Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating Proposed Control Measures
Risk
Rating
S L R S L R
Power Tools
• Rotating Parts
• Electrocution From Damage Cables
• Inhalation (Dust)
• Dust/Objects In Eye
• Lead Man
• Flushing Crew
• Supervisor
• General Helpers
5 5 25 • Flushing Crew Shall Be Trained & Competent.
• Work Crews Will Use Appropriate PPE.( Safety Goggles,
Face Shields, Dust Mask )
• STARRT Talks For All Crews by Supervisor/Foreman.
• Power Tools Training As Tool Box Talks Topic.
• Power Tools And Cables Shall Be Inspected Daily And
Color Coded Prior To Start Of Work.
• Damage or Defective Power Tools Shall Be Tagged Out Of
Service And Immediately Returned To The Tool Room for
Repair.
• Grounding/Earthling Will Be Provided On All Mobile
Generators.
5 1 5
Noise (Equipment)
• Ear Damage
• Lead Man
• Flushing Crew
• General Helpers
• Supervisor
• Inspector
5 4 20 • Work Crews Will Use Appropriate PPE (Ear Muff, Ear
Plug).
• STARRT Talks For Crews Working In Noisy Environment.
• Noise (Ear Protection) As Training In Tool Box Talks Topic.
• Ensure Appropriate Barricades (Tape) & Sign Boards “Ear
Protectors Must Be Worn In This Area” Placed Around In
The Equipment.
• All Silencers Must Be Inspected For Maintenance To Ensure
The Proper Condition Of Equipment Prior To Start Of Work.
• All Equipment On Site Must Utilize Silencer.
4 1 4
6of 1 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
Manual Handling • Supervisor
• Lead Man
• Flushing Crew
• General Helpers
5 5 25 • STARRT Talks For Crews.
• Manual Handling As Tool Box Talks Topic.
• Work Crews Will Use Appropriate PPE. ( Safety Goggles,
Welder Gloves, Argon Gloves)
• Plan The Route Before You Lift.
• Keep Work Area & Walkways Clear.
• Allow Rest Periods.
• Workers Are Trained To Move Feet Instead Of Twisting
Body.
5 1 5
Hazardous Substances
• Skin Burning
• Eye Irritations
• Health Impairment-Inhalation
• Fire
• Supervisor
• Lead Man
• Flushing Crew
• General Helpers
• Inspector
5 5 25 • STARRT Talks For Crews Working In Hazardous
Substances.
• Hazardous Communication Program Shall Be Implemented.
• Material Safety Data Sheet (MSDS) Shall Be Posted On Site.
• Workers Shall Be Instructed On The Proper Use Of
Materials In Accordance With MSDS Requirements.
• MSDS Requirements for Transport, Storage, Use and
Disposal Shall be Implemented.
• Work Crews Will Use Appropriate PPE. ( Hand Gloves,
Safety Goggles, Face Masks, Cover All and Respirators)
• Control of Substances Hazardous To Health Training As
Tool Box Talks Topic.
• Appropriate Training Prior To Start Of Work.
• First Aid Kit Will Be Available.
• STARRT Talks for Crews Working In Hazardous Substances.
• Control of Substances Hazardous To Health Training As Tool
Box Talks Topic.
• Appropriate Training Prior To Start of Work.
5 1 5
6of 2 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
• Work Crews Will Use Appropriate PPE.
• Sufficient Water Available For Eye And Skin Wash.
Compressed Air
• Air Impact
• Eyes
• Skin
• Hose Whip Check
• Supervisor
• Lead Man
• Flushing Crew
• Inspector
• General Helpers
5 4 20 • Pressure Testing Crew Shall Be Trained And Competent.
• Work Crews Will Use Appropriate PPE
• STARRT Talks For All Crews.
• Compressed Air Training As Tool Box Talks Topic.
• Provide Adequate Fire Protection (Provision Of Sand, Fire
Blanket, and Fire Watchman & Fire Extinguisher).
• Air Hose Must Be Keeping Free Of Grease And Oil.
• Hose Ends Must Be Secured To Prevent Whipping.
• Compressed Air Shall Be Identified the Maximum Working
Pressure.
• Proper Training Prior To Start Of Work.
• Compressed Air System Shall Be Inspected Regularly.
• Proper Communication During Operation
• First Aid Kit Will Be Available.
4 1 4
Working At Heights
• Fall Person
• Fall Material
• Supervisor
• Lead Man
• Flushing Crew
• General Helpers
• Inspector
5 5 25 • Working At Heights Training As Tool Box Talks Topic.
• STARRT Talks for Crews Working At Heights.
• Scaffold Erection by Competent Person.
• Scaftag Inspection Approval before Use.
• Safety Full Body Harness Required (Fall Protection).
5 1 5
Foreign Body on Eye • All 5 4 20 • STARRT Talks For All Crews.
• Work Crews Will Use Appropriate PPE.( Welding Masks,
Safety Goggles )
• Eye Protection Training as Tool Box Talks Topic.
4 1 4
6of 3 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
Electrical Works
• Fire & Explosion
• Electrocution
• Supervisor
• General Helpers
• Flushing Crew
• Lead Man
5 5 25 • Electricians Shall Be Trained & Competent.
• Helper Shall Be Trained & Competent.
• Work Crews Will Use Appropriate PPE.
• Safe Insulated Tools Will Be Used In Order To Carry Out
Electrical Work.
• STARRT Talks For All Crews Involve In Site Electricity.
• Site Electricity Training as Tool Box Talks Topic.
• Lock Out/Tag out System.
• First Aid Kit Will Be Available.
5 1 5
Electrical Equipment
• Fire & Explosion
• Electrocution
• Supervisor
• Lead Man
• Flushing Crew
• General Helpers
5 5 25 • Work Crews Will Use Appropriate PPE.
• Grounding/Earthling Will Be Provided On All Mobile
Electrical Generators.
• Ground Fault Circuit Interrupter (GFCIs) / Earth Leakage
Circuit Interrupter (ELCBs) Will Be Provided For All Areas
Having A Wet Atmosphere Where Electrical Equipment or
Portable Electrical Tools May Be Used.
• Equipment Shall Be Maintained In A Good Condition And
Color Coded.
• STARRT Talks for All Crews.
• Site Electricity Training As Tool Box Talks Topic.
• Lock Out/Tag out System.
• Power Tools & Cables Inspected And Color Coded.
5 1 5
Slips, Trips And Fall • Supervisor
• Lead Man
• Flushing Crew
• Inspector
• Helpers
5 5 25 • STARRT Talks for Crews.
• Work Crews Will Use Appropriate PPE.
• Check The Route Prior To Start Of Work.
• First Aid Kit Will Be Available.
• Housekeeping Training As Tools Box Talks Topic.
5 1 5
6of 4 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
• Always Check The Area Free From Unnecessary Materials.
• Work Place Shall Be Maintained In A Good Condition That
Is Clean And Tidy.
General Welfare • All 5 4 20 • Work Crews Will Use Appropriate PPE.
• Dust Masks Required In Windy/Dusty Condition.
• Provide Sufficient Cool Drinking Water Near Workers.
• Provide Sufficient Toilets In Close Vicinity Of Workers.
• Provide Shaded Rest Areas In Close Vicinity Of Workers.
• Provide Sufficient Lights Near Workers At Night.
• Employees Shall Be Trained on Heat Stress Prevention,
Recognition And Treatment.
4 1 4
Fluid Spills From Vehicles Equipment
• Ground Contamination
• Water Contamination
• Environment 5 4 20 • Daily Inspection of Equipment for Leaks.
• Routine Preventive Maintenance Program.
• Maintenance Performed By Competent Persons.
• Drip Pans Sheets Used during Service and all joint point of
hoses.
• Spills Kit (Sand) Available In Service Area.
• Impervious Material under Fuel Tanks (Bounded) Fuelling
Area, Service Area.
• Impervious Material under Waste Oil Storage Area.
• Proper drainage system.
• Barricade the area and sign board posted (Danger Flushing in
progress) all around the area.
4 1 4
6of 5 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
Originator Signature: Sajid Ali Date: 18-09-2015
6of 6 Page
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Assessment No: Assessed By: Activity: Flushing/Chemical Treatment
Hazard Persons at Risk
Risk
Rating
Proposed Control Measures
Risk
Rating
Originator Signature: Sajid Ali Date: 18-09-2015
6of 6 Page

More Related Content

What's hot

9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templatesDwarika Bhushan Sharma
 
Work at Height | Safety during work at hight
Work at Height | Safety during work at hightWork at Height | Safety during work at hight
Work at Height | Safety during work at hightGaurav Singh Rajput
 
Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of RiggerMajid Hussain
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.pptIrfanAwan25
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxssuser926916
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptKamran Zafar
 
Working with and around our equipment1
Working with and around our equipment1Working with and around our equipment1
Working with and around our equipment1Sheena Baker
 
Safety in mechanical maintenance
Safety in mechanical  maintenanceSafety in mechanical  maintenance
Safety in mechanical maintenancePrasadroshan Mythin
 
Step 3 duties and fire watch
Step 3 duties and fire watchStep 3 duties and fire watch
Step 3 duties and fire watchfqf383
 

What's hot (20)

9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Work at Height | Safety during work at hight
Work at Height | Safety during work at hightWork at Height | Safety during work at hight
Work at Height | Safety during work at hight
 
Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of Rigger
 
Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
Lifting & Rigging by NEIS
Lifting & Rigging by NEISLifting & Rigging by NEIS
Lifting & Rigging by NEIS
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Work safe with grinder
Work safe with grinderWork safe with grinder
Work safe with grinder
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
Ladder safety
Ladder safetyLadder safety
Ladder safety
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.ppt
 
Working at height slides
Working at height slidesWorking at height slides
Working at height slides
 
Working with and around our equipment1
Working with and around our equipment1Working with and around our equipment1
Working with and around our equipment1
 
Safety in mechanical maintenance
Safety in mechanical  maintenanceSafety in mechanical  maintenance
Safety in mechanical maintenance
 
Step 3 duties and fire watch
Step 3 duties and fire watchStep 3 duties and fire watch
Step 3 duties and fire watch
 

Viewers also liked

Aqua pump
Aqua pumpAqua pump
Aqua pumpKPM
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesDavid Horowitz
 
Chemical safety
Chemical safetyChemical safety
Chemical safetySchierlen
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Safety In Storage / handling / Transportation Of Chemicals. By Bimal Chandra...
Safety In Storage / handling / Transportation  Of Chemicals. By Bimal Chandra...Safety In Storage / handling / Transportation  Of Chemicals. By Bimal Chandra...
Safety In Storage / handling / Transportation Of Chemicals. By Bimal Chandra...Bimal Chandra Das
 
Chemistry related damage of components in thermal power plant
Chemistry related damage of components in thermal power plantChemistry related damage of components in thermal power plant
Chemistry related damage of components in thermal power plantSHIVAJI CHOUDHURY
 
Chemical safety
Chemical safety  Chemical safety
Chemical safety Prasad CSBR
 
Damage mechanism in boiler (thermal power plant)
Damage mechanism in boiler (thermal power plant)Damage mechanism in boiler (thermal power plant)
Damage mechanism in boiler (thermal power plant)SHIVAJI CHOUDHURY
 
Fire protection in thermal power station
Fire protection in thermal power stationFire protection in thermal power station
Fire protection in thermal power stationMOORTHY ASSOCIATES
 
Chemical Safety in the Workplace
Chemical Safety in the WorkplaceChemical Safety in the Workplace
Chemical Safety in the WorkplaceAWARE-NS
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYDilip Kumar
 
Safety health and environment aspects in thermal power plants
Safety health and environment aspects in thermal power plantsSafety health and environment aspects in thermal power plants
Safety health and environment aspects in thermal power plantsVudugundla Kodandapani
 
Safe Chemical Handling & Initial Spill Response
Safe Chemical Handling & Initial Spill ResponseSafe Chemical Handling & Initial Spill Response
Safe Chemical Handling & Initial Spill ResponseDavid Horowitz
 

Viewers also liked (20)

Aqua pump
Aqua pumpAqua pump
Aqua pump
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant Facilities
 
Chemical safety
Chemical safetyChemical safety
Chemical safety
 
Chemical safety
Chemical safety Chemical safety
Chemical safety
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Chemical Safety
Chemical SafetyChemical Safety
Chemical Safety
 
Safety In Storage / handling / Transportation Of Chemicals. By Bimal Chandra...
Safety In Storage / handling / Transportation  Of Chemicals. By Bimal Chandra...Safety In Storage / handling / Transportation  Of Chemicals. By Bimal Chandra...
Safety In Storage / handling / Transportation Of Chemicals. By Bimal Chandra...
 
Chemistry related damage of components in thermal power plant
Chemistry related damage of components in thermal power plantChemistry related damage of components in thermal power plant
Chemistry related damage of components in thermal power plant
 
Chemical safety
Chemical safety  Chemical safety
Chemical safety
 
Damage mechanism in boiler (thermal power plant)
Damage mechanism in boiler (thermal power plant)Damage mechanism in boiler (thermal power plant)
Damage mechanism in boiler (thermal power plant)
 
Fire protection in thermal power station
Fire protection in thermal power stationFire protection in thermal power station
Fire protection in thermal power station
 
Water treatment of steam boilers
Water treatment of steam boilersWater treatment of steam boilers
Water treatment of steam boilers
 
Chemical Safety in the Workplace
Chemical Safety in the WorkplaceChemical Safety in the Workplace
Chemical Safety in the Workplace
 
CHEMICAL SAFETY
CHEMICAL SAFETYCHEMICAL SAFETY
CHEMICAL SAFETY
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRY
 
Safety health and environment aspects in thermal power plants
Safety health and environment aspects in thermal power plantsSafety health and environment aspects in thermal power plants
Safety health and environment aspects in thermal power plants
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Safe Chemical Handling & Initial Spill Response
Safe Chemical Handling & Initial Spill ResponseSafe Chemical Handling & Initial Spill Response
Safe Chemical Handling & Initial Spill Response
 

Similar to RA- Flushing - Chemical Treatment

Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentationSamip Nathani nathani
 
Vinnu palaparthi r&ac(foundation) ppt 2018.
Vinnu palaparthi r&ac(foundation) ppt 2018.Vinnu palaparthi r&ac(foundation) ppt 2018.
Vinnu palaparthi r&ac(foundation) ppt 2018.vinnupalaparthi
 
Industrial safety.pptx
Industrial safety.pptxIndustrial safety.pptx
Industrial safety.pptxamarnadh307
 
OSHA Lockout Safety General Industry
OSHA Lockout Safety General IndustryOSHA Lockout Safety General Industry
OSHA Lockout Safety General IndustryJohn Newquist
 
Protecting Your Property Investment Before Disasters Occur
Protecting Your Property Investment Before Disasters OccurProtecting Your Property Investment Before Disasters Occur
Protecting Your Property Investment Before Disasters OccurNational Pork Board
 
Health & safety part 1
Health & safety part 1Health & safety part 1
Health & safety part 1Nmarksmith
 
Item 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practicesItem 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practicesSoils FAO-GSP
 
Drill Rig Safety.pdf
Drill Rig Safety.pdfDrill Rig Safety.pdf
Drill Rig Safety.pdfRaufHuseynov6
 
mod_6_confined_space2.pptx
mod_6_confined_space2.pptxmod_6_confined_space2.pptx
mod_6_confined_space2.pptxDeniThomasBoban1
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfIbukunOwolabi4
 
Milford Contractor Training Video
Milford Contractor Training VideoMilford Contractor Training Video
Milford Contractor Training Videojconroy1121
 
MILFORD POWER LLC Contractors Safety Brief
MILFORD POWER LLC Contractors Safety Brief MILFORD POWER LLC Contractors Safety Brief
MILFORD POWER LLC Contractors Safety Brief jconroy1121
 
Safety Orientation by Associated Builders and Contractors
Safety Orientation by Associated Builders and ContractorsSafety Orientation by Associated Builders and Contractors
Safety Orientation by Associated Builders and ContractorsAtlantic Training, LLC.
 
Contractor Safety Orientation - Sappi.ppt
Contractor Safety Orientation - Sappi.pptContractor Safety Orientation - Sappi.ppt
Contractor Safety Orientation - Sappi.pptAndreAntWilliams
 
HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputGaurav Singh Rajput
 

Similar to RA- Flushing - Chemical Treatment (20)

Safety_induction
Safety_inductionSafety_induction
Safety_induction
 
Site Induction
Site InductionSite Induction
Site Induction
 
Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentation
 
Vinnu palaparthi r&ac(foundation) ppt 2018.
Vinnu palaparthi r&ac(foundation) ppt 2018.Vinnu palaparthi r&ac(foundation) ppt 2018.
Vinnu palaparthi r&ac(foundation) ppt 2018.
 
Site Induction
Site InductionSite Induction
Site Induction
 
Industrial safety.pptx
Industrial safety.pptxIndustrial safety.pptx
Industrial safety.pptx
 
CONFINED SPACE TRAINING
CONFINED SPACE TRAININGCONFINED SPACE TRAINING
CONFINED SPACE TRAINING
 
OSHA Lockout Safety General Industry
OSHA Lockout Safety General IndustryOSHA Lockout Safety General Industry
OSHA Lockout Safety General Industry
 
Protecting Your Property Investment Before Disasters Occur
Protecting Your Property Investment Before Disasters OccurProtecting Your Property Investment Before Disasters Occur
Protecting Your Property Investment Before Disasters Occur
 
Health & safety part 1
Health & safety part 1Health & safety part 1
Health & safety part 1
 
Item 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practicesItem 9. Equipment installation, use a maintenance – good practices
Item 9. Equipment installation, use a maintenance – good practices
 
Drill Rig Safety.pdf
Drill Rig Safety.pdfDrill Rig Safety.pdf
Drill Rig Safety.pdf
 
mod_6_confined_space2.pptx
mod_6_confined_space2.pptxmod_6_confined_space2.pptx
mod_6_confined_space2.pptx
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdf
 
Milford Contractor Training Video
Milford Contractor Training VideoMilford Contractor Training Video
Milford Contractor Training Video
 
MILFORD POWER LLC Contractors Safety Brief
MILFORD POWER LLC Contractors Safety Brief MILFORD POWER LLC Contractors Safety Brief
MILFORD POWER LLC Contractors Safety Brief
 
Safety Orientation by Associated Builders and Contractors
Safety Orientation by Associated Builders and ContractorsSafety Orientation by Associated Builders and Contractors
Safety Orientation by Associated Builders and Contractors
 
Lab safety measures
Lab safety measuresLab safety measures
Lab safety measures
 
Contractor Safety Orientation - Sappi.ppt
Contractor Safety Orientation - Sappi.pptContractor Safety Orientation - Sappi.ppt
Contractor Safety Orientation - Sappi.ppt
 
HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh Rajput
 

RA- Flushing - Chemical Treatment

  • 1. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating S L R S L R Power Tools • Rotating Parts • Electrocution From Damage Cables • Inhalation (Dust) • Dust/Objects In Eye • Lead Man • Flushing Crew • Supervisor • General Helpers 5 5 25 • Flushing Crew Shall Be Trained & Competent. • Work Crews Will Use Appropriate PPE.( Safety Goggles, Face Shields, Dust Mask ) • STARRT Talks For All Crews by Supervisor/Foreman. • Power Tools Training As Tool Box Talks Topic. • Power Tools And Cables Shall Be Inspected Daily And Color Coded Prior To Start Of Work. • Damage or Defective Power Tools Shall Be Tagged Out Of Service And Immediately Returned To The Tool Room for Repair. • Grounding/Earthling Will Be Provided On All Mobile Generators. 5 1 5 Noise (Equipment) • Ear Damage • Lead Man • Flushing Crew • General Helpers • Supervisor • Inspector 5 4 20 • Work Crews Will Use Appropriate PPE (Ear Muff, Ear Plug). • STARRT Talks For Crews Working In Noisy Environment. • Noise (Ear Protection) As Training In Tool Box Talks Topic. • Ensure Appropriate Barricades (Tape) & Sign Boards “Ear Protectors Must Be Worn In This Area” Placed Around In The Equipment. • All Silencers Must Be Inspected For Maintenance To Ensure The Proper Condition Of Equipment Prior To Start Of Work. • All Equipment On Site Must Utilize Silencer. 4 1 4 6of 1 Page
  • 2. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating Manual Handling • Supervisor • Lead Man • Flushing Crew • General Helpers 5 5 25 • STARRT Talks For Crews. • Manual Handling As Tool Box Talks Topic. • Work Crews Will Use Appropriate PPE. ( Safety Goggles, Welder Gloves, Argon Gloves) • Plan The Route Before You Lift. • Keep Work Area & Walkways Clear. • Allow Rest Periods. • Workers Are Trained To Move Feet Instead Of Twisting Body. 5 1 5 Hazardous Substances • Skin Burning • Eye Irritations • Health Impairment-Inhalation • Fire • Supervisor • Lead Man • Flushing Crew • General Helpers • Inspector 5 5 25 • STARRT Talks For Crews Working In Hazardous Substances. • Hazardous Communication Program Shall Be Implemented. • Material Safety Data Sheet (MSDS) Shall Be Posted On Site. • Workers Shall Be Instructed On The Proper Use Of Materials In Accordance With MSDS Requirements. • MSDS Requirements for Transport, Storage, Use and Disposal Shall be Implemented. • Work Crews Will Use Appropriate PPE. ( Hand Gloves, Safety Goggles, Face Masks, Cover All and Respirators) • Control of Substances Hazardous To Health Training As Tool Box Talks Topic. • Appropriate Training Prior To Start Of Work. • First Aid Kit Will Be Available. • STARRT Talks for Crews Working In Hazardous Substances. • Control of Substances Hazardous To Health Training As Tool Box Talks Topic. • Appropriate Training Prior To Start of Work. 5 1 5 6of 2 Page
  • 3. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating • Work Crews Will Use Appropriate PPE. • Sufficient Water Available For Eye And Skin Wash. Compressed Air • Air Impact • Eyes • Skin • Hose Whip Check • Supervisor • Lead Man • Flushing Crew • Inspector • General Helpers 5 4 20 • Pressure Testing Crew Shall Be Trained And Competent. • Work Crews Will Use Appropriate PPE • STARRT Talks For All Crews. • Compressed Air Training As Tool Box Talks Topic. • Provide Adequate Fire Protection (Provision Of Sand, Fire Blanket, and Fire Watchman & Fire Extinguisher). • Air Hose Must Be Keeping Free Of Grease And Oil. • Hose Ends Must Be Secured To Prevent Whipping. • Compressed Air Shall Be Identified the Maximum Working Pressure. • Proper Training Prior To Start Of Work. • Compressed Air System Shall Be Inspected Regularly. • Proper Communication During Operation • First Aid Kit Will Be Available. 4 1 4 Working At Heights • Fall Person • Fall Material • Supervisor • Lead Man • Flushing Crew • General Helpers • Inspector 5 5 25 • Working At Heights Training As Tool Box Talks Topic. • STARRT Talks for Crews Working At Heights. • Scaffold Erection by Competent Person. • Scaftag Inspection Approval before Use. • Safety Full Body Harness Required (Fall Protection). 5 1 5 Foreign Body on Eye • All 5 4 20 • STARRT Talks For All Crews. • Work Crews Will Use Appropriate PPE.( Welding Masks, Safety Goggles ) • Eye Protection Training as Tool Box Talks Topic. 4 1 4 6of 3 Page
  • 4. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating Electrical Works • Fire & Explosion • Electrocution • Supervisor • General Helpers • Flushing Crew • Lead Man 5 5 25 • Electricians Shall Be Trained & Competent. • Helper Shall Be Trained & Competent. • Work Crews Will Use Appropriate PPE. • Safe Insulated Tools Will Be Used In Order To Carry Out Electrical Work. • STARRT Talks For All Crews Involve In Site Electricity. • Site Electricity Training as Tool Box Talks Topic. • Lock Out/Tag out System. • First Aid Kit Will Be Available. 5 1 5 Electrical Equipment • Fire & Explosion • Electrocution • Supervisor • Lead Man • Flushing Crew • General Helpers 5 5 25 • Work Crews Will Use Appropriate PPE. • Grounding/Earthling Will Be Provided On All Mobile Electrical Generators. • Ground Fault Circuit Interrupter (GFCIs) / Earth Leakage Circuit Interrupter (ELCBs) Will Be Provided For All Areas Having A Wet Atmosphere Where Electrical Equipment or Portable Electrical Tools May Be Used. • Equipment Shall Be Maintained In A Good Condition And Color Coded. • STARRT Talks for All Crews. • Site Electricity Training As Tool Box Talks Topic. • Lock Out/Tag out System. • Power Tools & Cables Inspected And Color Coded. 5 1 5 Slips, Trips And Fall • Supervisor • Lead Man • Flushing Crew • Inspector • Helpers 5 5 25 • STARRT Talks for Crews. • Work Crews Will Use Appropriate PPE. • Check The Route Prior To Start Of Work. • First Aid Kit Will Be Available. • Housekeeping Training As Tools Box Talks Topic. 5 1 5 6of 4 Page
  • 5. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating • Always Check The Area Free From Unnecessary Materials. • Work Place Shall Be Maintained In A Good Condition That Is Clean And Tidy. General Welfare • All 5 4 20 • Work Crews Will Use Appropriate PPE. • Dust Masks Required In Windy/Dusty Condition. • Provide Sufficient Cool Drinking Water Near Workers. • Provide Sufficient Toilets In Close Vicinity Of Workers. • Provide Shaded Rest Areas In Close Vicinity Of Workers. • Provide Sufficient Lights Near Workers At Night. • Employees Shall Be Trained on Heat Stress Prevention, Recognition And Treatment. 4 1 4 Fluid Spills From Vehicles Equipment • Ground Contamination • Water Contamination • Environment 5 4 20 • Daily Inspection of Equipment for Leaks. • Routine Preventive Maintenance Program. • Maintenance Performed By Competent Persons. • Drip Pans Sheets Used during Service and all joint point of hoses. • Spills Kit (Sand) Available In Service Area. • Impervious Material under Fuel Tanks (Bounded) Fuelling Area, Service Area. • Impervious Material under Waste Oil Storage Area. • Proper drainage system. • Barricade the area and sign board posted (Danger Flushing in progress) all around the area. 4 1 4 6of 5 Page
  • 6. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating Originator Signature: Sajid Ali Date: 18-09-2015 6of 6 Page
  • 7. Arabian Bemco Contracting Co. KSA Power Plant Project-10 RISK ASSESSMENT Assessment No: Assessed By: Activity: Flushing/Chemical Treatment Hazard Persons at Risk Risk Rating Proposed Control Measures Risk Rating Originator Signature: Sajid Ali Date: 18-09-2015 6of 6 Page