SlideShare a Scribd company logo
1 of 11
CIT 135 Fall 2011
2009
Energy and Atmosphere.
EA Credit 3: Enhanced Commissioning.
Possible earning points: 2 points.
Presented By : Sherif Teaima
Credit Summary
Intent:
To begin the commissioning process early in
the design process and execute additional
activities after systems performance
verification is completed.
Requirements:
 General Requirements.
 (CxA) Requirements.
 Activities Requirements.
What is commissioning?
Building commissioning is a quality assurance
program intended to demonstrate the the building
is constructed well and performs as designed.
Commissioning is also a powerful tool because it
can indicate if the designers and contractors have
done what they’ve been hired to do.
CxA or the commissioning agent have the
authority  to make the responsible parties fix the
problems up front instead of dealing with
maintenance problems or poor performance down
the road.
General Requirements.
 Implement, or have a contract in place to
implement, the following additional
commissioning process activities in addition to
the requirements of EA Prerequisite 1:
Fundamental Commissioning of Building Energy
Systems and in accordance with the LEED
Reference Guide for Green Building Design and
Construction, 2009 Edition:
 Prior to the start of the construction
documents phase, designate an independent
commissioning authority (CxA) to lead, review
and oversee the completion of all commissioning
process activities.
(CxA) Requirements.
 The CxA must have documented commissioning
authority experience in at least 2 building projects.
 Must be independent of the work of design and
construction.
 Must not be an employee of the design firm, though
he or she may be contracted through them.
 Must not be an employee of, or contracted through,
a contractor or construction manager holding
construction contracts.
 May be a qualified employee or consultant of the
owner.
 The CxA must report results, findings and
recommendations directly to the owner.
Activities Requirements.
 The CxA must conduct, at a minimum, 1 commissioning design
review of the owner’s project requirements (OPR) basis of design
(BOD), and design documents (DD/CD) prior to the mid-construction
documents phase and back-check the review comments in the
subsequent design submission.
 The CxA must review contractor submittals applicable to systems
being commissioned for compliance with the owner’s project
requirements and basis of design. This review must be concurrent
with the review of the architect or engineer of record and submitted to
the design team and the owner.
 The CxA or other project team members must develop a systems
manual that gives future operating staff the information needed to
understand and optimally operate the commissioned systems.
 The CxA or other project team members must verify that the
requirements for training operating personnel and building occupants
have been completed.
 The CxA must be involved in reviewing the operation of the building
with operations and maintenance (O&M) staff and occupants within
10 months after substantial completion. A plan for resolving
outstanding commissioning-related issues must be included.
The requirements of this credit can be
met through these strategies:
 Commissioning agent should be brought
on as part of the design phase, not after
the construction starts up.
 Owners must rely on a reputable and well
experienced commissioning agents
 Both the owner and the commissioning
agent should precisely follow The LEED
detailed guidance on the standards
expected for activities like:
• Commissioning design review
• Commissioning submittal review
• System manual
Benefits of the credit on the
Environment.
Commissioning does not only guarantee the integrity of
the construction process according to LEED, but it
contributes to energy conservation as well, through
adequate inspecting to energy related systems such as:
1. HVAC
2. Lighting and day lighting controls
3. Domestic hot water systems
4. Renewable energy systems (solar and wind)
 researches claim that owners can achieve savings in
operations of $4 over the first five years of occupancy
as a direct result of every $1 invested
in commissioning
Some of the materials needed for
commissioning activities
Success Story
In Jan. 2009, Rockefeller Hall at
Harvard Divinity School earned
the EA:c3 credit for enhanced
commissioning after meeting the
EAp1 requirements.
In Nov. of the same year, Rockefeller Hall has been
awarded LEED Gold certification through the U.S. Green
Building Council LEED. Now,
Rockefeller Hall is one of Harvard's
most energy efficient buildings.
WORK CITED
• www.LEEDUSER.com Accessed 10/20/2011
• www.WBDG.org Accessed 10/21/2011
• www.EPA.gov Accessed 10/21/2011
• www.HDS.HARVARD.edu Accessed 10/22/2011
• Google images

More Related Content

What's hot

20140311 final report
20140311 final report20140311 final report
20140311 final reportEUAlpineSpace
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0Aditya Pandey
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
How Quality Importance on Constructions
How Quality Importance on Constructions How Quality Importance on Constructions
How Quality Importance on Constructions Walid AlSarady
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Venkatesh planning cv
Venkatesh  planning cv Venkatesh  planning cv
Venkatesh planning cv Venkatesh -
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Know how to oversee building services work
Know how to oversee building services workKnow how to oversee building services work
Know how to oversee building services workcatherinelindsay
 
BIM Engineering US., L.L.C. | Best MEP Engineering in USA
BIM Engineering US., L.L.C. | Best MEP Engineering in USA BIM Engineering US., L.L.C. | Best MEP Engineering in USA
BIM Engineering US., L.L.C. | Best MEP Engineering in USA BIM Engineering LLC U.S.
 
Service levelagreementtemplate v8
Service levelagreementtemplate v8Service levelagreementtemplate v8
Service levelagreementtemplate v8Aditya Pandey
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUGL Engineering
 
Project initiation
Project initiationProject initiation
Project initiationukrulz4u
 

What's hot (20)

20140311 final report
20140311 final report20140311 final report
20140311 final report
 
Floyd cv
Floyd cvFloyd cv
Floyd cv
 
Quality application
Quality applicationQuality application
Quality application
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
How Quality Importance on Constructions
How Quality Importance on Constructions How Quality Importance on Constructions
How Quality Importance on Constructions
 
Project Plan - Docweb
Project Plan - DocwebProject Plan - Docweb
Project Plan - Docweb
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Venkatesh planning cv
Venkatesh  planning cv Venkatesh  planning cv
Venkatesh planning cv
 
Project closeout-report
Project closeout-reportProject closeout-report
Project closeout-report
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Know how to oversee building services work
Know how to oversee building services workKnow how to oversee building services work
Know how to oversee building services work
 
Douglas Carlesco Resume
Douglas Carlesco ResumeDouglas Carlesco Resume
Douglas Carlesco Resume
 
BIM Engineering US., L.L.C. | Best MEP Engineering in USA
BIM Engineering US., L.L.C. | Best MEP Engineering in USA BIM Engineering US., L.L.C. | Best MEP Engineering in USA
BIM Engineering US., L.L.C. | Best MEP Engineering in USA
 
Service levelagreementtemplate v8
Service levelagreementtemplate v8Service levelagreementtemplate v8
Service levelagreementtemplate v8
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM Contracts
 
Project initiation
Project initiationProject initiation
Project initiation
 
Lawrence_Jacobs_CV_2017
Lawrence_Jacobs_CV_2017Lawrence_Jacobs_CV_2017
Lawrence_Jacobs_CV_2017
 

Viewers also liked

Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Delmar
 
Scanned from a Xerox Multifunction Printer(1)
Scanned from a Xerox Multifunction Printer(1)Scanned from a Xerox Multifunction Printer(1)
Scanned from a Xerox Multifunction Printer(1)Ann T
 
Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Delmar
 
Passive_Intake_Screens
Passive_Intake_ScreensPassive_Intake_Screens
Passive_Intake_ScreensChee Terng Lee
 
Mario Youssef s2942706 REVIT
Mario Youssef s2942706 REVITMario Youssef s2942706 REVIT
Mario Youssef s2942706 REVITMario Y
 
Hijos triunfadores gatuncillo
Hijos triunfadores  gatuncilloHijos triunfadores  gatuncillo
Hijos triunfadores gatuncillodaniel fonseca
 
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀM
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀMĐẢM BẢO CHẤT LƯỢNG PHẦN MỀM
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀMThanCoi20102202
 
Tarea 3 daniel fonseca
Tarea 3 daniel fonsecaTarea 3 daniel fonseca
Tarea 3 daniel fonsecadaniel fonseca
 
My ppt popupquiz
My ppt popupquizMy ppt popupquiz
My ppt popupquizllq0510
 

Viewers also liked (14)

Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.
 
Scanned from a Xerox Multifunction Printer(1)
Scanned from a Xerox Multifunction Printer(1)Scanned from a Xerox Multifunction Printer(1)
Scanned from a Xerox Multifunction Printer(1)
 
Marlins ballpark
Marlins ballparkMarlins ballpark
Marlins ballpark
 
MSc Energy Management
MSc Energy ManagementMSc Energy Management
MSc Energy Management
 
Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.Alexander Del Mar - Executive Resume 2015.
Alexander Del Mar - Executive Resume 2015.
 
Ga Mashie Project
Ga Mashie ProjectGa Mashie Project
Ga Mashie Project
 
Kgadi Mach Mahla CV
Kgadi Mach Mahla CVKgadi Mach Mahla CV
Kgadi Mach Mahla CV
 
Passive_Intake_Screens
Passive_Intake_ScreensPassive_Intake_Screens
Passive_Intake_Screens
 
Mario Youssef s2942706 REVIT
Mario Youssef s2942706 REVITMario Youssef s2942706 REVIT
Mario Youssef s2942706 REVIT
 
Hijos triunfadores gatuncillo
Hijos triunfadores  gatuncilloHijos triunfadores  gatuncillo
Hijos triunfadores gatuncillo
 
Vitamina c
Vitamina cVitamina c
Vitamina c
 
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀM
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀMĐẢM BẢO CHẤT LƯỢNG PHẦN MỀM
ĐẢM BẢO CHẤT LƯỢNG PHẦN MỀM
 
Tarea 3 daniel fonseca
Tarea 3 daniel fonsecaTarea 3 daniel fonseca
Tarea 3 daniel fonseca
 
My ppt popupquiz
My ppt popupquizMy ppt popupquiz
My ppt popupquiz
 

Similar to EA credit 3

Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioningjeff_ranson
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 
Derek swift cv_2016
Derek swift cv_2016Derek swift cv_2016
Derek swift cv_2016Derek Swift
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioningluigiseta
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Logitrain: New Zealand
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
24 Concepts LEED AP
24 Concepts LEED AP24 Concepts LEED AP
24 Concepts LEED APRob Freeman
 
QAinDesignGuidance.pdf
QAinDesignGuidance.pdfQAinDesignGuidance.pdf
QAinDesignGuidance.pdfEnoOriarein
 
Commissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover PhaseCommissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover PhaseOlivia Wilson
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdfDereje Jima
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копияLAZOVOY
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorLAZOVOY
 

Similar to EA credit 3 (20)

Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Derek swift cv_2016
Derek swift cv_2016Derek swift cv_2016
Derek swift cv_2016
 
019113
019113019113
019113
 
Usgbc leed
Usgbc leedUsgbc leed
Usgbc leed
 
Qa qc-waste unit4
Qa qc-waste unit4Qa qc-waste unit4
Qa qc-waste unit4
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioning
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)
 
Opitz writing sample_technical
Opitz writing sample_technicalOpitz writing sample_technical
Opitz writing sample_technical
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
24 Concepts LEED AP
24 Concepts LEED AP24 Concepts LEED AP
24 Concepts LEED AP
 
QAinDesignGuidance.pdf
QAinDesignGuidance.pdfQAinDesignGuidance.pdf
QAinDesignGuidance.pdf
 
Commissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover PhaseCommissioning Best Practices to Follow during the Turnover Phase
Commissioning Best Practices to Follow during the Turnover Phase
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdf
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
An improved, productive, skilled, innovative and efficient sector копия
An improved, productive, skilled, innovative and efficient sector   копияAn improved, productive, skilled, innovative and efficient sector   копия
An improved, productive, skilled, innovative and efficient sector копия
 
An improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sectorAn improved, productive, skilled, innovative and efficient sector
An improved, productive, skilled, innovative and efficient sector
 

EA credit 3

  • 1. CIT 135 Fall 2011 2009 Energy and Atmosphere. EA Credit 3: Enhanced Commissioning. Possible earning points: 2 points. Presented By : Sherif Teaima
  • 2. Credit Summary Intent: To begin the commissioning process early in the design process and execute additional activities after systems performance verification is completed. Requirements:  General Requirements.  (CxA) Requirements.  Activities Requirements.
  • 3. What is commissioning? Building commissioning is a quality assurance program intended to demonstrate the the building is constructed well and performs as designed. Commissioning is also a powerful tool because it can indicate if the designers and contractors have done what they’ve been hired to do. CxA or the commissioning agent have the authority  to make the responsible parties fix the problems up front instead of dealing with maintenance problems or poor performance down the road.
  • 4. General Requirements.  Implement, or have a contract in place to implement, the following additional commissioning process activities in addition to the requirements of EA Prerequisite 1: Fundamental Commissioning of Building Energy Systems and in accordance with the LEED Reference Guide for Green Building Design and Construction, 2009 Edition:  Prior to the start of the construction documents phase, designate an independent commissioning authority (CxA) to lead, review and oversee the completion of all commissioning process activities.
  • 5. (CxA) Requirements.  The CxA must have documented commissioning authority experience in at least 2 building projects.  Must be independent of the work of design and construction.  Must not be an employee of the design firm, though he or she may be contracted through them.  Must not be an employee of, or contracted through, a contractor or construction manager holding construction contracts.  May be a qualified employee or consultant of the owner.  The CxA must report results, findings and recommendations directly to the owner.
  • 6. Activities Requirements.  The CxA must conduct, at a minimum, 1 commissioning design review of the owner’s project requirements (OPR) basis of design (BOD), and design documents (DD/CD) prior to the mid-construction documents phase and back-check the review comments in the subsequent design submission.  The CxA must review contractor submittals applicable to systems being commissioned for compliance with the owner’s project requirements and basis of design. This review must be concurrent with the review of the architect or engineer of record and submitted to the design team and the owner.  The CxA or other project team members must develop a systems manual that gives future operating staff the information needed to understand and optimally operate the commissioned systems.  The CxA or other project team members must verify that the requirements for training operating personnel and building occupants have been completed.  The CxA must be involved in reviewing the operation of the building with operations and maintenance (O&M) staff and occupants within 10 months after substantial completion. A plan for resolving outstanding commissioning-related issues must be included.
  • 7. The requirements of this credit can be met through these strategies:  Commissioning agent should be brought on as part of the design phase, not after the construction starts up.  Owners must rely on a reputable and well experienced commissioning agents  Both the owner and the commissioning agent should precisely follow The LEED detailed guidance on the standards expected for activities like: • Commissioning design review • Commissioning submittal review • System manual
  • 8. Benefits of the credit on the Environment. Commissioning does not only guarantee the integrity of the construction process according to LEED, but it contributes to energy conservation as well, through adequate inspecting to energy related systems such as: 1. HVAC 2. Lighting and day lighting controls 3. Domestic hot water systems 4. Renewable energy systems (solar and wind)  researches claim that owners can achieve savings in operations of $4 over the first five years of occupancy as a direct result of every $1 invested in commissioning
  • 9. Some of the materials needed for commissioning activities
  • 10. Success Story In Jan. 2009, Rockefeller Hall at Harvard Divinity School earned the EA:c3 credit for enhanced commissioning after meeting the EAp1 requirements. In Nov. of the same year, Rockefeller Hall has been awarded LEED Gold certification through the U.S. Green Building Council LEED. Now, Rockefeller Hall is one of Harvard's most energy efficient buildings.
  • 11. WORK CITED • www.LEEDUSER.com Accessed 10/20/2011 • www.WBDG.org Accessed 10/21/2011 • www.EPA.gov Accessed 10/21/2011 • www.HDS.HARVARD.edu Accessed 10/22/2011 • Google images