisition
– Recreation facilities
– Pisci-culture
– Other facilities, if any
– Need and recommendations for soil conservation measures in the catchment.
• POWER POTENTIAL & INSTALLED CAPACITY
Run-off H. E. Scheme
• The first step is to compute 90% dependable year :
– Obtain 10-daily hydrological inflow series in m3/sec for all hydrological years, year-
wise
– Calculate unrestricted energy generation in MUs.
– Arrange unrestricted annual energy generation in descending order
– 0.9(n+1)th year is the 90% dependable year, where n is the number of years for
which hydrological inflows data is available
• Fixating the installed capacity :
– Calculate firm power available based on average power generation during the lean
months flows in a 90% dependable year.
– Consider a number of alternatives of installed capacities in suitable steps say 5%,
for load factors say about 40% down to about 15%.
– Compute incremental energy generation (Δ KWH) for every incremental MW (Δ
MW) and plot result on a graph.
– Installed capacity is fixed at a value where the fall in the graph is sharp.
– B/C ratio and incremental benefit cost ratio (ΔB/ΔC) is also considered for fixing the
installed capacity. An alternative for installed capacities which provides maximum
net benefit (B-C) and ensures incremental (ΔB/ΔC) higher than unity is considered
optimum
• POWER POTENTIAL & INSTALLED CAPACITY
Pumped Storage Schemes
– Type of scheme – daily or weekly regulated
– Optimization of storage capacity, FRL, MDDL etc. of
upper and lower reservoirs - Studies carried out may
be discussed
– Optimization of installed capacity and number of
units –Studies carried out may be discussed
– Operating criteria of the project in generating and
pumping mode, availability of pumping energy for
pumping operations over the years.
– Cycle efficiency of the scheme
• INFRASTRUCTURAL FACILITIES
– Access roads
– Rail head
– Port facilities, As applicable
– Construction power requirement
– Power supply facilities
– Telecommunication facilities required during construction
and after completion of the project
– Project colonies / buildings
– Workshops
– Drinking water facilities
– Others
• ENVIRONMENTAL & ECOLOGICAL ASPECTS
– Status of Environmental clearance
– Status of Forest clearance
– Cost of proposed remedial & mitigative measures
• Rehabilitation measures
• Compensatory afforestation
• Disaster management plan
• Restoration of land in construction areas by filling, grading
• Control of aquatic weeds in submerged areas to provide improved
habitat for aquatic life
• Measures to salvage/rehabilitation of any rare or endangered
species of flora and fauna
• Catchment Area Treatment
• Details about Net Present Value of forest land
• COST ESTIMATES
o The Civil Cost Estimates of the project shall be prepared as per “Guidelines
for preparation of estimates for the river valley projects” issued by CWC
and Indian Standard IS: 4877 “Guide for Preparation of Estimate for River
Valley Projects”.
o The estimates of a Hydro Electric Scheme shall be divided under the
following heads:
• A. Direct Cost
• I. Works
• A - Preliminary
• B - Land
• C - Works
• J - Power Plant Civil Works
• K - Buildings
• M - Plantation
• O - Miscellaneous
• P – Maintenance during construction
• Q - Special T&P
• R - Communications
• COST ESTIMATES
– S - Power Plant and Electro- Mechanical system
– X - Environment and ecology
– Y - Losses on stock
• Total I-Works
– 1. Establishment
– 2. Tools and Plants
– 3. Suspense
– 4. Receipt And Recoveries
• Total (A) - Direct Cost
• B. Indirect Cost
– i. Capitalization of Abatement of Land Revenue
– ii. Audit and Account Charges
• Total (B) - Indirect Cost
• Total Cost (A+B)
• ALLOCATION OF COST
– The details in respect of allocation of cost for each
component of the Multipurpose Project shall be
based on the cost cleared by Technical Advisory
Committee of MOWR. The details in this regard
may be clearly spelt out under this Chapter.
– In case of projects involving flood moderation, it may
clearly be indicated whether the cost of flood
moderation as cleared by CWC shall be borne by the
concerned beneficiary State.
• ECONOMIC EVALUATION
– Phasing of expenditure half yearly
– Interest during construction (IDC)
– Cost of generation at power house bus bars (with IDC)
– Sale rate of energy (with IDC) (with and without free power to
home State)
– Levelised tariff (with and without free power to home State)
– Comparison of cost of generation with alternate source of
generation in the in state/region.
– Project estimated cost and financial package summary shall be
submitted
“Calculations Shall be carried out as per the tariff
order of the Appropriate Regulatory Commission.”
• FUTURE UTILISATION OF BUILDINGS
– Details of buildings to be constructed to meet peak
requirements of the project
– Departmental requirement of buildings after completion
of the project
– Requirement of the buildings by other agencies
– Utilization of surplus buildings
• RECOMMENDATIONS
– Economic justification of the project
– Socio-economic and other benefits
• CLEARANCES / INPUTS
– Authenticated Copies of the following
Documents/Certificates/Clearances are required to be
submitted to CEA for concurrence.
• Letter from the Registrar of Companies indicating that the company
has been registered as a Generating Company under Indian
Companies Act, 1956.
• Article of Association indicating that generation is one of the
objectives of the company.
• Letter from Competent Government authorizing the company to
establish, own and operate generating power plant.
• Land availability certificate from State Revenue Authorities
• Water availability certificate from State Irrigation Department/
concerned agency.
• Clearance of Ministry of Water Resources/ Central Water Commission
• Defense clearance(If, necessary).
• Recommendation of the State Govt. on the project cost in case of
private projects.
• Any other Statutory clearance from Ministries / Departments /
Organizations.
• Submit the DPR to the Authority for its
concurrence as under Sec. 8 of E.A.2003.
• 4-copies submit to Sec. of C.E.A. If DPR is correct
and complete then after 2- weeks DPR again be
submit with 21-copies along with one-soft copy
• CEA/CWC/GSI shall decide in another 2-weeks
whether the details furnished in DPR are adequate
or not.
POWER PROJECTS
• It involves Drinking water, irrigation, power, flood
control, navigation etc. so submit to C.W.C. of
M.O.W.R.(T.A.C. ).
• The Flood moderation aspects parts submit to
C.W.C./M.O.W.R.
MULTI-PURPOSE
PROJECTS
• Examination
– Appraisal of DPR
– Aspects to be appraised
• Concurrence
– Submission of Update DPR
– Information regarding Financial Closure
– Time Frame for accord of Concurrence
– Validity of concurrence
– Transfer of Concurrence
– Subsequently changes in Project parameters
• List of relevant Documents/ References
– 1. The Electricity Act, 2003
– 2. Indian Companies Act, 1956
– 3. Forest Conservation Act, 1980 and Notifications/Resolutions by MOE&F.
– 4. “Guidelines for preparation of DPRs of Irrigation and Multipurpose Projects” issued by CWC.
– 5. “Guidelines for preparation of project estimates for major irrigation and multipurpose project” issued by
CWC.
– 6. National Electricity Plan notified by CEA
– 7. Indian Electricity Sector – Widening Scope for Private Participation-Issued by Ministry of Power.
– 8. Policy on Hydro Power Development issued by Ministry of Power
– 9. Guidelines for “Investigation of major irrigation and hydro-electric projects” issued by CWC.
– 10. CBIP – Technical Report No.19 “Life of Reservoir (1977)”
• IS 5497 : Guide for topographical surveys for river valley projects
• IS 4890 : Method for measurement of suspended sediment in open rivers
• IS 13216 : Code of practice for geological explorations for reservoir sites.
• IS 4186 : Guide for preparation of project report for river valley projects.
• IS 4877 : Guide for preparation of Estimate for River Valley Projects.
• IS 5477 : Methods for fixing the capacities of reservoirs.
(Part 1-4)
• IS 7323 : Method for determining evaporation from reservoirs.
• IS 7323 : Guidelines for operation of reservoirs.
• IS 13028 : Guidelines for overall planning of river basin.
• IS 7560 : Guidelines for allocation of cost among different purposes of river
valley projects.
• IS 4247 : Code of practice for structural design of surface hydro power stations.
• IS 12837 : Guidelines for selection of hydraulic turbines for medium and large
hydro-electric power houses.
• IS 12800 : Guidelines for selection of turbines preliminary dimensioning &
layout of surface hydro electric power houses.
My presentation at N.P.T.I
My presentation at N.P.T.I

More Related Content

What's hot

Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Youn Sim, Ph.D., P.E.
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Fairfax County
 
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...Recycling and Resource Management Division
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationFairfax County
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationFairfax County
 
1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_riverRavi Naid Gorle
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting Fairfax County
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Recycling and Resource Management Division
 
Giles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationGiles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationFairfax County
 

What's hot (20)

Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
January 10, 2013
January 10, 2013January 10, 2013
January 10, 2013
 
Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017Gude Landfill Remediation - June 15, 2017
Gude Landfill Remediation - June 15, 2017
 
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
Sustainable Public Works: Benefits of Taking Envision Beyond the Boundary of ...
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
GLCC-DEP Presentation to Derwood Community, Waste Delineation & Nature and Ex...
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Gude Landfill Remediation update
Gude Landfill Remediation updateGude Landfill Remediation update
Gude Landfill Remediation update
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
 
1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river
 
Jim murphy
Jim murphyJim murphy
Jim murphy
 
Gude landfill remediation 161019
Gude landfill remediation 161019Gude landfill remediation 161019
Gude landfill remediation 161019
 
Bill hutchison
Bill hutchisonBill hutchison
Bill hutchison
 
JM Portfolio 04-2016
JM Portfolio 04-2016JM Portfolio 04-2016
JM Portfolio 04-2016
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting
 
Mark Cowin Same 10282009
Mark Cowin Same 10282009Mark Cowin Same 10282009
Mark Cowin Same 10282009
 
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
Gude Landfill Remediation Approach Update, Community Meeting, September 18, 2012
 
Giles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationGiles Run Pump Station Rehabilitation
Giles Run Pump Station Rehabilitation
 

Viewers also liked

How does a pocket watch work
How does a pocket watch workHow does a pocket watch work
How does a pocket watch workorientwatch01
 
у віночок кобзареві
у віночок кобзаревіу віночок кобзареві
у віночок кобзаревіPolinaMokrushina
 
Replication featuresinmysql5.7andbeyond osi-final
Replication featuresinmysql5.7andbeyond osi-finalReplication featuresinmysql5.7andbeyond osi-final
Replication featuresinmysql5.7andbeyond osi-finalSujatha Sivakumar
 
Tracfone LG 840g
Tracfone LG 840g Tracfone LG 840g
Tracfone LG 840g bestprep11
 
Jeeberella's Craft Castle - Product presentation
Jeeberella's Craft Castle - Product presentationJeeberella's Craft Castle - Product presentation
Jeeberella's Craft Castle - Product presentationNatasha Tideswell
 
Jeeberella's Craft Castle - what does it do?
Jeeberella's Craft Castle - what does it do?Jeeberella's Craft Castle - what does it do?
Jeeberella's Craft Castle - what does it do?Natasha Tideswell
 
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca Davies
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca DaviesImplementing analytics - Rob Wyn Jones, Shri Footring and Rebecca Davies
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca DaviesJisc
 

Viewers also liked (14)

How does a pocket watch work
How does a pocket watch workHow does a pocket watch work
How does a pocket watch work
 
у віночок кобзареві
у віночок кобзаревіу віночок кобзареві
у віночок кобзареві
 
Replication featuresinmysql5.7andbeyond osi-final
Replication featuresinmysql5.7andbeyond osi-finalReplication featuresinmysql5.7andbeyond osi-final
Replication featuresinmysql5.7andbeyond osi-final
 
Other Achievements
Other AchievementsOther Achievements
Other Achievements
 
україна єдина
україна єдинаукраїна єдина
україна єдина
 
Cepheus Group 2012 French
Cepheus Group 2012 FrenchCepheus Group 2012 French
Cepheus Group 2012 French
 
Medical Insurance Concept's
Medical Insurance Concept'sMedical Insurance Concept's
Medical Insurance Concept's
 
WOCA
WOCAWOCA
WOCA
 
Tracfone LG 840g
Tracfone LG 840g Tracfone LG 840g
Tracfone LG 840g
 
presentation lin enc
presentation lin encpresentation lin enc
presentation lin enc
 
Jeeberella's Craft Castle - Product presentation
Jeeberella's Craft Castle - Product presentationJeeberella's Craft Castle - Product presentation
Jeeberella's Craft Castle - Product presentation
 
Jeeberella's Craft Castle - what does it do?
Jeeberella's Craft Castle - what does it do?Jeeberella's Craft Castle - what does it do?
Jeeberella's Craft Castle - what does it do?
 
Zya00577
Zya00577Zya00577
Zya00577
 
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca Davies
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca DaviesImplementing analytics - Rob Wyn Jones, Shri Footring and Rebecca Davies
Implementing analytics - Rob Wyn Jones, Shri Footring and Rebecca Davies
 

Similar to My presentation at N.P.T.I

Planning of Water Resource Planning Projects
Planning of Water Resource Planning ProjectsPlanning of Water Resource Planning Projects
Planning of Water Resource Planning ProjectsDARSHAN MEHTA
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptxPradeepKumar504728
 
IPWEA Groundwater Separation Distances - Jun 17 - UrbAqua
IPWEA Groundwater Separation Distances - Jun 17 - UrbAquaIPWEA Groundwater Separation Distances - Jun 17 - UrbAqua
IPWEA Groundwater Separation Distances - Jun 17 - UrbAquaRichard Connell
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economicsSwapnil Gadgune
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic TechniquesChithraM26
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTvikaspanch
 
final CEA ppt 230221.pptx
final CEA ppt 230221.pptxfinal CEA ppt 230221.pptx
final CEA ppt 230221.pptxankanwal1
 
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...Robert Muir
 
Power and Energy Potential Study hydrology.pptx
Power and Energy Potential Study hydrology.pptxPower and Energy Potential Study hydrology.pptx
Power and Energy Potential Study hydrology.pptxMridu5
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNINGNishaDangi99
 
H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015Hlosokuhle Fuyana
 
Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)siva ch
 
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)glennmcgillivray
 
Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017Sustainable Severn
 
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...Robert Muir
 

Similar to My presentation at N.P.T.I (20)

Planning of Water Resource Planning Projects
Planning of Water Resource Planning ProjectsPlanning of Water Resource Planning Projects
Planning of Water Resource Planning Projects
 
Karnataka surface water
Karnataka surface waterKarnataka surface water
Karnataka surface water
 
44 ocea lmco-ascari
44 ocea lmco-ascari44 ocea lmco-ascari
44 ocea lmco-ascari
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
Engr. Asim Mahmood CV
Engr. Asim Mahmood CVEngr. Asim Mahmood CV
Engr. Asim Mahmood CV
 
IPWEA Groundwater Separation Distances - Jun 17 - UrbAqua
IPWEA Groundwater Separation Distances - Jun 17 - UrbAquaIPWEA Groundwater Separation Distances - Jun 17 - UrbAqua
IPWEA Groundwater Separation Distances - Jun 17 - UrbAqua
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economics
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic Techniques
 
SMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANTSMALL HYDRO POWER PLANT
SMALL HYDRO POWER PLANT
 
final CEA ppt 230221.pptx
final CEA ppt 230221.pptxfinal CEA ppt 230221.pptx
final CEA ppt 230221.pptx
 
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...
Green Infrastructure / Low Impact Development LID Design Tool and Lifecycle C...
 
Water Master Plan Northgate Update
Water Master Plan Northgate UpdateWater Master Plan Northgate Update
Water Master Plan Northgate Update
 
Power and Energy Potential Study hydrology.pptx
Power and Energy Potential Study hydrology.pptxPower and Energy Potential Study hydrology.pptx
Power and Energy Potential Study hydrology.pptx
 
Eng Mala Dubravica
Eng   Mala DubravicaEng   Mala Dubravica
Eng Mala Dubravica
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
 
H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015
 
Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)Planning of irrigation project/resrvoir(irrigation management)
Planning of irrigation project/resrvoir(irrigation management)
 
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)
ICLR Friday Forum: Modelling of Future Flood Risk Across Canada (May 31, 2019)
 
Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017
 
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
Extreme Weather Resiliency and Climate Adaptation Through Strategic Asset Man...
 

My presentation at N.P.T.I

  • 1. By: SANTOSH KUMAR SINGH ASSTT. MANAGER(TECH.) JAL POWER CORPORATION LTD.
  • 2. “AWARE OF THE PREPARATION OF DETAILED PROJECT REPORTS FOR HYDRO ELECTRIC SCHEMES, THEIR ACCEPTANCE AND EXAMINATION FOR CONCURRANCE.”
  • 3.
  • 4.
  • 5. Scheme aims at best ultimate development of the River Designed based on optimum benefits, not conflict with irrigation point of view. Scheme takes into account the development of water resource change over the period. Location of all parts of scheme be optimum. Scheme either included in N.E.P. or generation of Power at reasonable tariff. Prepared after essential site surveys and investigations are completed.
  • 6. • Introduction • Justification of project from power supply angle • Basin Development • Inter-state//Inter-national Aspects • Survey & Investigation • Hydrology • Reservoir • Power Potential & Installed Capacity • Design of Civil Structure • E&M Design • Transmission of Power & Communication facilities • Construction Programmes (PERT & BAR e.t.c.) • Project Organization • Infrastructure facilities • Environmental & Ecology Aspects • Cost Estimates • Allocation of Cost • Economic Evaluation • Future Utilization of Buildings • Reaccomodations • Clearance
  • 7. • INTRODUCTION – Types of Projects. – Location of the project area including Long. & Latit. – Access facilities & communication systems. – Climate Condition. – Description of Topography, physiographic and geology. – Historical background in respect of earlier 7 present proposal of the project. – Alternatives studies carried out for majors components and choice of project parameters. – Natural resources of state /Region. – Socio-economic aspects. – Land requirement for project construction- forest/village/ agriculture lands and area of submergence. – Population affected. – Environmental aspects. – Defense angle, if any. – Cost & benefits of scheme.
  • 8. • JUSTIFICATION OF PROJECT FROM POWER SUPPLY ANGLE – Demand considerations on all India/ regional basis. – Resources for power development in the region/state. – Available generating capacity in the state region from different sources. – Peak load and energy requirement in future in all India/region/state up to the likely date of project completion. – Likely addition to generating capacity in future in the all India/region/state indicating power supply position with or without the project under consideration and improvement I the hydro-thermal mix.
  • 9. • BASIN DEVELOPMENT – The course of the river – Power potential of the river basin and stages of the development. – Whether trans-basin diversion of waters involved. – Fitment of the scheme in the overall basin development. – Fitment of the scheme in the power potential assessment studies. – Effect of future upstream/downstream developments on the potential of proposed scheme.
  • 10. • INTER-STATE / INTER-NATIONAL ASPECTS – States/countries traversed by the river. – Distribution of catchment in states/countries and yields from the catchment of state/country concerned. – Effect of the following on the project: • a) Inter-state agreement on sharing of waters, sharing of benefits and costs, acceptance of submergence in the upstream state(s), if any. • b) Inter-state adjudication, if any • c) Interstate aspects of territory, property etc. coming under submergence, oustees rehabilitation, compensation etc. • d) Any other aspect of the project involving inter-state problems • e) Inter-national aspects, if any
  • 11. • SURVEY & INVESTIGATION – Topographical survey of various components of project. – Archaeological surveys in the reservoir area. – Mineral surveys in the catchment areas. – Right of way surveys for the reservoirs. – Communication surveys. – Geology & geo-technical features. – Seismicity. – Foundation investigations of different structures/components of the project indicating boreholes details, soil/rock strata etc. – Construction materials investigations – Hydrological and meteorological investigations
  • 12. • HYDROLOGY – Hydrological inputs for the project planning – Effect of project development on hydrologic regime – Hydrologic studies for water availability, design flood, design flood levels, sedimentation etc.
  • 13. – Catchment area, annual run-off, submergence, suitability of soil/rock, dead storage level – Sedimentation data and studies – Fixation of storage and reservoir levels, { maximum water level (MWL), full reservoir level (FRL), minimum draw down level (MDDL) }, flood cushion etc. – Life of reservoir in years with basis – Capacities at MWL, FRL, MDDL, Dead Storage level etc. at project planning stage and after 25, 50, 75 and 100 years or more of operation – Water tightness of the reservoir – Annual losses (month-wise) (evaporation, seepage etc.) – Flood absorption on regular/flash flood – Effect on subsoil water tables in the adjoining areas upstream and downstream of the dam – Seismic characteristics and effects due to construction of dam – Reservoir rim stability – Area of submergence – Land acquisition – Recreation facilities – Pisci-culture – Other facilities, if any – Need and recommendations for soil conservation measures in the catchment.
  • 14. • POWER POTENTIAL & INSTALLED CAPACITY Run-off H. E. Scheme • The first step is to compute 90% dependable year : – Obtain 10-daily hydrological inflow series in m3/sec for all hydrological years, year- wise – Calculate unrestricted energy generation in MUs. – Arrange unrestricted annual energy generation in descending order – 0.9(n+1)th year is the 90% dependable year, where n is the number of years for which hydrological inflows data is available • Fixating the installed capacity : – Calculate firm power available based on average power generation during the lean months flows in a 90% dependable year. – Consider a number of alternatives of installed capacities in suitable steps say 5%, for load factors say about 40% down to about 15%. – Compute incremental energy generation (Δ KWH) for every incremental MW (Δ MW) and plot result on a graph. – Installed capacity is fixed at a value where the fall in the graph is sharp. – B/C ratio and incremental benefit cost ratio (ΔB/ΔC) is also considered for fixing the installed capacity. An alternative for installed capacities which provides maximum net benefit (B-C) and ensures incremental (ΔB/ΔC) higher than unity is considered optimum
  • 15.
  • 16. • POWER POTENTIAL & INSTALLED CAPACITY Pumped Storage Schemes – Type of scheme – daily or weekly regulated – Optimization of storage capacity, FRL, MDDL etc. of upper and lower reservoirs - Studies carried out may be discussed – Optimization of installed capacity and number of units –Studies carried out may be discussed – Operating criteria of the project in generating and pumping mode, availability of pumping energy for pumping operations over the years. – Cycle efficiency of the scheme
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24. • INFRASTRUCTURAL FACILITIES – Access roads – Rail head – Port facilities, As applicable – Construction power requirement – Power supply facilities – Telecommunication facilities required during construction and after completion of the project – Project colonies / buildings – Workshops – Drinking water facilities – Others
  • 25. • ENVIRONMENTAL & ECOLOGICAL ASPECTS – Status of Environmental clearance – Status of Forest clearance – Cost of proposed remedial & mitigative measures • Rehabilitation measures • Compensatory afforestation • Disaster management plan • Restoration of land in construction areas by filling, grading • Control of aquatic weeds in submerged areas to provide improved habitat for aquatic life • Measures to salvage/rehabilitation of any rare or endangered species of flora and fauna • Catchment Area Treatment • Details about Net Present Value of forest land
  • 26. • COST ESTIMATES o The Civil Cost Estimates of the project shall be prepared as per “Guidelines for preparation of estimates for the river valley projects” issued by CWC and Indian Standard IS: 4877 “Guide for Preparation of Estimate for River Valley Projects”. o The estimates of a Hydro Electric Scheme shall be divided under the following heads: • A. Direct Cost • I. Works • A - Preliminary • B - Land • C - Works • J - Power Plant Civil Works • K - Buildings • M - Plantation • O - Miscellaneous • P – Maintenance during construction • Q - Special T&P • R - Communications
  • 27. • COST ESTIMATES – S - Power Plant and Electro- Mechanical system – X - Environment and ecology – Y - Losses on stock • Total I-Works – 1. Establishment – 2. Tools and Plants – 3. Suspense – 4. Receipt And Recoveries • Total (A) - Direct Cost • B. Indirect Cost – i. Capitalization of Abatement of Land Revenue – ii. Audit and Account Charges • Total (B) - Indirect Cost • Total Cost (A+B)
  • 28. • ALLOCATION OF COST – The details in respect of allocation of cost for each component of the Multipurpose Project shall be based on the cost cleared by Technical Advisory Committee of MOWR. The details in this regard may be clearly spelt out under this Chapter. – In case of projects involving flood moderation, it may clearly be indicated whether the cost of flood moderation as cleared by CWC shall be borne by the concerned beneficiary State.
  • 29. • ECONOMIC EVALUATION – Phasing of expenditure half yearly – Interest during construction (IDC) – Cost of generation at power house bus bars (with IDC) – Sale rate of energy (with IDC) (with and without free power to home State) – Levelised tariff (with and without free power to home State) – Comparison of cost of generation with alternate source of generation in the in state/region. – Project estimated cost and financial package summary shall be submitted “Calculations Shall be carried out as per the tariff order of the Appropriate Regulatory Commission.”
  • 30. • FUTURE UTILISATION OF BUILDINGS – Details of buildings to be constructed to meet peak requirements of the project – Departmental requirement of buildings after completion of the project – Requirement of the buildings by other agencies – Utilization of surplus buildings
  • 31. • RECOMMENDATIONS – Economic justification of the project – Socio-economic and other benefits
  • 32. • CLEARANCES / INPUTS – Authenticated Copies of the following Documents/Certificates/Clearances are required to be submitted to CEA for concurrence. • Letter from the Registrar of Companies indicating that the company has been registered as a Generating Company under Indian Companies Act, 1956. • Article of Association indicating that generation is one of the objectives of the company. • Letter from Competent Government authorizing the company to establish, own and operate generating power plant. • Land availability certificate from State Revenue Authorities • Water availability certificate from State Irrigation Department/ concerned agency. • Clearance of Ministry of Water Resources/ Central Water Commission • Defense clearance(If, necessary). • Recommendation of the State Govt. on the project cost in case of private projects. • Any other Statutory clearance from Ministries / Departments / Organizations.
  • 33. • Submit the DPR to the Authority for its concurrence as under Sec. 8 of E.A.2003. • 4-copies submit to Sec. of C.E.A. If DPR is correct and complete then after 2- weeks DPR again be submit with 21-copies along with one-soft copy • CEA/CWC/GSI shall decide in another 2-weeks whether the details furnished in DPR are adequate or not. POWER PROJECTS • It involves Drinking water, irrigation, power, flood control, navigation etc. so submit to C.W.C. of M.O.W.R.(T.A.C. ). • The Flood moderation aspects parts submit to C.W.C./M.O.W.R. MULTI-PURPOSE PROJECTS
  • 34. • Examination – Appraisal of DPR – Aspects to be appraised • Concurrence – Submission of Update DPR – Information regarding Financial Closure – Time Frame for accord of Concurrence – Validity of concurrence – Transfer of Concurrence – Subsequently changes in Project parameters
  • 35. • List of relevant Documents/ References – 1. The Electricity Act, 2003 – 2. Indian Companies Act, 1956 – 3. Forest Conservation Act, 1980 and Notifications/Resolutions by MOE&F. – 4. “Guidelines for preparation of DPRs of Irrigation and Multipurpose Projects” issued by CWC. – 5. “Guidelines for preparation of project estimates for major irrigation and multipurpose project” issued by CWC. – 6. National Electricity Plan notified by CEA – 7. Indian Electricity Sector – Widening Scope for Private Participation-Issued by Ministry of Power. – 8. Policy on Hydro Power Development issued by Ministry of Power – 9. Guidelines for “Investigation of major irrigation and hydro-electric projects” issued by CWC. – 10. CBIP – Technical Report No.19 “Life of Reservoir (1977)” • IS 5497 : Guide for topographical surveys for river valley projects • IS 4890 : Method for measurement of suspended sediment in open rivers • IS 13216 : Code of practice for geological explorations for reservoir sites. • IS 4186 : Guide for preparation of project report for river valley projects. • IS 4877 : Guide for preparation of Estimate for River Valley Projects. • IS 5477 : Methods for fixing the capacities of reservoirs. (Part 1-4) • IS 7323 : Method for determining evaporation from reservoirs. • IS 7323 : Guidelines for operation of reservoirs. • IS 13028 : Guidelines for overall planning of river basin. • IS 7560 : Guidelines for allocation of cost among different purposes of river valley projects. • IS 4247 : Code of practice for structural design of surface hydro power stations. • IS 12837 : Guidelines for selection of hydraulic turbines for medium and large hydro-electric power houses. • IS 12800 : Guidelines for selection of turbines preliminary dimensioning & layout of surface hydro electric power houses.