Topic of Lecture:
River Valley Development Project
&
Planning of Water Resource Development Projects
Prepared by:
Prof. Darshan J Mehta
Assistant Professor,
Civil Engineering Department,
Dr. S. & S. S. Ghandhy Government Engineering College, Surat 1
Subject: Water Resources Planning [3723303]
Dr. S & S. S. Ghandhy Government Engineering College,
Surat
9-Jul-20
Outline
• Multipurpose Projects
• Role of Multipurpose Projects
• Planning Of Multipurpose Projects
• Functional Requirements of Multipurpose Projects
• Merits & Demerits of Multipurpose Projects
• Estimation of Benefit Cost Ratio
• Case Study: Sardar Sarovar Dam
29-Jul-20
• Planning of Multi-purpose River Project represents the integrated
construction of two or more projects, each having a particular purpose or
function.
Multipurpose Projects
9-Jul-20 3
• Water is essential for sustenance of all forms of life on earth. It is not
evenly distributed all over the world and even its availability at the same
locations is not uniform over the year.
• The River valley projects which are constructed to meet several objectives
simultaneously or tackle various problems associated with river valleys in
an integrated manner.
• The basic motive behind the construction of multipurpose river valley
projects in India is to meet the critical requirements of irrigation for
agriculture, electricity for industries and flood control.
Introduction :
Multipurpose River Valley Projects
9-Jul-20 4
Role of Multipurpose River Valley Projects
• Reduce the threat of seasonal floods and bolster local economies.
• Aim to integrate agricultural development with the local economy through rapid
industrialization and growth.
• Irrigation for agriculture and electricity for industries
• Provide water for irrigation to towns, improve navigation, create habitats for fish
and wildlife and generate hydroelectric power for industrial purposes.
• The development of transportation facilities
• The creation of hydroelectric power.
• Economic self-sufficiency and improve the standard of living for citizens.
9-Jul-20 5
Planning of Multipurpose Projects
9-Jul-20 6
• Statement of Objectives
• Preparing Inventory of available resources
• Collection of Data
• Future Projection
• Project Formulation
• Project Evaluation
• Environmental Condition
Statement of Objectives
9-Jul-20 7
• Increased agricultural production
• Industrial development
• Improving the living standard of the people
• Social Stability
Preparing Inventory of available resources
9-Jul-20 8
• Water Resources
• Water Quality
• Land Resources
• Human Resources
• Means of Communications
• Financial Resources
Collection of Data
9-Jul-20 9
GENERAL DATA
• Physical Data
• Hydrological Data
• Geographical Data
• Cartographic Data
• Ecological Data
• Legal Data
• Demographic Data
• Economic Data
• Data on public opinion
• Data on existing data
Collection of Data
9-Jul-20 10
SPECIAL DATA
• Agricultural Data
• Water Supply Data
• Navigation Data
• Flood Control Data
• Hydropower Generation Data
• Pollution Control Data
• Fish and Wildlife Data
• Recreation and Tourism Data
Project for Future Planning
9-Jul-20 11
• Any project to be taken in hand should ne designed to serve not only or the present
need but also to serve for future needs for a period of at least 25 years.
• The historical and collected data (current) for project planning should be serve as a
base for future projection condition.
• All project must be plan to meet the future requirements.
Project Formulation
9-Jul-20 12
• After collection of basic data and evaluation future needs is completed actual
formulation of the project commence.
• This is a phase of planning where skill and imagination is required.
• Now, important step is compilation of a comprehensive list of alternatives. At the time
of compilation following steps are involved:
1) Define the boundary conditions
2) List all possible land use planning and their water requirements
3) List all possible projects
4) Prepare preliminary design and cost estimates for the projects
5) Estimates the benefits for all projects
6) Reject the projects which are no economical
7) Select 2/3rd combination which can give maximum return for detail study and
select final alternative
8) Prepare detailed report on final alternative which show costs, benefits, etc.
Project Evaluation
9-Jul-20 13
• The selection of most economical alternative from the various
alternatives known as Project Evaluation.
• For economic evaluation data on benefits and cost are collected.
• Economically Independent unit
• Physically Independent Unit
• A complete environmental impact assessment should be conducted before the
project is considered for clearance, and the results of the analysis should be
used to judge the viability and desirability of the project
• If the project is considered viable and desirable on social, economic,
environmental, and technical grounds, it is necessary to take preventive
measures related to the negative environmental impacts.
• This requires the formulation of precise and comprehensive work-plans, and
their implementation.
• At this stage it may even be necessary to redesign the project, if environmental,
social, or economic imperatives demand it.
Environmental Considerations :
9-Jul-20 14
Functional Requirement of Multi-Purpose
Projects
• Irrigation Facility
• Flood Control
• Generating Electricity
• Navigation
• Forests and Fisheries
• Drinking Water
• Development of Industry and Employment Generation
• Recreation
9-Jul-20 15
Demerits of Multi-Purpose Projects
• Exaggerated Benefits on Irrigation
• Higher Cost of Hydropower
• Least Flood Control Benefit
• Adverse Environmental Impact
9-Jul-20 16
Benefit Cost Ratio
• The benefit cost ratio is the ratio of annual benefits to the annual cost
• In India, the project is economical viable whose benefit cost ratio is greater
than unity.
• For Irrigation purpose this ratio is generally 1.5 and for flood control this ratio
is 1.10.
Annual Cost
• It is the summation of Annual Recovery cost and Recurring cost.
• Capital Cost – Expenditure done at the time of construction of a project.
• Recurring cost – Expenditure done on operation and maintenance of the project
during life span,
Estimation of Benefit Cost Ratio
9-Jul-20 17
Annual Benefits
• Benefits that are likely to be occur due to construction of project which should
fairly estimated.
• If there is an single purpose project it is easier to calculate those benefits for
multipurpose project.
• Damage data in India are generally collected from revenue department but it is
very difficult job to obtain such huge data.
Annual Cost
• It is the summation of Annual Recovery cost and Recurring cost.
• Capital Cost – Expenditure done at the time of construction of a project.
• Recurring cost – Expenditure done on operation and maintenance of the project
during life span,
Estimation of Benefit Cost Ratio
9-Jul-20 18
• Direct Cost
• Indirect Cost
Types of Cost
9-Jul-20 19
Types of Benefits
• Direct Benefits
• Indirect Benefits
• Tangible Benefits
• Intangible Benefits
India's One of the Most Productive
Multipurpose Projects
Sardar Sarovar Dam
9-Jul-20 20
• One of the most controversial and protested government schemes .
• Approved by “Narmada Water Disputes Tribunal” in 1978 which included 30
large dams, 135 medium dams, and 3,000 small dams.
• Initially, started at small level but later in 1985 the World Bank agreed to
finance.
• Estimated that project will irrigate more than 18,000 km2, most of it in drought
prone areas of Kutch and Saurashtra
Narmada Valley Development Project
9-Jul-20 21
Narmada Valley Development Project
9-Jul-20 22
• Location : Sardar Sarovar Dam, Near Navagam, Gujarat.
• Coordinates : 21°49′49″n 73°44′50″e
• Type of dam : gravity dam
• Proposed height of Sardar Sarovar dam: 163metres
• Reservoir total capacity : 9.5 km3
• Catchment area : 88,000 km2
• Construction cost : ₹25 billion INR
• Dam's main power plant houses six 200 mw Francis pump
• Total installed capacity of the power : 1,450 MW.
Details of Sardar Sarovar Dam
9-Jul-20 23
Sardar Sarovar Dam
9-Jul-20 24
• Feed 20 million people, provide domestic and industrial water for about 30
million, employ about 1 million, and valuable electricity.
• Irrigate land spread over 12 districts, 62 talukas and 3393 villages in 'Gujarat'
and 730 km2 in the arid areas of 'Barmer' and 'Jalore' districts of Rajasthan
• Set against the futures of about 70,000 project affected people.
• The ratio of beneficiaries to affected persons 100:1.
• In 1987 after construction of dams the injustices of the government's
relocation program were exposed.
• Consequences: Laid the foundation of “Narmada Bachao Andolan”
Projected Benefits
9-Jul-20 25
Thank You
9-Jul-20 26

More Related Content

What's hot

Flood Mapping using GIS
Flood Mapping using GISFlood Mapping using GIS
Flood Mapping using GISPrabhas Gupta
 
Seminar on Hydrological modelling
Seminar on Hydrological modellingSeminar on Hydrological modelling
Seminar on Hydrological modellingvishvam Pancholi
 
Transboundary waters and water conflicts - current perspectives for the manag...
Transboundary waters and water conflicts - current perspectives for the manag...Transboundary waters and water conflicts - current perspectives for the manag...
Transboundary waters and water conflicts - current perspectives for the manag...Isabela Espíndola
 
Reservoir capacity, Reservoir sedimentation and control
Reservoir capacity, Reservoir sedimentation  and controlReservoir capacity, Reservoir sedimentation  and control
Reservoir capacity, Reservoir sedimentation and controldeep shah
 
Flood risk assessment methodology
Flood risk assessment methodologyFlood risk assessment methodology
Flood risk assessment methodologyAmitSaha123
 
Flood frequency analyses
Flood frequency analysesFlood frequency analyses
Flood frequency analysesvivek gami
 
Data Requirements for Groundwater Modelling
Data Requirements for Groundwater ModellingData Requirements for Groundwater Modelling
Data Requirements for Groundwater ModellingC. P. Kumar
 
Flood forecasting presentation final
Flood forecasting presentation finalFlood forecasting presentation final
Flood forecasting presentation finalAbir Mohammad
 
Hydraulic geometry of a river
Hydraulic geometry of a riverHydraulic geometry of a river
Hydraulic geometry of a riverLalit Thakare
 
Use of toposheets in civil engineering projects
Use of toposheets in civil engineering projectsUse of toposheets in civil engineering projects
Use of toposheets in civil engineering projectsProf. A.Balasubramanian
 
Flood plain zoning
Flood plain zoningFlood plain zoning
Flood plain zoningSurpal Zala
 

What's hot (20)

Flood Mapping using GIS
Flood Mapping using GISFlood Mapping using GIS
Flood Mapping using GIS
 
Seminar on Hydrological modelling
Seminar on Hydrological modellingSeminar on Hydrological modelling
Seminar on Hydrological modelling
 
Hydrological modelling
Hydrological modellingHydrological modelling
Hydrological modelling
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
 
Transboundary waters and water conflicts - current perspectives for the manag...
Transboundary waters and water conflicts - current perspectives for the manag...Transboundary waters and water conflicts - current perspectives for the manag...
Transboundary waters and water conflicts - current perspectives for the manag...
 
Reservoir capacity, Reservoir sedimentation and control
Reservoir capacity, Reservoir sedimentation  and controlReservoir capacity, Reservoir sedimentation  and control
Reservoir capacity, Reservoir sedimentation and control
 
GROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEMGROUNDWATER MODELING SYSTEM
GROUNDWATER MODELING SYSTEM
 
Flood risk assessment methodology
Flood risk assessment methodologyFlood risk assessment methodology
Flood risk assessment methodology
 
Flood frequency analyses
Flood frequency analysesFlood frequency analyses
Flood frequency analyses
 
Data Requirements for Groundwater Modelling
Data Requirements for Groundwater ModellingData Requirements for Groundwater Modelling
Data Requirements for Groundwater Modelling
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
Stream flow
Stream flow Stream flow
Stream flow
 
Flood forecasting presentation final
Flood forecasting presentation finalFlood forecasting presentation final
Flood forecasting presentation final
 
Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Hydraulic geometry of a river
Hydraulic geometry of a riverHydraulic geometry of a river
Hydraulic geometry of a river
 
Stream gauging ppt
Stream gauging pptStream gauging ppt
Stream gauging ppt
 
Use of toposheets in civil engineering projects
Use of toposheets in civil engineering projectsUse of toposheets in civil engineering projects
Use of toposheets in civil engineering projects
 
Chapter 3 Fetter Properties of Aquifers
Chapter 3 Fetter Properties of AquifersChapter 3 Fetter Properties of Aquifers
Chapter 3 Fetter Properties of Aquifers
 
Flood plain zoning
Flood plain zoningFlood plain zoning
Flood plain zoning
 
Floods
FloodsFloods
Floods
 

Similar to Planning and Benefits of India's Sardar Sarovar Dam Project

Sudan workshop | Morocco Country Presentation (Part 2)
Sudan workshop | Morocco Country Presentation (Part 2)Sudan workshop | Morocco Country Presentation (Part 2)
Sudan workshop | Morocco Country Presentation (Part 2)ÖMER KILIÇ
 
My presentation at N.P.T.I
My presentation at N.P.T.IMy presentation at N.P.T.I
My presentation at N.P.T.ISantosh Singh
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )sandeepprasad87
 
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...India-EU Water Partnership
 
IWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureIWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureOswar Mungkasa
 
Multipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsMultipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsTannya
 
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...Deltares
 
Climate Resilience Improvement Project
Climate Resilience Improvement ProjectClimate Resilience Improvement Project
Climate Resilience Improvement ProjectJanathakshan Gte Ltd
 
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...India UK Water Centre (IUKWC)
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
India’s national river linking project [nrlp]
India’s national river linking project [nrlp]India’s national river linking project [nrlp]
India’s national river linking project [nrlp]'Denish Makvana'
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam JunaidAshraf31
 
Water resources planning & environmental considerations
Water resources planning & environmental considerationsWater resources planning & environmental considerations
Water resources planning & environmental considerationsAMIE(I) Study Circle
 
P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXMatt Meaker
 
Victorian desalination plant case study_FM
Victorian desalination plant case study_FMVictorian desalination plant case study_FM
Victorian desalination plant case study_FMsayandeep chandra
 
Constructed Wetland Guidance & Hub
Constructed Wetland Guidance & Hub Constructed Wetland Guidance & Hub
Constructed Wetland Guidance & Hub PAS_Team
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Robert Muir
 

Similar to Planning and Benefits of India's Sardar Sarovar Dam Project (20)

Sudan workshop | Morocco Country Presentation (Part 2)
Sudan workshop | Morocco Country Presentation (Part 2)Sudan workshop | Morocco Country Presentation (Part 2)
Sudan workshop | Morocco Country Presentation (Part 2)
 
My presentation at N.P.T.I
My presentation at N.P.T.IMy presentation at N.P.T.I
My presentation at N.P.T.I
 
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
ENVIRONMENTAL-IMPACT-ASSESSMENT (E I A )
 
Water Programme
Water ProgrammeWater Programme
Water Programme
 
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
 
IWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureIWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New Future
 
Multipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsMultipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methods
 
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...
DSD-Kampala 2023 Analytic Tools for Cooperative Water Resources Assessments i...
 
Climate Resilience Improvement Project
Climate Resilience Improvement ProjectClimate Resilience Improvement Project
Climate Resilience Improvement Project
 
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...
IUKWC Workshop Nov16: Developing Hydro-climatic Services for Water Security –...
 
National Water Mission
National Water MissionNational Water Mission
National Water Mission
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
India’s national river linking project [nrlp]
India’s national river linking project [nrlp]India’s national river linking project [nrlp]
India’s national river linking project [nrlp]
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 
Water resources planning & environmental considerations
Water resources planning & environmental considerationsWater resources planning & environmental considerations
Water resources planning & environmental considerations
 
P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTX
 
Victorian desalination plant case study_FM
Victorian desalination plant case study_FMVictorian desalination plant case study_FM
Victorian desalination plant case study_FM
 
Water resources
Water resourcesWater resources
Water resources
 
Constructed Wetland Guidance & Hub
Constructed Wetland Guidance & Hub Constructed Wetland Guidance & Hub
Constructed Wetland Guidance & Hub
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 

Planning and Benefits of India's Sardar Sarovar Dam Project

  • 1. Topic of Lecture: River Valley Development Project & Planning of Water Resource Development Projects Prepared by: Prof. Darshan J Mehta Assistant Professor, Civil Engineering Department, Dr. S. & S. S. Ghandhy Government Engineering College, Surat 1 Subject: Water Resources Planning [3723303] Dr. S & S. S. Ghandhy Government Engineering College, Surat 9-Jul-20
  • 2. Outline • Multipurpose Projects • Role of Multipurpose Projects • Planning Of Multipurpose Projects • Functional Requirements of Multipurpose Projects • Merits & Demerits of Multipurpose Projects • Estimation of Benefit Cost Ratio • Case Study: Sardar Sarovar Dam 29-Jul-20
  • 3. • Planning of Multi-purpose River Project represents the integrated construction of two or more projects, each having a particular purpose or function. Multipurpose Projects 9-Jul-20 3
  • 4. • Water is essential for sustenance of all forms of life on earth. It is not evenly distributed all over the world and even its availability at the same locations is not uniform over the year. • The River valley projects which are constructed to meet several objectives simultaneously or tackle various problems associated with river valleys in an integrated manner. • The basic motive behind the construction of multipurpose river valley projects in India is to meet the critical requirements of irrigation for agriculture, electricity for industries and flood control. Introduction : Multipurpose River Valley Projects 9-Jul-20 4
  • 5. Role of Multipurpose River Valley Projects • Reduce the threat of seasonal floods and bolster local economies. • Aim to integrate agricultural development with the local economy through rapid industrialization and growth. • Irrigation for agriculture and electricity for industries • Provide water for irrigation to towns, improve navigation, create habitats for fish and wildlife and generate hydroelectric power for industrial purposes. • The development of transportation facilities • The creation of hydroelectric power. • Economic self-sufficiency and improve the standard of living for citizens. 9-Jul-20 5
  • 6. Planning of Multipurpose Projects 9-Jul-20 6 • Statement of Objectives • Preparing Inventory of available resources • Collection of Data • Future Projection • Project Formulation • Project Evaluation • Environmental Condition
  • 7. Statement of Objectives 9-Jul-20 7 • Increased agricultural production • Industrial development • Improving the living standard of the people • Social Stability
  • 8. Preparing Inventory of available resources 9-Jul-20 8 • Water Resources • Water Quality • Land Resources • Human Resources • Means of Communications • Financial Resources
  • 9. Collection of Data 9-Jul-20 9 GENERAL DATA • Physical Data • Hydrological Data • Geographical Data • Cartographic Data • Ecological Data • Legal Data • Demographic Data • Economic Data • Data on public opinion • Data on existing data
  • 10. Collection of Data 9-Jul-20 10 SPECIAL DATA • Agricultural Data • Water Supply Data • Navigation Data • Flood Control Data • Hydropower Generation Data • Pollution Control Data • Fish and Wildlife Data • Recreation and Tourism Data
  • 11. Project for Future Planning 9-Jul-20 11 • Any project to be taken in hand should ne designed to serve not only or the present need but also to serve for future needs for a period of at least 25 years. • The historical and collected data (current) for project planning should be serve as a base for future projection condition. • All project must be plan to meet the future requirements.
  • 12. Project Formulation 9-Jul-20 12 • After collection of basic data and evaluation future needs is completed actual formulation of the project commence. • This is a phase of planning where skill and imagination is required. • Now, important step is compilation of a comprehensive list of alternatives. At the time of compilation following steps are involved: 1) Define the boundary conditions 2) List all possible land use planning and their water requirements 3) List all possible projects 4) Prepare preliminary design and cost estimates for the projects 5) Estimates the benefits for all projects 6) Reject the projects which are no economical 7) Select 2/3rd combination which can give maximum return for detail study and select final alternative 8) Prepare detailed report on final alternative which show costs, benefits, etc.
  • 13. Project Evaluation 9-Jul-20 13 • The selection of most economical alternative from the various alternatives known as Project Evaluation. • For economic evaluation data on benefits and cost are collected. • Economically Independent unit • Physically Independent Unit
  • 14. • A complete environmental impact assessment should be conducted before the project is considered for clearance, and the results of the analysis should be used to judge the viability and desirability of the project • If the project is considered viable and desirable on social, economic, environmental, and technical grounds, it is necessary to take preventive measures related to the negative environmental impacts. • This requires the formulation of precise and comprehensive work-plans, and their implementation. • At this stage it may even be necessary to redesign the project, if environmental, social, or economic imperatives demand it. Environmental Considerations : 9-Jul-20 14
  • 15. Functional Requirement of Multi-Purpose Projects • Irrigation Facility • Flood Control • Generating Electricity • Navigation • Forests and Fisheries • Drinking Water • Development of Industry and Employment Generation • Recreation 9-Jul-20 15
  • 16. Demerits of Multi-Purpose Projects • Exaggerated Benefits on Irrigation • Higher Cost of Hydropower • Least Flood Control Benefit • Adverse Environmental Impact 9-Jul-20 16
  • 17. Benefit Cost Ratio • The benefit cost ratio is the ratio of annual benefits to the annual cost • In India, the project is economical viable whose benefit cost ratio is greater than unity. • For Irrigation purpose this ratio is generally 1.5 and for flood control this ratio is 1.10. Annual Cost • It is the summation of Annual Recovery cost and Recurring cost. • Capital Cost – Expenditure done at the time of construction of a project. • Recurring cost – Expenditure done on operation and maintenance of the project during life span, Estimation of Benefit Cost Ratio 9-Jul-20 17
  • 18. Annual Benefits • Benefits that are likely to be occur due to construction of project which should fairly estimated. • If there is an single purpose project it is easier to calculate those benefits for multipurpose project. • Damage data in India are generally collected from revenue department but it is very difficult job to obtain such huge data. Annual Cost • It is the summation of Annual Recovery cost and Recurring cost. • Capital Cost – Expenditure done at the time of construction of a project. • Recurring cost – Expenditure done on operation and maintenance of the project during life span, Estimation of Benefit Cost Ratio 9-Jul-20 18
  • 19. • Direct Cost • Indirect Cost Types of Cost 9-Jul-20 19 Types of Benefits • Direct Benefits • Indirect Benefits • Tangible Benefits • Intangible Benefits
  • 20. India's One of the Most Productive Multipurpose Projects Sardar Sarovar Dam 9-Jul-20 20
  • 21. • One of the most controversial and protested government schemes . • Approved by “Narmada Water Disputes Tribunal” in 1978 which included 30 large dams, 135 medium dams, and 3,000 small dams. • Initially, started at small level but later in 1985 the World Bank agreed to finance. • Estimated that project will irrigate more than 18,000 km2, most of it in drought prone areas of Kutch and Saurashtra Narmada Valley Development Project 9-Jul-20 21
  • 22. Narmada Valley Development Project 9-Jul-20 22
  • 23. • Location : Sardar Sarovar Dam, Near Navagam, Gujarat. • Coordinates : 21°49′49″n 73°44′50″e • Type of dam : gravity dam • Proposed height of Sardar Sarovar dam: 163metres • Reservoir total capacity : 9.5 km3 • Catchment area : 88,000 km2 • Construction cost : ₹25 billion INR • Dam's main power plant houses six 200 mw Francis pump • Total installed capacity of the power : 1,450 MW. Details of Sardar Sarovar Dam 9-Jul-20 23
  • 25. • Feed 20 million people, provide domestic and industrial water for about 30 million, employ about 1 million, and valuable electricity. • Irrigate land spread over 12 districts, 62 talukas and 3393 villages in 'Gujarat' and 730 km2 in the arid areas of 'Barmer' and 'Jalore' districts of Rajasthan • Set against the futures of about 70,000 project affected people. • The ratio of beneficiaries to affected persons 100:1. • In 1987 after construction of dams the injustices of the government's relocation program were exposed. • Consequences: Laid the foundation of “Narmada Bachao Andolan” Projected Benefits 9-Jul-20 25